Glasser & Glasser v. Jack Bays, Inc. ( 2013 )


Menu:
  • PRESENT:    All the Justices
    GLASSER & GLASSER, PLC, TRUSTEE FOR
    FIRST MORTGAGE BONDHOLDER, 2006 SERIES
    v.   Record No. 120287                           OPINION BY
    JUSTICE DONALD W. LEMONS
    February 28, 2013
    JACK BAYS, INC., ET AL.
    CITIZENS BUSINESS BANK
    v.   Record No. 120288
    JACK BAYS, INC., ET AL.
    CELTIC BANK
    v.   Record No. 120289
    JACK BAYS, INC., ET AL.
    FROM THE CIRCUIT COURT OF PRINCE WILLIAM COUNTY
    Mary Grace O'Brien, Judge
    In this appeal, we consider the validity of various
    mechanics' liens filed under Code § 43-4.
    I.   Facts and Proceedings
    A.      New Life's Construction Project, Contractors,
    and Financing
    Jack Bays, Inc. ("Jack Bays") is a commercial general
    contracting firm with expertise in new church construction.
    In 2004, the company's President, Lynn Bays Fuechsel
    ("Fuechsel"), met the Senior Pastor and Founder of New Life
    Anointed Ministries International ("New Life"), Bishop Eugene
    Reeves ("Bishop Reeves").      At the time, New Life was beginning
    the process of building a church in Woodbridge, Virginia.
    Jack Bays ultimately became the general contractor on the
    project.
    On August 22, 2005, Jack Bays submitted a proposal for
    the site work portion of the project.   Site work included
    excavation and grading, utility installation, concrete and
    asphalt paving, landscaping, and fencing.   New Life accepted
    the proposal either contemporaneously or shortly thereafter by
    signing an owner/contractor agreement form ("August '05
    Agreement").   The agreement form stated that New Life would
    pay Jack Bays a stipulated sum of $4,209,532 for initial work
    at the project site.
    On September 29, 2005, Jack Bays began site work.     On
    April 26, 2006, a new Agreement ("April '06 Agreement")
    provided that New Life would pay Jack Bays a stipulated sum of
    $12,016,000.   The April '06 Agreement incorporated the sum and
    scope of work from the August '05 Agreement.
    On December 5, 2006, the parties increased the value of
    the contract for the final time.    Change Order 13 required
    construction on a preschool, sanctuary, lobby and corridors.
    The cost of this project was $5,858,732, which brought the
    total cost of the project to $17,874,732.   The contract
    provided for payment of requisitions from Jack Bays based upon
    percentage completion of the project.
    2
    To perform work at the site, Jack Bays contracted with
    several subcontractors, the following eleven of which are
    parties to this action: Structural Steel, LLC ("Structural
    Steel"), United Sprinkler Company, Inc. ("United Sprinkler"),
    Virginia Paving Company ("Virginia Paving"), Sparkle Painting
    Company, Inc. ("Sparkle Painting"), Scaffold Resource, LLC
    ("Scaffold Resource"), Miller Construction, Inc. ("Miller
    Construction"), Adrian L. Merton, Inc. ("Adrian Merton"),
    Century Contracting Corporation ("Century Contracting"),
    Clover Contracting, Inc. ("Clover Contracting"), General Glass
    Corporation ("General Glass"), and Becker Electric Company. ∗
    After briefly working with Branch Banking and Trust, New
    Life sought additional funds for the project.   To obtain these
    funds, New Life worked with Strongtower, a bonding company for
    church financing.   This collaboration led New Life to obtain
    additional financing, specifically in the amount of $13.6
    million.   San Joaquin Bank (the predecessor to and hereinafter
    "Citizens Business Bank"), 1st Centennial Bank (the
    predecessor to and hereinafter "Celtic Bank"), and Glasser &
    Glasser, PLC ("Glasser & Glasser") (collectively, "Lenders")
    were listed as "Lenders" on the Deed of Trust for the new
    financing, while Stewart Title Guaranty Company ("Stewart
    ∗
    When referring to the general contractor and the
    subcontractors we will use the term "Contractors."
    3
    Title") was designated "Trustee."     Glasser & Glasser was also
    designated Trustee for "First Mortgage Bondholders, 2006
    Series" ("Bondholders").     Citizens Business Bank obtained a
    note evidencing the debt in the principal amount of
    $8,962,000.    Celtic Bank obtained a note in the principal
    amount of $4,491,000.     Additionally, the Deed of Trust
    incorporated a $13,453,000 Trust Indenture "for the benefit of
    certain Bondholders," with Glasser & Glasser as Trustee, and
    Reliance Trust Company as the trust company and disbursement
    agent.    The Lenders recorded their Deed of Trust on June 27,
    2006.
    On September 29, 2005, Jack Bays issued its first
    requisition for payment to New Life.     New Life paid in full,
    and continued to pay its requisitions in full each month
    through March 2007.     New Life paid part of Jack Bays' April
    2007 requisition, falling $141,498.70 short of total payment.
    Thereafter, New Life made no payments to Jack Bays from May
    through October 2007, because funding for the project was
    exhausted.
    Throughout the May-October 2007 period, New Life
    attempted to obtain additional financing.     Jack Bays
    understood from Bishop Reeves that new funding would be
    obtained to cover the cost of the project.     On July 27, 2007,
    Monika Taylor, an underwriter for Quest Capital Funding, wrote
    4
    to Fuechsel to "inform [Fuechsel] that we are going through
    final approval for a $20,000,000.00 (Twenty Million Dollar)
    loan for New Life Anointed Church."       From her conversations
    with Bishop Reeves, Fuechsel expected to be paid for Jack
    Bays' prior, ongoing, and future work on or around August 3,
    2007.    After the anticipated loan from Quest Capital Funding
    did not close, Fuechsel was told that financing would instead
    be in place by the end of August.       However, no further
    financing was obtained.       Jack Bays continued construction work
    at the site from May through September 28, 2007.
