C. Ray Davenport, Commissioner, Virginia Labor and Industry v. G.D.C., Inc. ( 2004 )


Menu:
  •                                COURT OF APPEALS OF VIRGINIA
    Present: Judges Benton, Humphreys and Senior Judge Coleman
    Argued at Chesapeake, Virginia
    C. RAY DAVENPORT, COMMISSIONER,
    VIRGINIA DEPARTMENT OF
    LABOR AND INDUSTRY
    MEMORANDUM OPINION* BY
    v.     Record No. 0015-04-1                                   JUDGE SAM W. COLEMAN III
    NOVEMBER 9, 2004
    G.D.C., INC.
    FROM THE CIRCUIT COURT OF YORK COUNTY
    Prentis Smiley, Jr., Judge
    Catherina F. Hutchins, Assistant Attorney General (Jerry W. Kilgore,
    Attorney General, on brief), for appellant.
    Paul C. Miller for appellee.
    The Commissioner of the Virginia Department of Labor and Industry (the
    “Commissioner”) appeals from an order of the circuit court dismissing citations he issued against
    G.D.C., Inc. (“GDC”) for two “serious violations” of the Virginia Overhead High Voltage Line
    Safety Act (the Act). Code § 59.1-406 et seq.; Code § 40.1-49.3. The Commissioner contends
    the trial court erred by (1) dismissing the two serious violations when the evidence had clearly
    established the violations, and (2) applying tort law analysis in determining whether GDC had
    violated Code §§ 59.1-408 and -410. Concluding the circuit court used an incorrect analysis, we
    vacate the circuit court’s order and remand the case for findings using an appropriate analysis.
    *
    Pursuant to Code § 17.1-413, this opinion is not designated for publication.
    BACKGROUND
    We view the facts in this case “in the light most favorable to sustaining the
    Commissioner’s action and ‘take due account of the presumption of official regularity, the
    experience and specialized competence of the Commissioner, and the purposes of the basic law
    under which the Commissioner has acted.’” Sentara Norfolk General Hosp. v. State Health
    Comm’r, 
    30 Va. App. 267
    , 279, 
    516 S.E.2d 690
    , 696 (1999) (internal brackets omitted) (quoting
    Bio-Medical Applications of Arlington, Inc. v. Kenley, 
    4 Va. App. 414
    , 427, 
    358 S.E.2d 722
    ,
    729 (1987)).
    GDC entered into a “Subcontract Agreement” with Browning-Ferris, Inc. (“BFI”) to
    transport waste material from BFI’s solid waste transfer station in York County to disposal sites.
    As part of the agreement, BFI would “provide the services and equipment necessary to load the
    trailers” and GDC would provide “all services and equipment required to drop load or live load
    the trailers and perform . . . transportation,” including trucks and trailers. Dominion Virginia
    Power has a 200 feet wide easement to suspend high voltage power lines across a portion of
    BFI’s transfer station property.
    On June 2, 2003, Kelly Smith, a truck driver employed by GDC, received a fatal electric
    shock as he stood on a trailer filled with garbage. Although there were no witnesses to the
    accident, the evidence suggested that Smith had climbed on the filled trailer to cover its contents
    with a tarpaulin. At the time of the accident, the trailer was parked beneath the overhead high
    voltage lines. Measurements taken after the accident showed that the distance between the top of
    the trailer and the closest overhead line was eight feet. At trial, there was no dispute that the
    driver, who stood five feet nine inches tall, would have been within six feet of the power lines
    when standing on the trailer. This incident caused the Commissioner to investigate whether
    GDC had violated the Act.
    -2-
    In a discussion with counsel and GDC’s representative concerning stipulations and
    undisputed facts, the trial judge learned that a cord had been hanging from the high voltage lines
    before the fatal accident. Although the record indicates investigators found a burned cord at the
    accident scene, the cord apparently was lost prior to trial. However, viewing photographs of the
    accident scene, the court noted the hanging cord was visible at the time the photos were taken.
