Walker Motors, Inc. v. City of Montpelier ( 2013 )


Menu:
  • Walker Motors, Inc. et. al. v. City of Montpelier et. al., No. 921-12-10 Wncv (Toor, J., Dec. 30, 2013).
    [The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the
    accompanying data included in the Vermont trial court opinion database is not guaranteed.]
    VERMONT SUPERIOR COURT
    WASHINGTON UNIT
    CIVIL DIVISION
    │
    WALKER MOTORS, INC. and SIERRA                                           │
    HOLDINGS, LLC,                                                           │
    Plaintiffs                                                              │
    │
    v.                                                                   │      Docket No. 921-12-10 Wncv
    │
    │
    CITY OF MONTPELIER, VT and                                               │
    J.A.MCDONALD, INC.,                                                      │
    Defendants                                                              │
    │
    RULING ON CROSS-MOTIONS FOR SUMMARY JUDGMENT, MOTION TO STRIKE,
    AND MOTIONS TO INTERVENE
    Plaintiffs in this case are a business and a landowner that each seek damages from the
    City and a road contractor for financial losses allegedly incurred during a road project involving
    construction of a roundabout on Routes 2 and 302. The complaint asserts three causes of action:
    a claim for an unconstitutional taking due to blocked access to Walker Motors, a claim that the
    management of traffic flow and work hours was done in a negligent manner, and a claim that
    Plaintiffs were third-party beneficiaries of a contract between Defendants, the terms of which
    (regarding traffic management) were breached. The parties have filed cross-motions for
    summary judgment.1 In addition, the Defendants’ insurers have filed motions to intervene.
    1
    The court is aware that the motions were ripe in July. However, perhaps as a result of some confusion due the
    amended discovery schedule that was filed in the midst of the summary judgment filings, the case was not brought
    to a judge for consideration until November. The court apologizes for the delay.
    Relevant Undisputed Facts
    The basic facts here are undisputed. In 2008 the City and McDonald entered into an
    agreement by which the latter would perform construction on a roundabout at Routes 2 and 302
    in Montpelier. The agreement incorporated Agency of Transportation requirements, including
    one that traffic not be delayed for more than ten minutes during road projects.
    Walker Motors operated the Walker Ford dealership at 265 River Street in Montpelier
    until late 2009. Sierra is the LLC (of which Walker Motors’ president is the CEO) that owns the
    real estate at that location. Drawings incorporated by reference in the contract include one stating
    that “reasonable access to driveways and to Walker Motors shall be maintained at all times.” In
    May of 2009, MacDonald was told by the City to have a flagger posted at Walker Motors to keep
    the entrance open. This was not always done. Obstruction of the entrance to Walker Motors was
    a “chronic problem” during the construction.
    Other Relevant Allegations
    Although neither party has submitted these facts in connection with the summary
    judgment motions, there are some other allegations in the complaint that help to clarify what this
    case is about. Plaintiffs allege that during the construction project “massive traffic jams occurred
    almost daily” on River Street and that “[i]ngress and egress to River Street commercial
    enterprises routinely was blocked for extended time periods.” Complaint ¶ 19. They further
    allege that on “many occasions . . . all entrances to Walker Ford were blocked, preventing
    ingress or egress to the dealership during normal business hours.” 
    Id. ¶ 20
    (emphasis added).
    The complaint alleges that even employees were at times unable to get to work at Walker Motors
    because all entrances were blocked. 
    Id. ¶ 26.
    Plaintiffs allege that the dealership suffered
    disastrous consequences due to the loss of business resulting from the blocked access.
    2
    Specifically, they allege that Walker lost 39% of its business due to the traffic problems, that the
    value of the real estate dropped by over a million dollars, and that they eventually sold the car
    business, leased the real estate to another dealer, and lost future profits as a result. 
