Attorney General v. State Corp. Comm'n ( 2014 )


Menu:
  • PRESENT: Kinser, C.J., Lemons, Millette, Mims and McClanahan,
    JJ., and Lacy and Koontz, S.JJ.
    OFFICE OF THE ATTORNEY GENERAL,
    DIVISION OF CONSUMER COUNSEL
    OPINION BY
    v.   Record Nos. 131872, 131873  JUSTICE ELIZABETH A. McCLANAHAN
    September 12, 2014
    STATE CORPORATION COMMISSION, ET AL.
    FROM THE STATE CORPORATION COMMISSION
    In these consolidated appeals, we consider whether the State
    Corporation Commission (“the Commission”) properly interpreted
    Code § 56-585.1(A)(6) (“Subsection (A)(6)”) to allow Virginia
    Electric and Power Company, d/b/a Dominion Virginia Power
    (“Dominion”), to recover an enhanced rate of return on common
    equity for transmission infrastructure associated with the
    Brunswick County Power Station and included in the Subsection
    (A)(6) rate adjustment clause for that facility.
    I.   Facts and Proceedings
    In 2012, Dominion filed an application with the Commission
    for certificates of public convenience and necessity approving
    construction of (1) the Brunswick County Power Station, an
    approximately 1,358 megawatt natural gas-fired combined cycle
    electric generating facility to be located in Brunswick County,
    and (2) transmission interconnection facilities associated with
    the Brunswick generation plant, including new transmission lines,
    two new switching stations, and facilities necessary to “tap”
    existing transmission lines in Brunswick and Greensville
    Counties.   The estimated costs of the Brunswick project total
    $1.27 billion, including approximately $89.1 million in
    associated transmission infrastructure costs.
    Pursuant to Code § 56-585.1(A)(6), Dominion’s application
    also sought approval of a rate adjustment clause (“RAC”),
    designated as Rider BW, to recover the costs of the Brunswick
    project and infrastructure associated therewith, “including the
    transmission facilities necessary to interconnect the facility
    with [Dominion’s] transmission system.” 1   At the time of its
    1
    At the time of Dominion’s application, Subsection
    (A)(6) read, in relevant part, as follows:
    To ensure a reliable and adequate supply of
    electricity, to meet the utility’s projected
    native load obligations and to promote
    economic development, a utility may at any
    time, after the expiration or termination of
    capped rates, petition the Commission for
    approval of a rate adjustment clause for
    recovery on a timely and current basis from
    customers of the costs of . . . one or more
    other generation facilities. . . .
    A utility that constructs any such facility
    shall have the right to recover the costs of
    the facility, as accrued against income,
    through its rates, including projected
    construction work in progress, and any
    associated allowance for funds used during
    construction, planning, development and
    construction costs, life-cycle costs, and
    costs of infrastructure associated therewith,
    plus, as an incentive to undertake such
    projects, an enhanced rate of return on common
    equity calculated as specified below.
    2
    application, Dominion’s general rate of return on common equity
    (“ROE”) authorized by the Commission during Dominion’s 2011
    biennial rate review was 10.4%.   As part of Rider BW, Dominion
    sought a 100 basis point (1%) enhancement on its general ROE for
    the projected construction work in progress period, the
    associated allowance for funds used during the construction
    period, and the first fifteen (15) years of the service life of
    The costs of the facility, other than return
    on projected construction work in progress and
    allowance for funds used during construction,
    shall not be recovered prior to the date the
    facility begins commercial operation.
    Such enhanced rate of return on common equity
    shall be applied to allowance for funds used
    during construction and to construction work
    in progress during the construction phase of
    the facility and shall thereafter be applied
    to the entire facility during the first
    portion of the service life of the facility .
    . . .
    Such enhanced rate of return on common equity
    shall be calculated by adding the basis points
    specified in the table below to the utility’s
    general rate of return, and such enhanced rate
    of return shall apply only to the facility
    that is subject of such rate adjustment clause
    . . . .
    The basis points to be added to the utility’s
    general rate of return to calculate the
    enhanced rate of return on common equity . . .
    shall vary by type of facility, as specified
    in the following table.