    B.      Contract Work and Demobilization,
    Mechanics' Liens, and Termination
    On September 28, 2007, Jack Bays sent a memorandum to its
    subcontractors.       The memorandum detailed New Life's efforts to
    obtain financing, and informed the subcontractors that delays
    in the approval process caused Jack Bays to immediately
    "stop[] active work on the site until all payments are
    current."    The letter asked the subcontractors to consider
    waiting until November 2007 to file a mechanics' lien so that
    title could remain clear and enable New Life to "have the best
    opportunity to obtain financing."
    After September 28, 2007, Jack Bays began to shut down
    active work on the project by collecting equipment and
    rectifying unsafe conditions on the premises.       Jack Bays
    5
    maintained a log of site work during this time and issued a
    requisition for October 2007 work it classified as
    "demobilization."
    According to Jack Bays, subcontractors continued work at
    the site through October 11, 2007.   However, United Sprinkler
    performed "normal course of business" work through at least
    October 18, 2007.   Sparkle Painting had an employee working on
    site through at least October 1, 2007, and possibly through
    October 9, although information supporting the latter date was
    inconclusive.   Scaffold Resource entered the premises on
    October 1 to remove scaffolding provided, completing this work
    – which was provided for in its contract with Jack Bays – on
    October 16.   Becker Electric continued contract completion
    work on the project by performing wiring work related to pulls
    and terminations at electrical panel locations and rooftop
    units through October 16, although this was primarily in an
    effort to address safety concerns associated with exposed live
    electrical wires.
    Jack Bays alleged that its activity at the project site
    between October 1 and November 16, 2007, was a necessary part
    of its demobilization efforts, and that any contract work
    performed by subcontractors during that time was at the
    subcontractors' own risk.   However, Jack Bays increased the
    percentage by which it evaluated the completeness of the
    6
    project's work between its September and October 2007
    requisitions by 2%, from 92% to 94%.   Whether Jack Bays'
    actions and the actions of the subcontractors in October and
    November 2007 constitute continuing contract work or
    demobilization is disputed by the parties to this action.
    On December 28, 2007, Jack Bays recorded its Memorandum
    of Mechanic[s'] Lien against New Life in the amount of
    $5,942,487.48 in the Circuit Court of Prince William County.
    The following table summarizes the dates on which
    subcontractors recorded their memoranda of mechanics' liens,
    and the value of those liens:
    Subcontractor        Date             Value
    Clover      12/20/07        $60,814.37
    Contracting
    Adrian L.      12/20/07       $323,165.20
    Merton
    General Glass      12/20/07       $50,544.00
    Century      12/20/07       $134,303.00
    Contracting
    Capital     12/21/2007      $217,575.00
    Contracting
    Virginia      12/27/07       $423,583.27
    Paving
    Sparkle      12/27/07        $13,950.00
    Painting
    Structural      12/27/07       $139,922.00
    Steel
    Miller      12/28/07        $99,654.00
    Construction
    Scaffold      1/11/08         $75,867.80
    Resource
    Becker      1/22/08        $549,545.00
    Electric
    United      1/29/08         $97,664.40
    Sprinkler
    7
    On May 8, 2008, Jack Bays sent a letter to New Life
    terminating the April 26, 2006 construction contract.   Between
    June 19 and July 14, 2008, all Contractors timely filed
    complaints in the Circuit Court of Prince William County
    ("circuit court") against the Lenders and Stewart Title.
    C.    Proceedings before the Commissioner of Accounts and the
    Circuit Court
    By Decree of Reference and Order of Consolidation and
    Reference entered by the circuit court in late 2008 and early
    2009, Prince William County Commissioner in Chancery Robert J.
    Zelnick ("Commissioner Zelnick") held a proceeding from
    January 11-15, 2010, to address "only issues concerning
    enforceability" of the mechanics' liens.   The issues of
    valuation and priority were "deferred to a subsequent hearing,
    if needed."
    On May 31, 2011, Commissioner Zelnick filed his report.
    He found that:
    •   All necessary parties were made defendants in the
    Contractors' suits to enforce their mechanics' liens;
    •   Jack Bays did not violate the 90-day rule embodied in
    Code § 43-4;
    •   Jack Bays complied with the 150-day rule embodied in Code
    § 43-4;
    •   The other Contractors complied with the 150-day rule
    embodied in Code § 43-4;
    •   Jack Bays did not include charges for labor and materials
    prior to May 1, 2007;
    •   Jack Bays acted reasonably in waiting until September 28,
    2007 to recommend ceasing current work on the New Life
    project, and therefore did not fail to mitigate damages;
    8
    •   The mechanics' liens of Century Contracting, Adrian L.
    Merton, Scaffold Resource, Becker Electric, United
    Sprinkler, General Glass, Miller Construction, Structural
    Steel, Sparkle Painting, Virginia Paving, and Clover
    Contracting were valid and enforceable;
    •   Capital Contracting's mechanics' lien was extinguished;
    •   The liens of Samaha Associates, Loudoun Sheet Metal
    Company, and Phillip C. Clarke, Incorporated, were not
    enforceable;
    •   A priority of liens existed, with the subcontractors
    holding top priority, Jack Bays second priority, the
    Lenders third priority, and a September 2008 Jack Bays
    Deed of Trust and Trustee for General Mortgage
    Bondholders holding fourth priority; and
    •   The property should be sold to satisfy the outstanding
    liens.