    Id. ¶ ¶
    31-42.2
    Defendants’ Motion for Summary Judgment
    Defendants Walker Motors and Sierra present several arguments in support of their
    motion. They argue that the claim for a taking (Count 1) must fail because any impact upon
    Defendants was temporary; that the negligence claim (Count 2) must fail due to the economic
    loss rule; and that the breach of contract claim (Count 3) must fail because Plaintiffs were not
    third-party beneficiaries of the contract and thus lack standing.3
    Count 1: The Takings Claim
    Plaintiffs’ first claim is that by barring access to their property for stretches of time
    during the construction project the City and McDonald engaged in an unconstitutional taking of
    their property. Defendants argue that a temporary interference with access to property as the
    result of public road work cannot as a matter of law be a taking.
    As on many topics, Vermont case law is sparse on this issue. There is clear authority for
    the proposition that a town’s winter closing of the road that provides the only access to
    someone’s land can be a taking for which the landowner must be compensated. Okemo
    Mountain, Inc. v. Town of Ludlow, 
    171 Vt. 201
    (2000). Plaintiffs argue that Okemo resolves this
    case, because blocking access to one’s property is a taking. However, that case involved the total
    closing of a road for an extended period each year, not the sort of intermittent blockage of access
    2
    Plaintiffs assert numerous other details in their amended statement of material facts, but not all are material to the
    court’s ruling today.
    3
    In their response to the Defendants’ summary judgment motion, Plaintiffs ask in the alternative for more time for
    discovery before the court rules. Plaintiffs’ Opposition at 19-20. However, they have not complied with the requisite
    procedures for making such a request, which include an affidavit explaining why they “cannot present facts essential
    to justify [their] opposition.” V.R.C.P. 56(d). The court therefore denies that request.
    3
    at issue here. While both denials of access are temporary in one sense, the Okemo case involved
    permanent winter blockage. However, the case does acknowledge a landowner’s right of access
    to an abutting public road, and that even a less-than-total denial of that access can be a taking.
    
    Id. at 211
    (“the Department’s prohibition of the use of the road in the winter represents a taking
    of Lysobey’s property right of access”).
    There is also an old case discussing the impact of a public bridge repair project upon an
    adjoining dam owner. Town of East Montpelier v. Wheelock, 
    70 Vt. 391
    (1898). Defendants
    argue that Wheelock says a temporary public works project cannot be a taking. It does have
    language suggesting that a temporary impact upon a business due to a public project is not a
    taking. However, it involved not a business adjoining a road but a business that was damming a
    public waterway for business purposes. 
    Id. at 396
    (“The complainant did not take the defendants’
    property; it only temporarily prevented the defendants from obstructing the natural flow of the
    river at a point where the State had an easement to repair a bridge for the safe passage of the
    public, and rendered the defendants’ mill less profitable for such time as the master has found
    was reasonable for making the repairs.”). Thus, the Court noted that the interruption of business
    was “a risk and burden assumed by the defendants in maintaining a dam across the river for
    private purposes.” 
    Id. Wheelock also
    seems to conclude, however, that this is true only if the public work is
    done in a reasonable manner: the town “had a right to have the water drawn as low as was
    necessary for the convenient prosecution of the work, and hence, it is not liable for damages
    occasioned thereby; but if it went beyond its right and thereby damaged the defendants, it is
    liable.” 
    Id. at 398-99.
    Moreover, the case appears outdated, as it also cites with approval another
    4
    case stating that appropriating private land to create a road is not a taking, which is certainly no
    longer the law.
    Neither of these cases addressed the precise issue on the table here: whether temporary
    lack of access to a business as a result of a public road project can be a taking. The issue of lost
    business as a result of various road projects has, however, been litigated in many other
    jurisdictions, with varying results. See, e.g., Kurt H. Garber, Eminent Domain: When Does a
    Temporary Denial of Access Become a Compensable Taking?, 25 U. Memphis L. Rev. 271, 277
    (Fall 1994)(“States have adopted different standards for determining whether a temporary
    deprivation constitutes a taking.”).
