Synchronized Constr. Servs. v. Prav Lodging ( 2014 )


Menu:
  • Present: Kinser, C.J., Lemons, Goodwyn, Millette, Mims, and
    Powell, JJ., and Koontz, S.J.
    SYNCHRONIZED CONSTRUCTION
    SERVICES, INC.                               OPINION BY
    JUSTICE LEROY F. MILLETTE, JR.
    v.   Record No. 131569                    October 31, 2014
    PRAV LODGING, LLC, ET AL.
    FROM THE CIRCUIT COURT OF ORANGE COUNTY
    Daniel R. Bouton, Judge
    In this appeal we consider whether a general contractor,
    who has no pecuniary interest in the bond posted to release the
    real estate subject to a subcontractor's mechanic's lien, is a
    necessary party to a subcontractor's mechanic's lien
    enforcement action.
    I.   Facts and Proceedings
    In 2008, Prav Lodging, L.L.C. ("Prav") acquired a parcel
    of real estate in Orange County, Virginia to build a hotel
    facility.   Secured by a credit line deed of trust, Virginia
    Community Bank ("VCB") financed the construction of the hotel
    facility.   Prav entered into a contract with Paris Development
    Group, LLC ("Paris") to act as construction manager for the
    project.    As construction manager, Paris had the authority to
    enter into subcontracts with subcontractors to facilitate the
    project.    Paris entered into several such subcontracts,
    including a subcontract with Synchronized Construction
    Services, Inc. ("Synchronized").
    The owner-construction manager contract between Prav and
    Paris was a cost-plus agreement, whereby Prav would pay Paris
    the cost of the work plus a $192,000 fixed fee.    Prav's
    payments were scheduled to be made on a monthly basis upon
    Paris' submission of an invoice to Prav.
    The construction manager-subcontractor subcontract between
    Paris and Synchronized was a fee agreement, whereby Paris would
    pay Synchronized a $398,000 fee subject to additions and
    deductions as the project progressed.   Paris' payments were
    scheduled to be made on a monthly basis upon Synchronized's
    submission of a pay application to Paris.
    By February 3, 2010, the construction project was
    "substantially complete," with the remaining work to be
    "obtainable in a matter of a few days."    On March 11, 2010,
    Synchronized recorded a mechanic's lien for unpaid work on the
    construction project in the amount of $208,250.80 with the
    Orange County Clerk's Office.   On September 9, 2010,
    Synchronized filed a complaint to enforce its mechanic's lien
    in the Circuit Court of Orange County, naming Prav, Paris, VCB,
    and numerous other subcontractors as defendants.    In its
    complaint, Synchronized asserted a claim to enforce its
    mechanic's lien as well as a claim that Paris breached its
    contract with Synchronized by failing to make all payments due
    to Synchronized under their subcontract.
    2
    Paris did not enter an appearance in the case.   Indeed, it
    could not do so because it no longer existed.     According to the
    public records of its state of incorporation, Paris was
    dissolved on March 12, 2010 – the day after Synchronized had
    recorded its mechanic's lien.
    Prav and VCB filed an application to post a bond in the
    amount of $237,906.80 in accordance with Code § 43-70.     The
    circuit court granted that application, thereby releasing the
    real estate which had been subject to Synchronized's mechanic's
    lien.
    Prav filed a motion to dismiss the entire complaint on the
    basis that Synchronized failed to timely serve numerous
    defendants.    In response, the circuit court held that
    Synchronized "failed to exercise due diligence" to serve Paris
    within one year of the date of the filing of the complaint, and
    therefore dismissed Synchronized's breach of contract claim
    against Paris.    However, the court declined to dismiss
    Synchronized's mechanic's lien claim.
    Later, VCB filed a motion to dismiss the mechanic's lien
    claim on the basis that Synchronized failed to timely serve
    Paris, who, as the construction manager, was a necessary party
    to the mechanic's lien enforcement action.     In response, the
    circuit court held that Paris was in fact a necessary party,
    and that Synchronized's failure to timely serve Paris required
    3
    dismissing Synchronized's mechanic's lien claim with prejudice.
    The court entered an order to that effect and denied
    Synchronized's motion for reconsideration.
