Appalachian Power co. v. State Corp. Comm'n ( 2012 )


Menu:
  • Present: Kinser, C.J., Lemons, Millette, McClanahan and Powell,
    JJ., and Russell and Lacy, S.JJ.
    APPALACHIAN POWER COMPANY
    v.   Record No. 120394              OPINION BY SENIOR JUSTICE
    ELIZABETH B. LACY
    STATE CORPORATION COMMISSION,           November 1, 2012
    ET AL.
    FROM THE STATE CORPORATION COMMISSION
    In this appeal, we consider whether the State Corporation
    Commission properly construed and applied Code § 56-
    585.1(A)(5)(e) to deny rate adjustment clause recovery for
    certain costs incurred by Appalachian Power Company (“APCO” or
    “the Company”).
    Background
    Prior to 1999, the State Corporation Commission (“the
    Commission”) determined the rates electric utility companies
    charged consumers pursuant to Chapter 10, Article 2 of Title 56,
    Code §§ 56-234 through -245.1:1.   Under that regulatory regime,
    the rates could be changed following a review initiated by the
    Commission or upon an application filed by an electric utility.
    The Commission had broad discretion in selecting the methodology
    for determining rates including the rate of return on equity
    guided by the principle that the rates were to be just and
    reasonable, allowing the utility a reasonable return and
    imposing just rates on the consumer.     Code § 56-235.2.
    In 1999, the General Assembly enacted the Virginia Electric
    Utility Restructuring Act, former Code §§ 56-576 et seq., which
    was designed to deregulate parts of the electric utility
    industry and introduce competition among the providers of
    electric generation.     1999 Acts ch. 411; Potomac Edison Co. v.
    State Corp. Comm’n, 
    276 Va. 577
    , 580, 
    667 S.E.2d 772
    , 773
    (2008).   The legislation established a transition period, during
    which the base rates of electric utilities were held constant or
    “capped.” 1   However, utilities were allowed to file annual rate
    applications to recover incremental costs incurred for system
    reliability and for compliance with governmental environmental
    laws or regulations.     Code § 56-582(B)(vi); 2004 Acts ch. 827.
    In 2007, the General Assembly ended its program of
    deregulation and enacted Code § 56-585.1 which prescribed a new
    regulation regime.     2007 Acts chs. 888, 933.   The new
    legislation reaffirmed the Commission’s authority to regulate
    electric utility rates but prescribed certain procedures and
    methodologies which the Commission must follow in establishing
    such rates.
    1
    The initial transition period extended from January 1,
    2001 to July 1, 2007, but was extended to December 31, 2008,
    “unless sooner terminated by the Commission pursuant to the
    provisions of subsection C; however, rates after the expiration
    or termination of capped rates shall equal capped rates until
    such rates are changed pursuant to other provisions of this
    title.” Code § 56-582(F); 2007 Acts chs. 888, 933.
    2
    Under the 2007 regulatory regime each utility was required
    to undergo an initial review by the Commission in 2009.        In this
    proceeding, the Commission conducted a review of each company’s
    2008 performance, set a rate of return and determined the rates
    to be charged going forward “until such rates are adjusted.”
    Code § 56-585.1(A).   The methodology for adjusting rates in this
    initial proceeding was set out in the statute.       Id.
    The legislation requires that, after the initial review
    proceeding, the performance of electric utility companies is
    reviewed every two years.   In the biennial review, the
    Commission considers the company’s rates, terms, and conditions
    for the provision of generation, distribution and transmission
    services for the preceding two years.   Id.   While the biennial
    review has some characteristics of the Chapter 10 base rate
    proceeding, the statute imposes significant limitations on the
    Commission’s discretion in adjusting rates.    Id.
    If the utility earned more than 50 basis points below the
    authorized fair combined rate of return, the Commission “shall
    order increases to the utility’s rates necessary to provide the
    opportunity to fully recover the costs of providing the
    utility’s services and to earn not less than such fair combined
    rate of return . . . .”   Code § 56-585.1(A)(8)(i).        If the
    utility earned more than 50 basis points above the fair combined
    rate of return established by the Commission, 60 percent of the
    3
    amount of the earnings above the fair rate of return must be
    credited to customers’ bills and the electric utility may retain
    the remaining 40 percent of the excess earnings.   Code § 56-
    585.1(A)(8)(ii).    The Commission may not order a rate reduction
    unless it finds that the electric utility earned more than 50
    basis points above the fair rate of return in two consecutive
    biennial reviews.   Code § 56-585.1(A)(8)(iii).