    First of all, it is generally accepted that one of the rights of a property owner is a right of
    access from abutting roads. Okemo says as 
    much. 171 Vt. at 207
    , 211. The right of access
    “includes not merely the ability of the abutting landowner to enter and leave his premises by way
    of the street or highway, but also the right to have the premises accessible to patrons, clients and
    customers.” City of Beaumont v. Marks, 
    443 S.W.2d 253
    , 255-56 (Tex. 1969), citing, inter alia,
    10 McQuillin, Municipal Corporations § 671 (3d ed. 1950). “It is well settled that ‘the right of
    ingress and egress is a property right which cannot be taken without compensation.’” State of
    Indiana v. Dunn, 
    888 N.E.2d 858
    , 862 (Ind. App. 2008)(citation omitted). “It is well-established
    that the owner of land adjoining a road or highway has a property right in the nature of an
    easement to access. This easement of access entitles the owner to go back and forth between his
    own land and the abutting public road without unreasonable interference.” Mark S. Dennison,
    Recovery of Damages for Temporary Conditions Ensuing from Construction or Repair of Public
    Improvement, 51 Am. Jur. Proof of Facts 3d 489, § 18 (Westlaw through Dec. 2013).
    5
    It also seems to be generally accepted that the inconvenience and reduction in traffic
    flow to a business occasioned by things such as addition of medians and changing of road design
    are not compensable takings. See, e.g., Palm Beach County v. Tessler, 
    538 So. 2d 846
    , 849 (Fla.
    1989) (“A taking has not occurred when governmental action causes the flow of traffic on an
    abutting road to be diminished.”); State v. Dunn, 
    888 N.E.2d 858
    , 869 (Ind. App. 2008)
    (“landowners have no property right to the free flow of traffic past their properties.”); State,
    Idaho Transp. Bd. v. HI Boise, LLC, 
    282 P.3d 595
    , 599-600 (Idaho 2012) (“state action that
    merely results in a change in traffic flow requiring traffic to reach property by a more circuitous
    route does not amount to a taking as a matter of law.”); State ex rel. BDFM Co. v. Ohio Dept. of
    Transp., No. 11AP–1094, 
    2013 WL 209132
    , ¶ 27 (Ohio App. Jan.17, 2013)(“any change in
    traffic flow occasioned by placing a median in the road results from the exercise of the police
    power of the state” and is non-compensable); Dennis, Recovery of Damages, § 18 (“A
    landowner’s right of access is, however, subject to reasonable restrictions under the
    government’s police power to protect the public welfare and regulate traffic.”); 26 Am. Jur. 2d
    Eminent Domain § 197 (Westlaw through Nov. 2013) (“The mere rerouting or diversion of
    traffic, although it results in diminishing the value of the adjacent property, is not a taking or
    damaging of private property within the constitutional provision requiring compensation
    therefor”).
    The question here, however, is a different one: can a government entity entirely block
    access to a business from the road during construction, and if so, for how long? See, e.g., 
    id. (diversion of
    traffic “is to be distinguished from a rerouting of a highway which impairs the
    adjacent owner’s right of access.”)(emphasis added). Although the cases are certainly not all
    6
    consistent in other jurisdictions,4 there are some doctrines that appear repeatedly. One is
    described in Nichols on Eminent Domain:
    When a street is so obstructed during the construction of a public
    work that access to abutting property is wholly cut off, the fact that
    the injury is only temporary is generally held to be no reason for
    denying the owner compensation. However, when access, though
    rendered difficult and inconvenient, is not wholly cut off, the
    owner is denied compensation. . . .
    However, if the temporary obstruction is a result of unreasonable,
    unnecessary, arbitrary or capricious acts or conduct by the one in
    charge of the improvement or construction, the abutting landowner
    has a right of action for damages resulting from such interference
    with access to his property.
    2A Nichols on Eminent Domain § 6.4442(2), quoted in Filler v. City of Minot, 
    281 N.W.2d 237
    ,
    244 (N.D. 1979). This is consistent with the analysis of a lengthy article on the subject:
    In inverse condemnation actions—where the landowner alleges a
    taking of property without formal condemnation by eminent
    domain—the general rule followed in most jurisdictions is that
    temporary conditions incident to the construction or repair of a
    public improvement can only give rise to a claim of consequential
    damages if the landowner offers proof that the construction or
    repair was performed negligently, was unlawful, or was
    unreasonably prolonged.
