APAC-Atlantic, Inc. v. General Insurance Co. , 273 Va. 682 ( 2007 )


Menu:
  • PRESENT: Hassell, C.J., Lacy, Keenan, Koontz, Lemons, and Agee,
    JJ., and Russell, S.J.
    APAC-ATLANTIC, INC.
    OPINION BY
    v.   Record Number 061106                JUSTICE G. STEVEN AGEE
    April 20, 2007
    GENERAL INSURANCE COMPANY
    OF AMERICA
    FROM THE CIRCUIT COURT OF FAIRFAX COUNTY
    Gaylord L. Finch, Jr., Judge
    APAC-Atlantic, Inc. (“APAC-Atlantic”) appeals the judgment
    of the Circuit Court of Fairfax County, which granted a motion
    for summary judgment filed by defendant General Insurance
    Company of America (“General Insurance”) and entered final
    judgment in its favor.   APAC-Atlantic contends the circuit court
    erred in finding APAC-Atlantic’s motion for judgment was not
    timely because it was filed after the expiration of the
    limitations period found in Code § 2.2-4341(C).   For the reasons
    set forth below, we will affirm the judgment of the circuit
    court.
    I. BACKGROUND AND MATERIAL PROCEEDINGS BELOW
    The parties stipulated to the following facts: General
    Insurance is the surety on two payment bonds issued in
    connection with two separate general construction contracts
    awarded by the Virginia Department of Transportation (“VDOT”) to
    New Construction, Inc. (“New Construction”).   The payment bonds
    cover obligations New Construction incurs during its performance
    of the VDOT contracts.   Both payment bonds state: “if [New
    Construction] shall promptly pay all just claims . . . then this
    obligation is to be void; otherwise; to be and remain in full
    force and virtue in law.”
    New Construction subcontracted some of the work on both
    VDOT projects to APAC-Atlantic.       APAC-Atlantic timely completed
    work on one project on August 28, 2003 and on the second project
    on October 9, 2003.   These dates are the respective “day[s] on
    which the person bringing such action last performed labor or
    last furnished or supplied materials” under Code § 2.2-4341(C).
    New Construction did not pay APAC-Atlantic the full amount owed
    for that work, and it filed for bankruptcy protection in
    February 2004, owing APAC-Atlantic $150,905.95 on one of the
    projects and $217,008.48 on the other.
    On December 3, 2004, APAC-Atlantic filed a motion for
    judgment against General Insurance, alleging that under the
    payment bonds General Insurance was liable in its capacity as
    surety for the amounts still owed by New Construction.      General
    Insurance filed an answer and grounds of defense alleging, inter
    alia, that the “[b]onds were issued pursuant to [Code] § 2.2-
    4337, the Virginia Public Procurement Act [“VPPA”], and APAC[-
    Atlantic]’s action is barred by the statute of limitations of
    [Code] § 2.2-4341.”   General Insurance contended that under the
    Code § 2.2-4341(C) limitations period, APAC-Atlantic was
    2
    required to have filed its motion for judgment on the respective
    bonds by August 28, 2004 and October 9, 2004.   The parties filed
    cross motions for summary judgment, which were argued to the
    circuit court under the stipulated facts.    In its final order
    dated March 4, 2006, the circuit court denied APAC-Atlantic’s
    motion for summary judgment, granted General Insurance’s motion,
    and entered judgment “in favor of General [Insurance] on all
    Counts in this action.”
    We awarded APAC-Atlantic this appeal.
    II. ANALYSIS
    APAC-Atlantic contends the trial court erred by failing to
    find “that under the language of the payment bonds [APAC-
    Atlantic’s motion for judgment] was timely filed.”   Citing
    Reliance Insurance Co. v. Trane Co., 
    212 Va. 394
    , 
    184 S.E.2d 817
    (1971), APAC-Atlantic contends the plain language of the payment
    bonds can – and in this case does – provide a longer period of
    time than the statutorily prescribed period for bringing suit.
    Specifically, APAC-Atlantic asserts the limitations period in
    Code § 2.2-4341(C) does not apply in the case at bar because the
    plain language of the payment bonds states they are “to be and
    remain in full force and virtue in law” unless New Construction
    pays the “claims for labor and material.”    APAC-Atlantic
    contends this language extends a timely right of action on the
    bonds beyond the statutorily prescribed period.   Furthermore,
    3
    APAC-Atlantic asserts Code § 2.2-4341(C) does not apply because
    the payment bonds do not expressly refer to that statute.   We
    disagree.
    The parties do not dispute that the underlying contracts
    for which the payment bonds were issued fall under the VPPA,
    Code § 2.2-4300 et seq.   “The VPPA is a specific statute
    relating to the acquisition of goods and services by public
    bodies [and] the provisions of that Act . . . apply to disputes
    arising from goods or services provided under the VPPA.”    Mid-
    Atlantic Business Communications, Inc. v. Virginia Dep’t of
    Motor Vehicles, 
    269 Va. 51
    , 56, 
    606 S.E.2d 835
    , 838 (2005).
    Code § 2.2-4341(C) of the VPPA states: “Any action on a payment
    bond shall be brought within one year after the day on which the
    person bringing such action last performed labor or last
    furnished or supplied materials.”    By its plain terms, this
    limitation period is generally applicable to “[a]ny action on a
    payment bond” issued under the VPPA.
    The bonds at issue in Reliance Insurance Co., on which
    APAC-Atlantic relies, were substantially different than those at
    issue here.   There, the parties’ contract expressly permitted a
    subcontractor to sue the principal even though the applicable
    statute only permitted such an action when certain conditions
    were met and did not expressly include an action by a
    subcontractor.   Reliance Insurance Co., 212 Va. at 395, 184
    4
    S.E.2d at 818.   Because the parties specifically agreed to those
    terms and the applicable statute did not prohibit them from
    doing so, we held that the parties were free to include “broader
    coverage than that required by the provisions” of the statute.
    Id.   In contrast, the payment bonds in the case at bar contain
    no provision permitting a claimant to bring suit after the
    expiration of the limitations period found in Code § 2.2-
    4341(C).
    APAC-Atlantic relies on the phrase “otherwise; to be and
    remain in full force and virtue in law” to support its
    contention.   However, this language does not establish a new
    period during which claimants can file an action, nor does it
    incorporate a limitations period contained in a statute other
    than Code § 2.2-4341(C).   It simply establishes that General
    Insurance’s obligation would only arise if New Construction did
    not pay a claim.
    Also without merit is APAC-Atlantic’s contention that the
    limitations period in Code § 2.2-4341(C) does not apply because
    the payment bonds failed to expressly incorporate this
    provision.    For example, the statute of limitations prescribed
    by the Uniform Commercial Code for disputes arising from
    contracts for the sale of goods (Code § 8.2-725) applies to UCC
    contracts regardless of whether such contracts expressly
    incorporate that limitations period.   See Code § 8.01-246.
    5
    Similarly, the statute of limitations for disputes arising from
    goods or services provided under the VPPA applies to contracts
    subject to the VPPA, regardless of whether they expressly
    incorporate Code § 2.2-4341(C).       Code § 2.2-4300(B) provides
    that the VPPA “shall apply whether the consideration is monetary
    or nonmonetary.”   Because the payment bonds in the case at bar
    were issued in accordance with the VPPA, disputes arising under
    them are subject to the limitations period contained in the VPPA
    – Code § 2.2-4341(C) – unless the parties specifically contract
    for a different time limitation.∗      See Reliance Insurance Co.,
    212 Va. at 395, 184 S.E.2d at 818.      The VPPA provision does not
    need to be incorporated by reference, but is applicable because
    of the nature of the dispute.
    ∗
    APAC-Atlantic contends the five-year limitations period
    under Code § 8.01-246(2), which is applicable to written
    agreements, would apply instead. Apart from the fact that the
    parties made no agreement to use any limitations period other
    than Code § 2.2-4341(C) under the VPPA, under settled principles
    of statutory interpretation, where two statutes are potentially
    applicable, “the two should be harmonized, if possible, and
    where they conflict,” the more specific statute applies. See
    Frederick County Sch. Bd. v. Hannah, 
    267 Va. 231
    , 236, 
    590 S.E.2d 567
    , 569 (2004) (quoting Virginia Nat’l Bank v. Harris,
    
