Tyger Construction v. Commonwealth ( 1997 )


Menu:
  •                     COURT OF APPEALS OF VIRGINIA
    Present: Judges Baker, Bray and Overton
    Argued at Norfolk, Virginia
    TYGER CONSTRUCTION COMPANY, INCORPORATED
    AND PENSACOLA CONSTRUCTION COMPANY,
    joint venturers d/b/a TYGER-PENSACOLA
    MEMORANDUM OPINION *
    v.        Record No. 1208-96-1       BY JUDGE JOSEPH E. BAKER
    APRIL 15, 1997
    COMMONWEALTH OF VIRGINIA,
    DEPARTMENT OF HIGHWAYS AND TRANSPORTATION
    AND COMPTROLLER OF THE COMMONWEALTH OF VIRGINIA
    FROM THE CIRCUIT COURT OF THE CITY OF NEWPORT NEWS
    Robert W. Curran, Judge
    Guilford D. Ware (Martha M. Poindexter;
    Crenshaw, Ware & Martin, P.L.C., on briefs),
    for appellants.
    Judith B. Anderson, Assistant Attorney
    General (James S. Gilmore, III, Attorney
    General; J. Steven Sheppard, III, Senior
    Assistant Attorney General; Kenneth C. Grigg,
    Assistant Attorney General, on brief), for
    appellees.
    Tyger Construction Company, Incorporated and Pensacola
    Construction Company, joint venturers d/b/a Tyger-Pensacola
    (jointly referred to herein as Tyger) appeal from a judgment of
    the Circuit Court of the City of Newport News (trial court) that
    denied Tyger's request for compensation claimed to be due
    pursuant to a contract with the Commonwealth of Virginia,
    Department of Highways and Transportation, and the Comptroller of
    the Commonwealth of Virginia (jointly referred to herein as
    *
    Pursuant to Code § 17-116.010 this opinion is not
    designated for publication.
    VDOT).   Although Tyger alleged several trial court errors, we
    need only respond to one.   That issue is whether Norfolk Dredging
    Company (NDC), a subcontractor of Tyger, is entitled to
    compensation for claimed "extra work" allegedly performed on
    behalf of Tyger pursuant to Tyger's contract with VDOT.   To
    recover from VDOT for that alleged "extra work," Tyger must prove
    that NDC is entitled to recover from Tyger for "extra work."
    On appeal, the dispositive issue is whether the trial
    court's finding that Tyger was not entitled to recover
    compensation from VDOT for "extra work" alleged to have been
    performed by NDC is supported by credible evidence in the record.
    We hold that the trial court's finding that Tyger was not
    entitled to recover for "extra work" is supported by the record.
    As the parties are fully conversant with the facts, we state only
    those facts necessary to an understanding of this opinion.
    Guided by well established principles, we construe the
    evidence in the light most favorable to the party prevailing
    below.   See Crisp v. Brown's Tysons Corner Dodge, Inc., 1 Va.
    App. 503, 504, 
    339 S.E.2d 916
    , 916 (1986).   If there is evidence,
    or reasonable inferences can be drawn from the evidence, to
    support the trial court's findings, they will not be disturbed on
    review, even though there is evidence in the record to support a
    contrary finding.   See Morris v. Badger Powhatan/Figgie Int'l.,
    Inc., 
    3 Va. App. 276
    , 279, 
    348 S.E.2d 876
    , 877 (1986).    In
    determining whether credible evidence exists, this Court will not
    - 2 -
    retry the facts, reweigh the preponderance of the evidence, or
    make its own determination of the credibility of the witnesses.
    Wagner Enters., Inc. v. Brooks, 
    12 Va. App. 890
    , 894, 
    407 S.E.2d 32
    , 35 (1991).
    In 1985, Tyger contracted with VDOT to perform work
    incidental to the construction of the Interstate 664 bridge
    approaches and tunnel between Newport News and Suffolk
    (contract).    With the approval of VDOT, Tyger entered into a
    subcontract with NDC to perform the dredging work in the sites
    designated as the North Island and South Island (subcontract)
    where the highway would exit the tunnel.   The contract provided
    that Tyger would excavate unsuitable materials from the channel
    bottom as necessary for the construction of the North and South
    Islands.   VDOT would pay for the dredging work by the cubic yard
    of material removed.
    VDOT prepared and provided copies of initial tests it had
    made that generally described the subsurface materials to be
    encountered at the North Island site as muck and soft cohesive
    soils.   On the copies, VDOT specifically warned that VDOT does
    not guarantee that the boring logs provided are indicative of