    The 2007 legislation also creates a new proceeding allowing
    a utility to petition the Commission for approval of a rate
    adjustment clause for the “timely and current” recovery from
    customers for costs incurred in certain identified programs.
    Code §§ 56-585.1(A)(4) through (6).   As relevant here, the
    Commission is directed to make rate adjustments allowing a
    company to recover projected and actual costs of projects which
    the Commission finds necessary to comply with state or federal
    environmental laws or regulations.    Code § 56-585.1(A)(5)(e).
    Once granted, a rate adjustment clause is combined with the
    company’s costs, revenues and investments in a biennial review
    proceeding if there are adjustments to the rates until the
    amounts of the adjustment clause are fully recovered.   Code
    § 56-585.1(A)(3).
    Proceedings
    Pursuant to the regulatory review regime outlined above,
    APCO filed its petition for its initial review in 2009.   In that
    4
    proceeding APCO sought a rate increase of approximately $167
    million based on the Company's performance in the 2008 test
    year.       The Commission’s order implementing APCO’s adjusted rates
    included recovery for some, but not all the amounts sought by
    APCO for compliance with various state and federal environmental
    laws and regulations.      These rates became effective in August of
    2010.       In re Appalachian Power Co., Case No. PUE-2009-00030,
    (July 15, 2010). 2
    In March of 2011, APCO filed a petition pursuant to Code
    § 56-585.1(A)(5)(e), seeking a rate adjustment clause to recover
    $77 million, which it asserted represented the 2009 and 2010
    actual costs incurred by the Company, but not recovered through
    base rates, to comply with state and federal environmental
    requirements. 3     The recovery APCO sought was incurred either
    directly by APCO for environmental projects required for
    compliance or through the capacity equalization charges it paid
    to its affiliates which included costs incurred by the
    2
    A copy of this order may be found using the Commission’s
    docket search website,
    http://docket.scc.state.va.us/CyberDocs/Libraries/Default_Librar
    y/Common/frameviewdsp.asp?doc=103033&lib=CASEWEBP%5FLIB&mimetype
    =application%2Fpdf&rendition=native (last visited September 28,
    2012).
    3
    APCO contemporaneously made its biennial filing pursuant
    to Code § 56-585.1(A)(3). That proceeding is not at issue in
    this appeal.
    5
    affiliates for compliance with state or federal environmental
    laws or regulations. 4
    The Commission published an order calling for notice and
    hearing, scheduled public hearings associated with the petition,
    established a procedural schedule for the case, and assigned a
    hearing examiner to conduct all further proceedings on behalf of
    the Commission.   A number of parties filed notices of
    participation including the Old Dominion Committee for Fair
    Utility Rates and the Office of the Attorney General Division of
    Consumer Counsel, appellees in this appeal.   Public hearings and
    evidentiary hearings were conducted by the Commission and the
    hearing examiner.
    In his report and recommendations to the Commission, the
    hearing examiner concluded that Code § 56-585.1(A)(5)(e)
    entitled APCO to recover the environmental compliance costs it
    sought but, based on the testimony and evidence received, the
    hearing examiner recommended that the appropriate amount of
    4
    Capacity equalization charges are charges APCO pays to
    acquire supplemental generation capacity to meet its native load
    demand. The supplemental generation is acquired from facilities
    owned by APCO’s affiliates which, like APCO, are subsidiaries of
    American Electric Power Company, Inc. The amount of the
    capacity equalization charges is determined through an
    Interconnection Agreement between APCO and its affiliates
    approved by the Federal Energy Regulatory Commission. The
    Interconnection Agreement sets out a formula to show the
    affiliates’ costs of owning, operating and maintaining the
    generation facilities that supply the capacity purchased by
    APCO.
    6
    revenue recovery should be $63.3 million rather than the
    approximately $77 million sought by APCO. 5
    The Commission rejected the hearing examiner’s construction
    and application of Code § 56-585.1(A)(5)(e) and held that the
    section did not authorize recovery of those costs which the
    Company had already been given the opportunity to recover
    through its base rates.
    The Commission also concluded that, even if APCO was
    entitled to recover actual compliance costs associated with
    categories of projects included in, but not recovered by the
    base rates, it could not recover the $27.3 million alleged as
    embedded in the capacity equalization charges because APCO
    failed to establish the actual amount of the environmental costs
    embedded in those charges.
