Commonwealth of Virginia v. Asphalt Roads ( 1998 )


Menu:
  •                      COURT OF APPEALS OF VIRGINIA
    Present: Judges Baker, Willis and Overton
    Argued at Norfolk, Virginia
    COMMONWEALTH OF VIRGINIA,
    DEPARTMENT OF TRANSPORTATION AND
    WILLIAM E. LANDSIDLE,
    COMPTROLLER OF THE COMMONWEALTH
    MEMORANDUM OPINION * BY
    v.          Record No. 1665-97-1       JUDGE JERE M. H. WILLIS, JR.
    MARCH 3, 1998
    ASPHALT ROADS & MATERIALS CO., INC.
    FROM THE CIRCUIT COURT OF THE CITY OF VIRGINIA BEACH
    Frederick B. Lowe, Judge
    Mark S. Paullin, Assistant Attorney General
    (Richard Cullen, Attorney General, on
    briefs), for appellants.
    Jack Rephan (Beth Hirsch Berman; Hofheimer,
    Nusbaum, McPhaul & Samuels, P.C., on brief),
    for appellee.
    The Commonwealth of Virginia, Department of Transportation
    (VDOT) appeals a judgment of the trial court granting additional
    compensation to Asphalt Roads & Materials Co., Inc. (Asphalt) on
    behalf of its subcontractors, Kevcor Corporation (Kevcor) and
    M.M. Gunter & Sons, Inc. (Gunter).    VDOT contends that the trial
    court erred:    (1) in awarding additional compensation for
    backfill material and for disposal of unsuitable material; (2) in
    awarding "undercut" compensation for excavation that was not
    "undercut"; (3) in failing to limit damages for "undercut" to the
    amount claimed by Asphalt; (4) in awarding damages for
    *
    Pursuant to Code § 17-116.010 this opinion is not
    designated for publication.
    construction delays without proof of the actual costs incurred by
    those delays; (5) in admitting hearsay evidence from an industry
    manual to calculate equipment-related damages; and (6) in
    incorrectly calculating days lost at a worksite operated by
    Gunter.   Asphalt contends that the trial court erred in denying
    damages for unabsorbed overhead.     For the reasons that follow, we
    affirm in part, reverse in part, and remand.
    Asphalt contracted with VDOT to widen Landstown Road in
    Virginia Beach.   The contract incorporated by reference the 1991
    VDOT Road and Bridge Specifications (Specifications), the project
    plans and drawings, the 1989 VDOT Standards, and VDOT's project
    proposal.
    Asphalt filed an administrative construction claim
    requesting additional compensation for itself and on behalf of
    Kevcor and Gunter.   See Code § 33.1-386.    The Commonwealth
    Transportation Commissioner allowed part of the claim.    Asphalt
    then filed this action seeking recovery for "such portion of the
    claims as were denied by the Commissioner."     See Code § 33.1-387.
    The trial court denied Asphalt any further recovery for itself,
    but allowed further recovery on behalf of Kevcor and Gunter.
    I.
    Asphalt subcontracted with Kevcor to perform drainage and
    water and sewer system work.   During construction, a VDOT
    inspector informed Kevcor that material being excavated for the
    installation of the storm drainage system was unsuitable for use
    - 2 -
    as backfill. 1   Kevcor requested additional compensation for costs
    incurred in acquiring off-site and placing suitable backfill
    material and in disposing of the unsuitable excavated material.
    VDOT responded that according to the specifications, the bid
    price for the pipes and backfill included these associated costs.
    However, VDOT paid Kevcor additional compensation for backfill
    material, based upon the plan dimensions and the contract unit
    price for select borrow. 2    VDOT also allowed additional
    compensation for disposal of the unsuitable material.
    The trial court awarded Asphalt, on behalf of Kevcor,
    additional compensation of $53,500.26 for backfill imported to
    the site and $98,286.12 for off-site disposal of the unsuitable
    excavated material. 3    VDOT contends that the contract bars
    recovery of additional compensation for these items.     We agree.
    Our resolution of this issue turns upon a reading of the
    parties' contract.      Because the parties presented for our review
    all of the evidence necessary to construe the contract, its
    1
    Specifications § 101.02 defines "backfill" as "Material
    used to replace or the act of replacing material removed during
    construction . . . ."
    2
    Specification § 101.02 defines "select borrow" as "borrow
    material that has specified physical characteristics." "Borrow"
    refers to suitable material from sources outside the roadway.
    Id.
    3
    The trial court had jurisdiction over this matter "as to
    such portion of the claim as was denied by the Commissioner."
    Code § 33.1-387. Contrary to the assertion made by Asphalt, the
    trial court had the authority to determine not only the amount of
    any award, but also whether Asphalt was entitled to an award.
