D.R. Horton, Inc. v. Board of Supervisors ( 2013 )


Menu:
  • PRESENT: All the Justices
    D.R. HORTON, INC.
    OPINION BY
    v.   Record No. 120384             JUSTICE ELIZABETH A. McCLANAHAN
    FEBRUARY 28, 2013
    BOARD OF SUPERVISORS FOR THE
    COUNTY OF WARREN
    FROM THE CIRCUIT COURT OF WARREN COUNTY
    William H. Ledbetter, Jr., Judge Designate
    D.R. Horton, Inc. (Horton) challenges the trial court's ruling
    that certain building permit fees it paid to Warren County, which
    were later found to be unlawful, were nonetheless paid "voluntarily"
    under the common law voluntary payment doctrine, thus defeating
    Horton's claim for their return.    We will affirm the judgment of the
    trial court.
    BACKGROUND
    At the request of Blue Ridge Shadows, LLC (BRS) (Horton's
    predecessor in title), the Board of Supervisors for Warren County
    (the Board) rezoned a tract of land owned by BRS near the Town of
    Front Royal from agricultural to suburban residential.      As part of
    the rezoning process, BRS made a number of written "proffers" to the
    Board as inducements for the right to develop the property as a
    subdivision containing up to 225 residential units.    The Board
    ultimately accepted BRS's "Revised Rezoning Request Proffer," (the
    revised proffer), in conjunction with approving BRS's rezoning
    application.   In the revised proffer BRS proposed, among other
    things, to construct and operate a centrally located wastewater
    treatment plant and water system to service the residential units
    within the development.   BRS also proposed to "make cash payments in
    the total amount of $8,000.00 per residential unit" payable each
    time Warren County (the County) issued a building permit for one of
    the units. 1
    Afterwards, in a "confidential" letter to the County attorney,
    BRS proposed: (i) that the Board allow BRS to obtain water and sewer
    services for the development from the Town of Front Royal in lieu of
    BRS constructing the proposed water and sewer systems; and (ii)
    that, in exchange, BRS would pay to the County an additional "hook-
    up fee" in the amount of $4,000 for "each residential water/sewer
    hookup obtained" from the Town.       The parties never executed an
    agreement regarding this proposal.       The Board, however, voted to
    allow the development to connect to the Town's water and sewer
    systems.   The Board also voted to amend BRS's revised proffer to the
    County by deleting BRS's obligation to construct such systems for
    the development.
    Horton, a real estate developer, subsequently purchased from
    BRS most of the property contained within the proposed development
    and identified as the "Blue Ridge Shadows Subdivision" (the
    subdivision).   Horton purchased the subdivision subject to BRS's
    1
    These proffered payments were offered to "offset the fiscal
    impacts" of the proposed development on the County's capital
    facilities, as authorized by Code § 15.2-2296.
    2
    revised proffer, as amended by the deleted obligation to construct
    the water and sewer systems.
    The County issued to Horton a total of 52 building permits
    between May 2006 and January 2010.   For each permit, Horton paid to
    the County a "proffer fee" of $12,000, amounting to $4,000 more than
    the $8,000 fee set forth in the revised proffer.
    Horton learned in early 2006 when applying for the first
    building permits that the County would be charging the additional
    $4,000 per permit as the "hook-up" fee BRS previously proposed to
    the County in lieu of constructing the water and sewer systems.
    After investigating the matter, Horton stated its objections to
    paying this fee during a series of meetings between Horton's
    representatives and County officials.   Horton's counsel also sent a
    letter to the County later that year stating that Horton did not
    believe it was obligated to pay the fee pursuant to the terms of the
    revised proffer; that it would pay the fee "until this matter has
    been resolved" in order "to avoid further damage to [Horton]"; and
    that it was paying the fee "only under protest and with a full
    reservation of its rights and remedies."
    In 2007 Horton filed a declaratory judgment action asking the
    trial court to declare that the County could not lawfully assess the
    $4,000 fee against it.   The court agreed with Horton and entered a
    3
    final order in 2011 (after the fee had been paid on all 52 permits)
    holding that Horton was not obligated to pay the fee. 2
    In 2008 Horton instituted the instant restitution action
    seeking reimbursement of the fees by filing a complaint against the
    Board in the form of an appeal to the circuit court, pursuant to
    Code § 15.2-1246. 3   In the appeal, Horton challenged the Board's
    denial of its claim for $104,000 based on its payment of the $4,000
    fee on each of its first 26 building permits. 4   The Board raised the
    voluntary payment doctrine as an affirmative defense.     The trial
    court consolidated this restitution action and Horton's declaratory
    judgment action for a bench trial.    After ruling in Horton's favor
    in the declaratory judgment action, the court held in this action
    that Horton was nevertheless barred from being awarded reimbursement
    of the unlawful fees because it paid them "voluntarily" within the
    meaning of the voluntary payment doctrine.