    The undisputed facts established that GDC drivers pulled empty trailers onto the
    property. BFI moved the empty trailers to the loading station, filled the trailers, and moved the
    trailers to a holding area. GDC drivers would later arrive with an empty trailer, leave the empty
    trailer on the property, secure a filled trailer to the tractor, and drive away with the filled trailer.
    Charles Nobles, a trash hauler, testified that he visited the facility approximately 1,000
    times a year in the course of his business. He testified that he frequently observed loaded trailers
    parked under the power lines, and explained he often saw GDC drivers climb on top of the
    trailers to cover them with tarpaulins while they were parked under the power lines. He
    identified a diagram showing several trailers in a row, with one parked under the power line. He
    said “one was always there.” The diagram showed that the loaded trailers were parked around a
    semicircular “dirt path” over which the power lines crossed any vehicle parked at the front of the
    “path.” According to the diagram, only the truck or trucks parked at the front of the semicircle
    would have been under the power lines.
    Ronald Cooper, vice-president of GDC, testified he visited the site an average of six
    times a year for the purpose of “looking for hazards or anything that causes a problem.” He
    testified that twenty-two of his trailers were assigned to the station to be filled by BFI and then to
    be individually hauled by eight of his tractors. He testified “it was a regular course of business
    that BFI would cover any loaded trailer at the end of the day.” He also testified that he never
    saw trailers parked under the power lines. Rather, he testified that he saw the loaded trailers
    -3-
    parked in the back of the station, and he drew that location on a diagram. He further testified
    that none of his drivers informed him of the power lines as a hazard. Cooper agreed that the
    power lines were readily apparent to anyone visiting the site. In fact, Cooper stated that he did
    not like to leave his car while visiting the site because the power lines “snap, crackle, and pop.”
    The circuit court, focusing on the foreseeability of the electric cord causing the accident,
    dismissed the Commissioner’s citations for the two serious violations of the Act. The judge
    found “this was an isolated incident, not foreseeable” and the “cause of this tragedy” was the
    hanging cord. The circuit court did hold, however, that GDC had committed “an other than
    serious” violation of the Act by failing to maintain an injuries log.
    ANALYSIS
    The federal Occupational Safety and Health Act (“OSHA”) regulates conditions in
    private industry workplaces which affect worker safety and health. The federal government
    assigned OSHA enforcement responsibilities in Virginia to the Virginia Occupational and Safety
    Health Program (“VOSH”). To maintain federal OSHA approval, Virginia is required to
    maintain an OSHA program standard that is “at least as effective as” the federal standard. See
    29 C.F.R. § 1902.37(b)(4).
    Under the Virginia OSHA plan, VOSH inspects the private industry workplace for
    compliance with the applicable standards. Upon “reasonable cause to believe” that a violation
    has occurred, VOSH will issue a citation to the employer. Code § 40.1-49.4(A)(1). VOSH
    identifies a violation as “serious” as follows:
    “Serious violation” means a violation deemed to exist in a place of
    employment if there is a substantial probability that death or
    serious physical harm could result from a condition which exists,
    or from one or more practices, means, methods, operations, or
    processes which have been adopted, or are in use, in such place of
    employment unless the employer did not, and could not with the
    -4-
    exercise of reasonable diligence, know of the presence of the
    violations.
    Code § 40.1-49.3.
    Following Smith’s electrocution, VOSH conducted an investigation of the incident. As a
    result of the investigation, the Commissioner alleged violations of Code § 59.1-408.1(i) and
    § 59.1-410(A) and issued GDC two “serious violation” citations. The Commissioner also issued
    one “other than serious violation” for failing to maintain an injury log as required by the VOSH
    Administrative Regulations. The other than serious violation is not at issue in this appeal.