    Synchronized timely filed a petition for appeal with this
    Court.   We granted the following assignments of error:
    1. The [c]ircuit [c]ourt erred in dismissing
    Synchronized's mechanic's lien enforcement action
    where Paris, the construction manager, did not have a
    recognized possessory or expectancy interest in the
    lien enforcement action which could be defeated or
    diminished as the result [of that] suit and therefore
    was not a necessary party to the action. While Paris
    may have had a contractual claim against the owner of
    the [p]roject arising out of its [c]ontract, the facts
    below reveal that Paris never satisfied the express
    conditions precedent[] found in its [c]ontract in
    order to preserve and maintain such claims. Hence,
    even if Paris had contractual claims, those claims
    would not be sufficient to mandate a finding that
    Paris was a necessary party to the lien enforcement
    action brought by Synchronized.
    2. The [c]ircuit [c]ourt applied an incorrect standard
    in analyzing whether Paris was a necessary party to
    the lien enforcement action and thus erred in
    dismissing Synchronized['s] mechanic's lien
    enforcement action where the presence of . . . Paris[,
    the general contractor,] was not required under
    Virginia law.
    3. The [c]ircuit [c]ourt erred in that Virginia Code
    § 43-22 does not explicitly require a [general
    contractor] to be included as a party to a mechanic's
    lien enforcement action or at all times be [a] viable
    party in a mechanic's lien enforcement action where
    the facts below showed that Synchronized had the
    ability to present proof at trial of the balance due
    under the Prav Lodging-Paris [c]ontract at all
    relevant times included at the time Synchronized's
    mechanic's lien was recorded.
    4
    II.   Discussion
    A.   Standard of Review
    Whether a party is a necessary party to a particular claim
    is a question of law that we review de novo.     Glasser &
    Glasser, PLC v. Jack Bays, Inc., 
    285 Va. 358
    , 369, 
    741 S.E.2d 599
    , 604 (2013).
    B.   Necessary Parties in Mechanic's Lien Enforcement Actions
    This appeal requires us to address the meeting of two
    different areas of law: mechanic's lien enforcement actions,
    and necessary party jurisprudence.    However, as this is not an
    issue of first impression, precedent controls our decision.
    A mechanic's lien was "[un]known to the common law or to
    courts of equity," and therefore is purely "a creature of the
    statute" allowing for its creation.     Shenandoah Valley R.R. Co.
    v. Miller, 
    80 Va. 821
    , 826 (1885); Sergeant v. Denby, 
    87 Va. 206
    , 208, 
    12 S.E. 402
    , 402 (1890).    Being in derogation of the
    common law, "there must be a substantial compliance with the
    requirement of that portion of the statute which relates to the
    creation of the [mechanic's] lien; but . . . the provisions
    with respect to its enforcement should be liberally construed."
    American Standard Homes Corp. v. Reinecke, 
    245 Va. 113
    , 119,
    
    425 S.E.2d 515
    , 518 (1993).     That is to say, a party must
    strictly comply with the "specific time frame and in the manner
    set forth in the statutes" to perfect its mechanic's lien, "or
    5
    the lien will be lost."   Britt Constr., Inc. v. Magazzine
    Clean, LLC, 
    271 Va. 58
    , 63, 
    623 S.E.2d 886
    , 888 (2006)
    (collecting cases).   Once a mechanic's lien is created by
    operation of law and is perfected in accordance with the
    relevant statutory requirements, the party holding the
    mechanic's lien is able to bring suit to enforce that lien.
    Code § 43-22.
    A mechanic's lien enforcement action "must name all
    necessary parties within the time set forth by Code § 43-17,
    and a failure to name a necessary party as defendant requires
    dismissal."   
    Glasser, 285 Va. at 369
    , 741 S.E.2d at 605.      The
    Code does not provide an answer as to which parties are
    necessary parties to a mechanic's lien enforcement action.       See
    Walt Robbins, Inc. v. Damon Corp., 
    232 Va. 43
    , 46-47, 
    348 S.E.2d 223
    , 226 (1986) (rejecting the argument that Code § 43-
    22 establishes who is a necessary party in mechanic's lien
    enforcement actions).   We have therefore relied upon our common
    law authority to supply the answer.
    We have consistently defined "necessary party" broadly.
    See, e.g., Asch v. Friends of Mt. Vernon Yacht Club, 
    251 Va. 89
    , 90-91, 
    465 S.E.2d 817
    , 818 (1996).    Generally, we have
    described necessary parties as follows:
    6
    Where an individual is in the actual enjoyment of the
    subject matter, or has an interest in it, either in
    possession or expectancy, which is likely either to
    be defeated or diminished by the plaintiff's claim,
    in such case he has an immediate interest in
    resisting the demand, and all persons who have such
    immediate interests are necessary parties to the
    suit.
