Davis Construction Corp. v. FTJ ( 2020 )


Menu:
  • PRESENT: All the Justices
    JAMES G. DAVIS CONSTRUCTION CORPORATION
    OPINION BY
    v. Record No. 190345                               JUSTICE STEPHEN R. McCULLOUGH
    May 14, 2020
    FTJ, INC., F/K/A CIESCO, INC.
    FROM THE CIRCUIT COURT OF ARLINGTON COUNTY
    Louise M. DiMatteo, Judge
    Relying on the doctrine of unjust enrichment, the trial court held that a general contractor,
    James G. Davis Construction Corporation (“Davis”), was liable for construction materials
    provided by a supplier to one of Davis’s subcontractors. Davis challenges this judgment on a
    number of grounds. For the reasons noted below, we affirm the trial court’s judgment.
    BACKGROUND
    Davis served as the general contractor for a residential condominium project in Arlington
    County. On February 19, 2016, Davis contracted with H&2 Drywall Contractors to complete the
    drywall and metal framing for this project. H&2 was required to provide all labor, materials,
    supervision, and equipment to complete those aspects of the construction project. The revised
    contract between Davis and H&2 called for H&2 to be paid a total of $1,269,396, which was to
    be paid in installments. The contract also called for 10 percent retainage, to be withheld until
    final payment was due.
    H&2 agreed to purchase materials for the project from Ciesco, now known as FTJ, Inc.
    H&2 completed a Credit Application and Agreement, in which it agreed to pay Ciesco for
    materials delivered to H&2. Renan Buendia, the principal of H&2, also provided a personal
    guarantee to pay Ciesco any amounts H&2 owed to Ciesco for building materials.
    To ensure the smooth operation of the project, Davis and H&2 entered into a joint check
    agreement. That agreement provided as follows:
    JOINT CHECK AGREEMENT
    THIS JOINT CHECK AGREEMENT (“Agreement”) is made this 29 day of
    April, 2016 by and among (1) JAMES G. DAVIS CONSTRUCTION
    CORPORATION, whose address is 12530 Parklawn Drive, Rockville, Maryland
    20852 (“DAVIS”), (2) H&2 Drywall Contractors (“Subcontractor”) whose
    address is 6702 Braddock Rd. Annandale VA 22003 and (3) (“Supplier”) Ciesco
    Inc. whose address is Corporate Office
    109 Millers Ln
    Harrisburg PA 17110
    The parties to this agreement hereby agree as follows:
    1. Any and all material checks issued by DAVIS to Subcontractor
    for invoices submitted by Supplier to Subcontractor on sales of
    materials in connection with the construction project known as
    Lot 3 Gas line (“Project”) shall be made payable to Supplier
    and Subcontractor, provided Subcontractor and Supplier agree
    upon the amount actually owed by Subcontractor to Supplier
    for such invoices.
    2. All such checks issued by DAVIS to Subcontractor shall be
    immediately endorsed by Subcontractor, then promptly
    delivered by Subcontractor to Supplier at the above address (or
    such other address as Supplier may designate in writing).
    3. DAVIS will only make payments to Subcontractor and
    Supplier by joint check to the extent that DAVIS actually owes
    money to Subcontractor on the Project.
    4. The sole purpose of this Agreement is to assist Subcontractor
    in making payment to Supplier of invoices on sales of all
    materials furnished by Supplier to Subcontractor for use in
    connection with the Project. This Agreement does not
    constitute an assignment of fund. Nothing contained in this
    Agreement is intended by the parties to create any contractual
    relationship or equitable obligation between DAVIS and
    Supplier; this Agreement is solely for the convenience of the
    parties. This Agreement may be cancelled at any time by
    DAVIS upon written notice to Subcontractor and Supplier.
    JAMES G. DAVIS CONSTRUCTION CORP.                  SUBCONTRACTOR H&2
    drywall contractor
    By Michelle Christen                               By Renan Buendia
    2
    Michelle Christen - VP Accounting &                Renan Buendia PM
    Financial Reporting
    SUPPLIER
    By Jeffrey G. Depew CFO
    Jeffrey G. Depew II
    The agreement thus specifies a method for how Ciesco would be paid for the materials it
    shipped to the job. Ciesco would send its invoices to Davis and H&2. Davis would pay via a
    joint check made payable to both H&2 and Ciesco and deliver the check to H&2. H&2 would
    then endorse the check and turn it over to Ciesco to apply against the invoices for the project.
    The joint check agreement specifies that “DAVIS will only make payments [to H&2] and
    [Ciesco] by joint check to the extent that DAVIS actually owes money to [H&2] on the
    Project.” 1
    Joint checking agreements are common in the construction industry. A joint checking
    agreement facilitates payment to a supplier, by providing a greater assurance to the supplier that
    it will be paid. With a joint check, the subcontractor cannot abscond with money owed to the
    supplier. From Ciesco’s perspective, the joint check agreement meant that there was no credit
    limit on the amount of materials it would ship to H&2 at one time. The agreement made Ciesco
    more confident that it would be paid and alleviated any concerns it might have about shipping a
    larger increment of materials.
    Ciesco began shipping materials in July 2016. Payment was due within 60 days of the
    date of the invoice. When Ciesco experienced repeated delays in the payment of its invoices,
    Jolene Finley, an accountant with Ciesco, reached out to Davis at repeated intervals: November
    11, 2016, December 13, 2016, and January 10, 2017. Ciesco’s policy was not to ship additional
    1
    The joint check agreement does not provide that it is subject to the terms of Davis’s
    subcontract with H&2.
    3
    materials on accounts that are past due. Each time Ciesco inquired about the past due invoices,
    Davis responded that a check had been or would be written. Initially, the parties contemplated
    that the check would be written pursuant to the joint check agreement and that is how Davis paid,
    writing joint checks to H&2 and Ciesco. Davis sent two “release of liens” forms to Ciesco for
    invoices that had been paid. Davis paid the invoices for materials Ciesco provided through
    December of 2016. Benjamin Mahoney, who managed the project for Davis, acknowledged that
    a supplier who is not paid might cut off supplies, and that there is “always a concern” about
    non-payment generating delays. Mahoney explained that Davis’s involvement with Ciesco’s
    invoices is “not a typical scenario for us to be in.” He testified that, ordinarily, the subcontractor
    is hired “to manage that process, to manage the orders, [and] to manage the invoices.” Davis’
    assurances to Ciesco in January 2017 resulted in Ciesco continuing to ship materials to H&2
    rather than withholding materials because the account was past due.
    As work on the project progressed, Davis noticed that H&2 was in difficulty. In early
    2017, Davis learned that H&2 had “payroll payment problems” and was not paying its
    employees. As a predictable result of not paying its employees, H&2 was having trouble
    supplying enough personnel to complete the project. By March 22, 2019, Davis came to the
    conclusion that H&2 would not be able to pay its suppliers. For its part, Ciesco was not aware of
    any issues H&2 was having. However, while Davis was communicating with Ciesco about
    Ciesco’s unpaid invoices, Davis was concerned about Ciesco cutting off supplies to H&2 based
    on, at least in part, H&2’s financial condition.
    Ciesco made deliveries of materials from January 10 through March 22. Neither H&2
    nor Davis paid for those materials. Ciesco did not deliver any additional materials after March
    2017.
    4
    On March 21, 2017, Davis issued a “notice to cure” to H&2, detailing the issues Davis
    was having with H&2. The second paragraph of the notice highlighted the ongoing nature of the
    problems with H&2. It stated “As previously notified, H&2 Drywall Contractors continued to
    underperform and manpower has steadily declined.”
    The following day, on March 22, 2017, Mahoney called Jolene Finley of Ciesco to
    inform her that there were “some problems between Davis and H&2” and he asked her not to
    ship any further materials on the joint check account. Mahoney requested a Ciesco credit
    application and a W-9 form. Finley and Mahoney discussed payment of Ciesco’s invoices.
    Mahoney assured Finley that there were ample funds to pay Ciesco. Ciesco discussed internally
    whether it needed to take any action, such as filing a mechanic’s lien or hiring legal counsel to
    collect the outstanding amounts due. Finley testified that Ciesco decided that it did not need to
    take any action, explaining that “we felt confident in the assurances we were provided by Mr.
    Mahoney and the Davis Company.”
    On March 23, 2017, Davis added Ciesco to its accounting system. Approximately two
    weeks later, Davis requested copies of invoices from January 2017, and Ciesco provided them
    the next day. Ciesco requested a status update on Davis’ outstanding payments on April 10.