    On June 10, 2011, Citizens Business Bank, Celtic Bank,
    and Glasser & Glasser filed exceptions to the report.   The
    Lenders filed a Joint Brief in Support of Exceptions to the
    report.   Their exceptions primarily focus on the
    Commissioner's interpretation of Code § 43-4 concerning filing
    procedures and lien value.   Additionally, the Lenders asserted
    that the Contractors failed to mitigate damages during their
    October 2007 work and that they also did not include necessary
    parties to their action to enforce the liens.   Finally, the
    Lenders disputed the validity of some of the subcontractors'
    liens.
    The circuit court issued a final order on November 18,
    2011, rejecting the Lenders' arguments in their entirety.     The
    circuit court incorporated its October 14, 2011 letter opinion
    9
    into its final order.     The circuit court further ordered that
    the property be sold at public auction to the highest bidder,
    with proceeds of the sale to be applied in satisfaction of the
    mechanics' liens in the order of priority established by
    Commissioner Zelnick.     Lenders timely filed notices of and
    petitions for appeal, raising fourteen assignments of error.
    We awarded an appeal.
    II.   Analysis
    A.     Standard of Review
    In their first assignment of error, the Lenders assert
    that "[t]he trial court lacked subject matter jurisdiction as
    necessary parties were not joined in any of the lawsuits which
    are the subject matter of this appeal."      This assignment
    involves a question of law and is reviewed de novo.       Conyers
    v. Martial Arts World of Richmond, Inc., 
    273 Va. 96
    , 104, 
    639 S.E.2d 174
    , 178 (2007).
    For the remaining assignments of error, the Lenders
    challenge the circuit court's conclusion that Commissioner
    Zelnick properly determined issues related to the Contractors'
    liens.   "When a circuit court approves a report by a
    commissioner in chancery who heard evidence ore tenus, we will
    affirm the court's decree unless it is plainly wrong or
    without evidence to support it."       Amstutz v. Everett Jones
    Lumber Corp., 
    268 Va. 551
    , 558, 
    604 S.E.2d 437
    , 441 (2004)
    10
    (citing Shepherd v. Davis, 
    265 Va. 108
    , 117, 
    574 S.E.2d 514
    ,
    519 (2003); Snyder Plaza Props., Inc. v. Adams Outdoor Adver.,
    Inc., 
    259 Va. 635
    , 641, 
    528 S.E.2d 452
    , 456 (2000)).       "[W]e
    look at the commissioner's conclusions, as approved by the
    circuit court, and determine whether the conclusions are
    supported by credible evidence."      Id. (citing Chaney v.
    Haynes, 
    250 Va. 155
    , 158, 
    458 S.E.2d 451
    , 453 (1995)); see
    also Code § 8.01-610.     However, this standard "is not
    applicable to pure conclusions of law contained in the
    report," which are reviewed de novo.      Hill v. Hill, 
    227 Va. 569
    , 577, 
    318 S.E.2d 292
    , 296 (1984) (citations omitted).
    B.     Necessary Parties
    Suits to enforce mechanics' liens must name all necessary
    parties within the time set forth by Code § 43-17, and a
    failure to name a necessary party as defendant requires
    dismissal.   Mendenhall v. Douglas L. Cooper, Inc., 
    239 Va. 71
    ,
    72, 75, 
    387 S.E.2d 468
    , 469-70 (1990).
    Citing James T. Bush Constr. Co. v. Patel, 
    243 Va. 84
    ,
    87-88, 
    412 S.E.2d 703
    , 704-05 (1992), the Lenders contend that
    "[i]n the context of mechanic[s'] lien litigation, necessary
    parties include the owner of the property, and both the
    trustee and beneficiaries of a deed of trust secured by the
    property."   The beneficiaries here, the Lenders assert, are
    the Bondholders under the Trust Indenture.      Because the
    11
    Contractors did not name the Bondholders, their suits must be
    dismissed, according to the Lenders.
    The Contractors rejoin that this Court stated otherwise
    in Michael E. Siska Rev. Trust v. Milestone Development, LLC,
    
    282 Va. 169
    , 181, 
    715 S.E.2d 21
    , 27 (2011), where we held that
    "the necessary party doctrine does not implicate subject
    matter jurisdiction."   They also allege that "[p]arties filing
    mechanic[s'] liens are entitled to rely on the land records,"
    citing Blue Ridge Constr. v. Stafford Dev. Grp., Ltd., 
    244 Va. 361
    , 365, 
    421 S.E.2d 199
    , 201 (1992) in support.    The
    Contractors finally assert that Glasser & Glasser, as Trustee
    for the Bondholders, is in position to protect the
    Bondholders' interests.
    In their Reply, the Lenders argue that Siska "does not
    address statutorily created causes of action such as
    mechanics' liens, or modify the clear line of authority of
    Bush v. Patel."   The Lenders also claim that the rule
    concerning whether parties may rely on land records is not the
    law in Virginia, citing a 1956 case, Chavis v. Gibbs, 
    198 Va. 379
    , 
    94 S.E.2d 195
    , in support.     Finally, the Lenders state in
    a footnote that "[the Contractors'] reliance upon the powers
    of the Trustee under the Trust Indenture to take action to
    prevent any impairment of the Trust Estate is misplaced as
    12
    they are no different in kind than the power any trustee has
    to take action to protect the Trust property."
