N.E, Materials Grp ( 2016 )


Menu:
  •                                            STATE OF VERMONT
    SUPERIOR COURT                                                            ENVIRONMENTAL DIVISION
    Environmental Division Unit                                                  Docket No. 35-3-13 Vtec
    N.E. Materials Group Amended A250 Permit
    ENTRY REGARDING MOTION
    Count 1, Act 250 District Commission Decision (35-3-13 Vtec)
    Title:            Motion to Amend/Alter (Motion 14)
    Filer:            North East Materials Grp., LLC
    Attorney:         James P.W. Goss
    Filed Date:       March 21, 2016
    Response filed on 04/05/2016 by Attorney Laura Bucher Murphy for party 2 Co-counsel
    Opposition
    Reply to Response filed on 04/18/2016 by Attorney James P.W. Goss for NEMG
    The motion is GRANTED IN PART and DENIED IN PART.
    Pending before the Court is a motion filed by Applicant North East Materials Group, LLC
    (NEMG) to alter our final merits decision in the case of In re North East Materials Group
    Amended A250 Permit. In response to the motion, Appellants in this matter, a group of
    twenty-six neighbors collectively known as “Neighbors for Health Communities,” also argued
    for an altered judgment, but on different bases.
    The underlying matter is an appeal from a district commission decision granting an Act
    250 permit to NEMG to operate a hot-mix asphalt plant on the Rock of Ages1 quarry tract in
    Barre, Vermont (the Project). The District 5 Environmental Commission granted the Act 250
    permit in February 2013, but limited asphalt production to an average of 4,500 tons per week
    during any given 45-day period (a “rolling average production limit”). Neighbors appealed the
    District Commission’s decision, seeking denial of the permit. NEMG cross-appealed, challenging
    the rolling average production limit. NEMG continued to operate its asphalt plant under the
    district commission permit while the appeal was pending.
    The Court issued a decision on the merits on March 11, 2016. In our decision, we
    approved NEMG’s application, subject to three conditions. One condition required that,
    “[w]hen using public roads, trucks associated with the Project will remain in their lane of travel
    at all times, including when traveling on the sharp curve in Graniteville Road at the intersection
    of Graniteville Road and Baptist Street.” We also interpreted a stipulation the parties filed
    before trial to waive NEMG’s challenge to the rolling average production limit in its permit. Our
    decision noted, however, that even if the rolling average production limit were within our
    1
    The Rock of Ages Corporation is a co-applicant in this appeal.
    scope of review, we would maintain the limit because our positive findings under several Act
    250 criteria were based on observed impacts from the Project while the production limit was in
    place. See In re N.E. Materials Grp. A250 Permit, No. 35-3-13 Vtec, slip op. at 2 n.3 (Vt. Super.
    Ct. Envtl. Div. Mar. 11, 2016).
    In its motion to alter judgment, NEMG objects to the lane-of-travel condition and the
    perceived waiver of its challenge to the rolling average production limit. NEMG asks the Court
    to remove the lane-of-travel condition, arguing that the Court does not have jurisdiction to
    impose this condition and that the condition is unenforceable. As to the rolling average
    production limit, NEMG argues that the stipulation was never meant to waive the production-
    limit issue and that the project complies with Act 250 without the limit. In their response,
    Appellants also take issue with the lane-of-travel condition, arguing that the condition is
    “meaningless.” They urge the Court to require NEMG’s customers to avoid the HCL curve
    altogether.2 With regard to the rolling average production limit, Appellants agree that the pre-
    trial stipulation was not meant to waive the production-limit issue, but they urge the Court to
    continue to impose the condition.
    A party may move to alter or amend judgment within ten days of the judgment’s
    issuance. V.R.C.P. 59(e). Rule 59(e) gives a court broad power to alter or amend a judgment.
    See V.R.C.P. 59(e), Reporter’s Notes. A court may “revise its initial judgment if necessary to
    relieve a party against the unjust operation of the record resulting from the mistake or
    inadvertence of the court and not the fault or neglect of a party.” Rubin v. Sterling Enters., Inc.,
    