    - 3 -
    meaning and effect is a question of law, capable of
    interpretation by us on appeal.   See Fry v. Schwarting, 
    4 Va. App. 173
    , 180, 
    355 S.E.2d 342
    , 346 (1987).
    Section 302 of the Specifications controls construction of
    drainage structures.   Measurement and payment for installation of
    drainage structures is governed by § 302.04, which states:
    Pipe shall be paid for at the contract unit
    price per linear foot. This price shall
    include excavating, when not a pay item;
    sheeting; shoring; dewatering; disposing of
    surplus and unsuitable material; backfill
    material; and restoring existing surfaces.
    Section 520 of the Specifications addresses installation of
    water and sanitary sewer facilities. Section 520.06 states:
    Water mains, water service lines, sanitary
    sewer pipe, and sanitary sewer force mains
    will be measured in linear feet of pipe
    through all valves and fittings,
    complete-in-place, and will be paid for at
    the contract unit price per linear foot.
    This price shall include excavating; testing;
    disinfecting; backfilling; compacting;
    dewatering; disposing of surplus and
    unsuitable material; . . .; and restoring
    property.
    Asphalt argues that the foregoing provisions are ambiguous
    when considered in conjunction with the other terms of the
    contract and the surrounding circumstances.
    Asphalt claims that Specifications §§ 302.04 and 520.06 must
    be interpreted with reference to § 303.06, which governs the
    measurement and payment of earthwork.   Specifications § 303.06(d)
    states in part that:
    Furnishing and placing backfill material
    . . . will be included in the price for
    - 4 -
    excavation and will not be measured for
    separate payment unless specific material is
    a pay item for backfill or unless suitable
    material is not available within the
    construction limits. When a specific
    material is a pay item, the unit of measure
    of the material will be in accordance with
    the unit specified in the Contract. When
    suitable backfill material is not available
    within the construction limits, the material
    furnished and placed by the Contractor will
    be paid for in accordance with Section
    109.05. 4
    The backfilling and unsuitable material disposal concerned in
    this case were not "pay items."   Specifications § 101.02 defines
    "pay item" as "a specifically described unit of work for which a
    price is provided in the Contract."
    4
    Specifications § 109.05 states in part that:
    Extra work performed in accordance with the
    requirements and provisions of Section 104.03
    will be paid for at the unit prices or lump
    sum specified in the work.
    Specifications § 104.03 states that:
    The Contractor shall perform unforeseen work
    for which there is no price specified in the
    Contract whenever it is deemed necessary or
    desirable. Such work shall be performed in
    accordance with these specifications and as
    directed by the Engineer and will be paid for
    in accordance with Section 109.05.
    Asphalt argues on appeal that these sections do not
    encompass "minor structure excavation," which is measured and
    paid for under § 303.06. However, the record does not indicate
    that Asphalt set forth that claim with particularity to the
    Commissioner. Because the Commissioner had no opportunity to
    deny additional compensation for minor structure excavation, the
    trial court would not have jurisdiction to hear the claim. Code
    § 33.1-387.
    - 5 -
    While acknowledging that the Commonwealth cannot be
    estopped, Asphalt cites VDOT correspondence that, referencing
    § 303.06, allowed additional compensation for furnishing backfill
    and disposal of unsuitable excavation material per the dimensions
    provided in the plans.   However, in that correspondence, VDOT
    acknowledged employing a "liberal" interpretation of the terms of
    the contract in order to accommodate Asphalt and to resolve the
    issues.   In the same correspondence, VDOT noted that the contract
    price included the cost of supplying suitable material and
    disposing of unsuitable material.
    We find no ambiguity as to payment for backfill or disposal
    of unsuitable material.
    "An ambiguity exists when language admits of
    being understood in more than one way or
    refers to two or more things at the same
    time." The fact that the parties attribute
    to the same terms variant meanings does not
    necessarily imply the existence of ambiguity
    where there otherwise is none.
    Smith v. Smith, 
    3 Va. App. 510
    , 513-14, 
    351 S.E.2d 593
    , 595
    (1986) (citations omitted).   Despite the variant interpretations
    placed on the terms of the contract by the parties, §§ 302.04 and
    520.06 state clearly and unambiguously that the unit price shall
    include the cost of backfill material and disposal of surplus and
    unsuitable material.
    Asphalt also argues that additional compensation is due,
    because the parties did not contemplate the quantity of
    unsuitable material encountered at the project site.   Special
    - 6 -
    Provision Copied Notes § 104.03 provides in part that:
    During the progress of the work, if
    subsurface or latent physical conditions are
    encountered at the site differing materially
    from those indicated in the contract . . .
    the party discovering such condition shall
    promptly notify the other party in
    writing . . . .
