Krag Special Zoning Permit for Culvert ( 2010 )


Menu:
  •                                  STATE OF VERMONT
    ENVIRONMENTAL COURT
    }
    In re Krag Special Zoning Permit for Culvert 1   }     Docket No. 51-4-09 Vtec
    (Appeal of Marks)                         }
    }
    Decision and Order on Pending Motions
    Appellant Andrew Marks (Appellant) appealed from a decision of the
    Development Review Board (DRB) of the Town of Shelburne, upholding the Zoning
    Administrator’s issuance of a special zoning permit to Appellee-Applicants David and
    Jesusa Krag (Applicants). The special zoning permit authorized Applicants to install a
    fifteen-foot culvert on their property. Appellant is represented by Thomas F. Heilmann,
    Esq.; Appellee-Applicants are represented by Michael T. Russell, Esq.; and the Town is
    represented by William E. Flender, Esq.
    Applicants have moved for summary judgment or to dismiss all nine questions
    in the Statement of Questions. The following facts are undisputed unless otherwise
    noted.
    Applicants own a 15.8-acre L-shaped parcel of property, which contains their
    residence, located at 76 Rivervale Road in the Town of Shelburne. Applicants’ property
    is bounded on the north and west by the LaPlatte River, which makes a bend at the
    northwest corner of Applicant’s property.
    Appellant owns a 3.1-acre rectangular parcel of property, which contains his
    residence, located at 150 Rivervale Road in Shelburne. Appellant’s property is bounded
    1  This appeal was originally captioned In re Krag Excavation and Fill Permits. The
    caption has been changed to more correctly describe the permit that is the subject of this
    appeal.
    1
    by the LaPlatte River on the west, bounded by Applicants’ property to the north and
    east, and bounded by an unrelated property to the south.
    On July 2, 2008, the Zoning Administrator issued an earlier zoning permit to
    Applicants, which authorized them to construct a berm on their property (the Berm
    Permit). Prior to the issuance of the Berm Permit, Applicants’ property had contained
    two ponds: a spring-fed pond used for swimming (the swim pond) and a pond at a
    lower elevation on Applicants’ property fed by surface water (the lower pond). The
    Berm Permit authorized Applicants to dig a third pond (the upper pond) and to use the
    fill extracted from the upper pond to construct a berm, which was meant to prevent
    surface water from contaminating the swim pond.2
    Appellant did not appeal the issuance of the Berm Permit to the DRB and it
    became final. 24 V.S.A. § 4472(d). It therefore cannot be challenged, either directly, or
    indirectly in the present appeal. See, e.g., In re: Freedom Foods, No. 243-10-08 Vtec,
    slip op. at 6 (Vt. Envtl. Ct. Mar. 19, 2009) (Wright, J.) (Where “Appellants did not appeal
    the issuance of the Zoning Permit to the DRB, . . . the zoning permit therefore cannot
    now be challenged, either directly, or indirectly in the present appeal.” (citing 24 V.S.A.
    § 4472(d))). The berm and upper pond were constructed in accordance with the Berm
    Permit and are not at issue in this appeal.
    On September 18, 2008, Applicants submitted a new application for
    “Extraction[,] Filling[,] or Removal of Natural Resource.” (Ex. A).3 The application
    sought approval to construct a
    2
    The parties have not provided a copy of the Berm Permit or the application for the
    berm project, and have not provided a map or plan showing the exact locations of the
    ponds or of the berm project. Nevertheless, no party suggests that any material facts
    are disputed as to the berm project.
    3 No party suggests that this application was treated as requesting an amendment to
    the Berm Permit; rather, it appears to have been treated as a separate application
    requesting a new permit for the culvert project.
    2
    15” pipe to reestablish flow from pond. Pipe end at surface of pond. Pipe
    buried within berm. Exit a[t] existing water collecting area.
    This fifteen-foot pipe, also referred to as a culvert, is located entirely on
    Applicants’ property and was intended to carry the flow of surface water from the area
    of the upper pond through the berm and into the lower pond, bypassing the spring-fed
    swim pond.