    164 Vt. 582
    , 588 (1996).
    With regard to the lane-of-travel condition, the Court DENIES in part NEMG’s motion to
    alter and maintains the condition as written. A tribunal reviewing an Act 250 application has
    the power to impose “appropriate” conditions that are an “allowable proper exercise of the
    police power.” 10 V.S.A. § 6086(c). Conditions are generally valid under this provision if they
    are “reasonable.” See In re Quechee Lakes Corp., 
    154 Vt. 543
    , 549 n.4 (1990). A reviewing
    tribunal has “broad authority to tailor permit conditions to reduce the environmental impacts
    of proposed projects.” In re J. Philip Gerbode, No. 6F-357R-EB, Findings of Fact, Conclusions of
    Law, and Order, at 9 (Vt. Envtl. Bd. Mar. 26, 1991).
    Reviewing tribunals frequently impose conditions that relate to the behavior of parties
    not before the court, especially when those conditions relate to traffic. See e.g., In re
    Hannaford Bros. Co. & Southland Enters., Inc., No. 4C0238-5-EB, Findings of Fact, Conclusions of
    Law, and Order (Altered), at 26 (Vt. Envtl. Bd. Nov. 27, 2002) (imposing condition that
    applicant’s customer’s forklifts and delivery trucks adhere to noise emission standard). While it
    would pose due process concerns if we were to attempt to penalize those third parties for their
    behavior, where the consequences attach to the permittee, the condition is properly imposed
    on “the project.”
    NEMG argues that this condition is unenforceable, and we may not impose
    “unenforceable” permit conditions, citing In re Old Vermont Wood Products., No. 5W 1305-EB,
    Findings of Fact, Conclusions of Law, and Order, at 16 (Vt. Envtl. Bd. Aug. 19, 1999). In Old
    Vermonter, the Environmental Board rejected a proposed permit condition because the
    condition was so vague an enforcement agency would not be able to tell if it had been violated.
    2
    Appellants also suggested that the Court should order NEMG to re-site the Project. We will not consider
    this suggestion because such a revision would fundamentally alter the proposed project, and likely require
    remand. See In re Lathrop Ltd. P’ship, 
    2015 VT 49
    , ¶ 99.
    