    Davis responded that a $160,670.05 payment was being processed, and that the delay was due to
    moving from the joint checking agreement account. Prior to replying to Ciesco’s request for a
    status update, Davis’ internal emails confirmed that the payment to Ciesco was being processed.
    The owner of H&2 responded to Davis’s notice to cure by stating that he could not
    provide the required personnel to complete the project, and that Davis should find a new
    subcontractor. After 72 hours had passed from the issuance of that notice, Davis terminated
    H&2 as a subcontractor. Davis paid H&2 a total of $969,779.70, or $299,616.30 less than what
    5
    the revised contract contemplated as full compensation for H&2. Davis then hired another
    subcontractor on March 28, 2017. Davis paid that subcontractor a total of $260,007 to complete
    the job. The scope of the work was the same for the new subcontractor. H&2’s default caused
    Davis to settle claims with other suppliers.
    On April 12, when Finley called again about invoices that were past due, Mahoney
    responded that payments in the amount of $160,670.05 were being currently processed, and he
    explained that “there was a slight delay with our Accounting program when we switched over
    from the joint check payments.” On April 21, however, Mahoney called Finley to tell her that,
    because of the problems between H&2 and Davis, the money that Davis had planned to use to
    pay Ciesco’s invoice had to be used instead to complete the project. What remained, Mahoney
    stated, was $58,000, and Mahoney offered to settle all the remaining invoices for this amount.
    Davis never ordered materials directly from Ciesco. Ciesco shipped $252,062.18 in
    materials for which it was not paid, either by H&2, Buendia, or Davis. Davis used these
    materials to complete the project. Ciesco invoiced Davis for the materials, and its prices were
    reasonable. Mahoney agreed that if Davis had not used those supplies, it would have had to pay
    the new subcontractor or supplier for those materials.
    Ciesco filed an amended complaint against Davis, H&2 and Buendia. Ciesco alleged
    breach of contract and unjust enrichment. Ciesco further sought to enforce a mechanic’s and
    materialmen’s lien. Ciesco obtained a default judgment against H&2 and Buendia. Following a
    bench trial, the court ruled in favor of Ciesco on its claim of unjust enrichment against Davis.
    The trial court further ruled that the joint check agreement was not a binding contract due to lack
    of consideration. Finally, the trial court found in favor of Davis on Ciesco’s mechanic’s lien.
    This appeal followed.
    6
    ANALYSIS
    The doctrine of unjust enrichment effects a “contract implied in law” requiring one who
    accepts and receives goods, services, or money from another to make reasonable compensation
    for those services. See Po River Water & Sewer Co. v. Indian Acres Club of Thornburg, Inc.,
    
    255 Va. 108
    (1998). It arises from the simple principle that one person may not “enrich himself
    unjustly at the expense of another.” Rinehart v. Pirkey, 
    126 Va. 346
    , 351 (1919). Typical
    examples of unjust enrichment involve a payment or overpayment under a mistake of fact,
    Central Nat. Bank of Richmond v. First & Merchants Nat. Bank of Richmond, 
    171 Va. 289
    , 311
    (1938), or the acceptance of services without a contract for those services. See Po River Water
    & Sewer 
    Co., 255 Va. at 115
    (unjust enrichment compelled payment for water and sewer
    services the association accepted and received).
    “Unjust enrichment” is a term of art. Restatement (Third) of the Law of Restitution and
    Unjust Enrichment § 1, at 4 (2011). The Third Restatement rightly cautions that “[i]n reality, the
    law of restitution is very far from imposing liability for every instance of what might plausibly
    be called unjust enrichment.”
    Id. at 5.
    A variety of limiting principles restrict the reach of this
    doctrine. Several such limiting principles are at issue in this case. In particular, Davis argues
    that unjust enrichment is unavailable to Ciesco because: (1) the existence of a contract, the joint
    check agreement, forecloses relief; (2) Davis ended up paying more than the original price to
    complete the project and, therefore, it has not been unjustly enriched; and (3) Ciesco had no
    expectation of being paid by Davis and Davis had no expectation of paying Ciesco. 2
    2
    Davis assigns the following errors:
    1. The trial court erred as a matter of law by ruling that there was no consideration for the
    JCA which governed the payment obligations and expectations of DAVIS, H&2 Drywall,
    7
    I.      THE JOINT CHECK AGREEMENT DOES NOT FORECLOSE RELIEF.
    Davis’ first argument in support of reversal is that the existence of a contract, the joint
    check agreement, bars any quasi-contractual relief. Whether the contract bars an unjust
    enrichment claim is an issue of law we review de novo. CGI Fed. Inc. v. FCi Fed., Inc., 
    295 Va. 506
    , 519 (2018). We have stated that “[t]he existence of an express contract covering the same
    subject matter of the parties’ dispute precludes a claim for unjust enrichment.”
    Id. See also
    Southern Biscuit Co. v. Lloyd, 
    174 Va. 299
    , 311 (1940) (“[A]n express contract defining the
    rights of the parties necessarily precludes the existence of an implied contract of a different
    nature containing the same subject matter.”); Restatement (First) of Restitution § 107(1) (1937).
    As the commentary to a pertinent provision of the modern version of Third Restatement on
    Restitution and Unjust Enrichment explains,
    [c]onsiderations of both justice and efficiency require that private
    transfers be made pursuant to contract whenever reasonably
    possible, and that the parties’ own definition of their respective
    obligations – assuming the validity of their agreement by all
    pertinent tests – take precedence over the obligations that the law
    would impose in the absence of agreement. Restitution is
    and Ciesco, because the JCA gave Ciesco assurances that monies would be paid to
    Ciesco, and that H&2 Drywall could not abscond with monies it owed to Ciesco.
    2. The trial court erred as a matter of law by ruling that DAVIS was unjustly enriched by
    Ciesco’s delivery of drywall materials to H&2 Drywall because Ciesco had no reasonable
    expectation to be paid by DAVIS for the balance of monies owed by H&2 Drywall to
    Ciesco for those materials given Ciesco’s prior written acknowledgment that DAVIS
    would not pay for materials except to the extent it owed money to H&2 Drywall, and the
    trial court determined that no monies were due from DAVIS to H&2 Drywall.
    3. The trial court erred as a matter of law in determining that DAVIS was unjustly enriched
    by Ciesco’s delivery of drywall materials to H&2 Drywall because DAVIS paid the full
    amount of the Subcontract for H&2 Drywall’s completed scope of work, which included
    the drywall materials, in accordance with the express, written Subcontract.
    8
    accordingly subordinate to contract as an organizing principle of
    private relationships, and the terms of an enforceable agreement
    normally displace any claim of unjust enrichment within their
    reach.
    Restatement (Third) of Restitution and Unjust Enrichment § 2, cmt. c, at 17.
    At the same time, and despite its forceful embrace of the primacy of contract over
    remedies implied in law, the Third Restatement acknowledges as “plainly erroneous” broad
    statements such as “there can be no unjust enrichment in contract cases.”
    Id. For example,
    unjust enrichment is not precluded where “a valuable performance has been rendered under a
    contract that is invalid, or subject to avoidance, or otherwise ineffective to regulate the parties’
    obligations.”
    Id. See also
    George E. Palmer, The Law of Restitution § 18.2, at 8 (1978). Sister
    courts have acknowledged such limitations. See, e.g., Campbell v. Asbury Automotive, Inc., 
    381 S.W.3d 21
    , 35-37 (Ark. 2011) (existence of contract did not bar claim for unjust enrichment
    based on allegation that fees charged were illegal); Clapp v. Goffstown Sch. Dist., 
    977 A.2d 1021
    , 1025 (N.H. 2009) (“Unjust enrichment may be available to contracting parties where the
    contract was breached, rescinded, or otherwise made invalid, or where the benefit received was
    outside the scope of the contract.”).
    Davis argues that the joint check agreement “was an express, written contract, supported
    by adequate consideration, that provided the terms and conditions by which Davis would pay
    Ciesco and H&2 Drywall by joint check for the Drywall Materials.” Davis Br. at 19-20.
    Persuasive authority supports the conclusion that joint check agreements are supported by
    consideration. See Plains Builders, Inc. v. Steel Source, Inc., 
    408 S.W.3d 596
    , 608 (Tex. Ct.
    App. 2013); City of Phila. ex rel. Allied Roofers Supply Corp. v. Joseph S. Smith Roofing, Inc.,
    
    599 A.2d 222
    , 226 (Pa. Super. Ct. 1991). For purposes of this opinion, we will assume, without
    9
    deciding, that this particular joint check agreement is supported by consideration. That,
    however, does not end the inquiry.
