Feeley Construction Permits ( 2010 )


Menu:
  •                                 STATE OF VERMONT
    ENVIRONMENTAL COURT
    }
    In re: Feeley Construction Permits       }
    Nos. 19687 & 21006               }       Docket Nos. 4-1-10 Vtec & 5-1-10 Vtec
    (Appeals of Doane)               }
    }
    Decision and Order on Motion for Summary Judgment to Dismiss as Untimely
    In January of 2010, Appellants Frederick and Heike Doane (Appellants) filed the
    above-captioned appeals from two concurrently issued decisions of the Development
    Review Board (DRB) of the Town of Colchester, ruling that Appellants’ attempted
    appeals of two zoning permits issued to Appellees Richard and Theresa Feeley
    (Appellees) were untimely. In Docket No. 4-1-10, Appellants seek to appeal the DRB’s
    decision regarding permit #19687, issued on August 15, 2005, which authorized
    Appellees to construct a replacement shed, replacement set of stairs, and new decks on
    their property. In Docket No. 5-1-10, Appellants seek to appeal the DRB’s decision
    regarding permit #21006, issued on June 26, 2008, which authorized Appellees to
    construct a second replacement deck and set of stairs on their property.
    Appellants are represented by Robert T. Gaston, Esq.; Appellees are represented
    by Matthew T. Daly, Esq.; and the Town is represented by Thomas G. Walsh, Esq.
    Appellees have moved to dismiss the appeal as untimely, or in the alternative
    have moved for summary judgment. Although Appellees initially moved to dismiss
    under V.R.C.P. 12(b), which allows parties to move for judgment on the pleadings
    alone, both Appellants and Appellees have submitted affidavits and other evidence for
    the Court to consider. Therefore, as provided in V.R.C.P. 12(c), the present motion will
    be treated only as one for summary judgment under V.R.C.P. 56, as “matters outside the
    1
    pleadings have been presented to and not excluded by the court.” V.R.C.P. 12(c); see
    also, e.g., In re UVM Construction and Landscape Permit, No. 169-8-08 Vtec, slip op. at
    1 (Vt. Envtl. Ct. Mar. 12, 2009) (Wright, J.).     A grant of “summary judgment is
    appropriate when, giving the benefit of all reasonable doubts and inferences to the
    nonmoving party, there are no genuine issues of material fact and the moving party is
    entitled to judgment as a matter of law.” Gade v. Chittenden Solid Waste Dist., 
    2009 VT 107
    , ¶ 7 (citing Mooney v. Town of Stowe, 
    2008 VT 19
    , ¶ 5, 
    183 Vt. 600
     (mem.); V.R.C.P.
    56(c)). The facts stated in this decision are undisputed unless otherwise noted.
    Factual and Procedural Background
    Appellees own a parcel of property located at 73 Irish Cove in Colchester, which
    contains a seasonal dwelling or camp structure that Appellees use during the summer
    months. The property is located on the shoreline of Lake Champlain in the Shoreland
    zoning district. Access to the property is by a private, dead-end road marked “Irish
    Cove,” which leads from the nearest public right-of-way, Marble Island Road.
    Appellants currently own a parcel of property with the address of 1021 Marble
    Island Road that is adjacent to Appellees’ parcel, also with frontage on the shoreline of
    Lake Champlain. Access to Appellants’ property is directly from Marble Island Road.
    Appellants previously owned a condominium located at 1067 Marble Island
    Road, which they acquired in June of 2005.         They were regularly present at the
    condominium during its remodeling from June of 2005 through January of 2006.
    During the summer of 2008, they were residing at the condominium at 1067 Marble
    Island Road during the construction of their current residence at 1021 Marble Island
    Road.