    The Commission entered an order allowing APCO to recover
    $30 million for actual environmental compliance costs over a
    one-year period and denying recovery of the remaining
    approximately $6 million APCO claimed it incurred directly but
    did not recover through base rates to comply with environmental
    regulations and laws and approximately $27.3 million alleged to
    be environmental compliance costs embedded in the capacity
    adjustment charges paid to its affiliates.    APCO filed an appeal
    5
    APCO did not challenge the amount of recovery recommended
    by the hearing examiner before the Commission and does not do so
    in this appeal.
    7
    with this Court pursuant to Rule 5:21(a) naming the Commission
    and intervenors, Old Dominion Committee for Fair Utility Rates
    and the Office of the Attorney General Division of Consumer
    Counsel, as appellees.
    Discussion
    1. Application of Code § 56-585.1(A)(5)(e)
    APCO raises three assignments of error containing a number
    of subpoints.   The overarching challenge which APCO advances is
    that the ratemaking methodology adopted by the Commission to
    implement Code § 56-585.1(A)(5)(e) ignored the plain and
    unambiguous language of the statute.
    The Constitution of Virginia vests administrative, judicial
    and legislative powers in the Commission in the exercise of the
    control and regulation of public utility companies.     Potomac
    Edison, 276 Va. at 586, 667 S.E.2d at 777.    In considering the
    appropriate standard of review to be applied when reviewing a
    Commission decision, we begin by giving a decision in which the
    Commission has exercised its expertise a presumption of
    correctness.    Id.   Our standard of review, however, will depend
    on the nature of the decision under review.     Id.   The decision
    under review here is the Commission’s construction and
    application of Code § 56-585.1(A)(5)(e).    This statutory
    construction issue is a question of law reviewed by this Court
    8
    de novo.   Christian v. State Corp. Comm’n, 
    282 Va. 392
    , 396-97,
    
    718 S.E.2d 767
    , 769 (2011).
    The Commission and other appellees, however, assert that we
    have limited the de novo standard of review in certain cases
    citing opinions in which we have recited that “the practical
    construction given by the Commission to a statute it is charged
    with enforcing is entitled to great weight by the courts and in
    doubtful cases will be regarded as decisive.”   Piedmont Envtl.
    Council v. Virginia Elec. & Power Co., 
    278 Va. 553
    , 563, 
    684 S.E.2d 805
    , 810 (2009) (citations and internal quotation marks
    omitted); Appalachian Voices v. State Corp. Comm’n, 
    277 Va. 509
    ,
    516, 
    675 S.E.2d 458
    , 461 (2009); Commonwealth v. Appalachian
    Elec. Power Co., 
    193 Va. 37
    , 45, 
    68 S.E.2d 122
    , 127 (1951).
    Acknowledging that an agency cannot advance an interpretation
    that contradicts the statute, Davenport v. Little-Bowser, 
    269 Va. 546
    , 554-55, 
    611 S.E.2d 366
    , 370-71 (2005)(citing Superior
    Steel Corp. v. Commonwealth, 
    147 Va. 202
    , 206, 
    136 S.E. 666
    , 667
    (1927)), the Commission suggests that our prior cases require
    that we treat the Commission’s decision as “decisive.” 6   We
    disagree with the suggestion that in this case the Commission’s
    statutory interpretation must be considered as “decisive.”
    6
    The arguments raised by the other appellees in this appeal
    are substantially similar to those raised by the Commission.
    9
    The Commission’s statutory construction was first
    characterized as “decisive” in Appalachian Elec. Power Co., 193
    Va. at 45, 68 S.E.2d at 127.    In that case, the Commission
    construed a tax statute and held that electric utilities doing
    business in this state could deduct certain monies derived from
    operations in other states before computing their liability for
    the tax at issue.   The Commission had applied this construction
    of the statute for approximately a decade.    After concluding
    that the statute was ambiguous, the Court not only described the
    Commission’s interpretation as being decisive, it explained the
    reason for ascribing this level of deference to the Commission’s
    decision in that case.    Id.   Citing a number of previous cases,
    the Court explained that the “[l]egislature is presumed to be
    cognizant of such construction and when long continued, in the
    absence of legislation evincing a dissent, the courts will adopt
    that interpretation.” 7   Id. at 45-46, 68 S.E.2d at 127.   In that
    7
    Miller v. Commonwealth, 
    180 Va. 36
    , 41-42, 
    21 S.E.2d 721
    ,
    723 (1942)(public official’s statutory construction accepted by
    bench and bar for long period of time is canon of construction,
    unless paramount reason is found for change in construction);
    Commonwealth v. Stringfellow, 
    173 Va. 284
    , 289, 
    4 S.E.2d 357
    ,
    359 (1939)(great weight afforded tax department’s long-standing
    and uniform statutory construction); Hunton v. Commonwealth, 
    166 Va. 229
    , 242, 
    183 S.E. 873
    , 878 (1936)(court defers to tax
    official’s practical construction of tax laws when, for over 30
    years, neither legislature nor tax commission recommended change
    in law due to constitutional conflict); Smith v. Bryan, 
    100 Va. 199
    , 204, 
    40 S.E. 652
    , 654 (1902)(court regards public
    official’s construction of statute of doubtful import as correct
    10
    case, as in others using this principle, the General Assembly
    had not altered the agency’s interpretation although it had the
    opportunity to do so during the intervening years.     Id.