    By its plain terms, the joint check agreement states that its “sole purpose” “is to assist
    Subcontractor in making payment to Supplier of invoices on sales of all materials furnished by
    Supplier to Subcontractor for use in connection with the Project.” It further states that “[n]othing
    contained in this Agreement is intended by the parties to create any contractual relationship or
    equitable obligation between DAVIS and Supplier.” Davis seeks to stretch the plain terms of the
    joint check agreement far beyond its stated, and limited, purpose. Ciesco is not making any
    claim governed by the contract. For example, Ciesco does not contend that Davis issued checks
    to H&2 that were not joint checks. The expressly limited contract here does not foreclose a
    claim for unjust enrichment when that claim falls outside of the plain terms of the agreement.
    Moreover, as Ciesco notes, the joint check agreement did not “preclude the parties from
    creating further or other expectations about payment through their actions and communications.”
    Ciesco Br. at 20-21. Here, Davis and Ciesco interacted at regular intervals when the invoices
    were past due. Davis’s involvement with Ciesco’s invoices was not typical for Davis. Mahoney
    testified that, ordinarily, the subcontractor is hired “to manage that process, to manage the orders,
    [and] to manage the invoices.” In this instance, Davis did not refer Ciesco to H&2 but instead
    responded directly to Ciesco by either paying the invoice or providing assurances that the invoice
    would be paid. Ciesco’s policy was to stop shipping materials when its invoices had not been
    paid within a certain time frame. Davis’s repeated direct dealings with Ciesco and the repeated
    10
    assurances it received from Davis, prompted Ciesco to continue shipping supplies with the
    expectation that Davis would pay for those supplies. 3
    II.     DAVIS IS NOT BEING COMPELLED TO PAY TWICE FOR THE MATERIALS.
    Courts have denied unjust enrichment claims when an owner or general contractor has
    previously paid for the goods or services in question. See, e.g. Kern v. Freed Co., Inc., 
    224 Va. 678
    , 680 (1983) (appliance store not entitled to unjust enrichment because homeowner had paid
    general contractor’s fee that included the appliances). 4 An owner or contractor should not have
    to pay twice for the same supplies or service. In that situation, there is no enrichment, much less
    unjust enrichment. As the commentary to the Third Restatement of Restitution and Unjust
    Enrichment indicates, there is no restitution when the defendant “has already paid the contract
    price for the benefits received, even if the contract price is less than the cost or value of the
    performance in question.” Restatement (Third) § 25, at 371; see also 2 Palmer, supra, § 10.7, at
    3
    Davis did not provide Ciesco with a copy of the subcontract between Davis and H&2.
    Paragraph 15 of the subcontract provided that in the event H&2 breached the subcontract,
    “Davis . . . may then have the work completed and may use Subcontractor’s material, supplies,
    tools, and equipment to complete. Subcontractor and its surety shall continue to be liable for all
    costs to complete and any damages and expenses . . . .” Paragraph 9 of the subcontract provided
    that “Material paid for shall belong to [] Davis . . . .” Construing these two provisions together,
    it is apparent that Davis would use the supplies of a defaulting subcontractor to finish the job,
    and that the subcontractor would have to be liable for any damages that flowed from the default,
    but that Davis did not have ownership over the supplies because, according to Mahoney’s
    testimony and as found by the trial court, Davis did not pay for them (and neither did H&2).
    4
    See also Breckenridge Mat’l Co. v. Allied Home Corp., 
    950 S.W.2d 340
    , 342 (Mo. Ct.
    App. 1997) (holding that unjust enrichment cannot exist when an owner would have to pay twice
    despite the subcontractor not having collected its fee); Hydro Conduit Corp. v. Kemble, 
    793 P.2d 855
    , 858 (N.M. 1990) (finding that unjust enrichment will not lie against a property owner who
    has already paid for the benefit supplied by the subcontractor); Columbia Wholesale Co. v.
    Scudder May N.V., 
    440 S.E.2d 129
    , 131 (S.C. 1994) (denying recovery on a claim of unjust
    enrichment by a subcontractor against an owner where the owner paid on its contract with the
    general contractor).
    11
    424 (1978). Relying on this principle, Davis argues that it had to pay more than originally
    projected to finish the job, so it was not unjustly enriched.
    We find this argument unpersuasive. In this instance, it is the payment for specific
    supplies that is at issue, not the overall cost of the project. The evidence from Davis’s own
    project manager established that Davis did not pay anyone for the supplies Ciesco delivered to
    the job site and that it used those supplies. The evidence further established that, absent those
    materials, Davis would have had to obtain them elsewhere and pay for them. Whether the
    installation of those materials was done by the original subcontractor or the replacement
    subcontractor is similarly irrelevant to whether Davis was unjustly enriched by possessing them
    without paying for them. Davis is not being forced to pay twice for supplies provided by Ciesco.
    It is being asked to pay once.
    Furthermore, the fact that Davis ultimately paid more than the original contract price to
    complete the project does not bar recovery. A reduction in obligations to third parties qualifies
    as “enrichment” in the context of unjust enrichment. Restatement (Third) § 1, at 7. It is
    undisputed that Davis used, and did not pay for, Ciesco’s materials to complete the project. It
    follows that if Davis was unable to use materials it obtained from Ciesco without payment, then
    Davis would have needed to purchase replacement materials from another supplier, thereby
    increasing the total cost of the project. Morris Pumps v. Centerline Piping, Inc., 
    729 N.W.2d 898
    , 905 (Mich. Ct. App. 2006) (“[T]he mere fact that [the subcontractor’s] breach cost
    defendant more than originally anticipated does not undo the wrongful nature of [contractor]
    defendant’s retention of [supplier] plaintiffs’ products. We reject the argument that payment in
    full of the originally anticipated subcontract price [to a new subcontractor] somehow negates
    defendant’s obligation to compensate plaintiffs for the inequitably retained materials.”).
    12
    This case is distinguishable from Kern. In Kern, the homeowner defendant paid the
    general contractor an overall fee for a “turnkey” project that included the costs of the 
    appliances. 224 Va. at 679
    . The homeowner also contracted with an interior designer, who ordered
    appliances. Both the general contractor and the interior designer left the state without paying for
    the appliances.
    Id. at 680.
    The store that provided the appliances sought to recover from the
    homeowner under a theory of unjust enrichment. We concluded that the homeowner was not
    unjustly enriched and the store could not obtain restitution against the owner.
    Id. at 681.
    Persuasive authority supports our conclusion. For example, in Wang Elec., Inc. v. Smoke
    Tree Resort, LLC, 
    283 P.3d 45
    , 49-50 (Ariz. Ct. App. 2012) the court observed that
    [t]hese cases fall into two categories: ones in which the owner has
    fully paid the general contractor and ones in which the owner has
    not fully paid the general contractor . . . [R]ecovery under a theory
    of unjust enrichment is not available in the former category,
    because the owner is not unjustly enriched if it fully paid its
    obligation. But when the owner has failed to fully pay its
    obligation, our courts have held that recovery for unjust
    enrichment is available because permitting the owner to retain the
    benefit without fully paying for it would be unjust. 5
    5
    Although the courts are divided on where to draw the line with claims of unjust
    enrichment, ample persuasive authority allows a recovery in circumstances similar to the one we
    face here, i.e. there is nothing “aberrant” about the conclusion we reach. Unerstall Foundations,
    Inc. v. Corley, 
    328 S.W.3d 305
    , 312-13 (Mo. Ct. App. 2010) (stating that “[p]ayment or non-
    payment determines whether a defendant was unjustly enriched” and upholding judgment for
    unjust enrichment because the evidence showed that the owner had not paid the contractor or the
    subcontractor for the work); Flooring Sys., Inc. v. Radisson Grp., Inc., 
    772 P.2d 578
    , 581-82
    (Ariz. 1989) (reversing summary judgment because hotel had not fully paid anyone, either the
    bankrupt general contractor or the subcontractor, for carpet installation by the subcontractor);
    Eastern Metal Products, Inc. v. Deperry, 
    686 A.2d 1003
    , 1004 (Conn. Ct. App. 1997)
    (evidentiary hearing needed to determine if tenant was unjustly enriched by suppliers provided to
    contractor, who did not pay for them); Morris 
    Pumps, 729 N.W.2d at 198
    (“We recognize that
    defendant may have paid more than the full contract price originally contemplated in the
    subcontract . . . . However, this does not lessen or alleviate defendant’s obligation to compensate
    plaintiffs for the materials that were taken and used in the course of the construction project.”),
    Trane Co. v. Randolph Plumbing and Heating, 
    722 P.2d 1325
    , 1329 (Wash. Ct. App. 1986)
    (supplier stated a claim for unjust enrichment by alleging materials were incorporated into final
    project but were never paid for by bankrupt contractor).