    2
    2005 Zoning Application & Permit
    On August 11, 2005, Appellees submitted zoning permit application #19687 (the
    2005 Application), which sought approval to do the following work on their property:
    to replace an existing set of stairs leading from the road down to the camp building; to
    replace an existing 6’ x 7’ shed with a new 8’ x 10’ shed adjacent to the stair landing; to
    construct an 8’ x 10’ deck over the new shed; and to construct a new 10’ x 17’ deck
    adjacent to the camp building down near the elevation of the lake. Appellees attached
    five diagrams or drawings to the 2005 Application form: one diagram depicting the
    existing layout of the property; two diagrams depicting plan views of the proposed
    layout, setbacks, and construction; one drawing showing the west or lake side elevation
    of the proposed new shed and stairs; and one drawing showing the south side elevation
    of the whole property from the road down to the lake, including the new stairs, the new
    shed, the new decks, and the existing camp building. Appellees’ signatures appear on
    the 2005 Application below the statement that “[w]e certify that all information,
    including attachments, in this application are complete, true and accurate.”
    The Zoning Administrator approved the 2005 Application on August 15, 2005,
    granting Appellees zoning permit #19687 (the 2005 Zoning Permit). The approval,
    which is noted on the application form itself, also shows the following requirement in
    the area on the form marked for “Development Review Board Stipulations”: “no further
    encroachment toward lake.” No party suggests that the DRB in fact issued any decision
    regarding the 2005 Zoning Permit.
    Upon receiving the 2005 Zoning Permit on August 15, 2005, Appellees were
    required by statute to post “a notice of permit . . . within view from the public right-of-
    way most nearly adjacent to the subject property until the time for appeal . . . has
    3
    passed.” 24 V.S.A. § 4449(b).1 Appellants assert that Appellees either failed to post the
    notice of permit at all, or failed to post notice within view from the public right-of-way
    of Marble Island Road. Appellants’ Objection to Appellees’ Motion to Dismiss or for
    Summary Judgment, at 4–6 (Mar. 4, 2010) [hereinafter Appellants’ Objection to
    Appellees’ Motion].
    The 2005 Zoning Permit stated that “[c]onstruction shall not commence before
    8/30/05,” that is, fifteen days after the issuance of the permit. This fifteen-day period
    represents the period during which interested persons could appeal the Zoning
    Administrator’s action to the DRB, as provided in 24 V.S.A. § 4465(a).2 Interested
    persons seeking to appeal the Zoning Administrator’s issuance of the 2005 Zoning
    Permit therefore had from August 15, 2005, through August 30, 2005, to file a timely
    appeal with the DRB; no such appeal was filed within the fifteen-day period.
    After receiving the 2005 Zoning Permit, at some time prior to October 11, 2005,
    Appellees completed the proposed work. At no time during construction did any party
    seek to take a late appeal of the 2005 Zoning Permit to the DRB, nor did any party raise
    the issue at that time that the posting of the notice of permit was deficient.
    On October 11, 2005, the Zoning Administrator inspected the completed work
    and issued a Certificate of Occupancy/Compliance to Appellees.3 No party appealed to
    1
    In addition, “[w]ithin three days following the issuance of a permit,” the
    Administrative Officer was required by statute to “[p]ost a copy of the permit in at least
    one public place in the municipality until the expiration of 15 days from the date of
    issuance of the permit.” Id. § 4449(b)(2). No party suggests that the Administrative
    Officer failed to properly post the 2005 Permit in accordance with 24 V.S.A. § 4449(b)(2).
    2
    See 24 V.S.A. § 4465(a) (stating that “[a]n interested person may appeal any decision
    or act taken by the administrative officer in any municipality by filing a notice of
    appeal . . . within 15 days of the date of that decision or act”); id. § 4449(a)(3) (stating
    that “[n]o permit issued pursuant to this section shall take effect until the time for
    appeal . . . has passed”).
    3 See Town of Colchester Zoning Regulations § 11.04 [hereinafter Zoning Regulations],
    available at http://colchestervt.gov/PlanningZ/zoningregs.shtml (“It shall be unlawful to
    4
    the   DRB   the   Zoning    Administrator’s       action   in   issuing   the   Certificate   of
    Occupancy/Compliance.
