NE Materials Group, LLC Act 250 ( 2015 )


Menu:
  •                                           STATE OF VERMONT
    SUPERIOR COURT                                                                 ENVIRONMENTAL DIVISION
    Vermont Unit                                                                    Docket No. 143-10-12 Vtec
    N.E. Materials Group LLC A250 JO #5-21                             DECISION ON THE MERITS
    This matter is comes to the Court on remand from the Vermont Supreme Court’s
    decision in In re N.E. Materials Grp. Act 250 JO, 
    2015 VT 79
    . In our original decision, thirteen
    citizens, collectively “Neighbors for Healthy Communities” (Appellants), appealed a September
    28, 2012 jurisdictional opinion of the District 5 Environmental Commission Coordinator (District
    Coordinator), which determined that North East Materials Group, LLC’s (NEMG) rock crushing
    operations, located at the Rock of Ages (ROA) quarry in the Town of Barre, Vermont,1 did not
    require an Act 250 permit.2 NEMG argued that its rock crusher was part of a preexisting
    development and therefore exempt from Act 250 jurisdiction.                           See 10 V.S.A. § 6081(b).
    Appellants argued that NEMG’s rock crushing operation constituted a “substantial change” to
    NEMG’s preexisting quarry activities and was therefore subject to Act 250 jurisdiction. See id.
    We held that NEMG’s rock crusher was not a substantial change to ROA’s preexisting quarry
    operation, and therefore not subject to Act 250 jurisdiction. In re N.E. Materials Grp. LLC A250
    JO #5-21, No. 143-10-12 Vtec, slip op. at 14–15 (Vt. Super. Ct. Envtl. Div. Apr. 28, 2014) (Walsh,
    J.). The Supreme Court reversed and remanded to this Court. 
    2015 VT 79
    , ¶ 36.
    On remand, this Court afforded the parties an opportunity to introduce new evidence.
    The parties declined the opportunity to reopen the trial and offer additional evidence;
    however, they did file post-remand briefs offering different ways of interpreting the Supreme
    Court’s remand decision. The Court therefore revisits the existing record in the case and
    renders the following findings of fact and conclusions of law. The factual findings include all
    1
    Although this appeal is captioned “In re North East Materials Group, LLC,” the Rock of Ages Corporation,
    the owner and operator of the Rock of Ages quarry, is also an appellee.
    2
    A thorough procedural history of the case is provided in our original decision on the merits. See In re
    N.E. Materials Grp. LLC A250 JO, No. 143-10-12 Vtec, slip op. at 1–3 (Vt. Super. Ct. Envtl. Div. Apr. 28, 2014) (Walsh,
    J.).
    1
    unchallenged findings from our first decision.3             We have stricken findings regarding the
    northernmost Wells-Lamson rock crushing facility (which provided a sub-base for I-89), since
    the northernmost Wells-Lamson parcel was never aggregated onto the ROA tract. See id. ¶ 34.
    We supplement our findings with several facts (all indicated “added on remand”) to help clarify
    the relative locations of the different historical crushing sites on the ROA tract. We have also
    added more detailed findings regarding the impacts of crushing on the neighbors. All of the
    findings have been put into context by the site visit the Court conducted on December 4, 2013,
    at which Alan Biederman and James Goss, attorneys for Applicant, and Christopher Ahlers and
    Douglas Ruley, attorneys for Appellants, were present.4
    Findings of Fact
    1.      NEMG operates a rock crusher on large tract of land owned by the Rock of Ages
    Corporation. (Added on remand).
    2.      The Rock of Ages Corporation is a quarrying operation comprised of several smaller
    individual quarries active from the late 1800s to current times, now all aggregated as a single
    parcel under the Rock of Ages Corporation ownership and operation.
    3.      All total, ROA comprises approximately 930 acres in Barre, Vermont and 230 acres in
    Williamstown, Vermont.
    4.      Some of the historic individual quarries were previously owned and operated by the
    Boutwell, Milne & Varnum Corporation, the E.L. Smith & Company, the Wetmore & Morse
    Granite Company, and the Wells-Lamson quarry Company.
    5.      The NEMG crusher is located on what was historically the Boutwell, Milne & Varnum
    Corporation quarry. (Added on remand).
    6.      These quarries are adjacent to one another and are aligned in a more or less north-
    south configuration.
    3
    We have made minor stylistic alterations to some of our original findings, but the original findings
    remain substantively unchanged unless otherwise noted.
    4
    Attorney Ruley has withdrawn from this appeal as of December 21, 2015. Laura Murphy is now lead
    counsel for Appellants.
    2
    7.     The northernmost historic quarry is the Wells-Lamson quarry (which is bisected by
    Websterville Road). South of Wells-Lamson lies the Smith quarry. South of that is the Boutwell,
    Milne & Varnum quarry site (later known as the McCullough, McDonald & Pike site), where the
    NEMG crusher is presently located). South still lies the Adams quarry. (Added on remand).
    8.     Websterville Road marks the northern boundary of the ROA tract. (Added on Remand).
    9.     Several roads transect the ROA property, including Graniteville Road.           Roads also
    connect work areas throughout the ROA property.
    10.    Three sites, including the Smith quarry and the former Wells-Lamson crusher site, are
    located north of Graniteville Road. Two quarrying sites, including the Adams quarry, are
    located south of Graniteville Road, as is the NEMG crushing operation at issue here.
    11.    Granite quarrying is a process of cutting and extracting large blocks of stone for sale or
    to be further processed into monuments or other industrial products and then sold. The large
    blocks of granite suitable for monuments and similar uses are referred to as “dimension stone.”
    12.    Quarrying activity moves deeper into the earth over time. Typically, higher quality
    material is found the deeper one mines a quarry.
    13.    The depth of a quarry is limited by the ability of derricks to lift the blocks out of the
    quarry or by the horizontal acreage available to build roads down into the quarry.