    13
    Davis is not being forced to pay twice for supplies provided by Ciesco. Consequently,
    this limiting principle does not bar Ciesco from seeking unjust enrichment relief against Davis.
    III.    DAVIS REASONABLY EXPECTED TO PAY FOR THE SUPPLIES AND CIESCO
    REASONABLY EXPECTED TO BE PAID.
    We have adopted a three-part test to govern unjust enrichment claims: (1) the plaintiff
    conferred a benefit on the defendant; (2) the defendant knew of the benefit and should
    reasonably have expected to repay the plaintiff; and (3) the defendant accepted or retained the
    benefit without paying for its value. Schmidt v. Household Fin. Corp., II, 
    276 Va. 108
    , 116
    (2008). The first and third elements are not in dispute in this case. With respect to the first
    element of the test, there is no question that Ciesco conferred a benefit on Davis. See R. 677.
    Ciesco provided a significant supply of materials that Davis, by its own admission, used to finish
    the project. With respect to the third element, it is plain that the defendant accepted or retained
    the benefit without paying for its value. Davis raises a number of arguments concerning the
    second element.
    Davis argues that it had no expectation of paying for the materials based on the joint
    check agreement. It cites to clause 3 of the joint check agreement, which specifies that “DAVIS
    will only make payments to Subcontractor and Supplier by joint check to the extent that DAVIS
    actually owes money to Subcontractor on the Project.” Davis points out that it did not owe H&2
    any money under the subcontract. Here, however, Davis repeatedly responded directly to
    Ciesco’s inquiries about late invoices and provided assurances that Ciesco would receive
    payment. Davis was concerned about ensuring a continued flow of supplies. By January 2017,
    Davis was aware of H&2’s precarious condition, notably its late payments to Ciesco and failure
    to pay its employees. Nevertheless, Davis directly encouraged Ciesco to continue shipping
    14
    supplies. In addition, Davis’ internal communications and actions following termination of the
    subcontract and JCA are consistent with an intent on the part of Davis to pay Ciesco’s
    outstanding invoices, initially via joint check and later directly from Davis. On March 23, Davis
    added Ciesco to its accounting system. By April 12, Davis internally approved and was
    processing a $160,670.05 payment to Ciesco, although it soon halted that payment. The
    factfinder could plausibly conclude that Davis expected to pay for the materials based on Davis’
    course of conduct with Ciesco, and that Ciesco expected to be paid for materials it was
    encouraged to ship. Based on these facts, we cannot say that the trial court’s award on the unjust
    enrichment claim was “plainly wrong or without evidence to support it.” Online Res. Corp. v.
    Lawlor, 
    285 Va. 40
    , 61 (2013).
    This case is closely analogous to Morris Pumps. In that case, the general contractor
    continued using supplies provided by a supplier to a bankrupt subcontractor. The general
    contractor did not pay anyone for those 
    supplies. 729 N.W.2d at 901-02
    . The Michigan Court of
    Appeals held that the general contractor was unjustly enriched, reasoning as follows:
    [N]either defendant nor the replacement contractor retained by
    defendant to finish the project ever paid plaintiffs for the materials
    and supplies. As the general contractor, defendant was responsible
    for overseeing all construction and was charged with supervising
    all subcontractors present on the site, including the replacement
    contractor retained after [the subcontractor] left the project.
    Moreover, as the general contractor, defendant was surely aware
    that the materials and supplies used to complete the project had
    been specially delivered to the site by plaintiffs. Defendant was
    also likely aware that [the subcontractor], which had gone out of
    business and had left the project, had not paid for the items.
    Regardless of whether defendant itself retained and used the
    materials, or merely acquiesced in the replacement contractor’s
    retention and use of the materials, defendant was necessarily a
    party to the decision to use and retain the materials without paying
    plaintiffs.
    15
    If defendant’s retention of the materials supplied by plaintiffs
    had been completely innocent and without knowledge, we might
    be inclined to conclude that defendant’s enrichment was not unjust.
    . . . . However, we simply cannot classify defendant’s act of
    retaining and using the materials, without ever ensuring that
    plaintiffs were compensated for the materials, as innocent, just, or
    equitable.
    Id. at 904-05.
    Davis contends that we should not “allow[] any lower-tiered subcontractor or supplier to
    ‘leap frog’ up the chain of privity to recover against remote a party.” Davis Br. 6. But here it is
    Davis that willingly climbed down the chain of privity to deal directly with a supplier in order to
    keep supplies flowing. Davis then used the supplies to complete the project without paying
    anyone for those supplies. 6
    We emphasize the limited scope of our decision. In ordinary circumstances, a supplier of
    labor or materials to a subcontractor will not be able to obtain a judgment against an owner or a
    general contractor. Moreover, where a contract actually governs the relationship of the parties, it
    will foreclose relief under an unjust enrichment theory. Contractors, subcontractors and
    suppliers remain free to structure their contracts and their conduct in such a way as to preclude
    claims for unjust enrichment. Here, the limited scope of the joint check agreement does not bar
    the unjust enrichment claim. In addition, unjust enrichment precludes an owner or a general
    contractor from having to pay twice for a service or supplies. That is not the situation here.
    Davis knew of the subcontractor’s difficulties and past due invoices, and, to ensure a continued
    flow of supplies, interacted directly with the supplier and led the supplier to believe that payment
    6
    Ciesco did not plead fraud. The trial court based its judgment on the theory of unjust
    enrichment. No part of our decision is based on a theory of fraud.
    16
    for those supplies would be forthcoming. These distinct circumstances permit Ciesco to obtain
    relief for Davis’ unjust enrichment.
    CONCLUSION
    For all of these reasons, we will affirm the judgment of the trial court.
    Affirmed.
    JUSTICE KELSEY, with whom CHIEF JUSTICE LEMONS and JUSTICE CHAFIN join,
    dissenting.
    The construction industry relies heavily upon financial and legal predictability, a public
    policy highly favored by the law of contracts. In this case, that reliance has been undermined by
    an aberrant use of the doctrine of quasi-contracts. The scenario is typical: A supplier does not
    get paid by an insolvent subcontractor, the only party that had agreed to pay the supplier, so the
    supplier sues the general contractor. The result is atypical: A trial court orders the general
    contractor to pay the subcontractor’s debt to the supplier, and the majority affirms.
    I respectfully dissent.
    I.
    The very use of the adjective “quasi” (legalese for “sort of”) betrays itself as a linguistic
    stretch. A quasi-contract is not sort of a contract. It is “no contract at all.” J.B. Ames, The
    History of Assumpsit, 2 Harv. L. Rev. 53, 63 (1888). No one agrees to a quasi-contract. It is
    imposed upon a party against his will. The idea originated in the Roman civil law, migrated into
    continental ecclesiastical law, and was absorbed into English equity practice. See generally City
    of Norfolk v. Norfolk Cty., 
    120 Va. 356
    , 360-68 (1917). English and American courts ultimately
    17
    incorporated the idea into the common-law “action of assumpsit.”
    Id. at 361.
    1 They did so with
    considerable caution, however, recognizing that “[i]n this class of cases, the notion of a contract
    is purely fictitious.”
    Id. at 363
    (citation omitted). And they no doubt knew, as do we, that a
    legal “fiction becomes wholly safe only when it is used with a complete consciousness of its
    falsity,” L.L. Fuller, Legal Fictions, 
    25 Ill. L
    . Rev. 363, 370 (1930).
    Generations of jurists and legal scholars have attempted to sculpt the quasi-contract
    concept into a workable legal doctrine. This effort has produced the cause of action generally
    called “unjust enrichment.” 2 To be successful, an unjust-enrichment plaintiff must satisfy a
    threshold requirement — proving that the defendant was “enriched” at the plaintiff’s “expense.”
    See Hamm v. Scott, 
    258 Va. 35
    , 38-39 (1999); Kern v. Freed Co., 
    224 Va. 678
    , 680-81 (1983).