    The Zoning Administrator approved the culvert application and issued Permit
    No. EF08-08 (the Culvert Permit) to Applicants on September 26, 2008. (Ex. B). The
    Culvert Permit described the project as a “[p]roposed earthwork/outflow pipe
    associated with excavation and fill project,” and stated that
    [t]his letter constitutes a Special Zoning Permit, under § 1720.2 of the
    Town of Shelburne Zoning Bylaws, authorizing the work associated with
    the on-going construction of a pond/berm on your property. The project is
    approved as shown and described [in] the submitted application and site
    plan received by the Planning and Zoning Office on September 18, 2008.
    As stated in the Culvert Permit, the Zoning Administrator reviewed and
    approved the proposed culvert project under § 1720.2 of the Town of Shelburne Zoning
    Bylaws (Bylaws), which governs projects that involve the “Extraction, Filling or
    Removal” of “loam, gravel, stone, fill, topsoil or other similar materials.”4
    The preceding provision in the Bylaws, § 1720.1, governs projects that involve
    the “Diversion of Water Courses.” Even though Applicants’ culvert project proposed to
    divert the flow of surface water, the Zoning Administrator did not require them to
    apply under § 1720.1 and did not review the proposal under § 1720.1. Applicants only
    submitted a § 1720.2 application and the Zoning Administrator only applied § 1720.2,
    stating that the culvert project was “associated with the on-going construction of a
    4  The parties have provided only a five-page excerpt of the Bylaws, containing its title
    page, the table of contents, and pages 93 through 95, which contain the full text of
    § 1720.
    3
    pond/berm on Applicants’ property.”
    Appellant appealed the Zoning Administrator’s issuance of the Culvert Permit to
    the DRB. On March 4, 2009, the DRB upheld the Zoning Administrator’s decision
    granting the Culvert Permit to Applicants.5 On April 1, 2009, Appellant appealed the
    DRB decision to this Court; as of that date, Applicants had completed the culvert project
    in accordance with the Culvert Permit as issued by the Zoning Administrator.
    Question 6
    Question 6 of the Statement of Questions asks whether the Culvert Permit
    application should be “approved by this Court when much of the work for which the
    [Culvert Permit] was sought had already been completed prior to the time of the
    application in violation of the [Bylaws].”      Applicants have moved for summary
    judgment or to dismiss Question 6.
    Although commencement of construction in advance of obtaining a required
    zoning permit may be grounds for a municipality to issue a notice of violation and to
    bring an enforcement action under 24 V.S.A. §§ 4451 and 1452, no appeal has been filed
    with the Court relating either to a notice of violation or to the Zoning Administrator’s
    denial of a request to take enforcement action. See Application of Carrier, 
    155 Vt. 152
    ,
    161 (1990) (In an appeal of a permit approval, “the failure of the [applicants] to obtain
    the proper permits in a timely manner is not before [the Court].”); In re Keenan
    Conditional Use Approval, No. 266-12-07 Vtec, slip op. at 3 (Vt. Envtl. Ct. June 4, 2009)
    (Durkin, J.) (The Court can “only address . . . enforcement actions after such
    proceedings go through the proper municipal processes and are brought before this
    Court in a timely appeal.” (citing In re Maple Tree Place, 
    156 Vt. 484
    , 500 (1991))). In
    addition, Appellant has not provided any section of the Bylaws suggesting that the
    5   The parties have not provided a copy of the March 4, 2009 DRB decision.
    4
    Zoning Administrator, and hence this Court in this de novo appeal, must deny or
    decline to rule on an application for an as-built zoning permit.
    Accordingly, because the issue of whether the work was completed in advance of
    the issuance of the permit is irrelevant to whether the Culvert Permit application should
    be granted or denied by this Court in this de novo appeal, Question 6 must be
    dismissed as beyond the scope of the present appeal.
    Question 5
    Question 5 of the Statement of Questions asks, “[w]hen a culvert and water
    diversion are proposed as part of a proposed earthwork, excavation and fill permit,”
    whether the provisions of both §§ 1720.1 and 1720.2 are applicable.6 Applicants only
    submitted an application for a excavation and fill permit under § 1720.2, and the Zoning
    Administrator only reviewed the Culvert Permit application under § 1720.2. Appellant
    argues that the application should instead be reviewed only under § 1720.1.
