Roger Rowe Act 250 ( 2016 )


Menu:
  •                                   STATE OF VERMONT
    SUPERIOR COURT                                             ENVIRONMENTAL DIVISION
    Vermont Unit                                                  Docket No. 96-7-12 Vtec
    Roger Rowe et al A250 Gravel Pit                       DECISION ON THE MERITS
    This matter relates to an existing gravel pit located off Furnace Road in Pittsford,
    Vermont. Roger and Erma Rowe obtained an Act 250 land use permit to operate the gravel pit
    in 1980 (Permit #1R0387). In 2001, Casella Construction, Inc. and the Rowes applied for and
    received an Act 250 permit amendment in order to enlarge the pit (Permit #1R0387-2). Permit
    #1R0387-2 was appealed to the former Environmental Board, now the Land Use Panel of the
    Natural Resources Board, by a group of interested parties and the applicants. The parties
    reached a settlement agreement dated April 1, 2003. The Environmental Board issued Permit
    #1R0387-2-EB (the EB Permit), expressly incorporating additional conditions expressed within
    the parties’ settlement agreement as well as the amended conditions from Permit #1R0387-2.
    Among other conditions, the EB Permit included conditions restricting the amendment of
    permit conditions regarding phasing, rates of extraction, and reclamation.
    In February 2012, Casella Construction, Inc., Roger and Erma Rowe, and the State of
    Vermont (Applicants) filed an application to amend the EB Permit and expand the existing pit
    onto a portion of adjacent lands owned by the State of Vermont and to extract up to 100,000
    cubic yards of gravel per year in five phases over a 20-year period (-3 Application). Casella had
    a pre-application meeting with Act 250 Coordinator William Burke. Casella’s representative,
    Mr. Poirier, left that meeting with the understanding that Applicants were required to file a
    permit amendment application, not a new permit application.
    Neighboring property owners (the Neighbors), most of whom were parties to the EB
    Permit negotiations, oppose the amendment, arguing that it is barred by the terms of the EB
    Permit, the parties’ prior settlement agreement, and Act 250 Rule 34(E) (the Stowe Club
    Highlands doctrine).
    On June 21, 2012, the District 1 Commission (the Commission) dismissed the -3
    Application, concluding that the permit amendment was barred by both the terms of the EB
    Permit and Rule 34(E). Casella Construction, Inc. timely appealed the Commission’s dismissal to
    this Court and raised four questions for the Court’s review. These questions include whether its
    application should be treated as a new and distinct application and not an amendment, and, if
    treated as an amendment, whether the amendment application violates the non-amendment
    provisions in Applicants’ EB Permit and Act 250 Rule 34(E). Our consideration of this matter
    was placed on inactive status while the parties litigated related issues in the Civil Division of the
    Vermont Superior Court.
    In a July 22, 2015 decision on cross-motions for summary judgment, we announced our
    intention to grant summary judgment under Rule 56(f) to the Neighbors, on grounds that the
    pit had been fully reclaimed and jurisdiction under the EB permit had ceased, meaning that
    there was no longer a valid permit to amend. See In re Roger Rowe A250 Gravel Pit, No. 96-7-
    12 Vtec, slip op. at 7 (Vt. Super. Ct. Envtl. Div. July 22, 2015). The parties filed responses, and
    we determined that issues of material fact existed regarding whether the pit was actually
    reclaimed. See In re Roger Rowe A250 Gravel Pit, No. 96-7-12 Vtec, slip op. at 2 (Vt. Super Ct.
    Envtl. Div. Sept. 11, 2015). We therefore scheduled the matter for a merits hearing on the
    limited issue of whether the pit was in fact reclaimed.
    The Court conducted a site visit to the subject property on January 13, 2016,
    immediately followed by a single day merits hearing at the Vermont Superior Court, Rutland
    Criminal Division courthouse in Rutland, Vermont. Appearing at the site visit and trial were
    Casella Construction, Inc., represented in this appeal by Harry R. Ryan, Esq.; Mary Marzec-
    Gerrior, represented by Benjamin W. Putnam, Esq.; the Natural Resources Board represented
    by Gregory J. Boulbol, Esq.; and interested party Kelly Lyon appearing pro se.
    Based upon the evidence presented at trial, which was put into context by the site visit,
    the Court renders the following Findings of Fact and Conclusions of Law.
    Findings of Fact
    1.     In 1980, Roger and Erma Rowe obtained Land Use Permit #1R0387 to operate a gravel
    pit on their property off Furnace Road in Pittsford, Vermont (the Rowe Pit).