    Code § 56-585.1(A)(6) (as amended by 2012 Acts ch.
    435)(emphasis added).
    3
    the Brunswick facility. 2   Dominion proposed applying the resulting
    11.4% enhanced ROE to the costs of the generation facility as
    well as the costs of associated transmission and non-transmission
    infrastructure.
    After receiving Dominion’s application, the Commission’s
    staff filed a motion for ruling asking the Commission to rule
    that the enhanced ROE authorized by Subsection (A)(6) “applies
    only to the ‘facility,’ i.e., the generating plant, and not to
    ‘infrastructure associated therewith[.]’”    The Office of the
    Attorney General’s Division of Consumer Counsel (“Consumer
    Counsel”) and the Virginia Committee for Fair Utility Rates each
    filed responses supporting the Staff’s interpretation of
    Subsection (A)(6).
    Dominion filed a response opposing the Staff’s motion,
    arguing that the Staff’s position is inconsistent with the plain
    language of Subsection (A)(6), which establishes that costs of
    associated infrastructure are “costs of the facility.”    Moreover,
    Dominion argued that the Staff’s interpretation of Subsection
    2
    Subsection (A)(6) includes a table designating the number
    of basis points to be added in calculating the enhanced ROE
    recoverable by a utility based on the type of generation
    facility constructed. At the time of Dominion’s application, a
    100 basis point enhancement was available for natural gas
    combined-cycle generation facilities. See 2012 Acts ch. 435.
    However, in 2013, the General Assembly amended Subsection
    (A)(6). As a result, electric utilities may no longer receive
    an enhanced ROE for new generation construction projects filed
    for approval after January 1, 2013, except for nuclear and
    offshore wind facilities. See 2013 Acts ch. 2.
    4
    (A)(6) is inconsistent with the General Assembly’s stated goal of
    providing “an incentive to undertake such projects,” which
    necessarily require transmission and other infrastructure to
    function. 3
    The Commission held a public evidentiary hearing at which
    Dominion presented evidence in support of its application.
    Significantly, Dominion presented testimony that “but for”
    construction of the Brunswick generating facility, the related
    transmission lines and facilities would not be built.
    As relevant to this appeal, the Hearing Examiner found that
    Subsection (A)(6) authorizes an enhanced ROE on all costs of a
    qualifying generating facility, “including the costs of
    infrastructure necessitated by the facility.”     Consequently, the
    Hearing Examiner recommended that the Commission should accept
    Dominion’s proposed rate design contained in Rider BW, including
    the application of the enhanced ROE to the project’s transmission
    infrastructure, if the project were approved. 4
    3
    Dominion also asserted that the Staff’s position
    contradicted the Commission’s established precedent from 12
    previous cases in which it had approved recovery of an enhanced
    rate of return for transmission infrastructure.
    4
    The Hearing Examiner also concluded that Dominion should
    receive the enhanced ROE for the first 10 years of the plant’s
    service life, rather than the 15 years sought by Dominion. This
    finding was adopted by the Commission in its final order and is
    not at issue in this appeal.
    5
    The Commission issued a final order approving construction
    and operation of the Brunswick County Power Station and
    associated transmission interconnection facilities. 5   The
    Commission also approved Dominion’s proposed rate design for
    Rider BW, including application of the enhanced ROE to “the
    transmission infrastructure approved herein as part of the
    [p]roject.”   Specifically, the Commission found that the plain
    language of Subsection (A)(6) “expressly includes ‘costs of
    infrastructure associated therewith’ as ‘costs of the facility.’”
    Therefore, because Subsection (A)(6) requires that the enhanced
    ROE be applied to the “entire facility,” the enhanced ROE must be
    applied to costs of associated infrastructure approved as “costs
    of the facility” that is the subject of the RAC. 6
    5
    The Commission’s approval of the project is not disputed
    in this appeal.
    6
    The Commission further noted that it had recently approved
    an enhanced ROE for the transmission infrastructure of three
    other new generation facilities. Thus, it reasoned, “[a]ny other
    result would be a clear departure from the Commission’s
    consistent implementation of the plain language of [Subsection
    (A)(6)].”