    Dennison, Recovery of Damages, supra, § 13. The rationale is this:
    The inconvenience and damage which a property owner suffers
    from these temporary obstructions are incident to city life and must
    be endured. The law gives him no right to relief, recognizing that
    he recoups his damage in the benefit which he shares with the
    general public in the ultimate improvement which is being made.
    The law, however, does afford him a relief, if the city or a
    contractor interferes with the highway without authority; or, if
    acting legally, prolongs the work unnecessarily or unreasonably.
    The obstruction of streets and highways, or the work carried on in
    them of a public nature, must be reasonable and necessary for the
    public improvement which is being made.
    4
    One judge has noted that “the changing concepts of ‘taking’ and ‘property,’ and ‘police-power’ versus “eminent-
    domain’ have resulted in ‘a jumble of doctrines, lack of uniformity of decisions, and . . . dissimilar treatment of
    landowners who have suffered similar kinds of harm.’” Constance v. State Through Dept. of Transp. and
    Development Office of Highways, 
    626 So. 2d 1151
    , 1159 (La. 1993)(Dennis, J. concurring)(citation omitted).
    7
    Farrell v. Rose, 
    170 N.E. 498
    , 499 (N.Y. 1930). Under such an approach, the question is whether
    the government (and, as here, its agent) has acted unreasonably. “So long as the work is lawful,
    and is pursued with reasonable diligence, liability for damages to those whose access is
    temporarily restricted does not attach.” Lewis v. Globe Const. Co., Inc., 
    630 P.2d 179
    , 184 (Kan.
    App. 1981). “If the temporary obstruction is a result of unreasonable, unnecessary, arbitrary or
    capricious acts or conduct,” then “the abutting landowner has a right of action for damages
    resulting from such interference with access to his property.” Hadfield v. State of Idaho ex rel.
    Burns, 
    388 P.2d 1018
    , 1022 (Idaho 1964).
    Another approach used by some courts is to ask not about the nature of the government
    action, but about the nature of the impact upon the landowner. In these jurisdictions, the question
    is whether the interference with the landowner’s access was “substantial.” See, e.g., Eminent
    
    Domain, supra
    , 25 U. Memphis L. Rev. at 279-80 (discussing Georgia and North Dakota cases).
    One example is a case similar to this one, where a 27-month road project was found to have
    blocked access to a truck dealership, leading the dealership to close. Newman v. Comm. of
    Pennsylvania, Dept. of Transportation, 
    791 A.2d 1287
    (Pa. Commw. Ct. 2002). The court
    rejected the argument that because the blocking of access was temporary, it was not a taking.
    The court held that the issue was whether the dealership “established a substantial deprivation of
    the use and enjoyment of” the property as a result of the lack of access. 
    Id. at 1290
    (emphasis
    added). See also, Maloley v. City of Lexington, 
    536 N.W.2d 916
    , 921 (Neb. App.
    1995)(property owner entitled to present evidence as to whether his “right of access has been
    destroyed or substantially impaired” due to temporary lack of access from road during jail
    construction project). ``
    8
    Given all of the cases addressing temporary access issues, the court rejects Defendants’
    argument that there is a bright line rule that a temporary denial of access is not a taking. Accord,
    First English Evangelical Lutheran Church of Glendale v. Los Angeles County, Cal., 
    482 U.S. 304
    , 319 (1987)(temporary takings which “deny a landowner all use of his property, are not
    different in kind from permanent takings, for which the Constitution clearly requires
    compensation.”). Nor, however, is there a bright-line rule that denial of access is automatically a
    taking. Instead, it is a case-by-case issue dependent upon the level of impact to the business and
    the reasonableness of the government action. See, e.g., Dennis, Recovery of Damages, § 18 (“A
    case-by-case approach is generally employed to determine whether the facts and circumstances
    show reasonable access or substantial interference with access. Only when the landowner’s
    evidence establishes that the temporary restriction on access meets the court’s standard of
    unreasonableness can it rise to the level of a compensable taking.”); State of Florida Dept. of
    Transp. v. Rubano, 
    636 So. 2d 749
    , 752 (Fla. App. 4 Dist. 1994)(“While we realize that a loss of
    access does not have to be permanent in order to be compensable, we believe the duration of the
    loss is still one fact to be considered.”), aff’d, 
    656 So. 2d
    . 1264 (Fla. 1995).
