    NRB v. Stratton Corporation
    ENTRY REGARDING MOTION
    Count 1, NRB Enfc. Land Use Panel AOD (106-7-14 Vtec)
    Title:        Motion to Amend Scheduling Order (Motion 12)
    Filer:        Treetop at Stratton Condo Assn
    Attorney:     A. Jay Kenlan
    Filed Date:   September 25, 2015
    Response filed on 10/12/2015 by Attorney Lisa B. Shelkrot for Respondent Stratton Corporation
    Opposition
    The motion is GRANTED IN PART and RESERVED IN PART.
    Count 1, NRB Enfc. Land Use Panel AOD (106-7-14 Vtec)
    Title:        Motion to Add Expert Witness (Motion 13)
    Filer:        Treetop at Stratton Condo Assn
    Attorney:     A. Jay Kenlan
    Filed Date:   September 25, 2015
    Response filed on 10/15/2015 by Attorney Lisa B. Shelkrot for Respondent Stratton Corporation
    Opposition
    The motion is RESERVED.
    Pending before the Court are two discovery motions filed by Treetop at Stratton
    Condominium Association (the Association) in the Association’s underlying challenge to the
    adequacy of an assurance of discontinuance (AOD) between Treetop Development Company,
    LLC; Treetop Three Development Company, LLC; Intrawest Stratton Development Corporation;
    and The Stratton Corporation (collectively, Stratton) and the Vermont Natural Resources Board
    (NRB). The first is a motion to amend the Court’s scheduling order of September 9, 2015 to
    require Stratton to organize produced documents either topically or in a manner consistent
    with the ordinary course of business. The second is a motion to add an expert witness to the
    trial list beyond the deadline for expert disclosures.
    The AOD that is the basis for the underlying dispute concerns Stratton’s construction of
    twenty five three-unit townhomes near Stratton Mountain in Stratton, Vermont (the
    Development). The Association’s members own condominiums in the Development. Stratton
    obtained an Act 250 permit for the Development in 2002, but then deviated from the permit
    during construction without first obtaining an amended permit. Stratton’s violations involved
    three components of the Development: the stormwater system, fire truck accessibility, and the
    Development’s retaining walls. Stratton ultimately obtained an amended Act 250 permit in
    2013. The amended permit largely accommodated the Development as built, though it did also
    require Stratton to undertake certain remedial measures. The Association participated in the
    permit amendment proceedings. No party appealed the amended permit, and it therefore
    became final and binding. See In re Stowe Club Highlands, 
    166 Vt. 33
    , 37 (1996) (“[A]n original
    permit is a prior judgment that without question binds the parties.”); see also Re: Roger V. and
    Beverly Potwin, No. 3W0587-1-EB, Mem. of Decision, at 12 (Vt. Envtl. Bd. Jul. 15, 1997).
    As part of the permit amendment proceedings, the District Commission referred
    Stratton’s violations of its Act 250 permit to the NRB for enforcement. Pursuant to 10 V.S.A.
    § 8007, Stratton and the NRB negotiated an AOD that required Stratton to comply with its
    amended permit, perform the remedial work to the Development’s stormwater system
    specified in the amended permit, and pay a monetary penalty.
    The NRB filed the AOD with the Court, and the Association moved for permissive
    intervention to challenge the adequacy of the AOD. In its motion to intervene, the Association
    argued that it was an “aggrieved person” under 10 V.S.A. § 8020 because it had a particularized
    interest in ensuring that the AOD contained adequate stormwater remediation measures. The
    Court granted its motion.
    In a decision dated July 13, 2015, the Court dismissed on summary judgment the
    Association’s challenges to the adequacy of the remedial measures in the AOD, reasoning that
    these challenges amounted to an impermissible collateral attack on the final and binding
    amended Act 250 permit, which the Association failed to appeal. NRB v. Stratton Corp., No.
    106-7-14 Vtec, slip. op. at 1 (Vt. Super. Ct. Envtl. Div. Jul. 13, 2015) (citing In re Cent. Vt. Pub.
    Serv. Corp., 
    172 Vt. 14
    , 20 (2000)). This left only the issue of whether the AOD imposed
    adequate monetary penalties.
    Since the Court’s July 13, 2015 summary judgment decision, the parties have been
    involved in a discovery dispute that has absorbed significant time and resources of the parties
    and the Court.1 As the Court has continued to deliberate over the issues in this matter, the
    Court now sua sponte raises the issue of whether the Association continues to qualify as an
    “aggrieved person” under 10 V.S.A. § 8020 with standing to participate in a proceeding that is
    entirely dedicated to the adequacy of the AOD’s monetary penalty.
    Section 8020 of Title 10 of the Vermont Statutes allows an “aggrieved person” to move
    for permissive intervention in an enforcement matter in order to challenge the adequacy of an
    administrative order, assurance of discontinuance, or civil citation. 10 V.S.A. § 8020(c), (h). To
    be an aggrieved person, a party must allege an “injury to a particularized interest” protected by
    one of the environmental statutes listed in 10 V.S.A. § 8003(a), and that injury must be
    attributable to the violations addressed in the order, assurance, or citation. 10 V.S.A. § 8020(a).
    An organization may be an aggrieved person if “one or more of [the organization’s] members
    would be an aggrieved person in his or her own right, the interests at stake are germane to the
    purposes of the organization or association, and neither the claim asserted nor the relief
    1
    The Association filed a motion to compel discovery on August 18, 2015. The Court held an in-person hearing on
    the motion to compel on September 9th. The Court ordered additional discovery and issued a revised scheduling
    order after this hearing. The Association filed the present motions following the Court’s September 9 Order.