    Commissioner Dimitri concurred and joined in the final
    order on the approval of the project and agreed with the 100
    basis point enhancement to the ROE for the generation plant for
    10 years. However, he dissented from the majority’s extension
    of the Subsection (A)(6) ROE enhancement to the project’s
    transmission infrastructure, asserting that the enhancement is
    “focused specifically on generation facilities and not upon
    transmission or distribution,” which are treated differently
    under the statutory framework. Commissioner Dimitri further
    contended that, while the portion of Subsection (A)(6)
    6
    Consumer Counsel filed a petition for reconsideration,
    requesting that the Commission reconsider its final order and
    enter an order finding that the enhanced ROE authorized by
    Subsection (A)(6) applies only to the costs of the generation
    facility, and not to costs of associated transmission
    infrastructure.
    The Commission subsequently entered an order on
    reconsideration and opinion, rejecting Consumer Counsel’s
    interpretation of Subsection (A)(6) and denying the petition.    In
    its order, the Commission reiterated its previous interpretation
    of the plain meaning of Subsection (A)(6) that transmission
    infrastructure was part of the “entire facility” subject to the
    enhanced ROE and found, as a matter of fact, that both the
    transmission and non-transmission infrastructure included in
    Rider BW were associated with the Brunswick facility. 7   The
    Commission further stated that its interpretation of Subsection
    (A)(6) was both consistent with the General Assembly’s express
    intent to encourage utilities to construct generation facilities
    discussing the categories of costs a utility may recover through
    a RAC includes both “costs of the facility” and “costs of
    infrastructure associated therewith,” the discussion of the
    enhanced ROE is addressed solely in terms of the “facility,” a
    term that clearly means “generation facility” when read in the
    context of the statute.
    7
    The Commission noted that these findings of fact were not
    contested by Consumer Counsel.
    7
    to “ensure a reliable and adequate supply of electricity . . .
    and to promote economic development” and with federal regulatory
    treatment of interconnection infrastructure.     Finally, the
    Commission noted that its decision was consistent with prior
    Commission precedent applying the Subsection (A)(6) enhanced ROE
    to “transmission – and all other – infrastructure costs
    statutorily included as costs of the facility in the RAC.” 8
    Consumer Counsel appeals from both the Commission’s final
    order (Record No. 131872) and its order on reconsideration and
    opinion (Record No. 131873). 9
    II.   Standard of Review
    We have long recognized that “[t]he Constitution of Virginia
    and statutes enacted by the General Assembly thereunder give the
    Commission broad, general and extensive powers in the control and
    regulation of a public service corporation.”     Virginia Elec. &
    Power Co. v. State Corp. Comm’n, 
    284 Va. 726
    , 735, 
    735 S.E.2d 684
    , 688 (2012) (quoting Northern Virginia Elec. Coop. v.
    Virginia Elec. & Power Co., 
    265 Va. 363
    , 368, 
    576 S.E.2d 741
    ,
    743-44 (2003)).   Thus, “[i]n considering the appropriate standard
    of review to be applied when reviewing a Commission decision, we
    8
    Commissioner Dimitri again dissented, restating his view
    that the enhanced ROE in Subsection (A)(6) applies only to the
    “generation facility” and nothing more.
    9
    The assignments of error asserted by Consumer Counsel are
    identical for both cases. Consequently, we consolidated the
    cases for our consideration.
    8
    begin by giving a decision in which the Commission has exercised
    its expertise a presumption of correctness.”      Appalachian Power
    Co. v. State Corp. Comm'n, 
    284 Va. 695
    , 703, 
    733 S.E.2d 250
    , 254
    (2012).   However, we have also made clear that the standard of
    review applied to a Commission decision “will depend on the
    nature of the decision under review.”     