    In the context of commercial disputes involving goods or services, one is enriched only if his
    economic position has been measurably improved. If a defendant’s economic position is exactly
    1
    See also Great-West Life & Annuity Ins. v. Knudson, 
    534 U.S. 204
    , 213 (2002);
    Baltimore & Ohio R.R. v. Burke & Herbert, 
    102 Va. 643
    , 646-47 (1904) (quoting Lord
    Mansfield’s opinion in Moses v. Macferlan (1760) 97 Eng. Rep. 676, 681; 2 Burr 1005, 1012,
    which states that the “gist” of a quasi-contract action in assumpsit is that the defendant “is
    obliged, by the ties of natural justice and equity, to refund the money”); Dan B. Dobbs & Caprice
    L. Roberts, Law of Remedies § 4.2(2), at 391-92 (3d ed. 2018) (explaining that restitution
    developed in common law through assumpsit and stating that quasi-contract cases first arose in
    assumpsit “sometime between around 1650 and 1700”). See generally Restatement (Third) of
    Restitution and Unjust Enrichment § 4 (2011) (“Liabilities and remedies within the law of
    restitution and unjust enrichment may have originated in law, in equity, or in a combination of
    the two.”).
    2
    We are not dealing here with an implied-in-fact contract, which is a true (not fictitious)
    contract implied from the parties’ “acts and conduct” and is “created only when the typical
    requirements to form a contract are present, such as consideration and mutuality of assent,”
    Spectra-4, LLP v. Uniwest Commercial Realty, Inc., 
    290 Va. 36
    , 45 (2015) (citing City of
    
    Norfolk, 120 Va. at 361-62
    ). The measure of recovery for an implied-in-fact contract is quantum
    meruit — the reasonable value of the services provided. See Mongold v. Woods, 
    278 Va. 196
    ,
    203 (2009); Hendrickson v. Meredith, 
    161 Va. 193
    , 200-02 (1933). Properly understood,
    quantum meruit denotes only a “measure of damages” and not an underlying theory of
    obligation. John L. Costello, Virginia Remedies § 12.03, at 12-10 & n.39 (4th ed. 2011).
    18
    the same after the plaintiff’s actions as before, the expenses incurred by the plaintiff in taking
    such actions are irrelevant.
    The plaintiff’s threshold requirement, even if fully satisfied, is insufficient to justify an
    award of unjust enrichment. “One may not recover under a theory of implied [in law] contract
    simply by showing a benefit to the defendant . . . .” Nedrich v. Jones, 
    245 Va. 465
    , 476 (1993).
    An “enrichment of the defendant” does not alone “suffice since the defendant will be deprived of
    the enrichment only if its retention is regarded as unjust.” 1 George E. Palmer, The Law of
    Restitution § 1.7, at 41 (1978). “Issues of considerable difficulty sometimes arise with respect to
    the question whether there is an enrichment, but in a much larger number of cases the problem is
    whether retention of a recognizable enrichment is unjust.”
    Id. To prove
    an unjust enrichment, the plaintiff must show that the defendant “knew of the
    benefit” and could “reasonably have expected” to pay for it. Schmidt v. Household Fin. Corp.,
    II, 
    276 Va. 108
    , 116 (2008). The key qualification, legal reasonableness, has well-recognized
    limits. As a matter of law, an enrichment cannot be unjust if the defendant has “a bona fide
    hostile claim of right” to whatever benefit was allegedly bestowed on him. City of 
    Norfolk, 120 Va. at 374
    . In such a circumstance, “the law will not indulge the fiction of the existence of an
    implied promise of defendant to plaintiff; for that would in such case be in itself inequitable.”
    Id. In multi-party
    commercial transactions, a plaintiff may render a benefit to a defendant
    while performing a contractual obligation to a third party. The defendant, in turn, may claim a
    right to retain the benefit because he contracted to receive it from the third party. This scenario
    differs from the two-party scenarios that typically arise in the unjust-enrichment context. The
    usual examples are situations in which the plaintiff mistakenly confers a benefit on the wrong
    19
    person, delivers the wrong goods to the right person, or performs under a contract that is
    unenforceable. 3 Those situations do not involve a third party in direct, but separate, privity
    relationships with both the plaintiff and the defendant.
    In the third-party context, “[l]egitimate concerns about privity of contract” must be
    “accommodated by imposing a test of unjust enrichment that is highly protective of the
    defendant,” Restatement (Third) of Restitution and Unjust Enrichment ch. 3, topic 2, intro. note
    (2011) (emphasis added), and by establishing “a rigorous test of unjust enrichment as a threshold
    requirement of the claim,”
    id. § 25
    cmt. b (emphasis added). This protective, rigorous test
    focuses on whether the defendant has paid anyone for the benefit received and thus has a bona
    fide claim of right to it. See generally J.R. Kemper, Annotation, Building and Construction
    Contracts: Right of Subcontractor Who Has Dealt Only with Primary Contractor to Recover
    Against Property Owner in Quasi Contract, 
    62 A.L.R. 3d 288
    , § 2 (1975) (collecting cases).
    It is a “fundamental requirement of unjust enrichment in these circumstances . . . that [the
    defendant] must stand to obtain a valuable benefit at [the plaintiff’s] expense without paying
    anyone for it.” Restatement (Third) of Restitution and Unjust Enrichment § 25 cmt. b (emphasis
    added). As a matter of law, therefore, there can be “no unjust enrichment” if the defendant has
    “paid the contract price” to a third party — that is, “the price originally fixed by contract for the
    work to which [the plaintiff] has made an uncompensated contribution.” Id.; see also Dobbs &
    Roberts, supra note 1, § 12.18(3), at 889-90; 2 Palmer, supra, § 10.7, at 424.
    This fundamental requirement can never be satisfied, for example, where an “[o]wner can
    show that its aggregate payments to Builder and the other firms with which it dealt following
    3
    See Dobbs & Roberts, supra note 1, § 4.1(2), at 380 (categorizing unjust-enrichment
    cases into common patterns).
    20
    Builder’s default equal or exceed the original contract price for the work performed.”
    Restatement (Third) of Restitution and Unjust Enrichment § 25 cmt. b, illus. 1. This principle
    holds true “even if the contract price is less than the cost or value of the performance in
    question.”
    Id. § 25
    cmt. b. If a claimant seeks an unjust-enrichment award “for a performance
    that the defendant has previously agreed to pay for — the typical setting of the claim asserted by
    an unpaid subcontractor — the issue of unjust enrichment will be dominated, in many instances,
    by the question of defendant’s payment.”
    Id. § 25
    cmt. c. “If the defendant has paid (or remains
    liable to pay) the agreed-on price for the benefits in question, the defendant has not been unjustly
    enriched.”
    Id. These requirements
    are not esoteric points on the edges of a debatable legal doctrine.
    “Cases denying restitution to an unpaid subcontractor on the ground that the [defendant] has
    already paid all of (or more than) the price fixed by contract for the work in question, counting
    payments made both to the defaulting [party] and to other parties, are extremely numerous.”
    Id. § 25
    reporter’s note (emphasis added). 4 In this context, “restitution frequently is sought from the
    4
    See, e.g., Datastaff Tech. Grp., Inc. v. Centex Constr. Co., 
    528 F. Supp. 2d 587
    , 598
    (E.D. Va. 2007) (stating that “[w]here one is obligated by an express contract to pay for a benefit
    he receives, and has in fact paid, he is not liable for that benefit to another party under a theory of
    unjust enrichment” (citation omitted)); Providence Elec. Co. v. Sutton Place, Inc., 
    287 A.2d 379
    ,
    382 (Conn. 1971) (finding that if the defendant “has paid its contractor . . . for those appliances,
    then the enrichment, in the absence of fraud, has not been unjust”); Commerce P’ship 8098 Ltd.
    P’ship v. Equity Contracting Co., 
    695 So. 2d 383
    , 390 (Fla. Dist. Ct. App. 1997) (“As we have
    observed, where an owner has given consideration for the subcontractor’s work by paying out
    the contract price for the work, an unpaid subcontractor’s claim that the owner has been unjustly
    enriched must fail.”); C. Szabo Contracting, Inc. v. Lorig Constr. Co., 
    19 N.E.3d 638
    , 649-50
    (Ill. App. Ct. 2014) (granting payment to an unpaid sub-subcontractor when there was no
    evidence that the general contractor had paid the subcontractor, or anyone else, the contract price
    for the benefit in question); International Paper Co. v. Futhey, 
    788 S.W.2d 303
    , 306 (Mo. Ct.