    
    Id. (internal quotation
    marks omitted).      What constitutes the
    "subject matter" or res of a mechanic's lien enforcement action
    narrows the necessary party analysis to a specific set of
    interests in this type of litigation.
    1.      Enforcement of a Mechanic's Lien Against Real Estate
    A mechanic's lien enforcement action seeks to enforce the
    mechanic's lien "against the property bound thereby."      Code
    § 43-22.    As a mechanic's lien enforcement action implicates
    real property rights, we have turned to due process principles
    to determine who is a necessary party in such litigation.        See
    Walt 
    Robbins, 232 Va. at 46-47
    , 348 S.E.2d at 226.
    Such due process principles qualify a necessary party as
    any party who has a real property interest in the real estate
    subject to the mechanic's lien.       See, e.g., James T. Bush
    Constr. Co. v. Patel, 
    243 Va. 84
    , 87-88, 
    412 S.E.2d 703
    , 705
    (1992) (beneficiary of a deed of trust, recorded after the real
    estate subject to the mechanic's lien was improved, is a
    necessary party); Mendenhall v. Douglas L. Cooper, Inc., 
    239 Va. 71
    , 75-76, 
    387 S.E.2d 468
    , 740-71 (1990) (owner of real
    7
    estate subject to the mechanic's lien is a necessary party);
    Walt 
    Robbins, 232 Va. at 47
    , 348 S.E.2d at 226 (beneficiary of
    a deed of trust, recorded before the real estate subject to the
    mechanic's lien was improved, is a necessary party); 
    id. at 48,
    348 S.E.2d at 227 (trustee of a deed of trust, recorded before
    the real estate subject to the mechanic's lien was improved, is
    a necessary party).   In sum, the "subject matter" or res of a
    mechanic's lien enforcement action is the real estate subject
    to the mechanic's lien, and a necessary party is one who has a
    real property interest in such real estate because it is that
    real property interest "which is likely either to be defeated
    or diminished by the plaintiff's claim."    
    Asch, 251 Va. at 90
    ,
    465 S.E.2d at 818.
    Importantly, the focus is on which parties actually have a
    relevant interest in the real property.    Just because a party
    may be generally "interested" in the mechanic's lien
    enforcement action, such as having a pecuniary interest in the
    outcome of the litigation, does not mean that the party is
    necessary to the proceedings.   See, e.g., Air Power, Inc. v.
    Thompson, 
    244 Va. 534
    , 537-38, 
    422 S.E.2d 768
    , 770 (1992) (land
    trust beneficiaries are not necessary parties to a mechanic's
    lien enforcement action against the trust's real estate because
    they only have a personal property interest in the profits from
    8
    the trust's real estate, and have "no interest, [either] legal
    or equitable, in the [real estate] itself").
    2.   Release of the Real Estate by a Posted Bond
    Certain "parties in interest" may, in accordance with the
    rules set forth by the General Assembly, post a bond after a
    mechanic's lien enforcement action has been filed.   Code § 43-
    70.   A properly posted bond releases the real estate from the
    mechanic's lien enforcement action.   
    Id. We have
    previously
    recognized that this bonding-off process only "substitutes the
    bond for the real estate" that had been subject to the
    mechanic's lien.   York Fed. Sav. & Loan Ass'n v. William A.
    Hazel, Inc., 
    256 Va. 598
    , 602, 
    506 S.E.2d 315
    , 317 (1998).
    Because the real estate is no longer subject to the mechanic's
    lien enforcement action once a bond is properly posted, the
    "subject matter" or res of the suit is no longer the real
    estate, but is instead the posted bond itself.
    This has a logical impact on the necessary party analysis.
    If no bond has been posted the inquiry turns upon which parties
    have a real property interest in the real estate subject to the
    mechanic's lien, but when a bond is posted the inquiry focuses
    upon which parties have a pecuniary interest in the bond itself
    which is "likely either to be defeated or diminished" by the
    plaintiff's "claim against the bond."   George W. Kane, Inc. v.
    9
    NuScope, Inc., 
    243 Va. 503
    , 509, 
    416 S.E.2d 701
    , 705 (1992)
    (internal quotation marks omitted).
    To this end, we have previously considered which parties
    constitute "necessary parties-defendant to [a] bond enforcement
    suit."    