    Code § 59.1-408.1 provides, in pertinent part:
    No person shall, individually or through an agent or employee,
    perform, or require any other person to perform, any work or
    activity upon any land, building, highway or other premises that
    will cause (i) such agent, employee or other person to be placed
    within six feet (1.8 meters) of any overhead high voltage line . . . .
    Code § 59.1-410 requires any person desiring to work in closer proximity to the overhead high
    voltage lines to notify the owner or operator of the line. The manner of notification is prescribed
    in Code § 59.1-411, and work may take place only after negotiation and agreement between the
    employer and the line owner. The Commissioner concluded GDC had allowed an employee to
    work within six feet of the high voltage lines in violation of Code § 59.1-408.1(i) and had failed
    to notify Dominion Virginia Power, the owner of the lines.
    Undisputed Facts
    Before trial, both parties agreed to all the pertinent facts surrounding the incident and
    indicated the only dispute involved GDC’s knowledge that a hazardous condition or practice
    existed and whether GDC was a responsible person required under the Act to contact the owner
    of the power lines. Although GDC contends on appeal that the evidence failed to establish Smith
    was within six feet of the wires at the time he was injured, GDC’s counsel agreed before trial
    that “their calculations place [Smith] within that zone. And I can’t put on any evidence to show
    -5-
    otherwise.” When the court announced, “Okay. That’s not in dispute,” GDC agreed. GDC may
    not now argue on appeal Smith was not within six feet of the wires when its acquiescence at the
    hearing obviated the necessity for the Commissioner to further prove that fact. “The defendant,
    having agreed upon the action taken by the trial court, should not be allowed to assume an
    inconsistent position.” Clark v. Commonwealth, 
    220 Va. 201
    , 214, 
    257 S.E.2d 784
    , 792 (1979).
    Prohibited Activity
    “[U]nder Code § 40.1-49.3, the Commissioner’s burden of proof may be met upon a
    showing that [the employer] should have known of the violation in the exercise of reasonable
    diligence.” Magco of Maryland, Inc. v. Barr, 
    33 Va. App. 78
    , 85, 
    531 S.E.2d 614
    , 617 (2000).
    The trial court, in its review of the evidence, was required to determine under the Act whether
    the hazard was “open and obvious” and whether GDC “knew or should have known of the
    problem [or practice or condition] on the worksite that resulted in [Smith’s] death.” Id.
    Instead, the trial court focused solely on the cause of the fatal accident, concluding the
    hanging cord caused Smith to come into contact with the electrical wires and that his death
    therefore was not reasonably foreseeable. The trial court did not determine whether a GDC
    employer or its employees were working in violation of the Act due to a prohibited condition or
    practice in the workplace and whether GDC knew or should have known of any violations.
    Although the trial court determined that the proximate cause of Smith’s death was from other
    than a violation of the Act, that finding did not end the inquiry. Remaining to be decided was
    whether Smith’s presence within six feet of the overhead wires constituted a violation of the
    statute. In other words, even if Smith had not been fatally injured, did GDC know or should
    -6-
    have known that its employees were working beneath the wires in such proximity to be in
    violation of the Act.1
    Although the court noted that “Nobles’ observations were better than” Cooper’s
    regarding the working conditions at the site, that comment does not constitute a finding that
    GDC knew or should have known that its employees were working so close to the wires to be in
    violation of the Act. We also cannot presume that the judge’s foreseeability ruling concerning
    the cord’s position also relates to GDC’s knowledge of the practice of parking the trucks. We do
    not presume that the trial judge made the necessary findings to support his ruling when the
    record shows that an incorrect standard was applied. Thus, we vacate the trial court’s order and
    remand the case to the trial court to make the necessary, additional findings consistent with this
    opinion.