    As this is a de novo appeal, the Court must independently determine which
    section or sections of the Bylaws are applicable to the culvert project at issue in this
    appeal. It appears from the application that the culvert or pipe is proposed to be
    “buried within [the] berm.” However, material facts are in dispute, or at least have not
    been provided to the Court, as to whether the project involves any additional extraction
    of earth materials for use off the site, or any additional fill, beyond that which had
    already been approved in the Berm Permit. To the extent that it does propose such
    6  As written, Question 5 is posed as an impermissibly advisory hypothetical question:
    that is, whether both bylaw sections should be applied to any project proposing a
    culvert and water diversion in connection with an earthwork project. See In re 232511
    Investments, Ltd., 
    2006 VT 27
    , ¶ 19, 
    179 Vt. 409
     (stating that “any conclusion [the] court
    might reach” regarding a “hypothetical” question presented to it “would be advisory”
    (citing In re Bennington Sch., Inc., 
    2004 VT 6
    , ¶¶ 18-19, 
    176 Vt. 584
     (mem.)). For the
    purposes of the present motions, the Court will treat Question 5 as asking whether both
    §§ 1720.1 and 1720.2 are applicable to the culvert project at issue in this appeal.
    5
    activity, § 1720.2 is applicable. To the extent that it does not, § 1720.2 is not applicable
    to the culvert project.
    Similarly, material facts are in dispute, or at least have not been provided to the
    Court, as to whether the proposed culvert diverted, redirected, or relocated any natural
    drainage or water runoff pattern, as those terms are used under § 1720.1.7 To the extent
    that the proposed culvert had such an effect on a natural drainage or water runoff
    pattern, § 1720.1 is also applicable.     However, the application merely describes the
    culvert installation as being proposed to “reestablish” the “flow from pond.” To the
    extent that the culvert installation restored the previously existing natural drainage or
    water runoff pattern, § 1720.1 may not be applicable.
    Under the present state of the undisputed facts, an evidentiary hearing is
    necessary to resolve Question 5, and therefore summary judgment must be denied.8
    7
    Even if the Applicants’ four requests to admit, discussed further below, are
    considered to be admitted, they only deal with the effect of the culvert project on
    drainage patterns on Appellant’s property; they do not resolve whether the culvert had
    any effect on the natural drainage pattern on Applicants’ own property. Therefore,
    regardless of whether the admissions are or are not withdrawn, those admissions
    cannot by themselves resolve the issue of whether § 1720.1 applies to the project, as
    § 1720.1 could apply to a diversion located entirely on Applicants’ own property.
    8  The parties should note that, if § 1720.2 is applicable to the culvert project, the Court
    has authority to proceed with the appeal on its merits, as that is the type of permit for
    which Applicants applied and which the DRB had before it. On the other hand, if
    §1720.1 is applicable to the culvert project, then it will be for the Zoning Administrator
    in the first instance, and then the DRB, to review an application for a special zoning
    permit under that section, as Applicants have not applied for a § 1720.1 permit and
    neither the Zoning Administrator nor the DRB considered the application under that
    provision. See In re King Garage Construction Permit, No. 202-9-08 Vtec, slip op. at 9–10
    (Vt. Envtl. Ct. July 9, 2009) (Durkin, J.) (stating that the Court’s “jurisdiction is limited to
    the application put forth for approval [below]” (citing In re Maple Tree Place, 
    156 Vt. 494
    , 499–500 (1991); In re Torres, 
    154 Vt. 233
    , 235)); id. at 11 (The court does “not have
    the authority to consider a land use application that ha[s] not been first noticed and
    heard before the municipal panel below.” (citing Torres, 154 Vt. at 235–36)).
    6
    Questions 1 and 4
    Question 1 of the Statement of Questions asks whether the proposed culvert
    project is “permissible and appropriate under §§ 1720.1 and 1720.2” of the Bylaws.
    Question 4 asks whether the application properly “address[es] and fulfill[s] the criteria”
    of §§ 1720.1 and 1720.2 of the Bylaws. Applicants ask this Court to dismiss Questions 1
    and 4 of the Statement of Questions under V.R.C.P. 12(b)(6), arguing that they are too
    vague to state a claim for which relief may be granted.
    As discussed in footnote 8, above, if § 1720.1 is applicable to the culvert project,
    this matter may have to be remanded to the Zoning Administrator to consider an
    application under that section in the first instance.