    14.    At the inception of a quarry, the overburden soil and rock is removed to expose the
    underlying granite. The granite closest to the surface is called “bedding” and is typically
    unsuitable for sale or use as dimension stone. It is typical for ROA to need to remove 80 to 200
    feet of bedding to reach suitable dimension stone. Removal of overburden soil and bedding is
    referred to as quarry “development.” Development is expensive and produces considerable
    volumes of soil and stone which is either trucked off-site or piled on-site.
    15.    This overburden is waste material unless the rock component is crushed into usable and
    salable product. Up to 80 percent of quarry material is waste.
    16.    “Grout” is waste granite which is not suitable for the high-end dimension stone.
    17.    Crushing makes use of the waste from development material, including grout, by
    reducing the material to usable and salable sizes.
    18.    Much of the material in ROA’s grout piles is too large for crushing.
    3
    19.     The crushing process is common at dimension quarries in order to utilize the otherwise
    waste material.
    20.     Crushing is not absolutely necessary for quarrying, but it does “help your bottom line,”
    because it turns what would otherwise be waste material into a valuable product. (Added on
    remand).
    21.     Crushing rock at various locations is customary in the industry because the equipment is
    often portable and the source of material (or “feedstock”) may change.
    22.     Rock crushing is also customarily intermittent. The frequency and location of rock
    crushing varies depending on the availability and location of feedstock and demand for crushed
    rock.
    23.     Crushing entails drilling, blasting, removal, and transport of rock to the crusher
    equipment. While many of today’s crushing operations use portable equipment, material is
    typically moved from the extraction area to the crusher.
    24.     Don Murray, ROA Engineer, has personal knowledge of crushing at ROA since the 1960s.
    Mr. Murray has completed significant research into crushing activities at ROA preceding 1960.
    25.     Don Murray has worked at Rock of Ages since 1979. (Added on remand).
    26.     In the early 1900s there was a crushing plant in Barre installed by J.M. Boutwell at the
    Boutwell, Milne & Varnum Corporation quarry. This crushing plant utilized waste stone from
    the quarries.5
    27.     Photographic evidence shows that crushing activity took place around 1912 near the
    current compressor building on the south side of Graniteville Road in close proximity to NEMG’s
    crushing location. It was common at this time for crushed material to be placed in rail cars and
    transported off-site.
    28.     As far back as 1926, the former Wells-Lamson quarry Company conducted crushing,
    including a crushing operation producing poultry grit and road aggregate.                       This crushing
    continued through the 1940s and into the 1960s. By 1948, this quarry and crusher had been
    conveyed to ROA.
    5
    To better conform to the evidence before the Court, this finding is modified on remand by deleting “As
    early as 1904” and replacing it with “In the early 1900s.”
    4
    29.      This crushing operation described in Finding 28 was on the southern portion of the
    Wells-Lamson parcel (south of Websterville Road).          Wells-Lamson also built a crushing
    operation on the northern side of Websterville Road in 1956. This crushing operation produced
    much of the sub-base for Interstate 89. This northern portion of the Wells-Lamson quarry was
    never aggregated into the ROA tract. (Added on remand).
    30.      Kelley Construction, Inc. contracted with ROA in August 1969 to remove overburden and
    rock in the Smith quarry. Activities included the planned crushing of approximately 40,000
    cubic yards of material for sale. This work was undertaken between September 1969 and April
    1970.
    31.      In 1988, Rock of Ages entered into a ten-year contract with Cooley Asphalt Paving
    Corporation, in which Cooley agreed to remove rock from ROA’s grout piles and crush it off-site.
    This contract begins by noting that Cooley had been removing rock from ROA’s tract for a
    “period of time” before the contract, and that the parties “wish[] to formalize this practice in a
    written agreement.” From this, the Court infers that it was common practice in the quarrying
    industry to conduct crushing without formal contracts. (Added on remand).
    32.      McCullough Crushing, Inc. was awarded an Air Pollution Control Permit in January 1990
    from the Vermont Agency of Natural Resources for a portable crushed stone/gravel processing
    plant.
    33.      From July 1990 to November 1990 McCullough Crushing removed more than 55,000
    tons of crushed granite from the Adams quarry.
    34.      McCullough Crushing’s equipment included a jaw crusher, a cone crusher, a conveyor,
    and a screen. This equipment is similar to NEMG’s crushing equipment.
    35.      During the 1990s, McCullough’s crushing took place in a similar area to NEMG’s current
    location. This activity included similar truck traffic.
    36.      In 1992 and 1993, Pike Industries, a crushing subcontractor, primarily crushed rock at
    the northern Wells-Lamson parcel (off-site), but also crushed 18,118 tons of rock on the current
    NEMG site. (Added on remand).
    37.      The E.L. Smith & Company quarry included crushing activity from 2005 to 2007. The E.L.
    Smith & Company quarry is located approximately 0.8 miles to the north of NEMG operations.
    5
    38.    According to Donald Murray’s credible testimony, rock crushing within the ROA tract
    has been “pretty much continuous” since 1979, when he started working for Rock of Ages.
    (Added on remand).
    39.    NEMG entered into a contract with ROA to crush waste rock on-site into salable
    material.
    40.    The rock crusher at issue, operated by NEMG between the Smith and Adam quarries,
    began operating in 2009 after the District 5 Environmental Commission Coordinator
    determined, in a December 17, 2008 jurisdictional opinion, No. 5-01, that the proposed
    crushing operation did not require an Act 250 permit.
    41.    The District Coordinator issued additional jurisdictional opinions in 2010 and 2012
    finding that rock crushing operations adjacent to the Smith quarry at Rock of Ages did not
    constitute a substantial change to a preexisting development and that the associated rock
    crusher therefore did not require an Act 250 permit.
    42.    NEMG crushed 20,285 tons of material in 2010; 155,577 tons in 2011; 89,667 tons in
    2012; and 59,279 tons in 2013. The spike in crushing in 2011 was due to Tropical Storm Irene
    when the Vermont Natural Resources Board suspended Act 250 permitting needs for gravel and
    quarry operators due to the increased need for road-building material in order to rebuild
    infrastructure destroyed in the storm.