    In Siska, we stated that "the necessary party doctrine
    does not implicate subject matter jurisdiction. If the
    doctrine involved subject matter jurisdiction, the absence of
    a necessary party would, by definition, deprive the court of
    the power to render a decree. There could not logically be
    exceptions."   282 Va. at 177, 715 S.E.2d at 25.   We observed
    that questions of personal jurisdiction and the ability to
    "render complete relief" guide the decision whether to
    exercise subject matter jurisdiction.   Id.
    However, Siska's rule is not applicable in the present,
    limited context.   As "purely a creature of statute," Wallace
    v. Brumback, 
    177 Va. 36
    , 40, 
    12 S.E.2d 801
    , 802 (1941), a
    mechanics' lien must be "perfected within the proper time and
    in the proper manner, as outlined by the statute, [or] it is
    lost."   American Standard Homes Corp. v. Reinecke, 
    245 Va. 113
    , 119, 
    425 S.E.2d 515
    , 518 (1993) (internal quotation marks
    omitted).
    The Lenders are correct that both trustees and trust
    beneficiaries to a deed of trust are necessary parties to a
    mechanics' lien suit.   See Bush, 243 Va. at 87, 412 S.E.2d at
    704; Walt Robbins, 232 Va. at 47, 348 S.E.2d at 226.     Although
    Bush did not concern the question whether a beneficiary of a
    13
    trust indenture was a necessary party, its principles remain
    clear: a party must name a beneficiary to the deed of trust
    because that beneficiary has "a substantial interest in being
    given the opportunity to challenge the validity of the
    mechanic[s'] lien, or otherwise to litigate the elements of
    the lien."   243 Va. at 88, 412 S.E.2d at 705.   Because this
    purpose is fulfilled by the deed of trust beneficiaries, it
    follows that the beneficiaries of a trust indenture are not
    necessary parties.   As a named beneficiary of the Deed of
    Trust and as a Trustee for the Bondholders, naming Glasser &
    Glasser is sufficient to comply with the requirements of Bush.
    Also, we note that there is little evidence supporting
    the Lenders' contention that the Contractors were aware of the
    Bondholders' identity or that the Contractors could have
    inquired to determine it.   The Trust Indenture states that
    Reliance Trust Company would maintain in Georgia a bond
    register containing names, addresses, bond numbers, and
    amounts of purchase of all issued bonds.   However, Reliance
    had no obligation to keep the list accurate.     ("[Reliance]
    shall be under no responsibility with regard to the accuracy
    of [the bond registration] list.").   Nor could the Contractors
    have obtained the information on the list without the express
    written consent of another entity, California Plan of Church
    Finance, Inc.   Even without regard to the Bush precedent, the
    14
    Contractors could not be expected to accurately ascertain the
    identity of bondholders under these circumstances.     A rule to
    the contrary would render compliance with the statute
    effectively impossible.
    C.   Code § 43-4
    1.   The Ninety-Day Rule
    In relevant part, Code § 43-4 provides:
    A general contractor, or any other lien
    claimant under §§ 43-7 and 43-9, in order to
    perfect the lien given by § 43-3, provided such
    lien has not been barred by § 43-4.01 C, shall
    file a memorandum of lien at any time after the
    work is commenced or material furnished, but not
    later than 90 days from the last day of the
    month in which he last performs labor or
    furnishes material, and in no event later than
    90 days from the time such building, structure,
    or railroad is completed, or the work thereon
    otherwise terminated.
    Therefore, each contractor had ninety days from the end of the
    last month in which it last performed labor or furnished
    material to file a lien, unless work on the church was
    complete or "otherwise terminated."
    It is not disputed that as of the date of Jack Bays'
    September 28, 2007 letter, the church was incomplete.      Nor is
    it disputed that Jack Bays recorded its lien on December 28,
    2007.    The Lenders allege that although work was not complete,
    Jack Bays' September 28 letter "otherwise terminated" work on
    the church, beginning the ninety-day filing limitation.     If
    15
    this is true, then we must dismiss Jack Bays' suit: The
    difference between September 28 and December 28 is ninety-one
    days.    If it is not, then Jack Bays earns the benefit of
    starting the ninety-day clock on the last day of September,
    two days later.    Importantly, the difference between the last
    day in September and December 28 is eighty-eight days.
    Accordingly, in order for Jack Bays to have timely filed its
    lien, its letter of September 28, 2007, cannot have operated
    to "otherwise terminate[]" work on the church, as the Lenders
    insist.
    The Lenders cite to Mills v. Moore's Super Stores, Inc.,
    
    217 Va. 276
    , 279, 
    227 S.E.2d 719
    , 722 (1976) and Northern
    Virginia Savings and Loan Ass'n v. J.B. Kendall Co., 
    205 Va. 136
    , 
    135 S.E.2d 178
     (1964), in support of their argument.    In
    the latter case, they allege, this Court found that a
    contractor's work had "otherwise terminated" when work on the
    project came to a "standstill" due to the property owner's
    lack of financing and the contractor's failure to provide
    labor or material to the job.     See J.B. Kendall Co., 205 Va.
    at 147-48, 135 S.E.2d at 186.    The Lenders conclude that J.B.
    Kendall Co. should apply here because work came to a
    standstill after September 28, 2007.
    Jack Bays argues that September 30, 2007, is the proper
    date to use for the 90-day deadline imposed by Code § 43-4,
    16
    because the statute gives a claimant "90 days from the last
    day of the month in which he last performs labor or furnishes
    material."   Jack Bays claims that Virginia law on the matter
    is contrary to the Lenders' assertion; "the law provides that
    all activity must have come to an end in order for the work to
    be deemed terminated as of September 28, 2007[,] which plainly
    did not occur here."   See Mills, 217 Va. at 276, 227 S.E.2d at
    719; J.B. Kendall Co., 205 Va. at 148, 135 S.E.2d at 187.