    App. 1990) (finding that “[n]o unjust enrichment accrued to the [defendant] because [the general
    contractor] defaulted forcing them to expend additional sums in order to obtain what they were
    entitled to under the contract” and that “[t]he question of unjust enrichment focuses not upon
    what the contractor has received, but rather what the owner has paid”); Pella Windows & Doors,
    21
    landowner, but nearly always denied.” 2 Palmer, supra, § 10.7, at 423. In short, absent a
    showing of fraud or other tortious wrongdoing, traditional unjust-enrichment principles have
    never required a defendant to pay a remote, non-privity plaintiff when the defendant has already
    paid or is legally obligated to pay a party with whom he is in privity for the same benefit.
    Virginia law is entirely in agreement with this traditional understanding of unjust-
    enrichment principles. In Kern v. Freed Co., a homeowner hired a general contractor to build a
    house for a fixed price. The house was to include major kitchen appliances. The homeowner
    also retained an interior designer to decorate the house for a fixed price. After the house had
    been constructed, a supplier of kitchen equipment sued the homeowner because neither the
    general contractor nor the interior designer had paid for the equipment supplied to the house.
    The supplier argued that the homeowner had received the equipment and should pay for it. The
    trial court agreed; we did not.
    Reversing the unjust-enrichment award, we pointed out the third-party nature of the
    dispute. The homeowner was never in privity of contract with the supplier. See 
    Kern, 224 Va. at 680
    . “Therefore,” we concluded, the homeowner was “not liable” under contract principles to
    the supplier for any appliances sold to the general contractor or to the interior designer.
    Id. We Inc.
    v. Faraci, 
    580 A.2d 732
    , 733 (N.H. 1990) (per curiam) (denying restitution to an unpaid
    window supplier when the homeowner had “spent well in excess of their originally anticipated
    construction costs” and thus were not unjustly enriched); Sundance Mech. & Util. Corp. v. Atlas,
    
    880 P.2d 861
    , 866 (N.M. 1994) (denying the subcontractor’s claim for unjust enrichment when
    the defendant had paid “a very substantial part” of the contract amount owed to the general
    contractor (citation omitted)); Columbia Wholesale Co. v. Scudder May N.V., 
    440 S.E.2d 129
    ,
    131 (S.C. 1994) (“Courts addressing a claim of unjust enrichment by a subcontractor against a
    property owner have typically denied recovery where the owner in fact paid on its contract with
    the general contractor.”); Morrisville Lumber Co. v. Okcuoglu, 
    531 A.2d 887
    , 889 (Vt. 1987)
    (“The retention of a benefit is not unjust where defendants have paid for it. Defendants were not
    unjustly enriched since defendants satisfied their obligation by paying in excess of the original
    contract price.”).
    22
    then pointed out that the homeowner had paid the general contractor and the interior designer
    everything that they had been owed under their respective contracts — and both fixed-price
    contracts included the delivery of major appliances.
    Id. at 680-81.
    On this ground alone, we held that the “quasi-contract” award of unjust enrichment was
    erroneous as a matter of law. See
    id. It was
    not enough that the supplier had not been paid and
    that the homeowner was benefiting from the new appliances. The supplier “should not be
    allowed to shift the burden of its loss” to the homeowner because the homeowner was
    contractually entitled to the appliances under his fixed-price contracts with the general contractor
    and interior designer.
    Id. at 681.
    In short, the homeowner “was not unjustly enriched by keeping
    the items in question” because he had paid the general contractor and the interior designer
    everything they were owed for providing the appliances.
    Id. The conclusion
    in Kern should be all the more certain in construction scenarios, in which
    the Virginia mechanics’ lien statute provides remedies to those “who, by their labor and
    materials, have enhanced the value of a building or structure,” United Sav. Ass’n of Tex., F.S.B.
    v. Jim Carpenter Co., 
    252 Va. 252
    , 260 (1996) (alterations and citation omitted); see Code § 43-
    3. A “historic provision of the law,” Rosser v. Cole, 
    237 Va. 572
    , 576 (1989), the mechanics’
    lien statute creates “a powerful weapon for the protection of small contractors, suppliers and
    salaried employees,” Costello, supra note 2, § 16.14[6], at 16-33. This weapon — a statutory
    lien — is “in derogation of the common law.” American Standard Homes Corp. v. Reinecke,
    
    245 Va. 113
    , 119 (1993). The inverse could be said of unjust-enrichment law if it were extended
    beyond its traditional boundaries. It would then become an unwitting judicial derogation of the
    mechanics’ lien statute. See generally 2 Palmer, supra, § 10.7, at 423-24 (1978 & Supp. 2019)
    (collecting cases).
    23
    II.
    The undisputed facts of this case fit squarely within the third-party, claim-of-right context
    and therefore preclude the unjust-enrichment claim as a matter of law.
    A.
    This case involves the typical contractual hierarchy found in the construction industry.
    An owner has a contract with a general contractor, who in turn has contracts with subcontractors,
    who in turn have contracts with suppliers. The relational riggings that hold everyone’s
    commercial expectations together are the actual contracts they entered into — not the “purely
    fictitious” ones, City of 
    Norfolk, 120 Va. at 363
    , that might be asserted later when the project
    falls apart. In such scenarios, the parties’ actual contracts “convey clearly the limited kinds of
    liability and exposure each party has in mind.” Dobbs & Roberts, supra note 1, § 4.8(4), at 494.
    It is true that “[e]ach party may benefit by the work or payments of both other parties, but the
    parties understand that their responsibilities and rights are only those set up by the contract.”
    Id. “Respect for
    that contract arrangement requires the courts to refuse restitution between the
    parties who did not contract with each other.”
    Id. In this
    case, the contract between James G. Davis Construction Corporation (the “general
    contractor”) and H&2 Drywall Contractor, LLC (the “subcontractor”) established a fixed
    contract price of $1,194,000 in exchange for completed drywall and metal framing, among other
    things. See 1 J.A. at 310. The parties later agreed to certain change orders that increased the
    fixed price to $1,269,396.
    Id. The general
    contractor paid the fixed contract price in
    installments calculated on a “percent complete basis” that allowed the general contractor to
    “evaluate things on a 100 percent complete basis by area or by activity basis.”
    Id. at 438-40.
    The installment payments covered “[e]verything that’s required to complete [the] scope” of that
    24
    area or activity basis.
    Id. at 440.
    Nothing in this contract obligated the general contractor to
    calculate its installment payments to correspond to individual shipments of drywall sheets, metal
    wall framing, or any other itemized list of materials.
    The subcontractor needed raw materials, including drywall sheets, and contracted with
    FTJ, Inc., formerly Ciesco, Inc., (the “supplier”) for a steady supply. Pursuant to an existing
    credit agreement, the subcontractor agreed to pay the supplier for any materials supplied. The
    subcontractor’s owner executed a personal guarantee to the supplier. The general contractor was
    not a party to either the credit agreement or to the personal guarantee.
    At no point did the general contractor agree to be liable to the supplier in the event that
    the subcontractor failed to pay its own bills. Instead, in a form entitled “Joint Check
    Agreement,” the general contractor stated that it would do only one very specific thing: When
    the general contractor issued checks to the subcontractor who was seeking payment for the
    subcontractor’s services, some of those checks would include the supplier as a joint payee. See
    2
    id. at 704.
    The “sole purpose” of doing so was to “assist” the subcontractor, not the general
    contractor, in “making payment” to the supplier for “invoices on sales” of drywall by the
    supplier to the subcontractor, not to the general contractor.
    Id. Consequently, joint
    checks
    would “only” be issued “to the extent that [the general contractor] actually owes money to
    [s]ubcontractor on the Project.”
    Id. As the
    supplier’s accountant testified, “My understanding
    was that the joint checks were going to only come when there [were] payments due to [the
    subcontractor].” 1
    id. at 409.
    The Joint Check Agreement was poorly named as it was not much of an agreement. It
    stipulated that it did not create “any contractual relationship” between the general contractor and
    the supplier. 2
    id. at 704.
    Nor did it impose any “equitable obligation” on the general contractor
    25
    to pay the supplier anything.
    Id. Insisting further
    that it did not “constitute an assignment of
    fund[s],” the Joint Check Agreement stated that it was “solely for the convenience of the parties”
    and could be “cancelled at any time” by the general contractor upon written notice.
    Id. 5 Under
    the Joint Check Agreement, the subcontractor and supplier would agree among
    themselves what the former owed the latter for drywall delivered to the subcontractor. The
    general contractor would then be informed of this agreed-upon amount and would include it in
    the next installment check for payment to the subcontractor pursuant to the subcontract. The
    general contractor did not pay the supplier directly for anything or agree to do so. The general
    contractor was simply paying its subcontractor and, as an accommodation to its subcontractor’s
    request, adding the supplier as a joint payee.