    The Commission’s construction of the statute in this case
    is not a long-standing one and is not a construction which the
    General Assembly has had the opportunity to consider.    Thus, the
    presumption of legislative acquiescence does not apply.      Compare
    Beck v. Shelton, 
    267 Va. 482
    , 492, 
    593 S.E.2d 195
    , 200
    (2004)(when General Assembly was aware of interpretation of
    statute embodied in an Opinion of the Attorney General for five
    years and “fail[ed] to make corrective amendments” to statute
    during that time, such “failure . . . evinces legislative
    acquiescence in the Attorney General’s view”)(quoting Browning-
    Ferris, Inc. v. Commonwealth, 
    225 Va. 157
    , 161-62, 
    300 S.E.2d 603
    , 605-06 (1983)).
    In any case involving statutory construction we begin with
    the language of the statute.   Code § 56-585.1(A)(5)(e) provides
    in pertinent part:
    5. A utility may at any time, after the
    expiration or termination of capped rates, but
    not more than once in any 12-month period,
    petition the Commission for approval of one or
    more rate adjustment clauses for the timely and
    current recovery from customers of the
    following costs:
    when that construction remains unchanged by legislature or
    judicial decision over time).
    11
    . . . .
    e. Projected and actual costs of projects
    that the Commission finds to be necessary to
    comply with state or federal environmental
    laws or regulations applicable to generation
    facilities used to serve the utility’s native
    load obligations. The Commission shall
    approve such a petition if it finds that such
    costs are necessary to comply with such
    environmental laws or regulations . . . .
    The Commission contends that because Code § 56-
    585.1(A)(5)(e) “is silent on the intersection of base rate
    recovery and adjustment clause recovery,” subsection (C) of Code
    § 56-585.1 requires the Commission to adopt a “ratemaking
    methodology” to implement the adjustment rate clause section
    which will produce just and reasonable rates as directed in
    Chapter 10 of Title 56 of the Code. 8   Noting that nothing in the
    statute gives a utility the right to recover all of its actual
    environmental compliance costs, the Commission reasons that by
    including such costs in its base rates, a company has the
    opportunity to recover such costs, which can be supplemented by
    costs for projects not already included in the base rates.     This
    8
    Code § 56-585.1(C) provides:
    Except as otherwise provided in this section, the
    Commission shall exercise authority over the rates,
    terms and conditions of investor-owned incumbent
    electric utilities for the provision of generation,
    transmission and distribution services to retail
    customers in the Commonwealth pursuant to the
    provisions of Chapter 10 (§ 56-232 et seq.),
    including specifically § 56-235.2.
    12
    result, the Commission concludes, is “fully supported by the
    plain language of the Act.”
    The Commission also contends that the ratemaking
    methodology it chose is consistent with Code § 56-585.1 when
    read as a whole.   Subdivision (7) of Code § 56-585.1(A) requires
    the Commission to consider a petition for a rate adjustment
    clause for environmental compliance costs “on a stand-alone
    basis without regard to the other costs, revenues, investments,
    or earnings of the utility.”    Thus, the Commission continues,
    the base rate and rate adjustment clause proceedings are
    separate proceedings and incorporation of base rate items when
    setting adjustment clause rates “would exceed the Commission’s
    authority in adjustment clause proceedings.”      According to the
    Commission, other “costs, revenues, investments, or earnings”
    are appropriately disregarded by limiting the adjustment clause
    rates only to environmental costs not already included in base
    rates.
    The primary objective in statutory construction is to
    determine and give effect to the intent of the legislature as
    expressed in the language of the statute.      Halifax Corp. v.