    Upon written notification, the Engineer will
    investigate the conditions, and if he/she
    determines that the conditions materially
    differ and cause an increase or decrease in
    the cost or time required for the performance
    of any work under the contract, an
    adjustment, excluding anticipated profits,
    will be made and the contract modified in
    writing accordingly.
    Cf. Chantilly Constr. Corp. v. Department of Highways & Transp.,
    
    6 Va. App. 282
    , 292, 
    369 S.E.2d 438
    , 444 (1988) (stating general
    rule that contractor will not be entitled to additional
    compensation due to an unforeseen difficulty).
    The exact quantity of unsuitable material was not known
    prior to excavation.    VDOT identified the presence of the
    unsuitable material and allowed compensation in accordance with
    the plan dimensions and terms of the contract.    However, the
    record does not establish that Kevcor was entitled to further
    compensation for backfill or for off-site disposal of unsuitable
    backfill material.    Moreover, Specifications § 102.04 provides
    that:
    The submission of a bid will be considered
    conclusive evidence that the bidder has
    examined the site of the proposed work,
    proposal, plans, standard drawings,
    specifications, supplemental specifications,
    special provisions, special provision copied
    notes, and any other documents specified in
    - 7 -
    the proposal before submitting a bid and is
    satisfied as to the conditions to be
    encountered in performing the work and
    requirements specified in the proposal.
    *    *     *    *      *      *    *
    The submission of a bid will       be considered
    conclusive evidence that the       bidder is
    satisfied with regard to the       subsurface
    conditions to be encountered       in the work.
    Thus, the evidence failed to establish that Kevcor was
    entitled to further compensation for backfill or for off-site
    disposal of unsuitable backfill material.       We reverse the trial
    court's award of $151,786.38 to Asphalt for those items.
    II.
    VDOT contends that the trial court erred in awarding
    Asphalt, on behalf of Kevcor, $9,400 in additional compensation
    for undercut.   VDOT argues that no evidence supports the finding
    that undercut occurred.    We agree and reverse the trial court's
    award for this item.
    Specifications § 303.06(a)(3) defines "undercut" as the
    excavation of unsuitable material from below the lower of "the
    bottom of the lower theoretical slab or culvert thickness or
    below the excavation limits shown on the plans."         Under familiar
    principles, we review the evidence in the light most favorable to
    the prevailing party and place upon the aggrieved party the
    burden to show that reversal is appropriate.        See Lutes v.
    Alexander, 
    14 Va. App. 1075
    , 1077, 
    421 S.E.2d 857
    , 859 (1992).
    The plans required the contractor to excavate one foot below
    - 8 -
    the pipe.    Thus, undercut would occur only to the extent that the
    contractor excavated more than one foot below the bottom of the
    pipe.    Nothing in the record supports a finding that Kevcor
    excavated to that level.     Therefore, we reverse the award for
    excavation of undercut.     We need not address whether the trial
    court erred in awarding Asphalt a sum greater than was sought in
    its motion for judgment.
    III.
    VDOT next contends that the trial court erred in awarding
    Asphalt damages in the amount of $138,544.88 on behalf of Gunter
    and in the amount of $115,680.72 on behalf of Kevcor for five
    construction delays attributable to VDOT.       VDOT argues:   (1) that
    Asphalt failed to prove the "actual costs incurred" due to the
    delays, (2) that the trial court erred in admitting hearsay
    evidence, and (3) that the trial court miscalculated the number
    of days that Gunter's equipment remained idle at its Holland Road
    Pit.    Asphalt contends that the trial court erred in denying it
    damages for unabsorbed overhead costs.
    A.   Proof of Actual Costs
    Generally, compensation is determined by computation of
    actual damages.    "'[I]t is sufficient if a reasonable basis of
    computation is afforded.'"      Washington Golf & Country Club, Inc.
    v. Briggs and Brennan Developers, Inc., 
    198 Va. 586
    , 592, 
    95 S.E.2d 233
    , 237 (1956) (quotation omitted).         See 5C Michie's
    Jurisprudence Damages § 19 (1983).        "'[A]bsolute certainty as to
    - 9 -
    the amount of damages is not essential when the existence of a
    loss has been established.   The quantum may be fixed when the
    facts and circumstances are such as to permit . . . an
    intelligent and probable estimate thereof.'"        Pebble Bldg. Co. v.
    G.J. Hopkins, Inc., 
    223 Va. 188
    , 191, 
    288 S.E.2d 437
    , 438 (1982)
    (quoting Wyckoff Pipe & Creosoting Co., Inc. v. Saunders, 
    175 Va. 512
    , 518-19, 
    9 S.E.2d 318
    , 321 (1940)).
    Asphalt, Kevcor, and Gunter presented no evidence of actual
    damages resulting from delay.      See 
    id.
     (upholding award for delay
    damages based upon difference between estimated and actual
    costs).   Rather, they introduced testimony of lay witnesses
    calculating equipment-related delay damages by using an industry
    manual used to calculate rental values of such equipment.