    Id. at 509,
    416 S.E.2d at 704.   The principal on the
    bond and the surety on the bond are necessary parties.     
    Id. However, the
    owner of real estate, the trustee under the deed
    of trust, and the beneficiary of the deed of trust are no
    longer necessary parties when their only relation to the
    litigation is their respective real property interests in the
    real estate that had been subject to the mechanic's lien, but
    that was no longer encumbered once the bond had been posted in
    accordance with Code § 43-70.     
    Id. at 510,
    416 S.E.2d at 705.
    3.      Concerns Not Addressed by the Necessary Party Doctrine
    The circuit court incorporated into its necessary party
    analysis concerns that go beyond the scope of this precedent,
    and the parties dispute these concerns on appeal.    We address
    these points to underscore that they are not part of the
    necessary party analysis.
    First, the court expressed concerns about issues of proof.
    The amount that the owner is indebted to the general
    contractor, and the amount that the general contractor is
    indebted to the subcontractor, are factual issues that the
    parties may dispute when a subcontractor seeks to enforce its
    10
    mechanic's lien.   See Code § 43-7(A).   And such disputes remain
    present even "with respect to a bond enforcement suit,
    [because] the party-plaintiff has the burden of proving the
    same elements of his claim that he would have had to prove in a
    suit to enforce the lien released by that bond."    George W.
    Kane, 243 Va. at 
    509, 416 S.E.2d at 704
    .
    However, concerns regarding which parties might be vital
    to proving the plaintiff's case are not relevant to the
    necessary party analysis.   See 
    id. at 509-10,
    416 S.E.2d at
    704-05.   This conclusion is compelled by the fact that we have
    previously held that the owner of the real estate subject to a
    mechanic's lien is no longer a necessary party once a bond is
    posted to release and replace that real estate as the res
    subject to the lien.   
    Id. at 510,
    416 S.E.2d at 705.    If an
    owner is not a necessary party even though the mechanic's lien
    enforcement action may implicate issues relating to a contract
    entered into by that owner, see Code § 43-7(A), then a general
    contractor is not a necessary party simply because the
    mechanic's lien enforcement action may implicate issues
    relating to a contract entered into by that general contractor.
    Simply put, the controlling considerations of the
    necessary party doctrine are not issues of proof and issues as
    to which party may be best situated to provide proof.    Instead,
    the necessary party doctrine is calculated to ensure that all
    11
    parties central to a dispute can have their interests resolved,
    so that absent parties' interests are not adversely affected
    and participating parties may be awarded complete relief.     See
    Michael E. Siska Revocable Trust v. Milestone Dev., LLC, 
    282 Va. 169
    , 173-77, 
    715 S.E.2d 21
    , 23-25 (2011).    As established,
    this requires defining a necessary party to a mechanic's lien
    enforcement action as a party who has a recognized interest in
    the "subject matter" or res of the litigation.
    Second, the circuit court believed that the "subject
    matter" or res of a mechanic's lien enforcement action was more
    than simply the real estate or the posted bond.   The court
    expanded those terms to include the contractual issues that may
    arise through the course of a plaintiff's prima facie case or
    by way of an affirmative defense.
    This position incorrectly conflates a mechanic's lien
    enforcement claim with a breach of contract claim.   A necessary
    party to a mechanic's lien enforcement action must have a
    specifically defined interest in the "subject matter" or res of
    that litigation, which we have repeatedly defined as being
    either the real estate or posted bond.   See George W. 
    Kane, 243 Va. at 509
    -10, 416 S.E.2d at 705; Air 
    Power, 244 Va. at 537-38
    ,
    422 S.E.2d at 770; James T. Bush Constr. 
    Co., 243 Va. at 87-88
    ,
    412 S.E.2d at 705; 
    Mendenhall, 239 Va. at 75-76
    , 387 S.E.2d at
    470-71; Walt 
    Robbins, 232 Va. at 47
    -48, 348 S.E.2d at 226-27.
    12
    A party whose only relation to a mechanic's lien enforcement
    action is his status as a party to a contract, the terms of
    which may be contested during the course of litigation, is akin
    to a party who has only a general pecuniary interest in the
    outcome of a mechanic's lien enforcement action.   We have
    previously recognized that such a general, tangential interest
    is insufficient to elevate a party to necessary party status.
    See Air 
    Power, 244 Va. at 537-38
    , 422 S.E.2d at 770.