    43.    NEMG’s crushing activity is intermittent. NEMG crushes when material is needed.
    Crushing typically does not take place during the winter months.
    44.    In 2011, NEMG crushed on 53 days. In 2012, NEMG crushed on 83 days, and in 2013,
    NEMG crushed on 43 days.
    45.    NEMG’s crushing operations have moved around the ROA property over this time.
    46.    NEMG’s current crushing operations include crushing and screening. The equipment
    includes two jaw crushers, a cone crusher, a triple-deck screen, loaders, and excavators.
    47.    The primary crusher breaks large material into smaller pieces that fit into the jaw
    crusher. The primary crusher is a hydraulic hammer.
    48.    There have been machinery improvements over time since the first crusher at the
    Boutwell quarry in the early 1900s; however, the process of crushing remains the same. A large
    6
    primary crusher crushes rock followed by a smaller crusher further reducing rock size. Screens
    are used to separate the crushed rock by size suitable for various purposes.
    49.    NEMG does not own delivery trucks. Material is transported off-site by customers using
    their own trucks. NEMG does own one truck that hauls grout.
    50.    On June 5, 2013, ANR issued an Air Pollution Control Permit to Construct to NEMG for
    installation of crushing, screening, and conveying equipment. The ANR permit allows two
    primary crushers, two secondary crushers, three screening decks, discharge and stacking
    conveyors, and a diesel powered electric generator.
    51.    Neighbors in the area of crushing experience noise, dust, and traffic. Common noises
    are material being loaded or unloaded. Dust accumulates on house windows, outside furniture,
    lawns, and cars. When traveling on area roads, it is common to encounter dump trucks on
    Graniteville Road traveling to or from the crushing activity.
    52.    Dimension stone is typically transported on flatbed tractor trailer trucks. Crushed
    material, also called aggregate, is typically transported in dump trucks. ROA’s dimension stone
    operations also use dump trucks.
    53.    ROA’s dimension stone quarrying activities also create noise, dust, and truck traffic.
    54.    Suzanne Bennet has lived at her current residence on Park Street off Graniteville Road
    since 1961. (Added on remand).
    55.    Ms. Bennet experiences noises like stone on metal that are loud enough to wake her up
    in the morning and that continue until 8:00 or 8:30 at night. These noises started in roughly
    2011. (Added on remand).
    56.    Ms. Bennett also experiences a coating of gritty dust on the exterior of her house, her
    lawn, her outdoor furniture, and her car. (Added on remand).
    57.    Ms. Bennet experiences increased truck traffic from the crusher. (Added on remand).
    58.    Pamela Austin has lived on Graniteville Road since 1982. Before that, she lived two
    houses down on Graniteville Road since 1969. (Added on remand).
    59.    Ms. Austin experiences loud noises from the crusher, which are distinct from the noises
    she hears from the ROA compressor house located behind her property. (Added on remand).
    7
    60.    Ms. Austin experiences a coating of dust on her property, which she attributes to dust
    coming off the dump trucks that haul aggregate from the NEMG crusher past her house. (Added
    on remand).
    61.    Ms. Austin experiences increased truck traffic due to trucks hauling aggregate from the
    NEMG site. (Added on remand).
    62.    Mark Bernier has lived at 11 Park Street in Graniteville, across the street from Suzanne
    Bennett, who is his mother-in-law, since 1993. (Added on remand).
    63.     Mr. Bernier lives roughly 2,000 feet from the NEMG crusher. Mr. Bernier experiences
    very loud noise from the crusher. (Added on remand).
    64.    Mr. Bernier also experiences dust in the area. (Added on remand).
    65.    Mr. Bernier experiences increased truck traffic on Graniteville Road from dump trucks
    hauling aggregate from the NEMG site. (Added on remand).
    Conclusions of Law
    After the Supreme Court’s decision, the basic skeleton of Act 250 jurisdiction is
    unchanged. A party proposing land “development” must obtain an Act 250 permit. 10 V.S.A.
    § 6081(a). Any development that was commenced before June 1, 1970 is a “pre-existing
    development” and is exempt from the permit requirement. 10 V.S.A. § 6081(b); Act 250 Rule
    (2)(C)(8). The preexisting development exemption disappears, however, if the land owner
    abandons the preexisting use. In re Village of Cambridge Water Sys., No. 272, Findings of Fact,
    Conclusions of Law, and Order, at 8 (Vt. Envtl. Bd. Sept. 15, 1993).
    A permit is also required for any “substantial change” to a preexisting development. 10
    V.S.A. § 6081(b). Vermont courts have long used a two-step test for substantial change—a test
    the Supreme Court affirmed in its North East Materials decision. 
    2015 VT 79
    , ¶¶ 16, 31 n.16.
    First, a court must find that there is a “cognizable physical change” in the preexisting
    development. Id. ¶ 43 (Eaton, J., dissenting) (quoting In re H.A. Manosh Corp., 
    147 Vt. 367
    , 370
    (1986)). If so (and only if so), the issue becomes whether the change has the potential for
    significant adverse impacts under the Act 250 criteria. 
    Id.
     (quoting Manosh, 147 Vt. at 370).
    8
    A landowner seeking a preexisting development exemption has the burden of proving
    that the development existed prior to June 1, 1970. Id. ¶ 20. The landowner must also prove
    that the preexisting use has not been abandoned. In re Village of Cambridge Water Sys., No.
    272, Findings of Fact, Conclusions of Law, and Order, at 8 (Vt. Envtl. Bd. Sept. 15, 1993). Once a
    development is determined to be preexisting, “the burden shifts to the proponents of
    jurisdiction to demonstrate that a project represents a substantial change to the preexisting
    development.” In re Vt. RSA Ltd. P’ship, 
    2007 VT 23
    , ¶ 10, 
    181 Vt. 589
    . The party seeking an
    exemption, however, retains the burden of producing sufficient information regarding the pre-
    1970 operation for the Court to determine whether a substantial change exists. N.E. Materials
    Grp., 
    2015 VT 79
    , ¶ 22.