    2
    2.       The Rowe Pit encompassed an area of 19.6 acres of the total 53.9 acres owned by the
    Rowes.
    3.       In 2001, Casella Construction, Inc. and the Rowes applied for and received an Act 250
    permit amendment to enlarge the Rowe Pit (Permit #1R0387-2). A group of interested parties,
    including the Marzec-Gerriors, appealed Permit #1R0387-2.
    4.       On February 12, 2003, the Rowes and Casella Construction, Inc., entered into a
    settlement agreement with the interested parties, including the Marzec-Gerriors.
    5.       On April 17, 2003, the Environmental Board issued amended Act 250 Land Use Permit
    #1R0387-2-EB (the EB Permit) with three conditions.
    6.       Condition 1 of the EB Permit expressly incorporates all but conditions 3 and 14 of Permit
    #1R0387-2. It also incorporates additional conditions expressed within the parties’ settlement
    agreement.1
    7.       Permit #1R0387-2 authorized the extraction of 100,000 cubic yards of gravel annually
    from the Rowe Pit; the construction of a temporary scale, scale housing building, and
    washroom facilities adjacent to the existing gravel extraction operation; and progressive
    reclamation as the Rowe Pit expanded.
    8.       Condition 33 of Permit #1R0387-2, which was incorporated into the EB Permit, required
    that all gravel extraction and site reclamation be completed by September 15, 2010.
    9.       Condition 7 of Permit #1R0387-2, which was incorporated into the EB Permit, provided
    “The commercial extraction from the pit shall cease, and the entire site be certified by affidavit
    to the town and to the commission as fully reclaimed no later than October 15, 2010.”
    10.      The Rowe Pit was excavated in four phases, with reclamation occurring at the
    conclusion of each phase.
    1
    This settlement agreement has been the subject of litigation between these same parties before the
    Vermont Superior Court, Civil Division. This Court admitted a copy of the settlement agreement as Exhibit 4. The
    Court required all text in the settlement agreement except for the “Agreed Permit Conditions” to be redacted
    because Attorney Putnam conceded that only the additional conditions were relevant to the issues before the
    Court, and because the agreement was subject to a confidentiality clause. Casella asked the Court to rule
    definitively that the language in the EB Permit incorporating “the terms of the parties’ settlement agreement”
    incorporates only the conditions in the settlement agreement (and not the preamble language). Because we
    ultimately find that the permit is expired, see infra p. 11, we decline to authoritatively construe the EB Permit on
    mootness grounds and because there was no offer that other provisions are relevant to the issues before the
    Court.
    3
    11.    Casella completed phases I through III, including reclamation, without complaints or
    violations.
    12.    In October 2010, Ms. Lyon contacted Robert Steadman, Chief Financial Officer (and de
    facto general manager) of Casella, and informed him that Casella was operating in violation of
    its permit, as the EB Permit required phase IV to be completed by October 15, 2010.
    13.    As Casella failed to timely complete and close the Rowe Pit, it self-reported to the Act
    250 District Coordinator to resolve the violation.
    14.    Casella worked cooperatively with the Land Use Panel of the Natural Resources Board
    and accepted, without appeal, a November 17, 2010 Administrative Order (AO).
    15.    The AO set new reclamation deadlines. The AO required and authorized Casella to
    complete the grading portion of the reclamation procedures by December 23, 2010.
    16.    The AO also required and authorized Casella to complete the remaining portions of the
    reclamation procedures by June 17, 2011.
    17.    The approved reclamation procedures required Casella to “hydroseed” exposed gravel
    areas and to plant a specified number of trees at specified locations. Casella was to see that all
    seeded areas were watered and kept in good condition and reseeded if and when necessary
    until a good, healthy, uniform growth was established over the entire area seeded.
    18.    Casella retained Transamerica Hydroseeding to perform the hydroseeding, and
    Transamerica completed hydoseeding of phase IV prior to June 17, 2011.
    19.    Seeds used for reclaiming the Rowe Pit were a seed mixture recommended by the USDA
    specifically for reclamation of gravel pits.
    20.    This hydroseeing mixture has unique germination and dormancy periods, which will
    remain dormant for longer than native grass. While native grass will be green by May, the grass
    variety used at the Rowe Pit will still be dormant.
    21.    The reclamation vegetation at the Rowe Pit will always appear different than native
    vegetation of hay fields.