    conditions beyond the limits of the borings.   Additionally, of
    the nine borings in the North Island site, two showed a "trace of
    wood fiber(s)."
    In the week prior to turning in its bid, NDC performed its
    own borings.   Of NDC's seven borings, one indicated a trace of
    - 3 -
    wood and another actually hit wood so hard that NDC could not
    penetrate it.    Instead of investigating in the vicinity of the
    hard wood, NDC simply moved over twenty feet and continued its
    borings.    At trial, NDC's employee responsible for its bid was
    asked whether he took subsurface wood obstructions into
    consideration in preparing NDC's bid and he responded:      "Why
    should I bid a different job than any other bidder?    Why should I
    take myself out of contention?"
    While performing the work at the North Island site, NDC
    encountered timber pilings, steel cables, rubber tires, and other
    subsurface remnants of a VDOT ferry terminal that had once
    occupied the site.    NDC claimed it spent more than nine
    additional days to remove the remnants of the ferry terminal.
    However, NDC had estimated a total of three months to complete
    the North and South Island dredging and completed the work in
    only two months.    NDC also excavated a smaller volume of material
    from the sites than anticipated.
    The contract provided that Tyger was to perform and be paid
    for unforeseen work for which there was no price in the contract
    whenever it was necessary or desirable in order to complete the
    work as contemplated.    Tyger asserts that NDC incurred
    $464,558.41 of expense in addition to the expenses required and
    contemplated by the contract.    VDOT refused to pay for the
    alleged "extra work," and Tyger brought suit for that sum against
    VDOT.
    - 4 -
    Based on the evidence presented, the trial court ruled that
    the work for which NDC sought additional compensation was not
    "extra work," as defined by the contract.   The contract
    definition of "extra work" sets out three elements that must be
    met before compensation for "extra work" is merited:   (1) the
    work must be unforeseeable; (2) no price must be included for it
    in the contract, i.e., it is not already part of the work
    described in the contract; (3) the work "is deemed necessary or
    desirable in order to complete fully the work as contemplated."
    Tyger contends that encountering the debris was
    unforeseeable because it was not described in the boring logs
    included in the contract.   However, disclaimers were included in
    the contract which warn the bidder against speculating as to
    general conditions based on the limited information given.    The
    nine one and three-quarter inch borings included in the contract
    identified only the nature of the material in the nine cylinders.
    The entire area of the North Island covers several thousand
    square feet.   NDC's own borings, conducted before it submitted a
    bid proposal to Tyger, revealed not only traces of wood, but wood
    so hard that the boring could not be completed at one location.
    Furthermore, Tyger's expert testified that trash and debris,
    including tires and logs can be expected along a shoreline or at
    the mouth of a harbor.   The record is replete with evidence that
    the material encountered was foreseeable.
    As to the second element of the "extra work" definition, the
    - 5 -
    contract contained a price for the work.   The unit price for
    Section 801 dredging constituted "full compensation for dredging
    . . . ."    Under the plain language of the contract, the unit
    price covered all of the North Island dredging including the
    bulky materials.   Since Tyger's claim fails the first two
    elements of the contract definition of "extra work," the third
    element is irrelevant.   The record supports the trial court's
    finding that the work performed was a foreseeable part of the
    contract.   The trial court's finding that Tyger was not entitled
    to compensation for "extra work" was amply supported by the
    evidence and based upon the wording of the contract and Virginia
    law.   We cannot say that the decision of the trial court was
    plainly wrong or without evidence to support it.
    Accordingly, we affirm the judgment of the trial court.
    Affirmed.
    - 6 -
    

Document Info

Docket Number: 1208961

Filed Date: 4/15/1997

Precedential Status: Non-Precedential

Modified Date: 10/30/2014