    In our original decision on the merits, we concluded that NEMG’s rock crushing activities
    were within the scope of ROA’s preexisting quarry development and did not constitute a
    substantial change to that development. In re N.E. Materials Grp. LLC A250 JO #5-21, No. 143-
    10-12 Vtec, slip op. at 10, 14–15 (Vt. Super. Ct. Envtl. Div. Apr. 28, 2014) (Walsh, J.). In reaching
    this conclusion, we considered ROA’s large quarry tract as a whole. Id. at 12. We also rejected
    Appellants’ claim that ROA abandoned its crushing activities after 1970, again basing this
    conclusion on an examination of the quarry tract as a whole. Id.
    The Vermont Supreme Court reversed on appeal. N.E. Materials Grp., 
    2015 VT 79
    , ¶ 35.
    The Supreme Court agreed that it was appropriate to treat the ROA tract as a unified whole in
    determining that rock crushing is, in a general sense, part of ROA’s preexisting development
    (and to shift the burden of persuasion to Appellants on that basis). See id. ¶ 24. But the
    Supreme Court concluded that we could not consider the tract as a whole in “establishing some
    sort of baseline” against which cognizable physical change could be measured. Id. at ¶ 24.
    Rather, the Supreme Court instructed us to apply “some level of granularity” to the tract in our
    cognizable physical change analysis on remand.          Id. ¶ 30.   Though the Supreme Court’s
    reasoning for this holding rested heavily on the potential impacts from the crusher, the
    Supreme Court affirmed the Environmental Board’s longstanding two-step test for substantial
    change: (1) is the challenged use a “cognizable physical change” to the development and (2) if
    9
    so, does this cognizable physical change have the potential for significant adverse impacts
    under the Act 250 criteria. 6 Id. ¶ 16.
    Given this legal framework, the Supreme Court concluded that our opinion lacked
    sufficient “subsidiary findings” to support the conclusion that crushing falls within the scope of
    ROA’s preexisting development; that ROA did not abandon its rock crushing operations; and
    that NEMG’s crushing does not constitute a substantial change to ROA’s development. 
    2015 VT 79
    , ¶¶ 32–36. We are instructed to revisit the evidence and reexamine these issues on
    remand. Id. ¶ 36.
    I.        Preexisting Development & Abandonment
    We turn first to whether rock crushing is within the scope of ROA’s preexisting quarry
    development and whether ROA ever abandoned rock crushing. We consider the two issues
    together because Applicant bears the burden on both. See id. ¶ 24; In re Village of Cambridge
    Water Sys., No. 272, Findings of Fact, Conclusions of Law, and Order, at 8 (Vt. Envtl. Bd. Sept.
    15, 1993). We consider both these issues using a tract-wide approach (as opposed to the more
    granular approach required for cognizable physical change, see N.E. Materials Grp., 
    2015 VT 79
    ,
    ¶ 30).7
    Our findings show a long history of rock crushing at various sites in the ROA tract. There
    was crushing at the Boutwell, Milne & Varnum parcel as early as 1912 and again in the 1920s.
    There was crushing on the southern portion of the Wells-Lamson quarry (which eventually
    6
    The majority opinion maintains the two-step substantial change analysis. Id. ¶¶ 16, 31 n.16. The
    Supreme Court’s primary rationale for rejecting our tract-wide approach to cognizable physical change was that
    the same activity might have different Act 250 impacts (or impacts on different neighbors) depending on where
    the activity occurs on the site. Id. ¶¶ 26–27. The majority’s cognizable physical change rationale therefore takes
    account of Act 250 impacts, which, under the two-pronged approach, are only relevant once there is a cognizable
    change. The dissent was therefore concerned that the majority opinion collapsed the traditional test. Id. ¶ 43
    (Eaton, J., dissenting). The majority responded, “[W]e are not, as the dissent suggests, ‘collapsing’ the two prongs
    of the substantial-change test into one.” Id. ¶ 31 n.16. We emphasize this language and note that, on remand, we
    understand the two-step substantial change analysis to remain intact.
    7
    The Supreme Court affirmed our tract-wide approach to preexisting-development analysis but was silent
    on whether abandonment required a more granular approach. We note that the non-abandonment requirement
    is not codified in the statute, but has been created by the Supreme Court’s and the Board’s Act 250 decisions. See
    In re Orzel, 
    156 Vt. 355
    , 359 (1985); In re Nadeau, No. 141, Findings of Fact, Conclusions of Law, and Order, at 3
    (Vt. Envtl. Bd. June 23, 1983). Because the continuous use requirement is outgrowth of the statutory preexisting
    use exemption, we hold that a tract-wide approach is appropriate for both issues.
    10
    became part of Rock of Ages) from various dates between 1926 to 1959. There was crushing at
    the Smith quarry from 1969 and 1970. After 1970, McCullough Crushing, a subcontractor,
    crushed at the NEMG site in the early 1990s. Pike Industries crushed at the NEMG site in 1992
    and 1993. The E.L. Smith Company had crushing on its site from 2005 to 2007. And Donald
    Murray testified, credibly, that crushing was “pretty much continuous” on the ROA tract since
    he began working for the company in 1979.
    Furthermore, the Court finds that crushing is a naturally mobile and intermittent
    activity—quarry operators tend to move their crushing operations around a given site and use
    them on an as-needed basis, depending on demand for rock and availability of feedstock.
    Industry cycles and custom can be relevant in determining whether a project has been
    abandoned. In re U.S. Quarried Slate Prods., Inc., Nos. 279 & 283, Findings of Fact, Conclusions
    of Law, and Order (Reconsidered), at 22 (Vt. Envtl. Bd. Oct. 1, 1993). Because crushing is, by its
    very nature, intermittent, gaps in crushing do not indicate abandonment; they indicate
    continuous, intermittent crushing throughout the decades.
    We also find that rock crushing is closely economically related to quarrying. Although
    crushing is not strictly necessary for quarrying, it certainly “helps your bottom line.” While this
    finding by no means conclusively shows that crushing occurred continuously throughout the
    ROA tract, it does support the Court’s reasonable inference that crushing was happening even
    when there are no concrete written records of it.