    With regard to § 1720.2, if it is applicable to the culvert project, the question of
    whether the culvert project meets the “criteria” of § 1720.2, and therefore whether a
    “special zoning permit” should be issued for the culvert project in this de novo
    proceeding, is the issue on which Applicants have the burden of proof at trial.9
    Questions 1 and 4 are therefore not too vague to state a claim for which relief may be
    granted, and the motion to dismiss them must be denied. However, they will be treated
    as presenting a single issue for the Court: whether Applicants’ culvert project meets the
    applicable provisions of § 1720.2 of the Bylaws.
    9 Both parties refer to the subsections of §§ 1720.1 and 1720.2 as containing “criteria” or
    standards for the zoning administrator to apply in issuing the “special zoning permit”
    authorized by each respective section. The parties have not raised, and the Court does
    not address, the scope of a zoning administrator’s statutory authority to make the
    decisions or to impose the conditions authorized by §§ 1720.1 and 1720.2. See 24 V.S.A.
    § 4448(a) (“The administrative officer shall administer the bylaws literally and shall not
    have the power to permit any land development that is not in conformance with those
    bylaws.”).
    7
    Questions 2, 3, and 8
    Questions 2, 3, and 8 of the Statement of Questions each ask whether the culvert
    project will violate §§ 1720.1 and 1720.2 of the Bylaws by causing changes to the
    drainage patterns on Appellant’s property. Specifically, Question 2 asks whether the
    culvert project will “impermissibly increase and modify the amount of water draining
    on to Appellant’s property” in violation of those Bylaw sections. Question 3 asks
    whether “Applicants’ proposed earthwork, berm, and culvert impermissibly alter,
    change, modify and interfere with the natural drainage patterns of the Applicants’ and
    Appellant’s respective properties” in violation of those Bylaw sections. Question 8 asks
    whether the culvert project will “create a nuisance under [§§ 1720.1 and 1720.2] in that
    water from the culvert, as well as the water diverted because of the berm . . . and other
    construction on Applicants’ property[,] is flowing and will flow on to Appellant’s
    property and cause a nuisance or harm to Appellant’s property” in violation of those
    Bylaw sections. Applicants have moved for summary judgment on Questions 2, 3, and
    8, and have also moved to dismiss Questions 3 and 8 to the extent that they relate to the
    berm project.
    First, it is again important to emphasize that the only proposal within the scope
    of the present appeal is the project proposed in Applicants’ culvert project application.
    The project authorized under the Berm Permit, which was not appealed and became
    final, is not at issue and cannot be indirectly challenged in this appeal. 24 V.S.A.
    § 4472(d). Therefore, Question 3 as it relates to the “berm” or any “earthwork” that was
    authorized under the Berm Permit, and Question 8 as it relates to “water diverted
    because of the berm” or because of any “other construction” not proposed in the culvert
    project application, must be dismissed as those issues are beyond the scope of the
    current appeal. See, e.g., Appeal of Yates, No. 158-9-04 Vtec, slip op. at 6–9 (Vt. Envtl.
    Ct. Apr. 17, 2007) (Durkin, J.) (dismissing several issues “on the basis that they [were]
    impermissible collateral attacks on previous DRB approvals and [were] therefore
    8
    outside the scope of [the] appeal”).
    Question 2 and the remainder of Questions 3 and 8 ask the Court to determine
    whether the proposed culvert project creates an “impermissible” increase in or
    modification of the drainage pattern, or creates a nuisance on or harm to Appellant’s
    property, that is “in violation of” §§ 1720.1 and 1720.2 of the Bylaws.
    In interpreting and applying administrative rules or regulations, such as the
    subsections of §§ 1720.1 and 1720.2, the Court approaches regulatory construction in the
    same manner as statutory interpretation. In re Williston Inn Group, 
    2008 VT 47
    , ¶ 14,
    
    183 Vt. 621
     (citing Conservation Law Found. v. Burke, 
    162 Vt. 115
    , 121 (1993)). As with
    a statute, the Court “will enforce the plain meaning of the [regulatory] language,”
    because the Court presumes that the municipality “intended the plain, ordinary
    meaning of the [regulatory] language.” In re Albert, 
    2008 VT 30
    , ¶ 10, 
    183 Vt. 637
    (internal citations omitted). See also Williston Inn Group, 
    2008 VT 30
    , ¶ 10 (The Court’s
    “overall goal is to discern the intent of the drafters,” first and foremost “by reference to
    the plain meaning of the regulatory language.” (citing Slocum v. Dep’t of Soc. Welfare,
    
    154 Vt. 474
    , 478 (1990))).