    Moreover, as with many mechanic's lien situations, in this
    case any litigation in the mechanic's lien enforcement action
    will not foreclose the ability for Paris, as the general
    contractor, to bring or defend a claim in the future relating
    to its contracts with the owner, Prav, or the subcontractor,
    Synchronized.   Neither collateral estoppel nor res judicata
    would encumber such future litigation because Paris would not
    have been a party to the mechanic's lien enforcement action,
    and no party in that mechanic's lien enforcement action
    identifies with Paris' interest to such a degree that it could
    be said to have represented Paris' legal rights.   See Rule 1:6
    (governing res judicata); Raley v. Haider, 
    286 Va. 164
    , 170,
    
    747 S.E.2d 812
    , 815 (2013) (setting forth the requirements for
    res judicata to bar suit, including identity of the parties or
    their privies); Ellison v. Commonwealth, 
    273 Va. 254
    , 258, 
    639 S.E.2d 209
    , 212 (2007) (noting the mutuality of parties
    13
    requirement among the standards for application of collateral
    estoppel to bar litigation of an issue of fact).
    C.   Whether Paris Is a Necessary Party
    In this case, Prav and VCB posted a bond that released the
    real estate subject to Synchronized's mechanic's lien.   Code
    § 43-70.   As a bond has been posted, the necessary party
    inquiry is whether Paris has a pecuniary interest in that
    posted bond, being the "subject matter" or res of
    Synchronized's mechanic's lien enforcement action, which is
    "likely either to be defeated or diminished" by Synchronized's
    "claim against the bond."   George W. 
    Kane, 243 Va. at 509
    , 416
    S.E.2d at 705 (internal quotation marks omitted).   The answer
    is no.
    Paris is neither the principal nor the surety on the bond.
    Moreover, Paris has no ability to be awarded a judgment to be
    paid out from the bond.   A posted bond is "subject to the final
    judgment of the court upon the hearing of the [mechanic's lien
    enforcement action] upon its merits," and is "for the payment
    of such judgment."   Code § 43-70.   That is, a posted bond can
    only be paid out to those claimants who have a valid mechanic's
    lien on the real estate released by the bond.
    Paris does not have such a mechanic's lien.    It is true
    that Paris was the construction manager and, by providing such
    services for the construction of the hotel facility, acquired a
    14
    mechanic's lien on that real estate.   Code § 43-3.   But the
    continued existence of a mechanic's lien requires the party
    acquiring the lien to perfect it in accordance with the Code.
    Id.; see Britt 
    Constr., 271 Va. at 63
    , 623 S.E.2d at 888
    (collecting cases).
    The requirements for perfection differ depending upon
    whether the party asserting the lien is a general contractor, a
    subcontractor, or a party who contracts with a subcontractor.
    See Code §§ 43-4; 43-7; 43-9.   Being the party who
    "contract[ed] directly with the owner," Paris was a "general
    contractor" for purposes of the mechanic's lien statutory
    scheme.   Code § 43-1.   Code § 43-4, governing the perfection of
    a general contractor's mechanic's lien, required Paris to file
    a "memorandum of lien" and "a certification of mailing of a
    copy of the memorandum of lien [to] the owner of the property"
    in the Orange County clerk's office.   The record reflects that
    Paris did not undertake these actions.   As such, Paris failed
    to perfect its mechanic's lien on the real estate, and that
    mechanic's lien was lost.    Britt 
    Constr., 271 Va. at 63
    , 623
    S.E.2d at 888.   Because Paris lost its mechanic's lien, the
    posted bond is incapable of being subject to a monetary
    judgment in favor of Paris through the course of Synchronized's
    mechanic's lien enforcement action.
    15
    We therefore hold that the circuit court can render
    "complete relief" in Synchronized's mechanic's lien enforcement
    action, even in Paris' absence, because Paris' lack of a
    pecuniary interest in the posted bond means that there is no
    monetary claim upon which the circuit court could award
    judgment in favor of Paris, and no interest held by Paris which
    might need to be shielded from an adverse judgment.    See Lamar
    Co. v. City of Richmond, 
    287 Va. 322
    , 324-25, 
    757 S.E.2d 15
    , 16
    (2014) (proper decree could be entered without participation of
    the absent and putatively necessary party).