    2008 Zoning Application & Permit
    On June 25, 2008, Appellees submitted zoning permit application #21006 (the
    2008 Application), which sought approval to “construct/replace deck – accessible +
    stairs.” The application form described the size of the then-existing decks as being 12’ x
    18’ and 12’ x 12’ ±, and the existing shed as being 8’ x 10’ in area, and stated the size of
    the proposed deck as 12’ x 36’ ±. Appellees attached four documents to the 2008
    Application form: one diagram depicting the existing layout of the property, two
    diagrams depicting the proposed layout and construction, and a hand-written
    description of some of the proposed work. As with the 2005 Application, Appellees’
    signatures appear on the 2008 Application below the statement that “[w]e certify that all
    information, including attachments, in this application are complete, true and accurate.”
    On June 26, 2008, the Zoning Administrator approved the 2008 Application,
    granting Appellees building permit #19687 (the 2008 Zoning Permit). Like the 2005
    Zoning Permit, the approval was noted on the application form itself, and contained the
    notation in the area on the form marked for “Development Review Board Stipulations”:
    “no further encroachment toward lake.”
    use, occupy or permit the use or occupancy of any land or structure or part thereof
    created, erected, changed, converted, or wholly or partly altered or enlarged in its use
    until the Zoning Administrator or designee issues a certificate of occupancy or
    compliance stating that such structure or land development conforms to all approved
    plans and specifications and the requirements of these regulations.”); 24 V.S.A.
    § 4449(a)(2) (“If the bylaws so adopted so provide, it shall be unlawful to use or occupy
    or permit the use or occupancy of any land or structure, or part thereof, created,
    erected, changed, converted, or wholly or partly altered or enlarged in its use or
    structure . . . until a certificate of occupancy is issued therefor by the administrative
    officer, stating that the proposed use of the structure or land conforms to the
    requirements of those bylaws.”).
    5
    As with the 2005 Zoning Permit, Appellees were required by statute to post a
    “notice of permit . . . within view from the public right-of-way most nearly adjacent to
    the subject property” until the time for appeal had passed.           24 V.S.A. § 4449(b).4
    Appellants assert that Appellees either failed to post a notice at all, or failed to post
    notice within view from a public right-of-way.
    The 2008 Zoning Permit stated that “[c]onstruction shall not commence before
    7/11/08,” fifteen days after the issuance of the permit. Interested persons seeking to
    appeal the Zoning Administrator’s issuance of the 2008 Zoning Permit therefore had
    from June 26, 2008, through July 11, 2008, to file a timely appeal with the DRB; no such
    appeal was filed within the fifteen-day period.
    After receiving the 2008 Zoning Permit, at some time prior to July 24, 2008,
    Appellees completed the proposed work.5 At no time during construction did any
    party seek to take a late appeal of the 2008 Zoning Permit to the DRB, nor did any party
    raise the issue at that time that the posting of the notice of permit was deficient.
    On July 24, 2008, the Zoning Administrator inspected the completed work and
    issued a Certificate of Occupancy/Compliance to Appellees. No party appealed to the
    DRB     the   Zoning     Administrator’s     action   in    issuing   the    Certificate   of
    Occupancy/Compliance.
    4
    As with the 2005 Zoning Permit, no party suggests that the Administrative Officer
    failed to properly post notice of the 2008 Zoning Permit in accordance with 24 V.S.A.
    § 4449(b)(2).
    5
    Appellants stated that their own construction at their present property adjoining
    Appellees’ property was ongoing in the summer of 2008, but they have not stated when
    or under what circumstances they first became aware of the construction done on
    Appellees’ property pursuant to the 2005 and 2008 Zoning Permits.
    6
    Appellants’ Meeting with Town Officials Regarding the Feeley Property
    As characterized by the DRB in the minutes of the November 18, 2009 hearing, in
    March of 2009, Mr. Doane received information that Mr. Feeley had alleged that Mr.
    Doane was cutting trees in the Shoreland setback. In re: Property of Richard & Theresa
    Feeley, Permit #19687 & #21006, Findings of Fact, at 2 (Town of Colchester DRB Dec. 9,
    2009) [hereinafter 2009 DRB Decisions]. In response, Mr. Doane inspected the Feeley
    property, was “surprised” by how large the decks and stairs were that were located in
    the Shoreland District setback, and commenced a review of the Planning and Zoning
    Department files. Id.