    Contrary to the majority’s recitation of the facts, 6 the general contractor did not directly
    pay the supplier for any invoices that the supplier had issued to the subcontractor. 7 The general
    contractor did not order supplies, count the number of drywall sheets delivered to the
    subcontractor, determine the timeliness of any shipments by the supplier, or approve the pricing
    in the supplier’s invoices to the subcontractor. 8 Every check that the general contractor issued to
    5
    The majority concludes that the Joint Check Agreement gave the supplier “a greater
    assurance” that “it will be paid” for its supply of drywall to the subcontractor, see ante at 3. In
    fact, however, the supplier had no assurance at all (either greater or lesser) that it would ever be
    paid for a single shipment under the Joint Check Agreement. The supplier’s invoices became
    due 60 days after shipment. The Joint Check Agreement made clear that the general contractor
    could unilaterally cancel it at any time, before or after any shipment by the supplier to the
    subcontractor.
    6
    See ante at 3, 10, 14.
    7
    As described above, the general contractor issued each joint check pursuant to a Joint
    Check Agreement Payment Verification form executed by the subcontractor and the supplier and
    then submitted to the general contractor, not pursuant to any invoices. It is undisputed that every
    joint check followed this same process. See 1 J.A. at 412-13, 461.
    8
    The majority implies that the general contractor managed the process, the orders, and
    the invoices with the supplier. See ante at 4. The general contractor’s project manager testified
    26
    the subcontractor was an installment payment required by the subcontract between the general
    contractor and the subcontractor, not the revolving credit agreement between the subcontractor
    and the supplier. In short, the Joint Check Agreement imposed no legal or equitable obligation
    upon the general contractor to pay the supplier anything.
    B.
    When the subcontractor began to underperform on the project at some point in early
    2017, the general contractor issued a notice to cure on March 21. On the next day, the general
    contractor warned the supplier not to deliver any more materials to the subcontractor. Hoping to
    nonetheless make the supplier whole, the general contractor predicted that there would be
    “[p]lenty of money left in [the] project” to directly pay the supplier (outside the parameters of the
    Joint Check Agreement) for the subcontractor’s breach of the supply agreement, see
    id. at 705.
    That prediction turned out to be wrong.
    During the next month, the general contractor began to calculate its expected losses
    associated with the defaulting subcontractor and concluded that the drywall project appeared to
    be financially underwater. On the date of the last joint check, March 1, the general contractor
    had responded to every payment request made pursuant to the Joint Check Agreement. Earlier
    deliveries by the supplier to the subcontractor were not overdue for payment on March 1 and, for
    that reason, had not been paid yet. But the supplier made no drywall deliveries after March 22
    when the general contractor had notified the supplier of the subcontractor’s breach. And the
    supplier made no deliveries after the general contractor’s optimistic prediction that there would
    only that being copied on invoices was “not a typical scenario,” but clarified that he did not
    check the invoices, manage the orders, or verify materials. See 1 J.A. at 474-75.
    27
    be sufficient project funds available to pay the supplier. It is illogical, therefore, to suggest that
    the supplier relied at all on the general contractor’s prediction. 9
    After the general contractor had hired a replacement subcontractor to finish the drywall
    project, the general contractor’s earlier fears of a financial loss proved to be true. The general
    contractor and the original subcontractor had agreed (including the initial price and the agreed-
    upon change orders) that the project would cost $1,269,396. See 1
    id. at 310.
    The subcontractor
    defaulted after the general contractor had made $969,779.70 in installment payments to the
    defaulting subcontractor.
    Id. at 311-12.
    The stipulated damages associated with the default
    amounted to $41,852.20. 10
    Id. at 313.
    Because the defaulting subcontractor had left the project
    undone, the general contractor hired a replacement subcontractor at a cost of $260,007. In the
    end, the general contractor lost $2,242.90 on the drywall project after having to pay the original
    subcontractor everything that it was owed.
    C.
    We must filter these undisputed facts through the third-party, claim-of-right principles
    governing unjust-enrichment claims. This case is not about whether the general contractor paid
    for each sheet of drywall delivered to the job site. The legally relevant question is whether the
    general contractor paid the subcontractor what the subcontractor was owed for anything
    (services, materials, etc.) it was supposed to provide under its fixed-price contract. The answer
    to that question is factually incontestable: The general contractor fully paid the defaulting
    9
    The majority points to the supplier’s testimony that they “felt confident in the
    assurances [they] were provided” by the general contractor during the March 22 conversation.
    See ante at 5. But this statement is irrelevant because the supplier did not rely on that assurance
    to deliver any materials.
    10
    Though I do not think it analytically necessary, in calculating the general contractor’s
    overpayment, I have omitted the legal expenses that the general contractor incurred as a result of
    the subcontractor’s default. See 1 J.A. at 313 (payments to Peckar & Abramson).
    28
    subcontractor everything the subcontractor was owed and suffered a loss on top of that. The
    general contractor was left with a $2,242.90 deficit on its books because of this subcontract — a
    loss that it could not recover from any party. The unjust-enrichment award in this case only
    compounds that loss. It is equally incontestable that the supplier’s materials fell within the scope
    of the agreed-upon contract price. 11
    In other words, the general contractor had a bona fide claim of right to the drywall. 12 The
    subcontractor had a contractual duty to buy the drywall, deliver it to the job site, and install it.
    The general contractor paid the subcontractor pursuant to a fixed-price subcontract that did not
    atomize the duty to pay for any one piece, stack, or truckload of drywall. In the third-party,
    claim-of-right context, the court cannot award unjust enrichment when the general contract has
    paid the contract price for the benefit it received “even if the contract price is less than the cost or
    value of the performance in question.” Restatement (Third) of Restitution and Unjust
    Enrichment § 25 cmt. b.
    11
    This is not a case in which the scope of the original contract “failed to cover significant
    aspects of the project,” making it impossible for the court to determine whether the benefit
    received had been paid for in the installment payments and other payments after the
    subcontractor’s default. See Restatement (Third) of Restitution and Unjust Enrichment § 25 cmt.
    b, illus. 2.
    12
    The majority seems to imply that neither the general contractor nor the subcontractor
    acquired title to the drywall, and their contract only permitted the general contractor to “use the
    supplies” even though it “did not have ownership over the supplies” because it “did not pay for
    them,” see ante at 11 n.3. The only logical conclusion from the majority’s implication is that
    title to the drywall remained with the supplier. In this heavily litigated case, the supplier has
    never claimed to have title or an ownership interest in any of the goods it sold to the
    subcontractor, which were then re-sold in a labor and materials contract to the general contractor.
    The supplier never made that argument because it conveyed title of the goods to the
    subcontractor upon delivery, see Code § 8.2-401(2) (adopting the Uniform Commercial Code
    provision that unless otherwise agreed, the title for goods passes to the buyer upon physical
    delivery of the goods), and the supplier had no right of repossession or self-help, see Code § 8.2-
    702(2) (articulating the limited circumstances under which a credit seller can reclaim goods).
    See also 1 Palmer, supra, § 4.16, at 499-500 (explaining that a credit seller cannot ordinarily
    reclaim goods after delivery because it has given up both title to and possession of the goods).
    29
    The majority comes to a different conclusion based upon a legally flawed premise and a
    mistaken interpretation of the factual record. The legal error stems from the majority
    disregarding the fact that the general contractor “had to pay more than originally projected to
    finish the job,” ante at 12. This very assertion misconstrues the general contractor’s argument.
    The general contractor focuses its argument on the cost to finish the scope of work in the
    subcontract — not the overall costs, projected or ultimately incurred, “to finish the job,” ante at
    12. Regardless, the majority reasons that none of this matters because “it is the payment for
    specific supplies that is at issue, not the overall cost of the project.” Ante at 12. That is akin to
    saying that the defendant was unjustly enriched because he ended up a little less impoverished.
    Such a view cannot possibly survive the “highly protective” legal standard applicable to
    restitution awards in the third-party, claim-of-right context, Restatement (Third) of Restitution
    and Unjust Enrichment ch. 3, topic 2, intro. note, which insists on “a rigorous test” as a threshold
    requirement for the imposition of unjust-enrichment liability,
    id. § 25
    cmt. b.
