Secretary, Vermont Agency of Natural Resources v. Richard Deso ( 2001 )


Menu:
  •                                     STATE OF VERMONT
    ENVIRONMENTAL COURT
    SECRETARY, Vermont
    }
    Agency of Natural Resources
    }
    }   Docket No. 204-9-00 Vtec
    v.
    }
    }
    RICHARD DESO, Respondent
    Decision and Order on Motion to Amend
    Respondent is represented by Richard A. Gadbois, Esq.; and the Secretary of the Agency of
    Natural Resources is represented by Gary S. Kessler, Esq. Respondent has moved to amend the
    November 27, 2001 Decision and Order with regard to the calculation of the civil penalty.
    First, Respondent argues that the court failed to consider that the Agency of Natural
    Resources allowed the subsequent owner of the gasoline pumping station to operate without
    immediately installing the required Stage II Vapor Recovery System (Stage II). The Agency
    agrees that testimony at trial reflected that the subsequent owner was granted an extension of
    time to install Stage II because he intended to demolish the old station and build a new station at
    that location. Respondent appears to argue that the fact that the subsequent owner was allowed to
    operate implies a more diminished A degree of actual or potential impact on public health, safety,
    welfare and the environment@ (10 V.S.A. ' 8010(b)(1)) than the imposed penalty suggests.
    However, any extension granted to the subsequent owner does not affect the actual impact on the
    environment and potential for harm during Respondent= s tenure, A due to the release of air
    pollutants that would not have been released if the [Stage II] had been had been in place and
    operating.@ Decision and Order at 11.
    Second, Respondent argues that the court erred by including in the calculation of Respondent=
    s economic benefit his post-violation profit rather than his relative A competitive advantage over
    his competitors,@ which he estimates to be significantly lower than his profit. However, ' 5-253.7
    of the Air Pollution Control Regulations prohibited Respondent from dispensing gasoline after
    the date on which Stage II was required to have been installed. The statute requires the removal
    of the economic benefit received from the violation. 10 V.S.A. ' ' 8010(b)(5). It is intended to A
    prevent the unfair economic advantage obtained by persons who operate in violation of
    environmental laws.@ 10 V.S.A. ' 8001(2). The benefit Respondent received is not limited to his
    avoided costs, as Respondent argues. Rather, it properly includes the profit illegally obtained
    after Stage II should have been installed, as the regulations otherwise required Respondent to
    have ceased operations. See Vermont Agency of Natural Resources v. Earth Construction, Inc.,
    
    165 Vt. 160
     (1996).
    Lastly, Respondent argues that the deterrence rationale under 10 V.S.A. ' 8010(b)(6) does not
    apply to him because he no longer owns any gasoline pumping stations. This is an argument that
    ' 8010(b)(6) only authorizes specific deterrence. The goal of deterrence authorized by 10 V.S.A.
    ' 8010(b)(6), however, is not limited to the specific deterrent effect on Respondent, but applies
    to others as well. See Vermont Agency of Natural Resources v. Bean, 
    164 Vt. 438
    , 443 (1995).
    Accordingly, based on the foregoing discussion, Respondent=s motion to amend is hereby
    DENIED.
    Done at Barre, Vermont this 28th day of January, 2002.
    ___________________
    Merideth Wright
    Environmental Judge
    

Document Info

Docket Number: 204-9-00 Vtec

Filed Date: 11/27/2001

Precedential Status: Precedential

Modified Date: 4/24/2018