    22.    Casella retained Pradico (a landscaping service) to plant trees as required by the
    reclamation plans.
    4
    23.      Jeff Chase is a Casella engineer.    He was responsible for establishing reclamation
    elevations and grades in conformance with approved reclamation plans and for verifying the
    hydroseeding and tree planting work.
    24.      By the end of December 2010, Mr. Chase confirmed that slope grades and elevations
    were close to complying with approved reclamation plans. In the spring of 2011, Mr. Chase
    confirmed that slope and elevations met or exceeded the requirements of the reclamation
    plans.
    25.      Mr. Chase concluded that reclamation was complete by June 17, 2011.
    26.      After the June 17, 2011 deadline for reclamation in the AO, Act 250 Compliance Officer
    John Wakefield performed a site visit. Representatives from Casella were present, as was Amy
    Loomis, the zoning administrator for the Town of Pittsford.
    27.      After that meeting, John Steadman (the CFO and general manager) was under the
    impression that the Act 250 Compliance Officer considered the pit to be reclaimed. Casella was
    not contacted about any other enforcement and, as far as it knew, the matter was resolved.
    28.      As part of the EB Permit, Casella was required to post a bond with the Town of Pittsford,
    which could be recovered when the pit was fully reclaimed.              Amy Loomis, the zoning
    administrator, released this bond after the June 17, 2011 site visit.
    29.      We therefore find, as a matter of fact, that Casella timely complied with the December
    23, 2010 and June 17, 2011 reclamation requirements of the AO.
    30.      Casella did not certify by affidavit to the Town or to the Commission by October 15,
    2010 that commercial extraction ceased or that the site was reclaimed, because neither had
    taken place by that date. Casella did not certify by affidavit that reclamation had been
    completed by June 17, 2011 (the deadline for reclamation in the AO). The AO did not require a
    similar affidavit.
    31.      Tropical Storm Irene crossed the Rowe Pit in late August 2011.
    32.      In the fall of 2011, Casella again retained Transamerica Hydroseeding to perform
    additional hydroseeding in areas where stormwater had washed away vegetated ground cover.
    33.      Mathew Poirier is a Professional Engineer with Sanborn, Head & Associates, Inc., whom
    Casella employed to assist with Act 250 permitting and reclamation work.
    5
    34.    Mr. Poirier was responsible for supervising reclamation work.
    35.    Mr. Poirier participated in a site visit to the Rowe Pit in 2012 with Act 250 Coordinator
    William Burke. Mr. Poirier showed Coordinator Burke that phases I through IV were complete
    and reclaimed as required.
    36.    Around this time, Casella was contemplating opening expanded gravel extraction
    operations on the Rowe property.
    37.    Mr. Poirier met with Coordinator Burke in advance of filing an application for this
    expansion. Mr. Poirier offered that it was appropriate to file an application for a new permit for
    this expansion, not a permit amendment, since Casella sought approval for a new gravel
    extraction operation on a separate and distinct area of land. Mr. Poirier was under the
    impression that Coordinator Burke would require a permit amendment application, not a new
    permit application.
    38.    On February 17, 2012, Appellants filed an application to amend Permit #1R0387-2
    (the -3 Application). The -3 Application proposes the extraction of 100,000 cubic yards of gravel
    from 15.6 acres of land owned by the Rowes and the State of Vermont.
    39.    The project proposed in the -3 Application shares access with the Rowe Pit, and
    significant portions of the Rowe Pit are proposed for staging and operational requirements.
    40.    Of the 15.6 acres proposed for excavation under the -3 Permit, 5.9 acres are owned by
    the State of Vermont and 9.7 acres are owned by Roger and Erma Rowe. Of the 9.7 acres
    owned by the Rowes, 5.7 acres overlap with the area permitted under the EB Permit.
    41.    The -3 Application proposes the construction of a temporary scale, scale housing
    building, and washroom facility within the Rowe Pit’s footprint.
    42.    Pursuant to the -3 Application, extraction is proposed to occur in five phases over the
    course of 20 years.
    43.    Mary Marzec-Gerrior lives on Furnace Road in Pittsford, Vermont. Her property abuts
    the Rowe property to the south. While standing on the common boundary of the Marzec-
    Gerrior and Rowe properties one has limited views of the Rowe Pit. There are no views of the
    Rowe Pit from the Marzec-Gerrior house.