    This appeal followed.
    2
    The trial court's decision was based on its finding that
    "there was never an agreement finalized that was . . . intended to
    be binding [between] the [C]ounty [and BRS] with respect to this
    [fee]." Therefore, the court concluded, the fee could not lawfully
    be assessed against Horton.
    3
    Code § 15.2-1246 establishes the procedure by which a party
    may challenge by an appeal to a circuit court the "disallowance" of
    a monetary claim by the decision of a county's governing body.
    4
    Although the record does not show that Horton amended its
    complaint in this case, both Horton and the Board indicate in their
    respective appellate briefs that the amount in dispute is $208,000
    based on Horton's payment of the $4,000 fee on all 52 building
    permits issued for the subdivision between May 2006 and January
    2010.
    4
    ANALYSIS
    Horton argues on appeal that it paid the unlawful building
    permit fees involuntarily.   The trial court erred, Horton contends,
    in denying its claim for reimbursement of the fees upon a
    misapplication of the voluntary payment doctrine and rejecting its
    argument on equitable grounds.
    Well-settled principles govern our review of the trial court's
    decision.    We will not disturb the trial court's findings of fact
    unless they are plainly wrong or without evidence to support them,
    but we will review de novo its conclusions of law.    City of Richmond
    v. SunTrust Bank, 
    283 Va. 439
    , 442, 
    722 S.E.2d 268
    , 270 (2012).
    The voluntary payment doctrine, as established under Virginia
    common law, provides as follows:
    "Where a party pays an illegal demand with a full knowledge
    of all the facts which render such demand illegal, [i]
    without an immediate and urgent necessity therefor, or [ii]
    unless to release his person or property from detention, or
    [iii] to prevent an immediate seizure of his person or
    property, such payment must be deemed voluntary, and cannot
    be recovered back. And the fact that the party at the time
    of making the payment, files a written protest, does not
    make the payment involuntary."
    Barrow v. County of Prince Edward, 
    121 Va. 1
    , 2-3, 
    92 S.E. 910
    , 910
    (1917) (quoting Lamborn v. County Commissioners, 
    97 U.S. 181
    , 187
    (1878)).    Furthermore, in the context of this doctrine, we have held
    that "[a]ll payments are presumed to be voluntary until the contrary
    is made to appear."    Town of Phoebus v. Manhattan Social Club, 105
    
    5 Va. 144
    , 149, 
    52 S.E. 839
    , 840 (1906).      Therefore, the plaintiff has
    the burden "to show that its payment was not voluntary."      Id.
    This doctrine has been strictly applied in Virginia for more
    than a century and a half.    See Mayor of Richmond v. Judah, 32 Va.
    (5 Leigh) 305, 315-321 (1834); Williams v. Consolvo, 
    237 Va. 608
    ,
    613, 
    379 S.E.2d 333
    , 336 (1989).       During that time when the doctrine
    has been implicated, this Court has held in "decidedly few" cases
    that payment of an unlawful demand was, in fact, involuntarily paid.
    Id. at 614, 379 S.E.2d at 336; see, e.g., Vick v. Siegel, 
    191 Va. 731
    , 734-36, 
    62 S.E.2d 899
    , 900-01 (1951) (landowner's payment of
    trustee's unlawful demand to avoid losing sale of property was
    involuntary).    The Court has acknowledged that the doctrine may
    appear to be somewhat "harsh."     Town of Phoebus, 105 Va. at 149, 52
    S.E. at 840. 5   Early on, however, the Court explained the
    significance of the doctrine in advancing certainty and finality
    between parties in the resolution of their legal affairs; and aptly
    noted that, without it, "the payment of money would soon become but
    the parent of a suit, and the settlement of an account the harbinger
    of litigation."    Judah, 32 Va. (5 Leigh) at 322 (Tucker, J.,
    concurring).
    5
    See also Judah, 32 Va. (5 Leigh) at 319 (explaining that the
    doctrine "may sometimes, indeed, operate hardly . . . but not more
    so than the statute of limitations, or many other principles of the
    law, which have been adopted with a view to general policy").