    At this stage of the case, the court need not decide precisely which analysis the Vermont
    Supreme Court is most likely to adopt in determining when a temporary denial of access to a
    property is a taking.5 Suffice it to say if Plaintiffs prove the facts alleged here, they could
    potentially establish both a substantial impact upon their property rights and unreasonable or
    negligent action by the Defendants. Thus, summary judgment for Defendants is not appropriate.
    5
    Nor does the court at this stage decide what kinds of damages Plaintiffs may be entitled to, as that issue is not
    necessary to the court’s decision today.
    9
    Count 2: The Negligence Claim
    In Count 2, Plaintiffs assert that they were injured financially as the result of negligence
    by Defendants in managing the traffic flow and hours of construction. Plaintiffs cite cases for the
    unremarkable proposition that a lack of reasonable care in doing road projects can constitute
    negligence, a proposition with which the court has no quarrel. The fact that it can be negligence,
    however, does not resolve the question before the court. There is negligence leading to physical
    injury to people or property, and there is negligence leading to financial harm. When only the
    latter is alleged, the economic loss rule comes into play.
    The general idea of the economic loss rule is that it “prohibits recovery in tort for purely
    economic losses.” EBWS, LLC v. Britly Corp., 
    2007 VT 37
    , ¶ 30, 
    181 Vt. 513
    . “It is well
    established in Vermont that absent some accompanying physical harm, there is no duty to
    exercise reasonable care to protect another’s economic interests.” Wentworth v. Crawford & Co.,
    
    174 Vt. 118
    , 126 (2002). “Negligence law does not generally recognize a duty to exercise
    reasonable care to avoid intangible economic loss to another unless one’s conduct has inflicted
    some accompanying physical harm, which does not include economic loss.” Gus’ Catering, Inc.
    v. Menusoft Sys., 
    171 Vt. 556
    , 558 (2000) (mem.).
    Plaintiffs argue that because they were allegedly third-party beneficiaries of the contract
    between the Defendants, they qualify for an exception to the doctrine. A professional services
    relationship can create an exception. “Purely economic losses may be recoverable in professional
    services cases because the parties have a special relationship, which creates a duty of care
    independent of contract obligations.” EBWS, 
    2007 VT 37
    , ¶ 31; see also, Sharon Academy v.
    Wieczorek Insurance, Inc., No. 442-7-13 Wncv (Toor, J.), 
    2013 WL 6631043
    (Vt. Super. Nov.
    13, 2013). However, “[t]o fit within this exception, the parties must have ‘a special relationship,
    10
    which creates a duty of care independent of contract obligations.’” Long Trail House Condo.
    Ass’n v. Engelberth Const., Inc., 
    2012 VT 80
    , ¶ 13, 
    192 Vt. 322
    , quoting EBWS at ¶ 31. A
    contractor on a construction project is not considered to be providing a professional service that
    creates a special relationship. EBWS, 
    2007 VT 37
    , ¶ 32. Nor is there anything to suggest that the
    City’s role here meets that definition. Thus, this exception does not apply.
    Plaintiffs argue in the alternative that because there was no contract here, the economic
    loss doctrine does not apply at all. Although many of the cases do discuss the distinction between
    tort recovery and contract recovery, none of the cases Plaintiffs cite state that the doctrine is
    inapplicable in the absence of a contract. To the contrary, the Vermont Supreme Court has
    expressly applied the doctrine where there was no contract between the parties. Long Trail, 
    2012 VT 80
    , ¶¶ 14-15 (noting that the Court had “applied the economic loss rule in the absence of
    contractual privity” and pointing to two prior cases in which “there was no contractual
    relationship between the parties”); 
    Wentworth, 174 Vt. at 126
    (applying the doctrine despite
    noting that there were no facts “supporting the existence of a contractual duty”).