    Id. Here, we
    are called
    upon to review the Commission’s interpretation of Code § 56-
    585.1(A)(6).    This Court reviews such questions of statutory
    interpretation de novo.     See 
    id. Furthermore, “although
    questions of law are reviewed de
    novo, the practical construction given by the Commission to a
    statute it is charged with enforcing is entitled to great weight
    by the courts and in doubtful cases will be regarded as
    decisive.”     Piedmont Envtl. Council v. Virginia Elec. & Power
    Co., 
    278 Va. 553
    , 563, 
    684 S.E.2d 805
    , 819 (2009)(internal
    quotation marks and citations omitted).    For these reasons, “we
    will not disturb the Commission’s analysis when it is based upon
    the application of correct principles of law.”      Virginia Elec. &
    
    Power, 284 Va. at 736
    , 735 S.E.2d at 688 (internal quotation
    marks and citations omitted). 10
    10
    We have also recognized that legislative acquiescence to
    the Commission’s interpretation is presumed, and the
    Commission’s interpretation will be considered decisive, when
    the interpretation is a long-standing one. Appalachian 
    Power, 284 Va. at 704
    , 733 S.E.2d at 255. Although the Commission has
    implicitly interpreted Subsection (A)(6) to include an enhanced
    9
    III.   Discussion
    A. Under the Plain Language of Subsection (A)(6), “Costs of the
    Facility” Include “Costs of Infrastructure Associated Therewith.”
    This appeal requires us to discern the categories of costs
    encompassed within the term “facility,” as it is used in
    Subsection (A)(6).   In this inquiry, we are guided by familiar
    principles of statutory construction:
    When construing a statute, [this Court’s]
    primary objective “is to ascertain and give effect
    to legislative intent,” as expressed by the
    language used in the statute. “When the language
    of a statute is unambiguous, [this Court] is bound
    by the plain meaning of that language.” And if
    the language of a statute “is subject to more than
    one interpretation, [this Court] must apply the
    interpretation that will carry out the legislative
    intent behind the statute.” . . . “[C]onsideration
    of the entire statute . . . to place its terms in
    context to ascertain their plain meaning does not
    offend the rule because it is [this Court’s] duty
    to interpret the several parts of a statute as a
    consistent and harmonious whole so as to
    effectuate the legislative goal.”
    Cuccinelli v. Rector & Visitors of the Univ. of Va., 
    283 Va. 420
    ,
    425-26, 
    722 S.E.2d 626
    , 629-30 (2012) (internal quotation marks
    ROE for transmission infrastructure since the adoption of the
    statute by the General Assembly in 2007, we have only applied
    this rule of construction in instances where we have found that
    the statutory language is ambiguous. See Commonwealth v.
    Appalachian Electric Power Co., 193 Va. 37,45-46, 
    68 S.E.2d 122
    ,
    127 (1951) (noting that the presumption of legislative
    acquiescence is a rule of construction that applies only when a
    statute is ambiguous).
    Because we hold, infra, that the language of Subsection
    (A)(6) is plain and unambiguous, we do not presume here that the
    General Assembly has acquiesced to the Commission’s
    interpretation.
    10
    and citations omitted).   Furthermore, we will not single out “a
    particular term or phrase, but . . . construe the words and terms
    at issue in the context of the other language used in the
    statute.”   Buonocore v. Chesapeake & Potomac Tel. Co., 
    254 Va. 469
    , 472, 
    492 S.E.2d 439
    , 441 (1997).    Finally, “[r]ules of
    statutory construction prohibit adding language to or deleting
    language from a statute.”   Appalachian 
    Power, 284 Va. at 706
    , 733
    S.E.2d at 256.
    Subsection (A)(6) was enacted by the General Assembly in
    2007 to create “a new proceeding allowing a utility to petition
    the Commission for approval of a [RAC] for the ‘timely and
    current’ recovery from customers for costs incurred in certain
    identified programs.”   
    Id. at 700-01,
    733 S.E.2d at 253.
    Specifically, Subsection (A)(6) states that:
    A utility that constructs [one or more other
    generation facilities] shall have the right to
    recover the costs of the facility . . .through
    its rates, including projected construction
    work in progress, and any associated allowance
    for funds used during construction, planning,
    development and construction costs, life-cycle
    costs . . . and costs of infrastructure
    associated therewith.