    On September 24, 2009, Appellants met with the Director of Planning and
    Zoning and the Zoning Administrator for the Town of Colchester.            Appellants’
    Supplemental Objection to Applicant’s Motion, at 1 (Mar. 10, 2010) [hereinafter
    Appellants’ Supplemental Objection]; Appellants’ Reply to Town’s Memorandum in
    Support of Dismissal, at 3 (Mar. 18, 2010) [hereinafter Appellants’ Reply to Town’s
    Memorandum]. Appellants state that during that meeting they gave the Director of
    Planning and Zoning and the Zoning Administrator “information as to various zoning
    violations” on the Feeley property. Appellants’ Supplemental Objection, at 1. More
    specifically, Appellants state that they met with the Town officials and provided them
    with a “written submission” regarding zoning violations on the Feeley property.
    Appellants’ Reply to Town’s Memorandum, at 3.6
    Appellants contend that their oral and written statements presented at the
    September 24, 2009 meeting, as well as their later “appeal and submissions to the DRB,”
    in effect constituted their request for the Zoning Administrator or the Town to take
    6
    In a letter dated October 8, 2009, the Town’s attorney refers to this “written
    submission” as “an unsigned memorandum/outline highlighting [Appellants’]
    concerns.” Letter from Thomas G. Walsh, Colchester Town Attorney, to Appellants
    (Oct. 8, 2009). The parties have not provided the Court with a copy of this “written
    submission.”
    7
    enforcement action against Appellees. Appellants’ Reply to Town’s Memorandum, at 3.
    It is not clear from their argument whether Appellants believed that they were
    requesting the Town’s enforcement of the terms of the permits or whether they were
    seeking enforcement of the Zoning Regulations, despite what was allowed by the terms
    of the unappealed 2005 and 2008 Zoning Permits. See generally Appellants’ Reply to
    Town’s Memorandum, at 1–2.
    By letter dated October 8, 2009, the Town attorney responded to Appellants on
    behalf of the Town, referring to the issues discussed at the September 24 meeting and
    further raised in the “unsigned memorandum/outline highlighting [Appellants’]
    concerns.” Letter from Thomas G. Walsh, Colchester Town Attorney, to Appellants
    (Oct. 8, 2009). The letter informed Appellants that “[p]ursuant to the exclusivity-of-
    remedy provision of § 4472(d), the Town and all interested parties are precluded from
    challenging the Feeley[s’] previous permits . . . [a]s no one took issue with the permits
    . . . by filing an appeal within the appeal periods,” which made them “final and
    binding.”    Id.   The letter also stated that the 2005 and 2008 Certificates of
    Occupancy/Compliance, which were not appealed and became final, also precluded
    Appellants from challenging the two permits. Id. Appellants contend that the October
    8 letter was an appealable “decision not to enforce the zoning laws,” even though it was
    issued by the Town’s attorney rather than by the Zoning Administrator. Appellants’
    Supplemental Objection, at 2.
    Appellants’ Appeals to the DRB
    On October 15, 2009, Appellants filed two appeals with the DRB: one regarding
    the 2005 Zoning Permit and one regarding the 2008 Zoning Permit. The appeals were
    filed with the DRB more than four years after the 2005 Zoning Permit and the 2005
    Certificate of Compliance were issued and more than a year after the 2008 Zoning
    Permit and the 2008 Certificate of Compliance were issued.
    8
    The parties have not provided the Court with the notices of appeal that were
    initially filed with the DRB, and therefore material facts have not been provided to the
    Court as to how Appellants characterized their appeal to the DRB. The DRB decisions
    characterize the appeals as being appeals of the issuance of the permits, and not as
    being appeals from any request to enforce the terms of the permits.             2009 DRB
    Decisions, at 3. As described by the DRB, Appellants cited the following three grounds
    for their appeals of the permits: that there was “defective notice of the appeal period” as
    required by 24 V.S.A. § 4449; that there was a “misstatement of material fact on the
    application warranting refusal of [each] permit”; and that the permits were “issued in
    violation of the Colchester Zoning Regulations.” Id. at 1, 2.