    The Commissioner concluded that
    [t]he Supreme Court has recognized that the 90-
    day time period "begins to run from the time
    the entire building is completed or work
    thereon is otherwise terminated, and not
    necessarily from the time the general
    contractor has completed his specific contract
    to furnish labor or materials, or both." [J.B.
    Kendall Co., 205 Va. at 144, 135 S.E.2d at
    184]. In light of the uncontroverted fact that
    the building was never completed, and that
    several subcontractors, such as Becker Electric
    and Scaffold Resources, Inc. continued to work
    on the Project in October, 2008, your
    Commissioner finds that Jack Bays' lien does
    not violate the 90-day rule.
    The circuit court "agree[d] with the Commissioner that the
    evidence established that Jack Bays properly used the last day
    of September, 2007, to begin calculating the ninety-day filing
    deadline."
    We held in Mills that "otherwise terminated" under Code
    § 43-4 meant when work under the contract ceased.   217 Va. at
    279, 227 S.E.2d at 722.   There, the contract ceased upon the
    17
    combination of several factors: financial difficulties
    encountered by the general contractor, uncontroverted evidence
    that neither the general contractor nor any subcontractors
    worked at the site after the termination date, and the owner's
    firing of the general contractor.     Id.   Here, unlike in Mills,
    work did not stop at the construction site; several
    subcontractors remained and performed contract work through
    October.    Jack Bays also terminated its involvement in May
    2008.    Therefore, it cannot be said that "work [on the
    structure was] otherwise terminated" under Code § 43-4, and
    the circuit court was not plainly wrong in upholding the
    Commissioner's ruling that Jack Bays complied with the ninety-
    day rule.
    2.   The 150-day Rule
    In relevant part, Code § 43-4 provides:
    The lien claimant may file any number of
    memoranda but no memorandum filed pursuant to
    this chapter shall include sums due for labor or
    materials furnished more than 150 days prior to
    the last day on which labor was performed or
    material furnished to the job preceding the
    filing of such memorandum.
    Accordingly, whether Jack Bays offered sufficient proof to
    conform to the 150-day rule prescribed by Code § 43-4 is a
    factual inquiry.    If a claimant violates this rule, their
    mechanics' lien is unenforceable.     Carolina Builders Corp. v.
    Cenit Equity Co., 
    257 Va. 405
    , 411, 
    512 S.E.2d 550
    , 553 (1999).
    18
    i. Does the Rule Provide for a Unitary Date
    Range for all Contractors?
    The Lenders first claim that the 150-day rule has a
    unitary date range for all contractors.
    As we stated in Carolina Builders, 257 Va. at 409, 512
    S.E.2d at 551, the 150-day rule
    specifies that "[t]he lien claimant may file any
    number of memoranda but no memorandum . . .
    shall include sums due for labor or materials
    furnished more than 150 days prior to the last
    day on which labor was performed or material
    furnished to the job preceding the filing of
    such memorandum."
    Id. (quoting Code § 43-4) (emphasis added);    see also Smith
    Mt. Bldg. Supply, LLC v. Windstar Props., LLC, 
    277 Va. 387
    ,
    390-91, 
    672 S.E.2d 845
    , 846 (2009).    The Lenders' argument
    that the 150-day rule does not apply separately for each
    claimant ignores the language of the statute, which plainly
    states that the period is calculated according to the actions
    of the lien claimant.   Code § 43-4.   Because time is
    calculated in this fashion, it cannot be "unitary" for all
    lien claimants.
    ii. Propriety of the September 28, 2007 End Date
    The Lenders allege that, even if the 150-day rule is not
    unitary, Jack Bays failed to comply with the rule because it
    used the wrong end date, September 28, 2007, from which it
    looked back.   Because the circuit court agreed with
    19
    Commissioner Zelnick's conclusion that Jack Bays complied with
    the 150-day rule prescribed by Code § 43-4, the Lenders must
    show that the decision was plainly wrong or without evidence
    to support it.    Amstutz, 268 Va. at 558, 604 S.E.2d at 441.
    Jack Bays' Site Superintendent for the New Life project,
    Steven Wise ("Wise"), supervised the work site during the
    September-November 2007 period.      The same day that Jack Bays
    informed its subcontractors to cease work via mail and fax,
    September 28, 2007, Wise began making phone calls to all
    subcontractors to inform them that, per instructions from
    Fuechsel, Jack Bays was "shut[ting active work on the project]
    down."   The afternoon of September 28, 2007, Wise made no
    fewer than nine phone calls to various subcontractors,
    explaining to them that Jack Bays was "demobilizing" and that
    the subcontractors should not return to the work site the
    following week and that if they did so, it would be at their
    own risk.
    Wise also vividly recounted his interaction with
    subcontractors and efforts related to Jack Bays' work at the
    site from October 1 through November 16, 2007, none of which
    work involved labor performed "to the job" – that is,
    construction of the church.   Fuechsel's testimony supported
    Wise's account.   The Lenders offered no controverting
    evidence, instead asserting that "value" was added to the
    20
    project through Jack Bays' labor after September 28, 2007, and
    that this added value precluded Jack Bays from using September
    28 as the end point for purposes of the 150-day rule.