    Code § 56-585.1(A)(6)(emphasis added).   The plain meaning of this
    language dictates that the “costs of the facility,” recoverable
    by a utility which petitions the Commission for approval of a
    RAC, include the “costs of infrastructure associated therewith.”
    11
    It is clear from the language used by the General Assembly
    that the phrase “associated therewith” relates to the term
    “facility.”   Thus, read as a whole, Subsection (A)(6) establishes
    that the “costs of the facility” recoverable through a RAC
    include “costs of infrastructure” associated with the facility.
    In other words, Subsection (A)(6) dictates that costs of
    associated infrastructure are a cost of the facility.   This
    interpretation of Subsection (A)(6) does not render the phrase
    “associated therewith” “unnecessary and redundant.”   Rather, it
    clearly establishes that costs of infrastructure associated with
    the facility, and only those infrastructure costs, are considered
    “costs of the facility” that may be recovered under a RAC.
    B. The Subsection (A)(6) Enhanced ROE Applies to the “Entire
    Facility,” Including the “Costs of Infrastructure Associated
    Therewith.”
    In addition to providing for recovery of the “costs of the
    facility,” Subsection (A)(6) states that “as an incentive to
    undertake such projects” a utility will receive “an enhanced
    [ROE] calculated as specified below.”   The statute then
    establishes that “[s]uch enhanced [ROE] shall be applied to
    allowance for funds used during construction and to construction
    work in progress during the construction phase of the facility
    and shall thereafter be applied to the entire facility during the
    first portion of the service life of the facility.”
    12
    Consumer Counsel contends that the term “facility,” as it is
    used throughout Subsection (A)(6), means “generation facility.”
    Additionally, Consumer Counsel asserts that we should construe
    the term “entire facility” to mean “completed facility.”   Thus,
    Consumer Counsel argues, the “entire facility” to which the
    Subsection (A)(6) enhanced ROE applies after the facility’s
    construction phrase is the completed generation plant itself and
    nothing more.
    This interpretation of Subsection (A)(6) misconstrues the
    plain language of the statute.    To have us reach its desired
    result, Consumer Counsel suggests that the portion of Subsection
    (A)(6) that defines the “costs of the facility” merely
    “enumerates the types of costs that a utility shall have the
    right to recover through a [Subsection (A)(6)] RAC” and does not
    apply to the portion of the statute discussing the application of
    the enhanced ROE.   We decline, however, to read the various
    portions of the statute in isolation.   See 
    Cuccinelli, 283 Va. at 425-26
    , 722 S.E.2d at 629-30 (holding that portions of a statute
    must be interpreted “as a consistent and harmonious whole.”).    We
    likewise decline to substitute the word “completed” for the word
    “entire” when interpreting the meaning of the phrase “entire
    facility” in Subsection (A)(6).    See Appalachian 
    Power, 284 Va. at 706
    , 733 S.E.2d at 256 (“Rules of statutory construction
    13
    prohibit adding language to or deleting language from a
    statute.”).
    “Entire” means: “with no element or part excepted;” or
    “complete in degree.”    Webster’s Third New International
    Dictionary 758 (1993).    Therefore, because “costs of
    infrastructure” associated with the facility are recoverable as
    “costs of the facility” under a RAC, the plain meaning of “entire
    facility” in the portion of the statute discussing the enhanced
    ROE encompasses all costs of the facility expressly delineated in
    the statute, including associated infrastructure costs.      Even
    assuming that the word “facility” must mean “generation
    facility,” Subsection (A)(6) establishes that “costs of
    infrastructure associated therewith” are “costs of the
    [generation] facility.”
    Moreover, in its order on reconsideration and opinion, the
    Commission found that both associated transmission and non-
    transmission infrastructure, “such as certain water and sewer
    lines, roads, administrative and security buildings, and other
    power lines that are included in the RAC under Subsection
    (A)(6),” should receive the enhanced ROE under the statute.