    Because rental calculations were not shown to constitute a
    reasonable approximation of actual damages, we reverse the
    judgment for damages resulting from delay and remand the case to
    the trial court for determination of actual damages.
    B.    Hearsay
    The trial court committed reversible error in admitting
    passages of the "Rental Rate Blue Book for Construction
    Equipment" into evidence as exhibits.        This book, and its
    component sections, was hearsay.
    An expert witness may give testimony and render an opinion
    based upon data made known to him prior to trial.       If the data is
    of a type normally relied upon by others in the particular field
    - 10 -
    of expertise, that data need not be itself admissible in
    evidence.   Code § 8.01-401.1.    To the extent called to the
    attention of an expert witness by cross-examination or relied
    upon by him in direct examination, statements contained in
    published treatises, etc., established as reliable authority by
    testimony or by stipulation, shall not be deemed hearsay and may
    be read into evidence, but may not be received as exhibits.       Id.
    Asphalt presented only lay testimony as to the equipment
    costs resulting from delay.   Its witnesses were not qualified as
    experts.    The witnesses did not tender expert opinions based on
    reference to the Blue Book.   Rather, the Blue Book itself was
    tendered as authoritative evidence of its contents.    No testimony
    or stipulation established the Blue Book as a document relied
    upon by experts in the construction equipment appraisal field.
    See Kern v. Commonwealth, 
    2 Va. App. 84
    , 87, 
    341 S.E.2d 397
    , 399
    (1986) (expert jewelry appraiser relied upon unidentified market
    data brochure which was not in evidence and testified that its
    use was standard in appraisal profession).    As an out-of-court
    statement offered to prove the truth of the matter asserted, the
    Blue Book was hearsay.    See Papuchis v. Commonwealth, 
    15 Va. App. 281
    , 
    422 S.E.2d 419
     (1992) (reversing gambling conviction upon
    error in admitting into evidence sports publications relied upon
    by expert).   The Blue Book fell into no recognized exception to
    the hearsay rule and was, therefore, inadmissible.     Cf. Code
    § 8.01-401.1 (permitting admission of learned treatises upon
    - 11 -
    direct examination of an expert witness); Code § 8.01-419.1
    (National Automobile Dealers' Association books admissible to
    prove the fair market value of an automobile).
    Asphalt relied upon the Blue Book to prove damages.
    "[A]dmission of hearsay expert opinion
    without the testing safeguard of
    cross-examination is fraught with
    overwhelming unfairness to the opposing
    party. No litigant in our judicial system is
    required to contend with the opinions of
    absent 'experts' whose qualifications have
    not been established to the satisfaction of
    the court, whose demeanor cannot be observed
    by the trier of fact, and whose
    pronouncements are immune from
    cross-examination."
    CSX Transportation, Inc. v. Casale, 
    247 Va. 180
    , 183, 
    441 S.E.2d 212
    , 214 (1994) (quoting McMunn v. Tatum, 
    237 Va. 558
    , 566, 
    379 S.E.2d 908
    , 912 (1989)).    Because it was used to prove the amount
    of actual damages, admittance of the Blue Book into evidence was
    both material and prejudicial to VDOT's interests.    See 
    id.
       We
    reverse this ruling.
    C.    Calculation of Days of Delay
    VDOT contends that the trial court erred in calculating the
    number of days Gunter's equipment sat idle at the Holland Road
    Pit because of delay. 5   We agree.
    The days for which delay compensation may be allowed must be
    5
    While the Commonwealth failed to argue specifically that
    the length of the delay was incorrectly calculated, the record
    shows that the Commonwealth introduced evidence concerning the
    length of the delay and laid that aspect of the damages award
    before the trial court.
    - 12 -
    days on which the equipment would otherwise have been used.      The
    evidence established that Gunter normally would not have worked
    on Sundays, holidays and, possibly, Saturdays.       Therefore, in
    calculating the number of days for which an award of compensation
    could be made, the trial court should have taken into account the
    non-working days embraced within the applicable time period.         The
    trial court failed to do so.    Accordingly, we reverse its
    calculation of days for which compensation might be allowed and
    remand that issue for recalculation.
    D.   Unabsorbed Overhead Costs
    Asphalt contends that the trial court should have used the
    Eichleay formula to calculate its unabsorbed overhead damages.
    We need not address the merits or application of the
    Eichleay formula to determine the amount of unabsorbed overhead
    during a delay.    The trial court considered the Eichleay formula
    and concluded that the evidence did not support its reliability
    to determine a damage award in this case.    The record supports
    this conclusion.   Finding no error, we affirm this ruling of the
    trial court.
    Affirmed in part,
    reversed in part,
    and remanded.
    - 13 -