    The Lenders' arguments to both Commissioner Zelnick and
    the circuit court on this issue were rejected.      Although
    several subcontractors added value to the project after
    September 28, 2007, the Commissioner concluded that the same
    was not true for Jack Bays.
    This Court "look[s] at the commissioner's conclusions, as
    approved by the circuit court, and determine[s] whether the
    conclusions are supported by credible evidence."      Amstutz, 268
    Va. at 558, 604 S.E.2d at 441.    Whether Jack Bays showed it
    complied with the 150-day rule was a factual inquiry for
    Commissioner Zelnick to decide.       Based on the testimony of
    Wise and Fuechsel, Jack Bays sufficiently demonstrated to the
    Commissioner and the circuit court that the last day it
    performed labor or furnished material to the job was September
    28, 2007.
    iii. Propriety of Fees Included in Jack Bays' Lien
    Jack Bays must also show that it did not include in its
    lien "sums due for labor or materials furnished" before May 2,
    2007, the date 150 days prior to September 28, 2007.      Code
    § 43-4.
    21
    The Lenders argue that Jack Bays' lien is invalid because
    it includes sums for work performed prior to May 2, 2007, the
    beginning of the 150-day period.
    First, the Lenders claim that
    [p]rior to May 1, 2007, Jack Bays had
    clearly not billed New Life for all of the work
    Miller Construction had performed to date. In
    the following months, Jack Bays' requisitions
    to New Life accounted for these previous
    shortcomings, and thus included sums
    attributable to work performed prior to May 1,
    2007. Therefore, because the liens were based
    on these later billings, they too included sums
    for work done prior to May 1, 2007.
    The Lenders offered the testimony of Thomas Chappell as
    an expert witness in construction accounting to support their
    argument before the Commissioner.    Chappell testified that
    between December 2006 and April 2007 Miller Construction
    billed $424,624 to Jack Bays, and Jack Bays billed only
    $327,362 to New Life for work that Chappell believed was
    attributable to Miller Construction.   Jack Bays subsequently
    charged New Life amounts varying from the monthly value
    invoiced to it by Miller Construction through July 2007.
    According to Chappell, Jack Bays' May 2007 billing
    appears to be a catch-up for the under-billing
    in the prior months which would mean that costs
    incurred, labor and materials incurred in the
    prior period are now being drawn into the May
    requisition by Jack Bays, which is also
    included as part of the basis for the
    mechanic[s'] lien.
    22
    It is true that Jack Bays invoiced New Life different
    values for masonry work – Miller Construction's job – than
    Miller Construction invoiced Jack Bays a month prior.   Jack
    Bays argues that the discrepancy exists because it billed New
    Life under a stipulated sum agreement, rather than a cost-plus
    contract.   Semon Samaha ("Samaha"), the project architect,
    described before the Commissioner the difference between the
    two billings:
    Well, the cost-plus is somewhat open-ended, I
    mean the contractor is providing a fee
    basically to do the work and then whatever
    costs are incurred plus that fee is what the
    owner pays, so part of the problem is trying to
    determine which cue [sic] the costs go in. And
    I know that one of the projects that we did a
    while back, there was a dispute, for example,
    about whether a saw that the contractor
    purchased should be part of the cost or part of
    the contractor's fee and whether it should have
    just been a rental charge, and so it becomes
    much more cumbersome, where a stipulated sum,
    the amount is agreed upon ahead of time and
    from then on, it's just based on how much of
    the work gets done as a percentage of that
    amount.
    Chappell also acknowledged that differences exist between
    stipulated sum agreements and cost-plus agreements.
    Fuechsel, who qualified before the Commissioner as an
    expert witness in commercial general contracting with a sub-
    specialty in new church construction, testified that
    requisitions were prepared around the 25th of each month and
    projected through the end of that month.   Jack Bays
    23
    "reasonably assume[d]" progress made in various construction
    areas as compared to the prior billing period, with the
    percentage increase serving as the basis for the requisition.
    This process is consistent with the April '06 Agreement and
    the AIA A201-1997 General Conditions ("General Conditions")
    incorporated therein.   Fuechsel testified that subcontractor
    billings were used to "confirm our percent complete at the
    time of each monthly invoice."    Additionally, all requisitions
    were submitted to and approved by Samaha.   Samaha could only
    approve requisitions for payment based on the value of work
    completed beyond the prior month's performance, not by a
    subcontractor's individual billing.
    Commissioner Zelnick was persuaded by Jack Bays'
    argument, finding that its monthly requisitions "were not
    formulated based on costs incurred from the subcontractors and
    suppliers, but rather were the product of Jack Bays'
    reasonable estimation of the value added to the project with
    that billing period."   He also found that Chappell's testimony
    was unpersuasive due to the differences between his testimony
    and the nature of a stipulated sum agreement.   The circuit
    court reviewed and accepted these findings without
    qualification.
    Whether Jack Bays proved that it did not include in its
    lien Miller Construction's sums due prior to May 1 was a
    24
    factual inquiry.   Although the Lenders offered expert
    testimony and cross examined Jack Bays' witnesses regarding
    the relationship between subcontractor billings and Jack Bays'
    requisitions, the Commissioner found that Jack Bays did not
    include charges for Miller Construction's work in its lien.
    The circuit court accepted these findings.   Based upon the
    record, we cannot say that these findings were plainly wrong
    or without evidence to support them.
    The Lenders also argue that the trial court erred in its
    conclusion that no charges for labor or material provided
    before May 2, 2007, were included in Jack Bays' lien.