    Turning to the regulatory provisions at issue, § 1720.1 requires submission of
    specific information related to the existence of and quantity of any increases in runoff.
    See Bylaws §§ 1720.1(3), (4). Nothing in § 1720.1 authorizes the Zoning Administrator
    to impose conditions, and nothing in § 1720.1 establishes any criteria whose failure to be
    met could be construed as a “violation” of § 1720.1. The only requirement of § 1720.1 is
    that a special zoning permit be obtained for any “diversion, redirection or relocation of
    any natural water course, drainage or water runoff pattern.” By its terms, the only
    potential “violation” of § 1720.1 is the failure to obtain a special zoning permit for those
    activities, or the failure to provide the required information with the application. In any
    event, if § 1720.1 is applicable, the Court will consider remanding the culvert permit
    application for consideration in the first instance by the Zoning Administrator. See
    9
    footnote 8, above.
    On the other hand, § 1720.2 allows the Zoning Administrator, and hence this
    Court in a de novo appeal, to impose conditions relating to the “creation of a nuisance,”
    § 1720.2(A)(5), resulting from a project involving extraction, filling or removal of
    materials such as earth, gravel or stone.       Nevertheless, other than the prohibition
    regarding flood plain activity discussed in relation to Question 9, below, nothing in
    § 1720.2 establishes any criteria whose failure to be met could be construed as a
    “violation” of § 1720.2.
    Therefore, those portions of Question 2, and those portions of the remainder of
    Questions 3 and 8, that ask whether various effects of the culvert project are “in
    violation of” §§ 1720.1 and 1720.2 of the Bylaws are dismissed.
    The remainder of Questions 2, 3, and 8 relate to the other questions presented in
    this appeal. The remainder of Questions 2 and 3, asking whether the culvert project will
    “increase and modify the amount of water draining on to Appellant’s property” or
    whether the culvert project will “alter, change, modify and interfere with the natural
    drainage patterns of Applicants’ and Appellant’s respective properties,” relate to the
    Court’s task under Question 5 in determining whether § 1720.1 applies to the culvert
    project. If § 1720.2 applies to the culvert project, the remainder of Question 8, asking
    whether the project creates a nuisance, relates to the Court’s task under Questions 1 and
    4 in determining whether any conditions should be imposed.            The remainder of
    Questions 2, 3, and 8 therefore are not dismissed at this time; however, Appellant will
    be required to restate them to clarify what remains in this appeal
    Question 7
    Question 7 of the Statement of Questions asks whether the culvert project will
    “have an adverse effect on public health, safety, and welfare under [§§ 1720.1 and
    1720.2].” Applicants have moved for summary judgment on Question 7.
    10
    First, the only subsection of § 1720 addressing a proposed project’s effect on
    public health, safety, or welfare is found in § 1720.2(A)(4); therefore, Question 7 must be
    restricted to § 1720.2.   The reference in Question 7 to § 1720.1 must therefore be
    dismissed.
    Under § 1720.2(A)(4), the Zoning Administrator is authorized to impose
    conditions on a special zoning permit “relating to,” among other factors, the proposal’s
    “[e]ffect on public health and safety and welfare.” If the culvert project requires a
    permit under § 1720.2, the Court will consider whether to impose conditions on the
    project under § 1720.2(A)(4) in the course of ruling on the permit application in this de
    novo appeal.
    Because material facts are in dispute, or at least have not been provided to the
    Court, as to whether the culvert project requires a permit under § 1720.2, as well as to
    whether the culvert project will have an effect on public health, safety, and welfare, and
    if so, what conditions are necessary in light of that finding, Question 7 of the Statement
    of Question remains for the merits of this appeal. Summary judgment as to Question 7
    is therefore denied.
    Question 9
    Question 9 of the Statement of Questions asks whether the culvert project will
    “interfere with or reduce the flood stage capacity of Applicants’ and Appellants’
    property in violation of the above[-]cited . . . Bylaws.” Applicants have moved for
    summary judgment on Question 9.