    III. Conclusion
    Under the facts of this case, Paris, as the general
    contractor, is a proper party but not a necessary party to a
    subcontractor's mechanic's lien enforcement action.    We will
    therefore reverse the circuit court's judgment to the contrary,
    vacate the order dismissing Synchronized's mechanic's lien
    enforcement claim with prejudice, and remand for further
    proceedings consistent with this opinion.
    Reversed and remanded.
    SENIOR JUSTICE KOONTZ, with whom JUSTICE MIMS and JUSTICE
    POWELL join, dissenting.
    I respectfully dissent.   This case presents the issue
    whether the general contractor in a project involving the
    construction of a hotel was a "necessary party" in a
    16
    subcontractor's action to enforce its mechanic's lien when that
    perfected lien had been discharged, pursuant to Code § 43-70,
    upon the filing of an appropriate bond by the owner of the real
    estate upon which the hotel was constructed.
    Today the majority of this Court holds that because the
    general contractor failed to perfect its statutorily granted
    mechanic's lien under Code § 43-3 it had no "pecuniary
    interest" in the bond and, therefore, was not a necessary party
    to the subcontractor's action to enforce its perfected
    mechanic's lien.   Neither the majority in its opinion, nor the
    subcontractor in its appellee's brief, cites to any prior
    decision by this Court in which we have held that a general
    contractor is not a necessary party to a subcontractor's action
    to enforce its mechanic's lien.    In my view, the statutory
    scheme involving the enforcement of a mechanic's lien by a
    subcontractor and the significant role of the general
    contractor in all construction projects provide persuasive
    reasons that such is the case.
    Initially, I am reminded of the old adage that bad facts
    can lead to bad law.   In this case no evidentiary hearing was
    conducted in the trial court and, thus, the material facts are
    drawn necessarily from the parties' pleadings, memoranda, and
    supporting exhibits filed in that court.   While the majority
    makes reference to the fact that the general contractor did not
    17
    enter an appearance in the case because it was apparently
    dissolved the day after the subcontractor recorded its
    mechanic's lien, there are no facts in the record reflecting
    the status of the general contractor at the time the
    subcontractor subsequently filed its action to enforce its
    mechanic's lien nor at the time the bond was posted by the
    owner of the real estate.
    What is undisputed, however, is the fact that the general
    contractor was not given notice of the subcontractor's action
    because the subcontractor "failed to exercise due diligence" to
    serve the general contractor.   That finding by the trial court
    was not challenged by the subcontractor even though it suggests
    that the general contractor could have been served.      Under
    these circumstances, the proper analysis of the issue in this
    appeal necessarily must be premised upon the fact that the
    subcontractor simply failed to give the general contractor
    notice of the proceeding and thereby deprived the general
    contractor of the opportunity to appear and provide evidence in
    the case if it desired to do so.       This is not a case in which
    the general contractor with notice declined to participate.
    Moreover, under these circumstances there is no factual basis
    upon which a determination can be made as to what pecuniary
    interest, if any, the general contractor had in the proceeding
    initiated by the subcontractor.
    18
    Nevertheless, the majority opinion seems to suggest that
    the posting of the bond made these "bad facts" irrelevant to
    its determination that the general contractor was not a
    necessary party in this case.   In that context, it is not clear
    what the reasoning would be had, for example, the general
    contractor been given notice, appeared, and asserted that the
    owner was indebted to it and that it was not indebted to the
    subcontractor.   For the reasons that follow, in my view, the
    statutory scheme for enforcing a mechanic's lien contemplates
    the central role of the general contractor in construction
    cases so that all claims may be resolved and future litigation
    avoided.
    The analysis in this appeal is guided by settled law
    regarding the enforcement of a mechanic's lien.   Mechanic's
    liens arise by statute and are in derogation of the common law.
    Britt Constr., Inc. v. Magazzine Clean, LLC, 
    271 Va. 58
    , 63,
    
    623 S.E.2d 886
    , 888 (2006); Carolina Builders Corp. v. Cenit
    Equity Co., 
    257 Va. 405
    , 410, 
    512 S.E.2d 550
    , 552 (1999).
    The statutory authority for a mechanic's lien for those
    whose labor or materials is incorporated in construction
    projects is found in Code §§ 43-1 to 43-23.2.   As pertinent to
    this appeal, Code § 43-3(A) provides that a mechanic's lien is
    created automatically by "performing labor or furnishing
    materials of the value of $150 or more . . . for the
    19
    construction, removal, repair or improvement of any building or
    structure."    Both the general contractor and subcontractor are
    granted a mechanic's lien in this manner.   See Code § 43-4
    (general contractors); Code § 43-7 (subcontractors).