    Fuechsel testified regarding how Jack Bays calculated the
    proper value for the 150-day period between May 2, 2007, and
    September 28, 2007.   This process involved using the
    requisitions from May to September to ascertain the value of
    the lien.   However, because May 1, 2007, was included in the
    May requisition but was not validly part of the lien, Fuechsel
    stated that Jack Bays omitted this day from its calculation.
    The company did so by taking the total number of work days in
    May and dividing by the total amount invoiced to come up with
    a per-day value of labor performed or materials furnished, and
    then subtracted a per-day value in an effort to comply with
    Code § 43-4.
    Referring to May 1, Fuechsel testified:
    25
    Looking at the daily reports, there wasn't, you
    know, it was kind of business as usual, it
    wasn't a big delivery day, no major activities
    or unusual activities happened, so we took the
    number of work days in May, which was twenty-
    one, divided it into the total May invoice, and
    deleted what essentially mathematically came out
    to one day. . . .
    Commissioner Zelnick found that testimony on this point was
    offered without contradiction.     The circuit court concurred
    with his assessment.     This factual determination was not
    plainly wrong or without evidence to support it.
    Jack Bays sufficiently proved to both the Commissioner
    and the circuit court that it did not include sums due for
    labor provided or material furnished before May 2, 2007, nor
    did it perform labor or furnish material after September 28,
    2007.    Accordingly, we hold that Jack Bays properly perfected
    its lien under Code § 43-4.
    It may appear inconsistent to use September 30, 2007, as
    the relevant date from which to analyze Jack Bays' compliance
    with Code § 43-4 for purposes of the 90-day calculation, and
    September 28, 2007, as the relevant date from which to analyze
    Jack Bays' compliance with Code § 43-4 for purposes of the
    150-day calculation.     These distinct dates are used because
    Code § 43-4 provides that in the circumstances presented by
    this case, the proper date to use when evaluating compliance
    with the 90-day rule is the end of the relevant month where a
    26
    contractor last works on a structure, when that structure is
    not fully completed.    The 150-day rule, on the other hand,
    requires that courts calculate time based on when the
    contractor last performs labor or furnishes material – not
    necessarily at the end of a month.
    3. Duty to Mitigate
    The Lenders contend that Jack Bays was obligated to
    mitigate its damages from May 25, 2007 onward, when New Life
    made its last payment to the contractor.      The Lenders also
    argue that Jack Bays never requested assurances from New Life
    that payments would be forthcoming, and instead accrued
    millions in charges when it knew it would not receive payment.
    Jack Bays notes that "[t]he failure to mitigate defense
    asserted by [the Lenders] apparently has never been applied in
    the mechanic[s'] lien context – the Lenders have been
    challenged to produce such authority, but it has never been
    forthcoming."   It asserts that the defense is contractual in
    nature, and that the Lenders have no grounds to assert the
    mitigation defense because they were not parties to the
    contract.   During oral argument, counsel for Jack Bays also
    argued that Code § 43-4 already contains a "mitigation-like"
    provision, the 150-day rule, which limits the fees a lien
    claimant may request.   Finally, in the event the Lenders can
    27
    raise a mitigation defense, Jack Bays asserts that its actions
    were reasonable under the circumstances.
    Assuming without deciding that the Lenders may raise the
    defense of failure to mitigate, Jack Bays took reasonable
    measures under the circumstances.   Specifically, Jack Bays
    introduced during the Commissioner's hearing evidence stating
    that in July 2007 New Life was in "final approval for a
    $20,000,000.00 (Twenty Million Dollar) loan."   It was also
    uncontroverted that Bishop Reeves told Fuechsel that New Life
    would pay for Jack Bays' prior, current, and future work in
    early August 2007, and if not then, shortly thereafter.    When
    it became apparent that additional funding would not be
    obtained, Jack Bays acted promptly and decisively.   The
    Commissioner and the trial court did not err in holding that
    Jack Bays properly mitigated its damages.
    Accordingly, the circuit court was not plainly wrong in
    failing to rule that Jack Bays was required to mitigate its
    damages.
    4. Subcontractor Liens
    The Lenders argue that if this Court determines that work
    on the structure "otherwise terminated" on September 28, 2007,
    then Scaffold Resource, Becker Electric, and United Sprinkler
    were untimely in filing their liens on January 11, 22, and 29,
    2008 respectively.
    28
    Because we find that the circuit court was not plainly
    wrong in concluding that work on the church did not terminate
    on September 28, 2007, and because we have held that the
    ninety-day deadline applies to each individual contractor,
    rather than the group collectively, United Masonry Inc. of Va.
    v. Riggs Nat'l Bank of D.C., 
    233 Va. 476
    , 479, 
    357 S.E.2d 509
    ,
    511 (1987) ("the [ninety-day] filing deadline [is] dependent
    upon each contractor's own activity"), the validation of the
    mechanics' liens of Scaffold Resource, Becker Electric, and
    United Sprinkler was not plainly wrong or without evidence to
    support it.
    D.     The Stipulation, Lien Priority, and Sale of Land
    1. The Stipulation
    The Lenders argue that at the January 2010 hearing before
    Commissioner Zelnick, "all parties stipulated, and the
    Commissioner ruled, that the hearing was confined to the issue
    of the enforceability of the liens, and all other issues of
    valuation and priority would be deferred to a subsequent
    hearing."   Relying on Bauer v. Harn, 
    223 Va. 31
    , 36, 
    286 S.E.2d 192
    , 194 (1982), they contend that "[s]tipulations are
    definitive of the issues" and are binding.   Unfortunately, the
    Lenders omit from their argument that the Commissioner's
    stipulation was contingent on future hearings being necessary.