    Notification
    GDC contends it was not responsible for notifying Dominion Virginia Power of work
    being done in close proximity to the wires, as required by Code § 59.1-410. Specifically, Code
    § 59.1-410 requires, in pertinent part, that “[w]hen any person desires to carry on any work in
    closer proximity to any overhead high voltage line than permitted by this chapter, the person
    responsible for the work shall promptly notify the owner or operator of the high voltage
    line . . . .” Code § 59.1-407 provides that “‘Person’ means natural person, firm, business
    association, company, partnership, corporation or other legal entity.” It further explains that
    “‘Person responsible for the work’ means the person performing or controlling the work.”
    The record indicates that GDC was operating on the site under a “Subcontract
    Agreement” with BFI. That agreement provides rights and obligations of the parties. Although
    1
    Effective July 1, 2003, Code § 59.1-408 has been amended to provide that “[n]o person
    shall . . . work . . . within ten feet (3.1 meters) of any overhead voltage line.”
    -7-
    the trial judge found that the cause of the accident was the hanging cord and, therefore,
    concluded that GDC did not violate the Act, he made no findings whether GDC and/or BFI was
    responsible for placing the trailers under the wires, whether GDC employees were the persons
    who regularly placed the tarpaulins on the loaded trailers, or whether GDC had been aware of the
    activity, and was a “person” required under the Act to notify the owner of the lines.
    Accordingly, we vacate the final order and remand the case to the circuit court to
    determine whether GDC knew or should have known that its employer or employees engaged in
    prohibited activity under the Act.
    Vacated and remanded.
    -8-
    Humphreys, J., concurring, in part, and dissenting, in part.
    I write separately both to amplify the majority’s discussion of the applicable law and to
    dissent from the majority’s holding that the trial court’s statement relating to foreseeability and
    causation necessarily indicates that the trial court applied the incorrect standard of law.
    Once a violation of the Virginia OSHA regulations has been established, that violation
    may be deemed “serious” if
    there is a substantial probability that death or serious physical harm
    could result from [the condition causing the violation] . . . unless
    the employer did not, and could not with the exercise of reasonable
    diligence, know of the presence of the violation.
    Code § 40.1-49.3 (emphases added). Accordingly, once the Commissioner has demonstrated
    both that an OSHA regulation applies, and that a violation of that regulation has occurred, the
    violation will be deemed “serious” if the Commissioner can demonstrate both: (1) that the
    violation has created a “substantial probability” of death or serious physical harm; and (2) that
    the employer had actual or constructive knowledge of the condition causing the violation.
    The statutory language, then, does not require proof of either actual injury or causation:
    The Commissioner is not obligated to show that a death or serious physical harm did result from
    the violation, but rather, that a death or serious physical harm could have resulted from the
    violation. Moreover, the Commissioner does not need to establish that the employer knew or
    should have known about the risk of death or serious physical harm. Rather, the Commissioner
    must prove that the employer knew or should have known of the violation. See Magco of Md.,
    Inc. v. Barr, 
    33 Va. App. 78
    , 85, 
    531 S.E.2d 614
    , 617 (2000) (“[T]he Commissioner’s burden of
    proof may be met upon a showing that [the employer] should have known of the violation in the
    exercise of reasonable diligence.” (emphasis added)).
    Here, the trial court found that the Commissioner failed to establish a “serious” violation,
    reasoning as follows:
    -9-
    [T]he evidence points to the real cause of this tragedy to be the
    wire that was hanging from the power lines. The photograph of
    the cord that was hanging, that’s the culprit as far as this Court is
    concerned. Therefore, this Court finds that this was an isolated
    incident, not foreseeable and, therefore the Court dismisses the
    charges.
    Thus, the trial court’s language appears to focus on whether this particular death was
    proximately caused by (i.e., a foreseeable result of) the violation. As discussed above, however,
    the Commissioner did not need to prove that the alleged violation actually and proximately
    caused Smith’s death. Rather, the Commissioner only needed to show that the violation created
    a substantial probability of an injury, not a substantial probability of this injury. To interpret the
    statute as requiring proof that a violation actually and proximately caused a particular injury
    would force the Commissioner to wait until a death or other injury has occurred before he could
    issue a citation for a “serious” violation. This interpretation would be antithetical to the
    preventative purposes of the OSHA regulations. Accordingly, I concur with the majority’s
    conclusion that the trial court erred if it relied solely on the lack of actual or proximate cause
    when it dismissed the “serious” violations.