    The Court also notes that, though landowners bear the burden of establishing a
    preexisting, continuous use, courts must (and do8) view the evidence landowners are able to
    provide through a practical lens. Before 1970, landowners had no notice that they might have
    8
    In the major cases in which the Environmental Board found abandonment of a preexisting use, there was
    some affirmative evidence of abandonment and not merely a gap in evidence of use. See, e.g., In re U.S. Quarried
    Slate Prods., Inc., Nos. 279 & 283, Findings of Fact, Conclusions of Law, and Order, at 16, 22–23 (Vt. Envtl. Bd. Oct.
    1, 1993) (holding that quarry tract was abandoned where, among other things, operator had filed a report with a
    federal agency stating that the quarry was “abandoned”); In re Champlain Marble Corp. (Fisk Quarry), No. 319,
    Findings of Fact, Conclusions of Law, and Order (Vt. Envtl. Bd. Oct. 2, 1996) (holding that blasting at a quarry tract
    was an abandoned use where there was no credible evidence of blasting since 1950 and where the quarry
    operator had failed to register the quarry with the federal Mining Safety and Health Administration after all active
    quarries were required to in 1973); cf. In re Orzel, 
    145 Vt. 355
    , 359 (1985) (“No evidence presented, nor findings
    made, indicates that the operations, although intermittent, were abandoned at any time.”).
    11
    to prove the existence of uses that had been occurring on their land for decades, and
    consequently often kept no records. This is especially true of activities that would have seemed
    so part-and-parcel with the land’s primary use that they were not worth formalizing in written
    documents. The fact that, for economic reasons, crushing often goes hand-in-hand with
    quarrying shows that crushing is precisely the kind of activity that might escape formal
    recording. The contract between ROA and Cooley Asphalt Paving Company, which notes in its
    preamble that Cooley had been crushing rock for ROA “for a period of time” without a written
    contract, illustrates this informality.
    This practical approach does not relieve NEMG of its burden of establishing a
    preexisting, continuous development, but it does color the Court’s understanding of how much
    evidence it can reasonably demand from NEMG and ROA. Rock of Ages has, through a diligent
    search of its historical records, uncovered impressive evidence of historical rock crushing.
    Given this evidence, and given the Court’s findings about the economic relationship between
    quarrying and crushing and about the industry custom of sub-contracting to crush rock without
    formal, written contracts, the Court concludes that crushing was occurring continuously
    (though intermittently) on the ROA tract since the early 20th century. We therefore conclude
    that the ROA quarry, including crushing activities, is a preexisting development within the
    meaning of 10 V.S.A. § 6081(b) and Act 250 Rule 2(C)(8) and that it was never abandoned.
    II.     Substantial Change
    Because we find that crushing is part of ROA’s preexisting development and has not
    been abandoned, we turn to whether the siting of NEMG’s crusher represents a substantial
    change to that development. In order for a challenged use to represent a “substantial change”
    to a preexisting development, it must first be found to be a “cognizable physical change” to the
    development. If, and only if, the challenged use is a cognizable physical change, the issue
    becomes whether the use has the potential for significant impacts under Act 250. N.E.
    Materials Grp., 
    2015 VT 79
    , ¶ 43 (Eaton, J., dissenting).
    12
    a.      Cognizable Physical Change
    In its decision, the Supreme Court held that we could not use a tract-wide approach in
    analyzing whether the NEMG crushing operation is a cognizable physical change to ROA’s
    preexisting development. Id. ¶ 30. In other words, historic instances of crushing at other sites
    within the ROA tract cannot “establish[] some sort of baseline defeating any claim that NEMG’s
    present operations constitute a cognizable change.” Id. ¶ 24. Rather, we must give appropriate
    “weight” to those instances of historic crushing, id. ¶ 30 n.14, and apply “some level of
    granularity” to the tract. Id. ¶ 30.
    While it is clear from the Supreme Court’s decision that we may not use a tract-wide
    approach in analyzing cognizable physical change, we are left with little guidance on what
    approach to apply instead. We note first that the Supreme Court’s reasoning is not fully
    compatible with traditional preexisting-development/substantial-change analysis.                The
    Environmental Board’s precedents use a binary approach: either a given use falls within the
    scope of a preexisting development or it represents a substantial change to that development.
    See, e.g., In re Barlow, No. 234, Findings of Fact, Conclusions of Law, and Order, at 9 (Vt. Envtl.
    Bd. Sept. 20, 1991). That is not to say that these cases are unsophisticated. In In re Clifford’s
    Loam & Gravel, Inc., an early preexisting development/substantial change case, the Board
    outlined four factors that could be used to restrict the boundaries of the “preexisting
    development” that could serve as a baseline for measuring cognizable physical change. In re
    Clifford’s Loam & Gravel, No. 90, Findings of Fact, Conclusions of Law, and Order, at 3 (Vt. Envtl.
    Bd. Nov. 6, 1978). But the analysis in these cases is still binary in the sense that the preexisting
    development, once defined, necessarily serves as the baseline for measuring substantial
    change: either a given use is within the scope of a preexisting development or it is a substantial
    change to that development. See In re Clifford’s Loam & Gravel, Inc., No. 90, Findings of Fact,
    Conclusions of Law, and Order, at 3 (Vt. Envtl. Bd. Nov. 6, 1978) (holding that public highways
    or waterways might “defin[e] the limits of the pre-existing operation” (emphasis added)); In re
    Weston Island Ventures, No. 169, at 5 (Vt. Envtl. Bd. June 3, 1985) (quoting Clifford’s Loam and
    Gravel); In re Barlow, No. 234, Findings of Fact, Conclusions of Law, and Order, at 9 (Vt. Envtl.
    Bd. Sept. 20, 1991) (characterizing the physical expansion of the gravel pit as a preexisting
    13
    development issue, and concluding that the area designated for expansion was “part of a pre-
    existing gravel pit” and therefore not a cognizable physical change).