    First Union Nat’l Bank, 
    262 Va. 91
    , 99-100, 
    546 S.E.2d 696
    , 702
    (2001).   When a statute is unambiguous, we must apply the plain
    meaning of that language.     Id.    If the statute is subject to
    more than one interpretation, we must apply the interpretation
    13
    that carries out the legislative intent.     Brown v. Lukhard, 
    229 Va. 316
    , 321, 
    330 S.E.2d 84
    , 87 (1985).     Rules of statutory
    construction prohibit adding language to or deleting language
    from a statute.   BBF, Inc. v. Alstom Power, Inc., 
    274 Va. 326
    ,
    331, 
    645 S.E.2d 467
    , 469 (2007).
    The statute quoted above clearly states the intent of the
    legislature.   It states that the Commission “shall” approve a
    utility’s petition for a rate adjustment clause filed pursuant
    to Code § 56-585.1(A)(5)(e) if the three conditions set out in
    the statute are met: (1) only one petition for a rate adjustment
    clause seeking recovery under the section is filed in any 12-
    month period; (2) the costs are actual or projected costs; and
    (3) the Commission finds that the costs were necessary to comply
    with state or federal environmental laws or regulations.
    Further, the statute states that the purpose of the rate
    adjustment clauses is to allow for the “timely” and “current”
    recovery of qualified costs.     Code § 56-585.1(A)(5).   The rate
    adjustment clause proceeding stands in direct contrast to the
    more lengthy base rate proceeding, which under Code § 56-585.1
    only occurs every two years. 9
    There is no dispute that the costs APCO seeks to recover
    were incurred in qualified environmental projects and that these
    9
    A utility company may still apply for temporary rate
    increases at any time. Code §§ 56-585.1(B) and -245.
    14
    costs have not been recovered and cannot be recovered in the
    future through the mechanism of the base rates.   Yet, the
    ratemaking methodology adopted by the Commission prevents the
    recovery of the very costs which the statute identifies as being
    recoverable through a rate adjustment clause.   Providing a
    utility with the opportunity to recover environmental compliance
    costs is inconsistent with the statutory mandate providing for
    the timely and current actual recovery of such costs which, in
    this case, means such costs will never be recovered.
    The Commission’s methodology not only contradicts the
    intent of the legislature reflected in the statute, it
    effectively adds a fourth condition to the statute: the costs
    sought were not costs that could have been recovered in the
    Company’s base rates.   Adding words to a statute in this manner
    violates a well-established tenet of statutory construction.
    BBF, Inc., 274 Va. at 331, 645 S.E.2d at 469 (courts, in
    construing a statute, must apply its plain meaning, and “we are
    not free to add [to] language, nor to ignore language, contained
    in statutes.”)(quoting SIGNAL Corp. v. Keane Fed. Sys., 
    265 Va. 38
    , 46, 
    574 S.E.2d 253
    , 257 (2003)).
    The Commission’s reliance on the authority contained in
    subsection (C) of Code § 56-585.1 as support for its ratemaking
    methodology is misplaced.   That subsection specifically makes
    the Commission’s exercise of its Chapter 10 ratemaking authority
    15
    subject to the other provisions of Code § 56-585.1.   Therefore,
    any ratemaking methodology which the Commission adopts to
    implement Code § 56-585.1(A)(5)(e) may not contradict that
    section.   As pointed out above, the ratemaking methodology
    adopted by the Commission conflicts with the intent and the
    plain language of Code § 56-585.1(A)(5)(e).
    Finally, the directive that the Commission consider a
    petition for a rate adjustment clause under Code § 56-
    585.1(A)(5)(e) on a stand-alone basis does not require the type
    of separation the Commission suggests.   Indeed, even under the
    Commission’s methodology, reference to a utility’s base rates
    would be required to determine whether the projects which
    incurred the actual or projected costs sought to be recovered
    were included in the computation of the base rates.
    Furthermore, reference to base rate revenues would be necessary
    to ensure that the amount requested as an actual unrecovered
    cost had in fact not already been recovered.
    Rather, the “stand-alone” language in subdivision (7) of
    subsection (A) of the statute means that the utility’s costs,
    revenues, investments or earnings should not be considered when
    determining the amount of the rate adjustment clause.    Nothing
    in the language of this subdivision suggests or requires that
    actual costs incurred in environmental compliance projects may
    16
    not include costs associated with such projects if the projects
    were included in formulating base rates.