    But I am not convinced, as is the majority, that the language used by the trial court
    automatically gives rise to the presumption that its dismissal of the “serious” violations was
    predicated solely on the quoted discussion regarding foreseeability and causation. “Absent clear
    evidence to the contrary in the record, the judgment of a trial court comes to us on appeal with a
    presumption that the law was correctly applied to the facts.” Yarborough v. Commonwealth,
    
    217 Va. 971
    , 978, 
    234 S.E.2d 286
    , 291 (1977). Thus, “we will not fix upon isolated statements
    of the trial judge taken out of the full context in which they were made, and use them as a
    predicate for holding the law has been misapplied.” Id. Moreover, a “trial court’s remark is not,
    in and of itself, ‘the full context’ simply because it represents the only point at which the court
    - 10 -
    [expressly] addressed the issue [in dispute].” Bassett v. Commonwealth, 
    13 Va. App. 580
    ,
    583-84, 
    414 S.E.2d 419
    , 421 (1992).
    Here, looking at the full context of the proceedings before the trial court, there is no
    “clear evidence” that the trial court did not know and correctly apply the law. Rather,
    considering both the proceedings as a whole and the lack of any evidence in the record
    establishing that the employer actually knew or should have known about its trucks being parked
    beneath the power line, it is plausible that the trial court, in addition to and separate from its
    commentary on foreseeability and lack of causation, concluded that the Commissioner failed to
    carry his burden of proof. Thus, in my view, although the trial court uses language more
    properly associated with a tort proceeding, the context in which the statement is made makes it
    clear to me that the trial court was merely stating, albeit inartfully, its finding that, because there
    had never been any similar accidents at the site, this was an “isolated incident.” And, because
    there had been no previous incidents that would have alerted the employer to the fact that the
    trucks were parking underneath the overhead power lines, the employer did not know, nor should
    it have known, about the condition causing the violation. In my opinion, then, the trial court
    implicitly concluded that the Commissioner failed to establish that the employer knew or should
    have known of the condition causing the violation.
    This conclusion is supported by a review of the entirety of the trial proceedings. In the
    “Plaintiff’s Memorandum of Law,” for example, the Commissioner provided the trial court with
    a correct statement of the required statutory factors. The court went through each of these
    factors with counsel during the trial proceedings. The trial court’s comments to counsel
    throughout the trial are demonstrative of the court’s concern that the employer did not have
    actual or constructive knowledge of the condition causing the violation. Specifically, the trial
    court repeatedly questioned whether the truck drivers had been instructed not to park underneath
    - 11 -
    the power lines, and additionally focused on the fact that no one, over the course of two and a
    half years, had been electrocuted at the site. Considering the trial court’s comments throughout
    the entirety of the proceedings, it is reasonable to conclude that the trial court was unwilling to
    impute knowledge of the condition causing the violation to the employer.
    In sum, there is no “clear evidence” that the trial court did not know and correctly apply
    the law, and we should not “fix upon [the] isolated statements of the trial judge . . . and use them
    as a predicate for holding the law has been misapplied.” Yarborough, 217 Va. at 978, 234
    S.E.2d at 291. Rather, as in Yarborough, we should “construe the trial judge’s statements as
    furnishing alternative bases, one correct and one erroneous,” for his holding that the “serious”
    violations should be dismissed. Id. Thus, because there is no “clear evidence” in the record that
    the trial court did not know and correctly apply the law, I would affirm the judgment of the trial
    court, and I respectfully dissent from the majority’s decision to remand this case for further
    proceedings.
    - 12 -