    First, the only regulation addressing “flood stage capacity” is found in
    § 1720.2(B)(5); therefore, Question 9 must be restricted to § 1720.2. The reference in
    Question 9 to § 1720.1 must therefore be dismissed.
    Section 1720.2(B)(5) “prohibit[s]” the excavation of earth materials within the
    100-year flood plain of the LaPlatte River “where the activity proposed will lower the
    11
    level of the water table, interfere with the natural flow patterns[,] or reduce the flood
    stage capacity.” Bylaws § 1720.2(B)(5).
    Material facts are in dispute, or at least have not been provided to the Court,
    regarding whether the culvert project involves any excavation of earth materials at all,
    beyond any excavation involved in the berm project covered by the final Berm Permit.
    If the culvert project does involve any excavation, material facts are in dispute, or at
    least have not been provided to the Court, regarding whether such excavation will
    occur within the 100-year flood plain of the LaPlatte River. Further, if the culvert
    project does involves excavation within the 100-year flood plain, material facts are in
    dispute, or at least have not been provided to the Court, as to whether such excavation
    with reduce the flood stage capacity of the flood plain area.
    Because material facts are in dispute, or at least have not been provided to the
    Court, summary judgment on Question 9 must be denied on the present record.
    However, at the scheduled telephone conference (see enclosed notice), please be
    prepared to discuss whether material facts are actually disputed as to Question 9, or
    whether any party wishes to present any supplemental affidavits or motions for partial
    summary judgment prior to trial.
    Applicants’ Requests to Admit and Appellant’s Motion to Deem Answer Timely
    On November 30, 2009, Applicants served on Appellant a Request for Admission
    under V.R.C.P. 36. See V.R.C.P. 36 (permitting a party to serve upon any other party a
    request for the admission of fact, and establishing that “[t]he matter is admitted unless,
    within 30 days after service of the request . . . the party to whom the request is directed
    serves upon the party requesting the admission a written answer or objection addressed
    to the matter”). The request sought admission by Appellant that each of the following
    facts is true:
    12
    1. Water from the culvert that is the subject of the permit appealed exits
    onto the Appellees’ property, flows on Appellees’ property into a pond on
    the Appellees’ property, flows from that pond through a swale on
    Appellees’ property and then discharges into the LaPlatte River at a point
    on Appellees’ property (the “Drainage System”).
    2. Water from the Drainage System does not flow onto Appellant’s
    property.
    3. The natural drainage pattern of Appellant’s property is not altered,
    changed, modified or interfered with by the Drainage System.
    4. The Drainage System does not increase or modify the amount of water
    draining on to Appellant’s property.
    From the date of service, Appellant had thirty days to timely answer or object to
    the request, which gave him until December 29, 2009. Id. Appellant did not file an
    answer to the requests to admit by that date; therefore, under V.R.C.P. 36, the
    statements in the Request for Admission were admitted as of December 29, 2009. Id.
    Appellant did not file an answer to the requests to admit until February 12, 2010,
    in which he denied all of the statements in the Request for Admission. However, as
    Appellant’s untimely answers did not withdraw or amend the admissions, on February
    16, 2009, Appellant moved the Court to deem his answers timely, that is, to withdraw
    the admissions under V.R.C.P. 36. See V.R.C.P. 36(b) (“Any matter admitted under this
    rule is conclusively established unless the court on motion permits withdrawal or
    amendment of the admission.”).
    In the motion to deem his answers timely, Appellant cites several reasons
    explaining why his answer to the requests to admit was not filed in a timely fashion,
    including the presence of the holiday season, and several complex and time-sensitive
    matters that demanded the attention of his attorneys. The Court makes no finding that
    this neglect was excusable; however, “excusable neglect is not a requirement for
    allowing withdrawal of admissions.” Record v. Kempe, 
    2007 VT 39
    , ¶ 10, 
    182 Vt. 17
    13
    (allowing withdrawal of an implied admission created by failure to respond to request
    to admit).
    Under V.R.C.P. 36(b), “a court has discretion to allow withdrawal of an
    admission if ‘the presentation of the merits of the action will be subserved’ by allowing
    withdrawal and the party who obtained the admission ‘fails to satisfy the court that
    withdrawal or amendment will prejudice that party in maintaining the action or
    defense on the merits.’” 
    Id.
     (quoting V.R.C.P. 36(b)).