    220 Va. 336
    , 340, 
    257 S.E.2d 867
    , 870 (1979)). The five-year
    general limitations period of Code § 8.01-246(2) would not apply
    here, because under the VPPA, Code § 2.2-4341(C) is specifically
    applicable to VPPA-derived actions. “Every action for which a
    limitation period is prescribed by law must be commenced within
    the period prescribed in this chapter unless otherwise
    specifically provided in this Code.” Code § 8.01-228 (emphasis
    added).
    6
    III.   CONCLUSION
    Accordingly, actions on the payment bonds had to be brought
    under the one-year limitations period contained in Code § 2.2-
    4341(C).   Because APAC-Atlantic finished work on each project in
    August and October 2003, its motion for judgment filed in
    December 2004 was not timely.   The circuit court thus did not
    err in granting General Insurance’s motion for summary judgment
    and entering judgment on behalf of General Insurance.   We will
    therefore affirm the judgment of the circuit court.
    Affirmed.
    7
    

Document Info

Docket Number: Record 061106.

Citation Numbers: 643 S.E.2d 483, 273 Va. 682, 2007 Va. LEXIS 49

Judges: Hassell, Lacy, Keenan, Koontz, Lemons, Agee, Russell

Filed Date: 4/20/2007

Precedential Status: Precedential

Modified Date: 10/19/2024