    6
    44.    Kelly Lyon lives on Furnace Road in Pittsford, Vermont. Her property abuts the Rowe
    property to the south. Ms. Lyon’s property is located to the west of the Marzec-Gerrior
    property. While standing on the common boundary of the Lyon and Rowe properties, one has
    limited views of the Rowe Pit. There are no views of the Rowe Pit from the Lyon house.
    45.    In April 2012, the Neighbors, including Ms. Marzec-Gerrior and Ms. Lyon, filed motions
    to dismiss the -3 Application, arguing that the plain terms of the EB Permit barred further
    expansion of the Rowe Pit.
    46.    On June 21, 2012 the Commission dismissed the -3 Application, determining that the -3
    Application was properly characterized as an amendment to the EB Permit rather than a new
    application for a separate and distinct project and that the terms of the EB Permit prohibited
    amendments.
    47.    Casella appealed the Commission’s decision dismissing the -3 Application.
    48.    This Court’s consideration of the -3 Application was placed on inactive status while the
    parties litigated a collateral issue in the Civil Division of the Vermont Superior Court.
    Conclusions of Law
    The fundamental issue in this case is whether the gravel extraction Casella proposes in
    its -3 Application requires an amendment to its EB Permit or a new Act 250 permit altogether.
    This distinction is significant because Act 250 Rule 34(E) and the terms of Casella’s EB Permit
    restrict permit amendments, but no such limits exist for new permit applications.
    As originally framed by the parties, the answer to this question hinges on whether the
    gravel extraction Casella proposes is within the scope of the development permitted in Casella’s
    previous permit (the EB Permit). See Act 250 Rules, Rule 34(A) (requiring a permit amendment
    for “any material change to a permitted development or subdivision”); see also In re
    Stonybrook Condominium Owners Association, No. 385, Findings of Fact, Conclusions of Law,
    and Order, at 17–18 (Vt. Envtl. Bd. May 18, 2001) (discussing scope of permitted project under
    Rule 34(A)); In re O’Neil Sand & Gravel, No. 48-2-07 Vtec, slip op. at 8–10 (Vt. Envtl. Ct. Sept. 11,
    2009) (discussing Stonybrook). Both the original Act 250 permit and the EB Permit authorized
    gravel extraction operations on the Rowe’s 53.9 acre parcel. Although the extraction occurred
    on a 19.6 acre portion of the parcel (the Rowe Pit), the entire tract falls under Act 250
    7
    jurisdiction. See Stonybrook, No. 385, at 14. Casella now seeks approval for a gravel extraction
    operation on 15.6 acres, 5.9 of which are on land owned by the State of Vermont and 9.7 of
    which are on land owned by the Rowes, which is also land under jurisdiction of the EB Permit.
    As the Court analyzes the issues raised in this appeal, we conclude that the
    determinative issue in this case is not whether the proposed project is within the scope of the
    project permitted by the EB Permit, but whether Act 250 jurisdiction over Casella’s previous
    operations and the Rowe land had expired by the time Casella applied for its -3 Permit. If so,
    there was no longer any permit to amend, and Casella’s proposal requires a new permit, not an
    amendment.2
    For most types of development, an Act 250 permit, and thus Act 250 jurisdiction,
    remains in place indefinitely. See 10 V.S.A. § 6090(b)(1) (“Other permits issued under this
    chapter shall be for an indefinite term, as long as there is compliance with the conditions of the
    permit.”). The Legislature has elected, however, to establish separate rules for permits for the
    extraction of mineral resources and requires that those permits be for a “specified period
    determined by the board in accordance with the rules adopted under this chapter. . . .” 10
    V.S.A § 6090(b)(1). The Natural Resources Board Act 250 Rules therefore require that permits
    granted for extraction of mineral resources “contain specific dates for completion of the
    project, reclamation of the land, and for expiration of the land use permit.” Act 250 Rules, Rule
    32(B).
    The EB Permit includes specific dates for completion of the project and reclamation of
    the land. Condition 33 provides, “All gravel extraction and site reclamation shall be completed
    in accordance with the approved plans by September 15, 2010 unless an extension of this date
    is approved in writing by the Commission.” Condition 7 requires that “commercial extraction
    from the pit shall cease, and the entire site be certified by affidavit to the town and to the
    commission as fully reclaimed no later than October 15, 2010.”
    The EB Permit does not, however, contain an explicit expiration date. Nevertheless,
    because all actions were scheduled to cease by October 15, 2010, the EB Permit does contain
    2
    We provided this analysis first in our July 22, 2015 decision on cross-motions for summary judgment and
    we continue this analysis in this decision.