    Id.
     Here, an enforcement agency will have no difficulty enforcing the Court’s condition: if a
    truck passes over the road’s centerline, the condition will be violated.
    When NEMG argues that the condition is unenforceable, it is really arguing that it is “un-
    compliable” to ensure compliance because NEMG does not have the legal power to control its
    customers’ truck drivers. But NEMG can ensure that its customers do not violate the condition
    through contracting with customers,3 just as applicants frequently must ensure compliance
    with their permits by controlling the behavior of independent contractors on their site. For
    instance, NEMG could require that its customers not use tractor-trailer-sized trucks, since the
    evidence showed that dump trucks have no difficulty staying in their lane. Or it could require
    that, if its customers use tractor trailers, those larger trucks use different access routes so the
    trucks don’t pass through the HCL at all.4 The Court would have the power to impose either of
    these requirements as conditions of the permit. By imposing the lane-of-travel condition, the
    Court gives Applicant more flexibility and control in determining the manner of compliance. As
    the Environmental Board has frequently said when it imposes conditions involving parties not
    before the Board: “Applicant, or its successors in interest, are responsible for complying with
    the conditions . . . . The method by which the permit holder achieves compliance is not of
    concern to the Board.” In re Liberty Oak Corp., No. W0496-EB-1, Findings of Fact, Conclusions
    of Law, and Order, at 5–6 (Vt. Envtl. Bd. Jan. 14, 1988).5
    Appellants argue that the lane-of-travel condition is meaningless because state law
    already requires vehicles to remain in their lane of travel. The Court disagrees. While state law
    already requires this, the condition adds new penalties, new enforcement mechanisms, and
    new incentives to comply with existing law. Thus, the condition is not duplicative or
    meaningless.
    Turning to the rolling average production limit, both parties agree that the pre-trial
    stipulation was not meant to remove the production-limit issue from our scope of review. To
    prevent injustice, we GRANT in part NEMG’s motion and will alter the merits decision to show
    that NEMG did not waive its challenge to the rolling average production limit, and to examine
    whether the Project complies with Act 250 the more permissive limit—180 tons per hour—that
    NEMG proposes.
    For reasons explained more fully in the altered Merits Decision that accompanies this
    entry order, we conclude that truck noise from the Project does not comply with Criterion 8
    with only a 180-ton-per-hour production limit. We acknowledge that the sound-modeling
    evidence NEMG submitted at trial demonstrated hourly Leq sound levels from truck traffic
    based on an assumed limit of 180 tons per hour. Nonetheless, loud truck noises (measured in
    3
    At NEMG’s hot-mix asphalt plant, “asphalt is manufactured on an as-needed, per-truck-load basis.” In re
    N.E. Materials Grp. A250 Permit, No. 35-3-13 Vtec, slip op. at 4 (Vt. Super. Ct. Envtl. Div. Mar. 11, 2016). NEMG
    therefore presumably has communication with its customers before delivery, and therefore has the ability to
    control some aspects of transport though contract.
    4
    There are two proposed access points to the Project: a northern access point on Graniteville Road and a
    southern access point on Pirie Road. Trucks leaving the site through the southern access point would approach
    Lower Graniteville via Baptist Street. At Baptist Street’s junction with Graniteville Road, trucks coming from
    Baptist Street would drive straight to continue onto Graniteville Road, and would not have to navigate the sharp
    curve in Graniteville Road. Though the southern access point is not yet open, NEMG could open the access point
    and require customers to use this point.
    5
    NEMG has also suggested that the lane-of-travel condition would enable an angry customer to jeopardize
    its permit by intentionally crossing over the centerline on the HCL curve. This is not a credible scenario, since the
    Natural Resources Board, which has exclusive power to enforce Act 250 permits, see In re Treetop Dev. Co. Act 
    250 Dev., 2016
     VT 20, ¶ 13, has sound enforcement discretion.
    Lmax, not Leq) would occur substantially more frequently without a rolling average production
    limit, and, at their theoretical maximum, would cause undue adverse aesthetic impacts. We
    therefore conclude that the rolling average production limit is necessary to control aesthetic
    impacts from truck noise under Criterion 8.
    An altered Merits Decision reflecting the above changes accompanies this entry order.
    So ordered.
    Electronically signed on April 18, 2016 at 10:54 AM pursuant to V.R.E.F. 7(d).
    _________________________________________
    Thomas G. Walsh, Judge
    Superior Court, Environmental Division
    Notifications:
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Pamela Austin
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Russell Austin
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Julie Barre
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Suzanne Bennett
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Jane Berard
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Lori Bernier
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Marc Bernier
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Charles Brown
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Melyssa Danilowicz
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Michael Danilowicz
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Cathy DeGreenia
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Forrest DeGreenia
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Earl Everhart
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Cynthia Fitzgerald
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Kaley Grenier
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Kirt Johnson
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Victoria Johnson
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Steve Martin
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Frederick McGrath
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Gustave Osterberg
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Rock Pariseau
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Dana Robinson
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Ricky Safford
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Padraic Smith
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Suzanne Smith
    Laura Bucher Murphy (ERN 5042), Attorney for Appellant Denise Viens-Kirkpatrik
    Elizabeth Lord (ERN 4256), Attorney for Interested Person Agency of Natural Resources
    Gregory J. Boulbol (ERN 1712), Attorney for Interested Person DO NOT USE Natural Resources
    Board
    James P.W. Goss (ERN 1997), Attorney for Cross Appellant North East Materials Grp.LLC
    Interested Person Barre Housing Authority
    Elaine O'Grady (ERN 5799), Attorney for party 28 Co-counsel
    Alan Philip Biederman (ERN 1015), Attorney for party 31 Co-counsel
    James P.W. Goss (ERN 1997), Attorney for Cross Appellant Rock of Ages Corp.
    Megan O'Toole (ERN 5149), Attorney for party 28 Co-counsel
    khambley
    

Document Info

Docket Number: 35-3-13 Vtec

Filed Date: 4/18/2016

Precedential Status: Precedential

Modified Date: 4/24/2018