    For the foregoing reasons, the court concludes that Count 2 is barred by the economic
    loss doctrine.
    Count 3: The Contract Claim
    Plaintiffs’ final claim is that they are third-party beneficiaries of the contract between the
    City and McDonald, entitled to assert a claim for its breach. They rely for this claim upon a
    drawing incorporated by reference in the contract. The notes to the drawing, which require a
    magnifying glass to read, state in relevant part: “Reasonable access to driveways and to Walker
    Motors shall be maintained at all times.” Defendants do not dispute that this was a term of the
    contract. On this basis, Plaintiffs argue that they were third-party beneficiaries of the contract,
    11
    and that the alleged failure to provide reasonable access to their business constitutes a breach of
    contract which they can enforce.
    Preliminarily, even if the argument is correct, it applies only to Walker Motors, not to
    Sierra Holdings. The document referenced only Walker Motors, and no evidence at all suggests
    that the contract was intended to benefit Walker’s landlord. Thus, summary judgment will be
    granted for Defendants on Sierra’s claim.
    To enforce the contract, Walker must prove that it was a third-party beneficiary rather
    than an incidental beneficiary. McMurphy v. State, 
    171 Vt. 9
    , 16 (2000). This depends upon the
    intent of the contracting parties. 
    Id. The issue
    in McMurphy was whether a contract between a
    town and the State to maintain an intersection, which stated that this was in “the public interest,”
    was intended to confer third-party beneficiary status on those members of the public using the
    intersection. The court held that it was not, noting: “Obviously, the public benefits from properly
    maintained highways; however, the most effective, convenient, and economical method of doing
    so is not for their direct benefit, but for their incidental benefit.” 
    Id. at 17.
    “Government contracts
    often benefit the public, but individual members of the public are treated as incidental
    beneficiaries unless a different intention is manifested.” Restatement (Second) Contracts § 313,
    Government Contracts, cmt. a (Westlaw through Oct. 2013).
    Here, however, the contract – in what seems a rather unusual provision for a government
    contract – expressly mentions Walker Motors, requiring that reasonable access to its business
    was to be “maintained at all times.” This arguably shows a direct statement of intent to benefit
    Walker. See, Legare v. Music & Worth Const., Inc., 
    486 So. 2d 1359
    , 1362 (Fla. App.
    1986)(contract requiring contractor to “refrain from isolating places of business [along
    Centerville Road] and [provide] access to all places of business whenever construction interfered
    12
    with existing means of access” might establish third-party beneficiary status). However, the
    “‘clear intent’ hurdle is a high one. It is not satisfied [merely] by . . . explicit reference to a
    third party, or even a showing that the contract operates to the [third parties’] benefit and was
    entered into with [them] in mind.” GECCMC 2005-C1 Plummer Street Office Limited
    Partnership v. JPMorgan Chase Bank, N.A., 
    671 F.3d 1027
    , 1033 (9th Cir. 2012)(internal
    citations and quotations omitted).
    An interesting case both for its similarities to, and its differences from, this one is Lewis
    v. Globe Const. Co., Inc., 
    630 P.2d 179
    (Kan. App. 1981). There, as here, a business affected by
    road construction argued that it was a third-party beneficiary of contract language concerning
    traffic flow. The language at issue stated that the contractor was to sequence the work so as to
    “maintain local traffic to the businesses between” two roads. 
    Id. at 181.
    Unlike this case, the
    contract did not expressly mention any particular business. Also unlike this case, the contract
    expressly stated that “it is not intended by any of the provisions of any part of the Contract to
    create the public or any member thereof a third party beneficiary hereunder, or to authorize any
    one not a party to this Contract to maintain a suit . . . pursuant to the terms or provisions of this
    Contract.” 
    Id. at 185.
    The court cited with approval another case holding that “[a]bsent a
    manifested intent to the contrary construction contracts between a contractor and a state or other
    public body for highway repair or construction of a new highway are generally not considered as
    being for the benefit of third persons…” and concluded that the benefit to the businesses along
    the road was merely incidental. 