    8
    an implicit date the permit was to expire. Further, we conclude that, when read together, the
    dates of completion—September 15, 2010—and reclamation—October 15, 2010—effectively
    establish a valid expiration date contingent on completion and full reclamation.                       As the
    Supreme Court has held, even when a permit has nominally expired, Act 250 jurisdiction
    continues if reclamation has not been properly completed. See In re Hamm Mine Act 250
    Jurisdiction (Jurisdictional Opinion No.2-241), 
    2009 VT 88
    , ¶ 19, 
    186 Vt. 590
    . Therefore, because
    Act 250 jurisdiction ceases once reclamation is complete, see 
    id.,
     we conclude that jurisdiction
    in this case ceased when reclamation was, in fact, complete.
    The parties dispute whether the project authorized by the EB Permit was reclaimed.
    Based upon the credible evidence, we conclude that the Rowe Pit was reclaimed in June of
    2011. Mr. Steadman, Mr. Chase, and Mr. Poirier all testified to their personal involvement and
    knowledge of Casella’s efforts to reclaim the Rowe Pit and all provided their opinion that the
    Rowe Pit was reclaimed by June 17, 2011, with additional reseeding being completed following
    Tropical Storm Irene. The Court finds this testimony credible, and concludes that reclamation
    was complete by June 17, 2011.
    Ms. Marzec-Gerrior testified that she did not believe that the Rowe Pit was reclaimed.
    Ms. Marzec-Gerrior admitted that she had limited personal observations of the Rowe Pit in
    2011 and 2012, that she could only see portions of the Rowe Pit from her property, and that
    she never asked permission to go into the Rowe Pit to make observations. Ms. Lyon introduced
    into evidence two pictures taken by her sister on the morning of September 1, 2011. These
    photographs show substantial ground vegetation within the Rowe Pit. The pictures also show
    areas without vegetation. Casella’s witnesses all credibly testified that, while the Rowe Pit was
    fully hydroseeded (and all required trees planted) in advance of Tropical Storm Irene, the
    significant rains washed away some ground vegetation. These same witnesses also testified
    that these areas were reseeded shortly after the storm.3
    3
    The evidence supports our conclusion that reclamation was complete during the summer of 2011, as
    that is “when a good, healthy, uniform growth [was] established.” The most conservative conclusion of complete
    reclamation, considering the evidence regarding reseeding which occurred shortly after Tropical Storm Irene,
    continues to support full reclamation well in advance of the February 2012 -3 Application.
    9
    Over the objection of Casella, the Court admitted Exhibit 7, which is a GoogleEarth
    satellite photograph of the Rowe Pit. Ms. Marzec-Gerrior, the sponsor of the Exhibit, testified
    that the date of the photograph was May 5, 2015. Ms. Marzec-Gerrior offered that Exhibit 7 is
    evidence that the Rowe Pit was not reclaimed because the area around the pit appears more
    brown than the agricultural areas of the Rowe property and neighboring properties, which
    appear green. We disagree. In rebuttal to Exhibit 7, Mr. Poirier testified that the seed used to
    reclaim the Row Pit was a mixture recommended by the USDA for reclamation of gravel pits
    and that the reclamation vegetation from this seed has unique germination and dormancy time
    periods. According to Mr. Poirier’s credible testimony, hydroseeded grass would still be
    dormant in early May (when the photo was taken), while grass in Vermont hay fields would
    already be green. Furthermore, Mr. Poirier testified that the reclamation vegetation will always
    appear different than native vegetation of hay fields. Lastly, we note that Exhibit 7 is from May
    2015, while reclamation activities were completed in 2011.                       The approved reclamation
    procedures required that all seeded areas be watered and kept in good condition, and reseeded
    if and when necessary until a good, healthy, uniform growth was established over the entire
    area seeded. We conclude that a good, healthy, uniform growth was established by the state
    inspection in June 2011, and that Casella’s obligations under the AO ceased at that time. Even
    if Exhibit 7 showed that the area around the Rowe Pit had no vegetation in 2015, this could be
    because of intervening events, and does not show that Casella failed to reclaim the area in
    2011. Again, based on the totality of the evidence, we conclude that the Rowe Pit was
    reclaimed in 2011.