    29
    The parties agreed that Commissioner Zelnick could
    address issues of priority and valuation at the January 2010
    hearing, and that those issues would be "deferred to a
    subsequent hearing, if needed."     The Commissioner reiterated
    the conditional nature of future hearings on priority and
    valuation by stating that a hearing on those matters would
    occur only if necessary.   For this reason, the stipulation did
    not require that further hearings be held.
    2. Lien Priority
    The Lenders argue that no evidence concerning lien
    priority was submitted to Commissioner Zelnick during the
    five-day hearing.   Consequently, they claim, the Commissioner
    and circuit court were plainly wrong in determining that the
    Contractors' liens had priority over the Lenders' Deed of
    Trust.
    Jack Bays argues that evidence of lien priority was
    introduced.   Various subcontractors claim that because Jack
    Bays commenced its contract work on the church before the Deed
    of Trust was recorded, "any mechanic[s'] liens arising out of
    that contract take priority over the Lenders' Deed of Trust."
    Commissioner Zelnick reviewed the validity of the liens
    filed by each of the dozen-plus claimants and concluded that
    "the Claimants' liens, with the exception of the lien filed by
    Capital Contracting, are valid and enforceable, [and] have
    30
    priority over the . . . Deed of Trust."   The Commissioner
    reasoned that "[p]ursuant to Virginia Code § 43-23, there is
    no priority among mechanic[s'] liens, 'except that the lien of
    a subcontractor shall be preferred to that of his general
    contractor. . . .' "   Accordingly, the Commissioner gave
    priority to subcontractor liens over Jack Bays' lien, and gave
    priority to Jack Bays' lien over the Lenders' lien.    See Code
    § 43-23.
    In relevant part, Code § 43-21 states that
    [n]o lien or encumbrance upon the land created
    before the work was commenced or materials
    furnished shall operate upon the building or
    structure erected thereon, or materials
    furnished for and used in the same, until the
    lien in favor of the person doing the work or
    furnishing the materials shall have been
    satisfied; nor shall any lien or encumbrance
    upon the land created after the work was
    commenced or materials furnished operate on the
    land, or such building or structure, until the
    lien in favor of the person doing the work or
    furnishing the materials shall have been
    satisfied.
    Of course, a "lien" or "encumbrance" upon land may include a
    deed of trust.   See Bayview Loan Servicing, LLC v. Simmons,
    
    275 Va. 114
    , 119, 
    654 S.E.2d 898
    , 900 (2008); see also
    Woodington Electric, Inc. v. Lincoln Sav. & Loan Ass'n, 
    238 Va. 623
    , 630, 
    385 S.E.2d 872
    , 875 (1989) ("the mechanic[s']
    lien 'leaps to the head of the class,' coming before virtually
    every other lien.").   With the possible exception of priority
    31
    concerning the land (discussed infra), the Commissioner was
    not plainly wrong or without evidence to support his
    determination concerning priority.
    3. Sale of the Land
    The Lenders also assert that, under Code § 43-3, a
    mechanics' lien applies only to " 'so much land therewith as
    shall be necessary for the convenient use and enjoyment
    thereof.' "   See Code § 43-3.   They maintain that there was
    "no basis for suggesting th[at] all of the land is necessary
    for the use and enjoyment of the improvements."    They argue
    that "[i]n the case of the property at issue, the uncompleted
    church sits on approximately 22 acres of land.    The
    uncompleted structure accounts for only 125,000 square feet
    (or 2.8 acres)."
    Jack Bays suggests that objections to the sale of the
    entire parcel of land were not preserved.    At the hearing on
    exceptions to the Commissioner's report, counsel for Citizens
    Business Bank stated to the circuit court, "I don't see how
    the property can be sold at this point because it is clear
    from the record that the way the hearing proceeded, those
    issues were not determined, and by agreement they were not
    determined.   They were deferred."    The question of objection
    to the sale of the entire parcel was adequately preserved.
    32
    Because of the significant total sum of the mechanics'
    liens, Commissioner Zelnick determined that a sale of the land
    was necessary to satisfy the liens.   See Code § 43-3.     The
    Commissioner stated that proceeds remaining after the sale and
    satisfaction of the liens would be payable to New Life.
    Code § 43-3(A) states as relevant here that
    [a]ll persons performing labor or furnishing
    materials of the value of $150 or more,
    including the reasonable rental or use value of
    equipment, for the construction, removal, repair
    or improvement of any building or structure
    . . . shall have a lien . . . upon such building
    or structure, and so much land therewith as
    shall be necessary for the convenient use and
    enjoyment thereof.
    (emphasis added).
    Commissioner Zelnick recommended the sale of the twenty-
    two acre property because there were liens totaling
    approximately $32,360,000, and sale of the entire parcel was
    necessary to pay all of the liens.    However, not all of these
    liens were mechanics' liens.   Additionally, sale of the
    property to satisfy a mechanics' lien may only extend to "so
    much [of the] land therewith as shall be necessary for the
    convenient use and enjoyment thereof."   Code § 43-3.    The
    record does not reflect evidence presented on this question.
    Sale of the entire property may or may not be proper.
    Determination of this question may affect priority
    determination as it applies to the land.
    33
    III. Conclusion
    For the reasons stated, we hold that on this record,
    Commissioner Zelnick and the circuit court erred in approving
    the sale of the entire parcel of land to satisfy the
    Contractors' liens, where no evidence was introduced to
    support this decision.   Accordingly, we will affirm in part
    and reverse in part the judgment of the circuit court and
    remand for further proceedings consistent with this opinion.
    Affirmed in part,
    reversed in part,
    and remanded.
    34