    Id. at 185.
    It noted that “the parties to the contract made it
    abundantly and expressly clear that they did not intend to create contractual rights in third
    parties.” 
    Id. 13 Here,
    Defendants have not pointed to any express contract language excluding the
    possibility of third-party beneficiaries, and the express naming of Walker is striking. Defendants
    argue that the provision in this case shows nothing more than an intent to keep traffic flowing
    past Walker Motors, but cite nothing concrete to support that. On the other hand, neither party
    offers any evidence as to what led to the insertion of Walker’s name in the contract documents,
    and the court at this point can only speculate. Nor have the parties fully addressed whether
    allowing Walker a right of action would or would not be consistent with other terms of the
    contract or the “policy of the law authorizing the contract.” 
    McMurphy, 171 Vt. at 17
    , quoting
    Restatement (Second) of Contracts § 313(2). On the current record, the court cannot determine as
    a matter of law what was intended by the contracting parties.
    Defendants argue that McMurphy requires two things: (1) an intent to benefit the third
    party, and (2) an intent to grant them a private right of action. Defendants read more into the case
    than this court does. McMurphy did not actually state that these are two separate requirements.
    Instead, it merely made a passing reference to a private right of action, but the entire focus of the
    Court’s discussion was on the intent of the contracting 
    parties. 171 Vt. at 16-17
    . This court reads
    McMurphy as saying that if the intent was to benefit the third party, the third party has a private
    right of action.
    Based upon the evidence presented, a jury could potentially find that “the circumstances
    indicate that the promisee [the City] intend[ed] to give the beneficiary the benefit of the
    promised performance,” and thus that it is enforceable by Walker. Restatement (Second)
    Contracts § 302, Intended and Incidental Beneficiaries, Section (b) (Westlaw through Oct. 2013).
    See also, Dillon v. Reid, 
    717 S.E.2d 542
    , 548 (Ga. App. 2011)(where site plan accompanying
    sale agreement specifically referenced planned location of dock, owner of dock was third-party
    14
    beneficiary); Peters v. Employers Mutual Casualty Co., 
    853 S.W.2d 300
    , 301 (Mo. 1993)(one is
    a third-party beneficiary if the contract terms “clearly express” an intent to benefit that party).
    Thus, Defendants’ motion for summary judgment on this claim will be denied. Accord, Oost-
    Lievense v. North American Consortium, P.C., 
    969 F. Supp. 874
    , 879 (S.D.N.Y. 1997)(“plaintiff
    is specifically mentioned in the [contract] on four separate occasions. Such specific reference to
    plaintiff supports the conclusion that he is an intended beneficiary under the contract.
    Nevertheless, because this determination turns on a question of the parties’ intent, the . . .
    resolution of plaintiff’s status is, ultimately, a question of fact for the jury to decide.”)(internal
    citation omitted).
    Plaintiffs’ Motion for Summary Judgment
    Plaintiffs seek summary judgment in their favor on the third-party beneficiary claim.
    However, as noted above, the court cannot resolve the third-party beneficiary issue as a matter of
    law based upon the record to date.              Moreover, even if Walker is such a beneficiary, the
    undisputed evidence before the court does not prove that “reasonable access to Walker Motors”
    was not maintained. These are questions for the jury.
    The Motion to Strike
    Defendants move to strike the Plaintiffs’ amended statement of material facts. The
    motion is denied.
    Acadia’s Motion to Intervene
    Acadia Insurance Company insures both the City and McDonald. It asserts that it is
    providing legal representation to them pursuant to “bilateral non-waiver agreements,”6 and
    6
    A bilateral non-waiver agreement “is assented to by both insured and insurer, and disclaims liability under the
    policy, reserves to each party his or her respective rights, and provides that the insurer will defend, at its own
    expense, and that nothing which is done under the agreement will be deemed to constitute a waiver of the respective
    rights.” 14 Couch on Insurance § 202:38 (Westlaw through Oct. 2013). “When coverage is in doubt, an insurer
    15
    moves to intervene here to seek a declaratory judgment as to the applicability of its policy.