    Ms. Marzec-Gerrior, with the NRB’s support, argued that the Court could not conclude
    that the Rowe Pit was reclaimed because no affidavit was filed with the Board certifying that
    the entire site was fully reclaimed no later than October 15, 2010 as required by condition 7 of
    Permit #1R0387-2, which is incorporated into the EB Permit.4 First, Mr. Poirier credibly testified
    4
    Ms. Marzec-Gerrior also suggested that Casella was required to certify compliance with its permit under
    Act 250 Rule 37 in order for jurisdiction to end and reclamation to be complete. But Act 250 Rule 37 merely
    provides an opportunity for permittees to seek certification of compliance. The Rule states, “a person may petition
    for a certification upon completion . . . .” Act 250 Rules, Rule 37. Because the Rule does not use mandatory
    language, but instead uses the term “may,” we do not consider Rule 37 to impose a mandatory requirement, and
    10
    that such an affidavit could not have been filed on or before October 15, 2010 because the
    Rowe Pit was not reclaimed by that date. Second, Ms. Marzec-Gerrior suggested that this
    language required a distinct affidavit, and that, because Casella had not submitted an affidavit
    certifying completion after the June 17, 2011 inspection, the site cannot be considered
    reclaimed. We disagree. Casella and the Land Use Panel of the NRB negotiated the November
    17, 2010 AO specifically addressing the necessary reclamation activities as a result of the
    missed October 15, 2010 deadline. We consider this enforcement proceeding to take the place
    of any affidavit requirement because the enforcement proceedings gave the NRB the same
    opportunity to ensure compliance that an affidavit requirement would have done.
    Based upon the evidence before the Court, we conclude that Casella completed all
    reclamation activities required by the EB Permit and the AO by June 17, 2011, and that
    jurisdiction over the permit expired when reclamation was complete. The -3 Application was
    filed with the District Commission on February 17, 2012. As Act 250 jurisdiction over the Rowe
    parcel had already ceased to exist, the Rowe Pit was no longer encumbered by the EB Permit or
    Act 250 jurisdiction.        Therefore, there was no valid Act 250 permit to amend. Because
    Applicants propose a new development of the Rowe Pit and state lands, constituting an
    independent trigger of Act 250 jurisdiction, Applicants must seek a new Act 250 permit
    authorizing mineral resource extraction of the Rowe Pit and adjacent state-owned lands. See 10
    V.S.A. § 6081(a) (requiring permits for “development”); 10 V.S.A. § 6001(3)(A) (defining
    “development”).
    Casella asks that the Court treat the pending -3 Application as a new independent
    application without remanding the application to the District Commission. The Neighbors and
    NRB object to this approach, arguing that the District Commission must first consider the
    application. As the District Commission dismissed the -3 Application on procedural grounds,
    and did not consider the merits of the application’s compliance with Act 250 Criteria, we
    conclude that the application must be remanded to the District Commission for its review. See
    In re Taft Corners Assocs., 
    160 Vt. 583
    , 591 (1993) (“The Board’s jurisdiction is limited, however,
    we do not find Casella’s reclamation incomplete simply because they did not elect to obtain a certificate of
    compliance under Rule 37.
    11
    by the scope of the proceedings below. It has no jurisdiction to decide issues regarding criteria
    that were not before the district commission and not ruled upon by it.”).
    Conclusion
    We conclude that the Rowe Pit was reclaimed as required by the EB Permit and AO, that
    Act 250 jurisdiction over the Rowe property no longer exists, that Casella proposes a new
    development of the Rowe Pit and state lands constituting an independent trigger of Act 250
    jurisdiction, and therefore, that Applicants must seek a new Act 250 permit authorizing mineral
    resource extraction of the Rowe Pit and adjacent state-owned lands. We therefore DISMISS
    the pending appeal and REMAND the -3 Application to the District Commission for
    consideration as a new application.
    Also pending before the Court is a related matter, Conditional Use Application of Rowe,
    No. 102-7-11 Vtec. We have coordinated this Act 250 appeal and the conditional use appeal
    pursuant to V.R.E.C.P. 2(b). At the request of the parties, we place the conditional use appeal
    on inactive status to await the decision of the District Commission on remand and any potential
    appeal of that decision. In the conditional use appeal, Casella is to report in writing with the
    Court every six months on the status of its Act 250 approval.
    Electronically signed on January 19, 2016 at 03:40 PM pursuant to V.R.E.F. 7(d).
    _________________________________________
    Thomas G. Walsh, Judge
    Superior Court, Environmental Division
    12
    

Document Info

Docket Number: 96-7-12 Vtec

Filed Date: 1/19/2016

Precedential Status: Precedential

Modified Date: 4/24/2018