    The DRB held a consolidated hearing on the two appeals on November 18, 2009.
    As reflected in the 2009 DRB Decisions, at the hearing Appellants’ attorney “stated that
    it is their position that they do have a right to appeal the permits” based on their
    assertion that Appellees failed to post proper notice. Id. at 3. In response, Appellees’
    attorney stated that the Feeleys “did properly and prominently display the notices for
    application of building permits.” Id.
    The DRB issued concurrent decisions regarding the two appeals on December 9,
    2009, which upheld both zoning permits on the ground that the appeals were untimely
    under 24 V.S.A. § 4465(a), and therefore that “all parties, including the Town, are bound
    per [24 V.S.A. § 4472(d)].” Id. The 2009 DRB Decisions on appeal do not refer to any
    claim made by Appellants that they had requested the Zoning Administrator to enforce
    the permits or the Zoning Regulations, nor do the decisions refer to the September 24,
    2009 meeting with the Town officials or to any written requests or documents filed by
    Appellants at that meeting.
    Appellants appealed the 2009 DRB Decisions to this Court in the present appeals.
    The notices of appeal filed with this Court state that Appellants seek to appeal the 2009
    DRB Decisions, which upheld the 2005 and 2008 Zoning Permits, and also state that
    9
    “[t]he appeal is taken against [Appellees] and the Town of Colchester for failing to
    follow and enforce the Town’s Zoning Regulations.”
    Appellants’ Motion for Summary Judgment
    In a de novo appeal such as this, “the Court sits in place of the ZBA to consider
    what was before the ZBA, applying the substantive standards that were applicable
    before the ZBA.” In re: Kibbe Zoning Permit, No. 173-8-07 Vtec, slip op. at 1–2 (Vt.
    Envtl. Ct. Nov. 6, 2008) (Wright, J.) (citing V.R.E.C.P. 5(g); 10 V.S.A. § 8504(h)). That is,
    the scope of this de novo appeal is limited to what was before the DRB. See, e.g., In re
    Maple Tree Place, 
    156 Vt. 494
    , 500 (1991) (stating that the “court is limited to
    consideration of the matters properly warned as before the local board” (citing In re
    Torres, 
    154 Vt. 233
    , 235 (1990))).
    Under the statutory scheme governing appeals to the Environmental Court,
    actions of the Zoning Administrator cannot be appealed directly to this Court; they
    must first be appealed to the DRB. Only decisions of the DRB (or other municipal
    panel) can be appealed directly to this Court.        See 24 V.S.A. § 4465 (setting forth
    procedure for appealing decisions of administrative officers to municipal panels); id.
    § 4471 (setting forth procedure for appealing decisions of municipal panels to the
    Environmental Court).
    Additionally, in order to appeal a decision of the DRB to this Court, an appellant
    must have standing to bring the appeal, as provided in 24 V.S.A. § 4471 and § 4465.7
    Under this statutory scheme, in order to have standing to appeal a decision of the DRB
    to this Court, an appellant must qualify as an “interested person” under 24 V.S.A.
    § 4465 and must have “participated” in the DRB hearing at the municipal level. Id.
    7See 24 V.S.A. § 4471(a) (stating that an “interested person” may appeal to the
    Environmental Court); id. § 4465(b) (defining who qualifies as an “interested person”).
    10
    § 4471(a).8
    To qualify as an “interested person” under 24 V.S.A. § 4465(b)(3), an individual
    appellant must show, among other things, that the challenged activity will have a
    “physical or environmental impact” on the his or her interests. A potential appellant
    “must fall squarely within the statutory requirements” of § 4471(a) and § 4465(b), In re
    Gulli, 
    174 Vt. 580
    , 582 (2002), to have standing to bring an appeal in this Court.