    A mechanic's lien cannot be enforced, however, unless it
    is first perfected in accord with Code § 43-7.   Britt 
    Constr., 271 Va. at 63
    , 623 S.E.2d at 888 (collecting cases).   Pertinent
    to the present case, Code § 43-7(A) provides that "the amount
    for which a subcontractor may perfect a lien . . . shall not
    exceed the amount in which the owner is indebted to the general
    contractor."   This statute further provides that it shall be an
    affirmative defense that the owner is not indebted to the
    general contractor, or that the amount owed to the general
    contractor is less than the amount of the subcontractor's
    asserted mechanic's lien.   These provisions reflect the central
    role of the general contractor in all construction projects.
    Thus, we have long held that the burden of proof in a suit to
    enforce a mechanic's lien requires the subcontractor to prove
    both that he is entitled to payment for labor and materials
    furnished under his contract with the general contractor and
    that the owner was indebted to the general contractor under
    their contract at the time notice of the subcontractor's lien
    was given or became so indebted thereafter.    John T. Wilson Co.
    v. McManus, 
    162 Va. 130
    , 135, 
    173 S.E. 361
    , 362 (1934).
    20
    Once a mechanic's lien has been perfected, Code § 43-22
    provides, in pertinent part, that the lien "may be enforced in
    a court of equity" by a complaint filed in the county or city
    wherein the property upon which the building was constructed is
    located.    The statutory scheme for enforcing a perfected
    mechanic's lien is a unique equity proceeding.    Once the
    subcontractor's suit invokes the equity jurisdiction of the
    trial court, "it may go on to a complete adjudication, even to
    the extent of establishing legal rights and granting legal
    remedies which would otherwise be beyond the scope of its
    authority."    Such is the case even though the complainant may
    have failed to establish its right to a mechanic's lien.
    Johnston & Grommett Bros. v. Bunn, 
    108 Va. 490
    , 493, 
    62 S.E. 341
    , 342 (1908); see also Erlich v. Hendrick Constr. Co., 
    217 Va. 108
    , 115, 
    225 S.E.2d 665
    (1976).
    In a suit by a subcontractor to enforce a mechanic's lien
    the focus of the equity court's determination is upon the
    status of the general contractor's accounts with the owner and
    the subcontractor.    In this context, we have observed that
    there is a distinction between a "proper party" and a
    "necessary party" in that the failure to include the former is
    not a ground for dismissing the suit whereas the failure to
    include the latter renders the court powerless to proceed with
    the suit.    Mendenhall v. Douglas L. Cooper, Inc., 
    239 Va. 71
    ,
    21
    74, 
    387 S.E.2d 468
    , 470 (1990).    There we explained that a
    necessary party's "interests in the subject matter of the suit,
    and in the relief sought, are so bound up with that of the
    other parties, that their legal presence as parties to the
    proceeding is an absolute necessity, without which the court
    cannot proceed.   In such cases the court refuses to entertain
    the suit, when those parties cannot be subjected to its
    jurisdiction."    
    Id. In Raney
    v. Four Thirty Seven Land Co., we stated that
    "[w]here an individual is in the actual enjoyment of
    the subject matter, or has an interest in it, either
    in possession or expectancy, which is likely either
    to be defeated or diminished by the plaintiff's
    claim, in such case he has an immediate interest in
    resisting the demand and all such parties who have
    such an interest are necessary parties to the suit."
    
    233 Va. 513
    , 519-20, 
    357 S.E.2d 733
    , 736 (1987) (quoting
    Gaddess v. Norris, 
    102 Va. 625
    , 630, 
    46 S.E. 905
    , 907
    (1904))
    Code § 43-70 provides that when a suit has been filed
    under Code § 43-22 to enforce a mechanic's lien, "parties in
    interest" may petition the court "for permission to pay into
    court an amount of money sufficient to discharge such lien."
    If the court permits the posting of the bond, "the property
    affected thereby shall stand released from such lien" and
    enforcement of the lien "shall be subject to the final judgment
    of the court upon the hearing of the case on its merits."      The
    22
    posting of the bond does not constitute a confession of
    judgment or otherwise resolve the underlying controversy of
    whether the alleged debt secured by the lien is owed.   See York
    Fed. Sav. & Loan Ass'n v. William A. Hazel, Inc., 
    256 Va. 598
    ,
    602, 
    506 S.E.2d 315
    , 317 (1998).    Thus, we held in George W.