    This is not the case with the Supreme Court’s decision. The Supreme Court upheld our
    tract-wide approach to preexisting development analysis, but held that we could not use a
    tract-wide approach to cognizable physical change. See N.E. Materials Grp., 
    2015 VT 79
    , ¶¶ 24,
    30. The Court’s opinion then re-characterized the Clifford’s Loam and Gravel factors as part of
    the substantial change analysis. See id. ¶ 29.
    The Supreme Court did not explain this departure. It is possible that the Supreme Court
    intended to simply relocate the Clifford’s line-drawing analysis from the preexisting
    development prong to the substantial change prong, leaving it substantively unchanged. But if
    this were the case, the only practical import of the Supreme Court’s holding would be to lighten
    the burden on landowners by reassigning the burden of persuasion on the Clifford’s factors
    from landowners to the proponents of jurisdiction (since landowners bear the burden of
    persuasion on preexisting use issues and proponents bear the burden of persuasion on
    substantial change issues, N.E. Materials Grp., 
    2015 VT 79
    , ¶ 20). If this were the Supreme
    Court’s sole intent, it could have explicitly said so.9 Rather, the Supreme Court’s opinion
    suggests that, in applying the Clifford’s factors in the substantial change analysis, we should not
    draw hard lines around some baseline portion the ROA tract, but rather that we assign
    appropriate “weight” to different uses on the ROA tract.10 N.E. Materials Grp., 
    2015 VT 79
    ,
    ¶ 30, n.14 (citing Clifford’s Loam & Gravel) (“We conclude that factors such as distance
    between sites and separation by a public highway affect the weight to be given to . . .
    operations at another site within a tract. . . . But we do not adopt a bright-line rule precluding
    any consideration of pre-1970 activities at formerly independently owned quarries in
    9
    The Court did explicitly shift the burden of persuasion on “whether the specific parameters of a
    proposed post-1970 development are consistent with the scope of an established preexisting development” from
    landowners to the proponents of jurisdiction, thereby converting preexisting development into a “threshold” issue.
    N.E. Materials Grp., 
    2015 VT 79
    , ¶ 22. But the Court did not acknowledge that it was reassigning the burden of
    defining a baseline for the cognizable physical change analysis.
    10
    If the Supreme Court’s opinion simply relocated the line-drawing analysis from the preexisting
    development prong to the cognizable physical change prong, there would be no room for “weight[ing]” uses;
    under the Board’s preexisting development precedents, either uses continuously occurred on the “baseline”
    development or they did not.
    14
    connection with post-1970 proposed development.” (internal citation omitted)). We therefore
    do not interpret the Supreme Court’s holding to require us to actually choose a precise “level of
    granularity” for the ROA tract or to delineate which parts of the tract may serve as a “baseline”
    for measuring substantial change.
    The fundamental question in cognizable physical change analysis is whether the
    development is being “operated in essentially the same manner as it was before June 1, 1970.”
    F.W. Whitcomb Constr. Co., No. 408, Findings of Fact, Conclusions of Law, and Order, at 10 (Vt.
    Envtl. Bd. Dec. 19, 2002) (internal quotation omitted). In the gravel cases, which the Supreme
    Court considered analogous, id. ¶ 30, the Environmental Board recognized that gravel pits, by
    their very nature, expand physically as gravel is extracted. N.E. Materials Grp., 
    2015 VT 79
    , ¶ 29
    (quoting In re Weston Island Ventures, No. 169, Findings of Fact, Conclusions of Law, and Order,
    at 6 (Vt. Envtl. Bd. June 3, 1985)). Thus, under these cases, gravel pits could continue to
    expand at their historic rates without triggering Act 250 jurisdiction because they were being
    operated in essentially the same manner as they were before 1970. 
    Id.
     If, however, a gravel pit
    either dramatically increased its rate of extraction or expanded into a sufficiently distinct
    portion of a tract, the expansion could be considered a cognizable physical change. Id. ¶ 30. In
    determining whether the area designated for expansion is sufficiently distinct from the already-
    developed area, these cases considered whether (1) new land had been acquired, (2) a
    substantial distance separated the historic and expanded gravel sites, (3) the operations
    themselves had changed (such as by adding a stone crusher) and (4) the presence of
    intervening rights of way or public waterways. Id. ¶ 29 (quoting Clifford’s Loam & Gravel). The
    Board also considered the previously undeveloped character of an area designated for
    expansion relevant in finding than an expansion was inconsistent with pre-1970 growth.
    Compare In re Weston Island Ventures, No. 169, at 5 (Vt. Envtl. Bd. June 3, 1985) (holding that
    an expansion to a previously undeveloped area across Route 100 was a cognizable physical
    change) with In re Barlow, No. 234, Findings of Fact, Conclusions of Law, and Order, at 9 (Vt.
    Envtl. Bd. Sept. 20, 1991) (holding that expansion of gravel extraction across a residential right
    of way to another pit that had already been used for extracting sand and dirt was not).
    15
    Just as gravel pits naturally and inherently expand, rock crushing operations are
    naturally and inherently mobile. Therefore, just as the gravel cases asked whether a particular
    expansion of a gravel pit was consistent with a pit’s historic pattern of expansion, we ultimately
    interpret the Supreme Court’s decision to require us to determine whether, under the Clifford’s
    factors, the relocation of rock crushing operations from one area of a well-developed,
    preexisting quarry to another is consistent with the rock crushing operation’s historic pattern of
    relocation. If, for instance, most rock crushing within a contiguous parcel had moved from site
    to site within a relatively contained area, and then the landowner sought to begin crushing in a
    previously undeveloped area a comparatively significant distance away and across
    comparatively significant natural boundaries, this move might mark a cognizable change. If, on
    the other hand, crushing has historically occurred on widely scattered, well-developed areas on
    a tract, a move to yet another (already developed) site, even across natural boundaries and
    even at significant distances, might still mean the development is “operated in essentially the
    same manner as it was before June 1, 1970.” F.W. Whitcomb Constr. Co., No. 408, Findings of
    Fact, Conclusions of Law, and Order, at 10 (Vt. Envtl. Bd. Dec. 19, 2002) (internal quotation
    omitted).