    Acadia alleges that the policy contains exclusions that may apply if it is established that
    Defendants “expected or intended harm” to Walker or Sierra, or if “property damage” arose out
    of inadequate work, delay, or breach of contract by McDonald. Motion to Intervene at 4.
    Acadia first argues that it has a right to intervene because it has an interest relating to the
    subject of this action, the result of this case may impair or impede its interests, and no other party
    will adequately represent its interests. V.R.C.P. 24(a). Alternatively, it requests permission to
    intervene under V.R.C.P. 24(b) on the grounds that there are common question of law or fact
    between this case and their coverage concerns. Acadia argues that the Vermont Supreme Court
    has essentially directed insurers in situations such as this to intervene, citing Pharmacists Mutual
    Insurance Co. v. Myer, 
    2010 VT 10
    , 
    187 Vt. 323
    . The Court in that case discussed the possibility
    of intervention when an insurer wishes to assure that issues relating to policy exclusions are
    addressed in special jury interrogatories. 
    Id. ¶¶ 15-16.
    McDonald and the City oppose the motion. They argue that Acadia has a fiduciary duty
    to provide them a zealous defense, and that Acadia cannot also advocate before the same jury in
    a manner that would undercut that defense. Acadia has not responded to this argument, and the
    court is persuaded by it. Acadia has, by virtue of the non-waiver agreement, reserved the right to
    challenge coverage issues in a separate case. It may not, however, litigate in this case against the
    very insureds to whom it is providing a defense. See, e.g., Safeco Insurance Co. v. Tholen, 
    173 Cal. Rptr. 23
    , 33 (Cal. App. 1981)(finding intervention to undercut insured’s position “could
    well be described as” a breach of the duty of good faith and fair dealing). Its intervention would
    also inject insurance coverage issues into the underlying case.
    defending the insured under such an agreement notifies the insured of the conflict of interest, and reserves to itself
    all policy defenses in case the insured is subsequently found liable.” 
    Id. 16 Moreover,
    Rule 24 requires a “timely application” to intervene. V.R.C.P. 24. The motion
    is untimely, as it comes almost three years after this case began and at a time when the parties
    have already agreed to only ninety more days for discovery. 171234 Canada Inc. v. AHA Water
    Corp., 
    2008 VT 115
    , ¶¶ 19-20, 
    184 Vt. 633
    (mem.).
    Finally, the court does not consider the coverage issue to raise the same questions of law
    or fact that the existing dispute raises. Intervention would inject entirely new coverage issues
    into what is now a case involving claims of a taking and a breach of contract.
    Nor does the court believe that Pharmacists Mutual requires it to grant intervention. That
    case merely suggested limited intervention for the purpose of requesting special jury
    interrogatories, not intervention as a full party seeking entirely new relief. Nor did it discuss the
    impact of non-waiver agreements such as the ones Acadia asserts exist in this case.
    Evanston’s Motion to Intervene
    Evanston Insurance Company has also filed a motion to intervene in this case to seek a
    declaratory judgment regarding the scope of its coverage. Its arguments essentially mirror those
    of Acadia. The court’s analysis above applies equally here, and the motion is denied for the same
    reasons.
    Order
    Defendants’ motion for summary judgment is denied as to Count 1 (Taking), granted as
    to Count 2 (Negligence), granted as to Count 3 (Contract) with respect to Sierra Holdings, and
    denied as to Count 3 with respect to Walker Motors. Defendants’ motion to strike is denied.
    Plaintiffs’ motion for summary judgment is denied. Both motions to intervene are denied.
    The scheduling order previously signed by Judge Bent in June requires the parties to
    mediate this case within 45 days of this ruling, and to complete discovery and be trial-ready
    17
    within ninety days of this ruling. The case will be scheduled for the April jury draw and a pretrial
    conference.
    Dated at Montpelier this 30th day of December, 2013.
    _____________________________
    Helen M. Toor
    Superior Court Judge
    18