    requested by the organization or association requires participation of the individual member.”
    10 V.S.A. § 8020(a). The Court infers a final requirement in the “aggrieved person” definition—
    that a party’s particularized injury be redressable in a given proceeding. This redressability
    requirement is necessary to give effect to the three other requirements in the definition; there
    would be no purpose in requiring an aggrieved party to identify a particularized injury caused
    by a violation if the Court did not have the power to redress that injury. A redressability
    requirement ensures that the aggrieved party’s participation is relevant to the specific matter
    before the court, and prevents the expenditure of court resources on unresolvable concerns.2
    In its original motion to intervene, the Association argued that it had a particularized
    interest in insuring the adequacy of the stormwater remediation measures in the AOD because
    the Association’s members, as residents and real property owners, would feel the brunt of any
    environmental degradation from an unremediated system and because the Association will
    ultimately assume control of the system. (Intervenor’s Mot. for Permissive Intervention at 7,
    filed Jul. 29, 2014). The adequacy of the AOD’s stormwater remediation measures is no longer
    at stake in this proceeding, however. The only remaining issue in this proceeding is the
    adequacy of the AOD’s monetary penalty. Because monetary penalties for environmental
    violations are paid into a general fund, see 10 V.S.A. § 8010(e), a larger penalty will not redress
    the particularized injuries the Association has identified. To maintain “aggrieved person” status
    in the remainder of this matter, the Association must therefore establish an additional interest
    it has at stake in this litigation—one that a larger monetary penalty will redress.
    Accordingly, the Court invites the Association to submit a brief and any accompanying
    affidavits on the following issues:
    1. Whether at least one of the Association’s members has an “injury to a particularized
    interest” at stake in this enforcement proceeding, the sole remaining purpose of
    which is to determine the amount of Stratton’s monetary penalty under the AOD.
    2. Whether the identified interest is one protected by an environmental statue listed in
    10 V.S.A. § 8003(a).
    3. Whether the identified interest is germane to the purposes of the Association.
    4. Whether the injury is attributable to the specific violations identified in the AOD.
    5. Whether the remedy sought—specifically, a larger monetary penalty—will redress
    this injury.
    In briefing these issues, the Court notes that the Association will bear the burden of
    demonstrating its status as an aggrieved party. Cf. Brod v. Agency of Nat. Res., 
    2007 VT 87
    , ¶ 9–
    10, 
    182 Vt. 234
     (citing Lujan v. Defenders of Wildlife, 
    504 U.S. 555
    , 560–61 (1992)). To meet this
    burden, Association must allege specific facts that show that the Association has a
    2
    The Court also infers a redressability requirement in Section 8020(a) because the statutory language generally
    tracks the constitutional requirements for standing, and redressability is a component of the constitutional test.
    See, e.g., Parker v. Town of Milton, 
    169 Vt. 74
     (1998) (outlining requirements for standing). Furthermore, the
    Vermont Supreme Court has interpreted the phrase “aggrieved” in other statutes to incorporate the general
    constitutional requirements to for standing. See, e.g., Blum v. Friedman, 
    172 Vt. 622
    , 624 (2001) (interpreting the
    word “aggrieved” in Vermont’s open meeting law to incorporate the general standing doctrine, and noting that
    “[w]e have applied general standing doctrine to similar statutory standing requirements.”); see also In re Goddard
    College CU, No. 175-12-11 Vtec, slip op. at 3 (Vt. Super Ct. Envtl. Div, Jul. 5, 2012) (Walsh, J.) (incorporating a
    redressability requirement into the test for interested party status in Act 250 proceedings).
    particularized interest at stake; a generalized grievance about an inadequate penalty will not
    suffice. Cf. Parker, 169 Vt. at 77 (quoting Town of Cavendish v. Vt. Pub. Power Supply Auth., 
    141 Vt. 144
    , 147 (1982)).
    For the reasons stated above, the Court RESERVES consideration of the Association’s
    motion to add a new expert and RESERVES in part the Association’s motion to amend the
    scheduling order. The Court GRANTS in part the Association’s motion to amend the scheduling
    order as follows:
    1. The Association will have until November 30, 2015 to submit a memorandum and any
    supporting affidavits demonstrating its continued status as an aggrieved person with
    standing to be heard on monetary penalties—the sole remaining issue in this case.
    2. The NRB and Stratton will then have until December 15, 2015 to submit any responsive
    memoranda.
    The three remaining deadlines in the Court’s September 9, 2015 scheduling order (the
    November 16, 2015 deadline for depositions; the November 30, 2015 deadline for additional
    pre-filed testimony; and the December 1, 2015 trial-ready date) are all SUSPENDED pending the
    Court’s resolution of the issues listed above.
    So ordered.
    Electronically signed on October 27, 2015 at 01:00 PM pursuant to V.R.E.F. 7(d).
    _________________________________________
    Thomas G. Walsh, Judge
    Superior Court, Environmental Division
    Notifications:
    Peter J. Gill (ERN 4158), Attorney for Petitioner Natural Resources Board
    Lisa B. Shelkrot (ERN 2441), Attorney for Respondent Stratton Corporation
    A. Jay Kenlan (ERN 3775), Attorney for Intervenor Treetop at Stratton Condo Assn
    Elizabeth B. McDonald (ERN 5715), Attorney for Interested Person Agency of Natural Resources
    khambley
    

Document Info

Docket Number: 106-7-14 Vtec

Filed Date: 10/27/2015

Precedential Status: Precedential

Modified Date: 4/24/2018