    Consumer Counsel does not, however, challenge the Commission’s
    findings with regard to the non-transmission infrastructure, and
    we can find nothing in the plain language of Subsection (A)(6)
    that supports carving out only transmission infrastructure for
    14
    purposes of applying the enhanced ROE.    Consumer Counsel asserts
    that Subsection (A)(6) “clearly deals with generation plants, not
    transmission lines.”    However, it is undisputed that the type of
    transmission interconnection infrastructure at issue here is
    properly included in a Subsection (A)(6) RAC. 11
    Consumer Counsel further argues that the portion of
    Subsection (A)(6) which states that “such enhanced rate of return
    shall apply only to the facility that is the subject of such
    [RAC]” limits the applicability of the enhanced ROE to the
    generation plant itself.    Again, we disagree.    The plain meaning
    of this provision establishes that the enhanced ROE applies only
    to the facility covered under the Subsection (A)(6) RAC, and not
    11
    Although a separate provision, Code § 56-585.1(A)(4)
    (“Subsection (A)(4)”), allows a utility to seek approval of a
    RAC for recovery of transmission costs, a Subsection A4 RAC is
    limited to recovery of:
    (i) costs for transmission services provided
    to the utility by the regional transmission
    entity of which the utility is a member, as
    determined under applicable rates, terms and
    conditions approved by the Federal Energy
    Regulatory Commission [“FERC”], and (ii) costs
    charged to the utility that are associated
    with demand response programs approved by
    [FERC] and administered by the regional
    transmission entity of which the utility is a
    member.
    The interconnection facilities included in Dominion’s Rider
    BW are not regulated by FERC. Therefore, they fall outside of
    the ambit of Subsection (A)(4).
    15
    to other facilities that are included in other RACs or in base
    rates.
    C. The Commission’s Interpretation of Subsection (A)(6) Furthers
    the General Assembly’s Expressly Stated Intention
    The General Assembly was clear about its intentions in
    enacting Subsection (A)(6), stating in the text of the statute
    that a utility may petition the Commission for a RAC seeking
    recovery of the costs of a generation facility “[t]o ensure a
    reliable and adequate supply of electricity, to meet the
    utility’s projected native load obligations and to promote
    economic development.”   Furthermore, the General Assembly
    expressly stated in Subsection (A)(6) that a utility “shall have
    the right to recover . . . as an incentive to undertake such
    projects, an enhanced [ROE].”   (Emphasis added).
    Here, the Commission found that the transmission
    interconnection facilities included in Dominion’s Rider BW “are
    associated with the Brunswick generation facility and must be
    constructed in order for the Brunswick facility to function and
    serve its statutory purpose.”   We agree with the Commission.   The
    expressly stated intention of the General Assembly in enacting
    Subsection (A)(6) and providing for the recovery of an enhanced
    ROE is to incentivize the construction of generation plants
    capable of “ensur[ing] a reliable and adequate supply of
    electricity” to citizens of the Commonwealth.   The application of
    16
    the enhanced ROE to the “entire facility,” including the costs of
    necessary transmission interconnection infrastructure associated
    with the facility, clearly and unambiguously furthers this
    statutory purpose.
    IV.   Conclusion
    For the reasons stated herein, we hold that a utility has
    the right to recover an enhanced rate of return on common equity
    for the costs of associated transmission infrastructure included
    in a Code § 56-585.1(A)(6) rate adjustment clause.      The
    Commission’s decision will be affirmed.
    Affirmed.
    JUSTICE MIMS, dissenting.
    The disposition of this case turns on the interpretation of
    the plain language of Code § 56-585.1.     The parties ably
    presented their arguments, and this is a close question on which
    reasonable minds can respectfully differ.      The majority’s
    conclusion is articulated in a well-reasoned and well-written
    opinion.   Nevertheless, I dissent for the reasons stated by
    Commissioner Dimitri in his opinions concurring in part and
    dissenting in part from the Commission’s final order and order
    on reconsideration.   I found his views persuasive and I have
    nothing new to add.   Mindful that the question is one of
    statutory interpretation, I am content to rely on the General
    17
    Assembly’s power to amend Code § 56-585.1 if the Court has
    misapprehended its intent.
    18