    For these reasons, we hold that Code § 56-585.1(A)(5)(e)
    allows recovery of unrecovered costs incurred by a utility for
    environmental compliance projects necessary to serve the
    utility’s native load obligations even if the projects which
    incurred those costs were included in the utility’s base rates.
    2. Recovery of Compliance Costs Embedded
    in Capacity Equalization Charges
    The Commission also denied recovery of the environmental
    compliance costs embedded in the capacity equalization charges
    that APCO sought because the evidence did not “accurately
    reflect actual ‘costs of projects’ used to serve the Company’s
    native load customers.”   APCO has assigned error to this
    alternate holding and we now address that issue.
    APCO argues that it produced sufficient evidence to support
    recovery for the environmental compliance costs embedded in the
    capacity equalization charges.   APCO points to uncontradicted
    evidence that a portion of the capacity payments included costs
    that its affiliates incurred for projects required to comply
    with environmental laws and regulations and evidence of the
    amount of capacity equalization charges APCO paid to its
    affiliates during the time periods in question.    APCO also
    relies on the testimony and exhibits of its witnesses and
    17
    Commission Staff which included computations or estimates of the
    portion of the capacity equalization charges attributable to
    environmental compliance costs incurred by its affiliates.    APCO
    asserts that the use of different formulae by its witnesses and
    Commission Staff to arrive at the amount of environmental
    compliance costs embedded in the capacity equalization charges
    did not absolve the Commission from weighing the evidence and
    determining a proper recovery amount.   Finally, APCO asserts
    that the evidence and calculations it presented were “identical
    in form, detail and scope” to evidence accepted by the
    Commission in prior cases under Code § 56-582 during the former
    deregulation transition period.
    The Commission, in its alternate holding denying these
    costs, noted that although Code § 56-585.1(A)(5)(e) allows
    recovery for actual and projected costs, in this proceeding APCO
    sought recovery of costs it identified as actual, not projected
    costs.   The Commission’s ruling was based on its determination
    that nothing in the testimony or calculations regarding the
    capacity equalization charges paid by APCO or the
    Interconnection Agreement contains any identification or
    specific quantification of the amount of environmental costs
    embedded in those charges.   In applying the statutory language
    referring to “actual costs,” the Commission held that estimates
    of environmental compliance costs produced in this case “did not
    18
    sufficiently demonstrate [the] actual costs” as required by the
    statute.   The Commission also noted that using “one of the
    varying calculations in the record could result in a double
    recovery of costs through the Company’s base rates and
    adjustment rate clauses.”
    The Commission’s decision under review here is that the
    evidence was insufficient to prove “actual costs.”   This finding
    of fact will not be reversed unless it is “contrary to the
    evidence or without evidence to support it.”   Mutual Sav. & Loan
    Ass'n v. Commonwealth, 
    212 Va. 557
    , 559, 
    186 S.E.2d 13
    , 14
    (1972).
    In its alternate holding, the Commission applied the plain
    language of the statute, which in this case limits rate
    adjustment clauses to “actual costs,” and held that the
    estimates of environmental compliance costs embedded in the
    capacity equalization charges did not meet the statutory
    requirement.   Acceptance of estimates in proceedings brought
    under other statutes which did not require evidence of “actual
    costs” does not require or suggest that estimates should be
    sufficient in this proceeding.   Furthermore, APCO’s argument
    that the Commission failed to weigh the evidence and instead
    ignored it is without merit.   The record is clear that the
    Commission considered the evidence and found that it did not
    satisfy the statutory requirement of “actual costs.”
    19
    Based on this record, we cannot say the Commission’s
    decision is contrary to the evidence or without evidentiary
    support.
    Conclusion
    In summary, in this appeal APCO sought recovery of $33.3
    million in environmental compliance costs that the Commission
    denied.    For the reasons stated, we hold that APCO is entitled
    to a rate adjustment clause for recovery of actual costs it
    directly incurred for environmental compliance in 2009 and 2010,
    but did not recover through its base rates.     We will reverse
    that portion of the Commission’s decision denying recovery of
    environmental compliance costs on the basis that those costs are
    connected with projects included in APCO’s base rates which the
    Company had the opportunity to recover.
    We will affirm that portion of the Commission’s decision
    denying APCO recovery of environmental compliance costs alleged
    to be embedded in the capacity equalization charges APCO paid to
    its affiliates in 2009 and 2010.      Accordingly, we will remand
    the case to the Commission for further proceedings consistent
    with this opinion.
    Reversed in part,
    affirmed in part
    and remanded.
    20