    Kane, Inc. v. NuScope, Inc., 
    243 Va. 503
    , 509, 
    416 S.E.2d 701
    ,
    704 (1992), that "with respect to a bond enforcement suit, the
    [subcontractor] has the burden of proving the same elements of
    his claim that he would have had to prove in a suit to enforce
    the lien released by that bond."
    In the present case, the subcontractor filed a complaint
    in the Circuit Court of Orange County to enforce its perfected
    mechanic's lien on September 9, 2010.   Subsequently, in August
    2011 the owner filed an appropriate bond in accordance with
    Code § 43-70 and the subcontractor's lien was discharged.
    Although the complaint named the general contractor as a
    defendant, the subcontractor failed to give the general
    contractor notice of the proceeding and the general contractor
    did not enter an appearance.
    It is readily apparent that when a bond is filed under
    Code § 43-70 the subject matter of the subcontractor's lien
    enforcement suit remains the determination of what
    indebtedness, if any, existed between the owner and the general
    contractor at the time the lien was perfected or thereafter,
    23
    and what indebtedness, if any, exists between the general
    contractor and the subcontractor.    The bond is not the subject
    matter of the suit.   Rather, the bond provides the monetary
    pool from which the equity court makes a "complete
    adjudication" of the financial issues between all the parties
    involved in the construction project that have been provided
    proper notice of the proceeding, while releasing the property
    of the owner in question from claims of parties involved in
    that construction project.   Significantly, in this way the bond
    provides the mechanism by which the equity court is able to
    resolve any financial claims that may exist between all the
    parties to the construction project and thus protect them from
    future litigation involving the construction project.
    In the present case, the general contractor was not
    provided the opportunity to assert any claims it may have had
    against the owner or to refute any assertions of the
    subcontractor against it in its capacity as the general
    contractor in the construction project.   Moreover, the equity
    court was called upon to render a complete adjudication of the
    financial issues in the case "on its merits" without the
    benefit of the general contractor's evidence of what, if any,
    indebtedness existed between it and the owner and what, if any,
    indebtedness existed between it and the subcontractor.    In that
    circumstance, in my view the general contractor was a necessary
    24
    party to the subcontractor's suit to enforce its mechanic's
    lien, and the trial court did not abuse its discretion in
    refusing to entertain that suit and dismissing it with
    prejudice.
    The majority relies, in part, upon our decision in Kane to
    conclude that a general contractor is not a necessary party to
    a bond enforcement suit by a subcontractor.   There, we held
    that the owner of the real estate subject to a mechanic's lien
    is no longer a necessary party once a bond is posted to release
    the real estate.   243 Va. at 
    510, 416 S.E.2d at 705
    .   The
    majority reasons that if an owner is not a necessary party in
    those circumstances then it follows that the general contractor
    is also not a necessary party.   In Kane, however, the general
    contractor, rather than the owner, posted the bond.     
    Id. at 505,
    416 S.E.2d at 702.   The distinction is significant.     When
    the owner posts the bond it does so to release a mechanic's
    lien claim so that the owner's property is no longer
    encumbered.   When the general contractor posts the bond it
    becomes a party to the subcontractor's enforcement suit and
    thereby protects itself from future litigation with the
    subcontractor.
    The majority also relies upon our decision in Air Power,
    Inc. v. Thompson, 
    244 Va. 534
    , 
    422 S.E.2d 768
    (1992), to
    support its reasoning in this case.   There, we held that land
    25
    trust beneficiaries are not necessary parties to a mechanic's
    lien enforcement action against the trust's real estate.    This
    was so because the beneficiaries only had a personal property
    interest in the profits of the trust's real estate.   Id. at
    
    537-38, 422 S.E.2d at 770
    .   Obviously, Air Power did not
    involve the status of a general contractor and the unique role
    the general contractor plays in a construction project and the
    resulting role it maintains in the resolution of a
    subcontractor's mechanic's lien enforcement suit.
    For these reasons, I would hold that the general
    contractor, where available for service by a subcontractor in
    its mechanic's lien enforcement suit in which a bond has been
    posted by the owner in accordance with Code § 43-70, is a
    necessary party.   Accordingly, I would further hold that the
    trial court did not abuse its discretion in refusing to
    entertain the subcontractor's action in this case and
    dismissing it with prejudice.
    26