    6
    Horton makes four alternative arguments for why its payment of
    the subject fees was involuntary so as to negate the County's
    voluntary payment defense.    First, Horton argues that it paid the
    fees involuntarily because the County's refusal to issue the
    building permits without payment of the fees constituted a seizure
    of a property right consisting of Horton's right to develop the
    subdivision.   We agree with Horton that "[d]evelopment rights are
    property rights" protected under Virginia law.    Bentley Funding
    Group, L.L.C. v. SK&R Group, L.L.C., 
    269 Va. 315
    , 331, 
    609 S.E.2d 49
    , 57 (2005).   We reject Horton's contention, however, that a
    seizure of such a right was effected by the County's unlawful demand
    for fee payments as Horton did not in any way "los[e] the right to
    develop its property" as a result of that demand; and indeed
    proceeded with development.    City of Virginia Beach v. Bell, 
    255 Va. 395
    , 403, 
    498 S.E.2d 414
    , 419 (1998) (emphasis and internal
    quotation marks omitted) (inverse condemnation case). 6
    Next, Horton asserts that it paid the fees involuntarily
    because it "face[d] other proceedings or actions if [it] refused to
    pay the fee and build without a building permit or refused to
    build."   Specifically, Horton claims it faced criminal charges if it
    proceeded without obtaining the permits from the County, or,
    alternatively, it faced breach of contract actions by third parties
    6
    Accordingly, Horton's reliance on condemnation cases such as
    Bell to advance the argument that the County seized its property is
    misplaced.
    7
    if it refused to go forward with its residential construction to
    avoid paying the fees.    We see no evidence in the record, however,
    that the County was threatening Horton with any criminal action or
    that Horton had executed any contract with a third party for
    construction of a residence in the subdivision.   Furthermore,
    neither circumstance could be considered under the voluntary payment
    doctrine as a basis for establishing an involuntary payment without
    Horton showing as a threshold matter that there was an "immediate
    and urgent necessity" for paying the County's unlawful demand, as we
    address in response to Horton's next argument.    Barrow, 121 Va. at
    2, 92 S.E. at 910.
    For its third argument, Horton asserts that an immediate and
    urgent need to pay the fees rendered its payments involuntary.   Such
    a need existed, Horton contends, because it "faced an immediate and
    urgent necessity" to "do what it could to build and sell houses,"
    which included paying the fees to obtain the permits authorizing
    their construction.    To establish the requisite necessity to pay an
    unlawful demand, a plaintiff must prove that it "did not have time
    and opportunity to relieve [itself] of [its] predicament by
    resorting to legal methods."   Vick, 191 Va. at 735-36, 62 S.E.2d at
    901.    Thus, Horton had to show that it had no time or opportunity
    before paying the County's unlawful demand to at least seek an
    appropriate legal remedy.   Horton failed to do so. Horton acquired
    the permits on which it paid the fees over a period of three and a
    8
    half years.   For that period, Horton did not establish any reason
    why it could not have sought injunctive relief before acquiring any
    one of the permits.   See Williams, 237 Va. at 615, 379 S.E.2d at 337
    (plaintiff could have secured injunction before paying unlawful
    demand).   Instead, Horton paid the fees to the County on its own
    both before and after filing the declaratory judgment action and the
    instant restitution action; and it continued doing so for the three
    and a half years until it had paid all of the fees to the County.
    Horton's fourth argument for why its fee payments were
    involuntary is that it adequately protested the assessment of the
    fees through its representatives' meetings with County officials,
    its protest letter to the County and ultimately its filing of the
    declaratory judgment action.   This argument is without merit because
    simply protesting an unlawful demand does not render payment of the
    demand involuntary under the voluntary payment doctrine, as
    explained above in Barrow.   See also Town of Phoebus, 105 Va. at
    149, 52 S.E. at 840 ("The mere declaration of the plaintiff when it
    made payment, that it was made under 'protest' does not show that it
    was not voluntarily made.").
    Finally, Horton argues that the trial court erred in rejecting
    its assertion that the County's retention of the fees unjustly
    enriched the County and was inherently inequitable.   Those claims
    constitute the basis for a restitution action, which is the nature
    of Horton's instant action seeking reimbursement of the fees.
    9
    However, the voluntary payment doctrine provided the County a valid
    defense to this action.   See Skyland Metro. Dist. v. Mountain West
    Enter., LLC, 
    184 P.3d 106
    , 127 (Colo. App. 2007) ("The [voluntary
    payment] rule is a defense to claims asserting unjust enrichment."
    (citation omitted)).
    CONCLUSION
    For the reasons stated above, we conclude the trial court did
    not err in holding that Horton's action for reimbursement of the
    disputed fees was barred under the voluntary payment doctrine.   We
    will therefore affirm the judgment of the trial court.
    Affirmed.
    10