    Applying this approach to the NEMG crusher on remand, we conclude that the crusher
    fits the latter fact pattern more closely than the former, and is not a cognizable physical change
    to ROA’s preexisting crushing operations. Again, we find that rock crushing is an inherently
    mobile activity. Quarry operators tend to move their crushing operations around their quarries
    in accordance with customer demand and supply of waste rock feedstock. This finding is
    supported by the “subsidiary” finding that rock crushing occurred at various sites within the
    ROA tract in significant quantities for over a century. Before 1970, there were rock crushing
    operations on the NEMG site, on Smith quarry site (roughly 0.8 miles from the NEMG site and
    across a public highway), and on the southern portion of the former Wells-Lamson quarry
    (roughly 1.6 miles from the NEMG site, at what is now the northernmost point of the ROA
    tract).     Thus, movement across significant distances and public highways has always
    characterized ROA’s (or its constituent quarry operators’) crushing operations. And, as in In re
    Barlow, the NEMG site has seen crushing before. In re Barlow, No. 234, Findings of Fact,
    16
    Conclusions of Law, and Order, at 9 (Vt. Envtl. Bd. Sept. 20, 1991). It is not as though the
    present relocation of crushing to the NEMG site is an unprecedented expansion of rock
    crushing to a previously undeveloped area. This pattern of mobile and intermittent crushing
    sets the baseline for how distinct a relocation within the tract must be to trigger Act 250
    jurisdiction. While the NEMG site is separated by a public highway and by some distance from
    other proven sites of historic crushing on the ROA tract (namely, the Smith and southern Wells-
    Lamson sites), these distances and intervening boundaries are characteristic of ROA’s pattern of
    mobile and responsive crushing operations.
    We also find that the other basis for a cognizable physical change—an increase in rate
    or intensity of activity, see id. ¶ 34—is not present in this case, for we are not persuaded that
    the NEMG crusher exceeds historic quantities of rock crushing. ROA and NEMG produced a
    contract between ROA and a crushing subcontractor anticipating that 40,000 cubic yards of
    rock would be crushed at the Smith quarry11 in the six months between September 1969 and
    April 1970.12 NEMG also produced yearly crushing totals for all the years it has operated.13
    Appellants, who bear the burden of persuasion, introduced no evidence showing that NEMG’s
    11  We recognize that this evidence relates to the Smith quarry, which is roughly 0.8 miles north of the
    NEMG site across Graniteville Road. But, again, we do not interpret the Supreme Court’s decision to place hard
    limits (or to require us to place hard limits) on what evidence of historic crushing may be relevant in establishing a
    baseline for ROA’s pre-1970 crushing operations. As we discussed in Part I, we hesitate to require landowners to
    establish, with scientific accuracy, the precise rates and intensities of their land uses before 1970. Before 1970,
    landowners had no notice that they might someday be required produce evidence in court of the way they had
    been using their land for decades. We therefore review evidence landowners can supply through a practical lens.
    Here, our overarching understanding of rock crushing operations is that they move within a quarry tract based on
    supply of rock and demand for gravel, but they generally remain unchanged otherwise. We therefore consider
    evidence of rates of crushing at the nearby Smith quarry to be sufficient evidence to form a baseline of “amount
    and frequency of pre-1970 crushing.” See N.E. Materials Grp., 
    2015 VT 79
    , ¶ 34.
    12
    On cross-examination, Appellants pointed out that an invoice for services under the contract did not
    distinguish between amounts ROA owed to its subcontractor (for the service of removing overburden rock) and
    amounts the sub-contractor owed to ROA (as a royalty for rock actually crushed). Donald Murray, ROA’s primary
    witness, conceded that this might show that no rock was actually crushed. The Court finds it equally possible that
    this handwritten invoice was merely hastily done. Appellants have, therefore, not persuaded the Court that ROA’s
    and NEMG’s evidence shows that anything other than 40,000 cubic yards of material were crushed under the
    contract.
    13
    We do not consider crushing from 2011 or 2012 to be representative of ROA’s post 1970 crushing
    quantities, since NEMG was crushing rock for road reconstruction after Hurricane Irene under emergency
    conditions in these years.
    17
    expected yearly crushing totals differ from this historic benchmark.14 We therefore find that
    the NEMG crusher does not represent any marked increase in crushing quantity, and find no
    cognizable physical change on that basis.
    In summary, while we do not hold the mere fact that crushing occurred on the NEMG
    site nearly a century ago to be conclusive in defeating a claim of cognizable physical change, we
    do hold that crushing at the NEMG site is no more dramatic a relocation than other relocations
    in ROA’s pre-1970 history, especially considering that the NEMG site has experienced crushing
    in the past. We conclude that the present relocation of ROA’s crushing to NEMG’s site is
    consistent with the intrinsically portable nature of rock crushing and with ROA’s historic pattern
    of mobile crushing operations. We therefore conclude that the ROA tract is being “operated in
    essentially the same manner as it was before June 1, 1970,” and that no cognizable physical
    change has occurred. F.W. Whitcomb Constr. Co., No. 408, Findings of Fact, Conclusions of Law,
    and Order, at 10 (Vt. Envtl. Bd. Dec. 19, 2002) (internal quotation omitted).
    b.       Potential for Significant Impacts
    Finally, we address the last prong in determining Act 250 jurisdiction: the potential for a
    cognizable change to have significant impacts under Act 250. We emphasize again that we do
    not consider the Supreme Court’s opinion to alter the sequence of the traditional two-step
    substantial change analysis, where we do not examine potential impacts unless we find a
    cognizable physical change. In re N.E. Materials Grp., 
    2015 VT 79
    , ¶ 30 n.14 Because we
    conclude there is no cognizable physical change to the ROA development, we do not reach the
    “impacts” prong of the substantial change analysis.