    Taking an aberrant view of this issue, the majority adopts the reasoning of an
    intermediate state court, see ante at 15-16, that is both internally inconsistent and in opposition to
    the Restatement. 13 In Morris Pumps v. Centerline Piping, Inc., 
    729 N.W.2d 898
    , 905 (2006), the
    13
    In an effort to demonstrate that its position is not aberrant, the majority cites to cases
    that apparently allow “recovery in circumstances similar to the one we face here,” see ante at 13
    n.5. In Flooring Systems, Inc. v. Radisson Group, Inc., 
    772 P.2d 578
    , 581 (Ariz. 1989) (en
    banc), the court reversed a summary judgment ruling against a subcontractor and remanded the
    case for an evidentiary hearing, noting that the owner had not paid the full contract price owed to
    the general contractor. In Eastern Metal Products, Inc. v. Deperry, 
    686 A.2d 1003
    , 1004 (Conn.
    App. Ct. 1997), the court reversed the trial court’s dismissal and remanded the case for an
    evidentiary hearing because the trial court had erroneously held that a tenant, unlike a landowner,
    could never be unjustly enriched by a general contractor’s work. In Trane Co. v. Randolph
    Plumbing & Heating, 
    722 P.2d 1325
    , 1328-29 (Wash. Ct. App. 1986), the court held that a
    general contractor was unjustly enriched when the defaulting subcontractor’s surety paid the
    general contractor to furnish and install six fans, and the general contractor did not pay the
    supplier for the fans it had delivered. Not only are these cases factually dissimilar in significant
    30
    Michigan Court of Appeals found that although the general contractor “may have paid more than
    the full contract price originally contemplated in the subcontract,” it was still obligated to
    compensate the supplier for the materials delivered to the job site. This view is opposed not only
    by the Restatement, 14 but also by the “extremely numerous” cases that turn on whether the
    defendant paid the contract price under a contract that included the benefit at issue, see
    Restatement (Third) of Restitution and Unjust Enrichment § 25 reporter’s note; supra note 4 and
    accompanying text. The question of whether the general contractor paid for the supplies should
    be answered by whether the general contractor paid the contract price for the scope of work
    encompassing those supplies.
    The majority also mistakenly implies that the general contractor, after the original
    subcontractor’s default, simply lucked into some free stacks of uninstalled drywall that were
    turned over to the replacement subcontractor in return for a dollar-for-dollar reduction in the cost
    of picking up where the defaulting subcontractor had left off — thus, no harm, no foul. See ante
    at 12. The supplier, however, has never made this factual assertion either at trial or on appeal,
    and the record does not support it.
    All we know is that the supplier did not deliver drywall to the job site after the general
    contractor had fired the defaulting subcontractor. No witness or exhibit at trial suggested (much
    less proved) that there had been stacks of drywall lying around on the job site ready for the
    replacement subcontractor to use. Nor did the supplier attempt to establish how much of the
    ways, but they do not support the majority’s conclusion that a general contractor can be unjustly
    enriched even when it has paid the full contract price for the benefit it received.
    14
    See Restatement (Third) of Restitution and Unjust Enrichment § 25 cmt. b (“There is
    accordingly no unjust enrichment if [the defendant] has paid the contract price to [the third
    party]; nor if [the defendant] has paid in full (to [the third party] and to others, following [the
    third party’s] default) the price originally fixed by contract for the work to which [the plaintiff]
    has made an uncompensated contribution.”).
    31
    drywall the subcontractor had already installed or left uninstalled prior to permanently leaving
    the job site. Despite having the burden of proof, the supplier offered no evidence on any of these
    factually dispositive points. The majority responds to this failure-of-proof point by summarily
    dismissing it as legally “irrelevant,” see ante at 12. Under traditional principles of unjust
    enrichment, I do not see how that could be true.
    III.
    Having failed to establish a quasi-contract claim, the majority adds to it a quasi-fraud
    claim — as if two half theories of liability make a whole.
    The majority emphasizes the general contractor’s conduct in dealing with the supplier,
    alleging that it directly paid the supplier’s invoices and communicated “repeated assurances” of
    payment. See ante at 10-11, 14, 16. The general contractor did this “to ensure a continued flow
    of supplies.” Ante at 16. Although the general contractor was aware of the subcontractor’s
    “precarious” financial position, it “directly encouraged [the supplier] to continue shipping
    supplies.” Ante at 14 (emphasis added). These facts prove, the majority concludes, that the
    general contractor misleadingly “led the supplier to believe that payment for those supplies
    would be forthcoming.” Ante at 16.
    This narrative comes quite close to accusing the general contractor of representing “as
    true what [was] really false, in such a way as to induce a reasonable person to believe it, with the
    intent that the person [would] act upon this representation,” Evaluation Research Corp. v.
    Alequin, 
    247 Va. 143
    , 148 (1994), which is one of the definitions of common-law fraud. The
    supplier, however, did not allege, prove, or even mention fraud of any kind. “Under Virginia
    law, ‘fraud, whether actual or constructive, is never presumed and must be strictly proved as
    alleged.’” Sweely Holdings, LLC v. SunTrust Bank, 
    296 Va. 367
    , 381 (2018) (alteration and
    32
    citation omitted). Litigants must plead fraud with particularity and prove it by clear and
    convincing evidence, a burden of proof “higher than a mere preponderance,”
    id. at 382.
    “The
    charge must be direct as the proof must be clear.”
    Id. (citation omitted).
    Virginia law does not
    recognize claims of quasi-fraud. 15
    What is more, the majority’s enticement theory relies upon two unsupportable factual
    assertions: (i) that the general contractor, breaking from industry custom, communicated directly
    with the supplier and directly paid the supplier’s invoices, and (ii) that the general contractor
    knew of the subcontractor’s inevitable default while enticing the supplier to continue shipments
    with false promises of future payments. The evidence supports neither of these assertions.
    As to the first assertion, the general contractor did not directly pay the supplier’s
    invoices, see supra note 7 and accompanying text, but consistently followed the standard process
    of issuing joint checks in response to payment-verification forms executed by the subcontractor
    and supplier, see 1 J.A. at 461, which the supplier agreed “was the process that was followed for
    all of the joint checks on this project,” see
    id. at 412-13.
    The communications between the
    general contractor and the supplier merely discussed the status of the joint checks pursuant to the
    payment-verification forms.
    As to the second assertion, no evidence proves that the general contractor knew the
    subcontractor would default (or be unable to pay suppliers) prior to sending the notice to cure on
    March 21. The evidence demonstrates only that the general contractor knew that the
    subcontractor had been having manpower issues at some unidentified point “early in 2017,” see
    id. at 465,
    sent the notice to cure on March 21,
    id. at 310,
    and knew on March 22 that the
    15
    I say “quasi-fraud” because the majority expressly disclaims any effort to say the
    general contractor committed actual fraud, see ante at 16 n.6.
    33
    subcontractor would not be able to pay its suppliers,
    id. at 467.
    The general contractor made no
    promises, express or implied, that it would guarantee payment to the supplier if the subcontractor
    defaulted.
    The majority repeatedly claims that the general contractor gave “assurances” of payment
    to the supplier. See ante at 4, 5, 10, 11, 14. The implication is that the general contractor’s
    communication regarding joint checks morphed into some kind of false assurance to the supplier
    of future payment for the continued delivery of supplies. The evidence the majority relies upon,
    however, is wholly insufficient to support this implication. 16 Not one conversation between the
    general contractor and supplier suggested an assurance of payment for a future delivery of
    supplies.
    The evidence in this case cannot support a viable fraud claim, even if one had been
    pleaded, and should not be used to support a quasi-fraud claim, even if one existed legally. I
    thus reject the enticement-by-false-assurances narrative that is just below the surface of the
    majority’s reasoning.
    IV.
    In sum, the trial court erred as a matter of law by awarding unjust enrichment to a
    supplier that had not been paid by its customer, a defaulting subcontractor, in a case in which the
    16
    The majority mentions three specific communications from November 2016,
    December 2016, and January 2017. Ante at 3. In November 2016, the general contractor replied
    to a question from the supplier regarding the status of its joint check by confirming the submitted
    payment-verification forms and providing the issue date for the next set of checks. See 2 J.A. at
    706-09. In December 2016, the supplier asked about the status of the recently submitted
    payment-verification form, and the general contractor replied that the joint check had already
    been issued. See R. at 1534-35. In January 2017, the general contractor told the supplier that it
    would be able to issue the joint check for the October (now past due) and November payment-
    verification forms by the end of January, see 2 J.A. at 710, which it did. The subcontractor was
    routinely copied in these conversations. See
    id. at 706-07,
    710-11; R. at 1533-35.
    34
    general contractor had paid the defaulting subcontractor everything the subcontractor had been
    owed and still suffered a loss.
    I respectfully dissent.
    35