    All four of the requested admissions may be of great interest to any private
    property dispute between the parties, but they are primarily of importance in the
    present case to the extent that they may assist the Court in determining the
    jurisdictional fact of whether § 1720.1 applies to the culvert application.             The
    presentation of the merits of the action as to that threshold jurisdictional fact will be
    served by allowing Appellant to withdraw the admissions and to present evidence as to
    whether the culvert itself causes a diversion, redirection, or relocation of a natural water
    course, drainage or water runoff pattern, without regard to any such diversions created
    by work done under the Berm Permit. To that extent only, the requested admissions are
    “key issues” that are better left to the merits of this case.       See id. (upholding a
    withdrawal of an admission “because the facts that would be deemed admitted were
    ‘both key issues,’ such that ‘denying Plaintiffs’ motion [to withdraw the admissions]
    would essentially preclude a determination of the substantive merits of the case”
    (citations omitted)).
    It is important to note that the requested admissions in the present appeal only
    relate to whether water from Applicants’ property flows onto Appellant’s property.
    The requested admissions do not resolve whether the culvert itself has caused a
    diversion, redirection, or relocation of a natural water course, drainage or water runoff
    pattern if it may have occurred solely on Applicants’ own property, in which case
    § 1720.1 would be applicable even without any effect on Appellant’s property.
    14
    However, if the culvert itself has not caused any diversion, redirection, or relocation of
    a natural water course, drainage or water runoff pattern, then a special zoning permit
    under § 1720.1 is not required. Because the admissions do not resolve the question of
    whether § 1720.1 is applicable, Applicants have not shown that withdrawal of the
    admissions “will prejudice [them] in maintaining the action or defense on the merits."
    Record v. Kempe, 
    2007 VT 39
    , ¶ 10.
    Therefore, for the limited purpose for which the issues are relevant to this
    appeal, withdrawal of Appellant’s admissions is appropriate under V.R.C.P. 36(b).
    Accordingly, Appellant’s Motion to Deem Answers to Appellees’ Requests for
    Admission as Timely Made, which the Court treats as a motion to withdraw the implied
    admissions and to replace them with the responses to the requests to admit filed on
    February 12, 2010, is GRANTED.
    Accordingly, based on the foregoing, it is hereby ORDERED and ADJUDGED
    that Applicants’ Motion for Summary Judgment or to Dismiss is GRANTED in part and
    DENIED in part, as discussed above with respect to each question in the Statement of
    Questions. On or before March 15, 2010, Appellant shall file a revised Statement of
    Questions, keeping the original numbering, and conforming each remaining question or
    portion of a question to the rulings in this decision. Any objections to the wording of
    the revised Statement of Questions shall be filed on or before March 22, 2010, so that
    they may be discussed at the telephone conference scheduled for March 29, 2010.
    Appellant’s Motion to Deem Answers to Appellees’ Requests for Admission as Timely
    Made, treated as a motion to withdraw the implied admissions and to replace them
    with the responses to the requests to admit filed on February 12, 2010, is GRANTED.
    The hearing on the merits of this appeal remains scheduled for May 4, 2010, to
    continue if necessary on May 5, 2010. However, at the telephone conference now
    15
    scheduled for March 29, 2010 (see enclosed notice), please be prepared to discuss
    whether the threshold facts of the scope of the culvert project can or should be resolved
    in advance of that hearing, as those facts determine whether § 1720.2 applies at all to the
    culvert. If § 1720.2 does not apply to the culvert, all that will remain for trial is whether
    § 1720.1 applies. If § 1720.1 does apply, the matter will have to be remanded for the
    Zoning Administrator in the first instance to determine whether a special zoning permit
    should issue for the culvert under § 1720.1. Similarly, if § 1720.1 does not apply, the
    matter will have to be remanded for the Zoning Administrator in the first instance to
    determine whether to act on the culvert application only under § 1710, which governs
    the issuance of zoning permits that do not require special zoning permits under either
    prong of § 1720.
    Done at Berlin, Vermont, this 5th day of March, 2010.
    _________________________________________________
    Merideth Wright
    Environmental Judge
    16
    

Document Info

Docket Number: 51-4-09 Vtec

Filed Date: 3/5/2010

Precedential Status: Precedential

Modified Date: 4/24/2018