    We do note, however, that even if the relocation of the NEMG crusher were a
    cognizable physical change, we think it unlikely to have significant Act 250 impacts. In order to
    trigger Act 250 jurisdiction, a cognizable physical change must have the potential for significant
    Act 250 impacts. Act 250 Rule 2(C)(7). While the Environmental Board and the Supreme Court
    14
    The contract for crushing on the Smith quarry in 1969 measured crushed rock in cubic yards, whereas
    the yearly crushing totals NEMG produced measure crushed rock in tons. Appellants introduced no evidence to
    enable the Court to compare these figures, and did not suggest that NEMG’s current crushing exceeds the
    quantities crushed in 1969 on the Smith quarry.
    18
    have repeatedly held that potential (and not actual) impacts are sufficient to trigger Act 250
    jurisdiction, this does not diminish the requirement that those impacts be significant. In re
    Barlow, 
    160 Vt. 513
    , 522 (1993) (“Any change in use has the potential for some impact on the
    statutory criteria. Thus, while we agree that the Board may act on potential impacts, we
    believe a finding of significant impacts is necessary if the requirement of ‘substantial change’ is
    not to be illusory.”). This is consistent with the Supreme Court’s language about the general
    purposes (and jurisdictional limits) of Act 250—that, in passing Act 250, the Legislature
    “intended to reach only those land use changes ‘where values of state concern are implicated
    through large scale changes in land utilization.’” In re Spencer, 
    152 Vt. 330
    , 334 (1989) (quoting
    In re Agency of Admin., 
    141 Vt. 68
    , 76 (1982)).
    Furthermore, it is essential to isolate those impacts stemming from the cognizable
    physical change from impacts that stem from baseline operation of the preexisting
    development; only the former are relevant to whether a cognizable physical change will have
    significant impacts under Act 250. For instance, in In re Kelly Green Recycling Facility, No. 293,
    Findings of Fact, Conclusions of Law, and Order (Vt. Envtl. Bd. Aug. 24. 1994), a recycling facility
    took over operation of a former Goodyear plant, which was a preexisting development. The
    Environmental Board concluded that the recycling facility’s disposal of chemicals did not
    represent a cognizable physical change to the previous operator’s use of the plant, but that the
    recycling facility’s dependence on truck transportation did. 
    Id.
     The Board then proceeded to
    analyze whether the truck traffic (and not the entire operation) had the potential for significant
    impacts under Act 250.15 Because we must consider impacts from a cognizable physical change
    in isolation, and these impacts must be significant, the potential impacts from the relocation of
    the NEMG crusher would only be significant if the relocation will have new and separate
    impacts under Act 250.
    15
    We draw analogous support for this proposition from the rules limiting the extent of Act 250
    jurisdiction over a preexisting development during the permitting process that follows a finding of substantial
    change. The Supreme Court has repeatedly held that, where a cognizable physical change is distinguishable from
    the rest of a preexisting development, permitting jurisdiction extends only to the cognizable change, and not the
    entire project. See In re Hale Mountain Fish & Game, 
    2009 VT 10
    , ¶ 6 (quoting In re Black River Valley Rod & Gun
    Club, Inc., No. 2S1019-EB, Memorandum of Decision, at 14 (Vt. Envtl. Bd. June 12, 1997)).
    19
    Our review of the facts shows that neighbors near the NEMG crusher experience noise,
    dust, and traffic impacts, all of which are relevant under Act 250. See 10 V.S.A. § 6081(a)(1) (air
    pollution); § 6081(a)(5)(A) (traffic); § 6081(a)(8) (noise). But the evidence in this matter does
    not show that the relocation causes new impacts.                      The relocation simply impacts new
    neighbors. Thus, even if we were to conclude that there is a cognizable physical change, we
    would conclude that Appellants have failed to persuade us that the impacts of noise, dust and
    traffic are any different than the impacts experienced by neighbors of crushing operations in
    other locations at the ROA tract.
    III.     Motion to Strike
    Having addressed the merits of this remanded appeal, we turn finally to a procedural
    matter. NEMG has moved to strike a portion of Appellants’ post-remand brief. The challenged
    portion requests that we remand this case to the District Commission if we find that the NEMG
    crusher is subject to Act 250 jurisdiction. It also argues that we should remand a related appeal
    pending before the Court (in which Appellants challenge NEMG’s Act 250 permit for an asphalt
    plant on its site) so that the District Commission may consider the two projects and their
    cumulative effects as a single development. Because we find that the NEMG crusher is not
    subject to Act 250 jurisdiction, we deny Appellants’ request for remand. We also decline to
    “strike” the request from the record, since the request is not “redundant, immaterial,
    impertinent, or scandalous . . . .” V.R.C.P. 12(f).16 Appellants’ request is not an attempt to argue
    the merits of the related asphalt plant appeal in this case. It is a procedural recommendation
    responsive to this Court’s suggestion, after remand of this appeal, that parties file briefs
    proposing next steps for this case. NEMG’s motion to strike is therefore also denied.
    Conclusion
    On remand, we conclude that the NEMG rock crushing operation is part of ROA’s
    preexisting quarry development, that ROA did not abandon rock crushing at any time before or
    after 1970, and that rock crushing at the NEMG site is not a cognizable physical change to ROA’s
    16
    We are also not convinced that Rule 12(f) can be used to strike material in motions, since the text of the
    Rule refers only to pleadings. V.R.C.P. 12(f).
    20
    preexisting development. Because we find no cognizable physical change to the development,
    we do not reach the issue of Act 250 impacts. We therefore conclude that the NEMG rock
    crusher is not subject to Act 250 jurisdiction.
    Electronically signed on December 23, 2015 at 3:45 PM pursuant to V.R.E.F. 7(d).
    _________________________________________
    Thomas G. Walsh, Judge
    Superior Court, Environmental Division
    21
    

Document Info

Docket Number: 143-10-12 Vtec

Filed Date: 12/23/2015

Precedential Status: Precedential

Modified Date: 4/24/2018