    In the present de novo appeal, it is apparent that Appellants seek to challenge the
    shed, stair, and deck work authorized by the unappealed 2005 and 2008 Zoning
    Permits, which was subsequently approved by the unappealed 2005 and 2008
    Certificates of Compliance. In bringing this appeal, however, Appellants seem to be
    conflating three possible actions of the Zoning Administrator related to the Feeley
    property and the work authorized under the 2005 and 2008 Zoning Permits. Appellants
    have not made clear which of these potential actions of the Zoning Administrator they
    claim has occurred, and which of these actions they sought to appeal to the DRB and
    then to this Court.
    First, Appellants may be attempting to file a very late appeal of the Zoning
    Administrator’s initial issuance of the zoning permits, which took place in 2005 and
    2008. Second, Appellants may be attempting to appeal the Zoning Administrator’s or
    the Town Attorney’s response to a request made by Appellants asking the Town to
    enforce the terms of the zoning permits or to enforce the Zoning Regulations. Finally,
    Appellants may be attempting to initiate revocation of the permits, or may be
    attempting to appeal the Zoning Administrator’s response to a request asking the Town
    to revoke the permits, based on their assertion that Appellees made material
    misrepresentations of fact in the applications.
    8   Participation is accomplished by “offering, through oral or written testimony,
    evidence or a statement of concern related to the subject of the proceeding.” 24 V.S.A.
    § 4471(a).
    11
    At the present time, without Appellants’ written submission to the town officials
    at the September 24, 2009 meeting, and without their notices of appeal to the DRB,
    material facts are in dispute, or at least have not been provided to the Court, regarding
    the subject matter or scope of what was actually appealed to the DRB. Therefore,
    without further filings, the Court cannot determine the scope of the present proceeding
    and cannot rule on the motion to dismiss or for summary judgment. See, e.g., Kibbe
    Zoning Permit, No. 173-8-07 Vtec, slip op. at 1–2 (“[T]he Court sits in place of the ZBA
    to consider what was before the ZBA (citations omitted); Maple Tree Place, 156 Vt. at
    500 (1991) (“[T]he court is limited to consideration of the matters properly warned as
    before the local board” (citation omitted)).    The following analysis may assist the
    parties in determining what evidence to present to the Court in support of their
    positions on the present motion.
    Appeal of the 2005 or the 2008 Zoning Permit
    Based on the materials currently before the Court, it appears that Appellants are
    at least seeking to take a late appeal of the 2005 and 2008 Zoning Permits under 24
    V.S.A. § 4465, more than four years late in the case of the 2005 Zoning Permit and more
    than one year late in the case of the 2008 Zoning Permit.9     However, they have not
    explicitly come forward with affidavits or other evidence as to why they should be
    9 Separately from the question of whether Appellants should or should not be given
    leave to file late appeals of the permits, Appellants do not appear to have sought to
    appeal either the 2005 or the 2008 Certificate of Occupancy/Compliance. Appellants
    have not addressed whether the 2005 and 2008 Certificates of Occupancy/Compliance—
    which were not challenged and became final—preclude a challenge to the work
    certified by those documents as being in compliance with the Zoning Regulations. See
    In re Tekram Partners, 
    2005 VT 92
    , ¶¶ 7–13, 
    178 Vt. 628
     (holding that when a certificate
    of occupancy has been issued for a project that is in violation of a zoning ordinance,
    those certificates serve as an “approval” of the violations so that 24 V.S.A. § 4472(a)
    precludes the municipality from bringing a later enforcement action.).
    12
    given leave to take such a late appeal, other than to argue that it is justified if notice of
    those permits was properly posted at the time they were issued.10
    Ordinarily, interested persons seeking to appeal the issuance of a zoning permit
    by an administrative officer must file their notice of appeal “within 15 days of the date
    of that decision or act.” 24 V.S.A. § 4465(a). This provision provides “the exclusive
    remedy for contesting local zoning decisions or actions.” Tekram, 
    2005 VT 92
    , ¶ 8
    (citing 24 V.S.A. § 4472(a)). The DRB, in the first instance, and this Court, in this de
    novo appeal, lack jurisdiction to entertain an untimely appeal. 24 V.S.A. § 4472(d); see
    also, e.g., Boutwell v. Town of Fair Haven, 
    148 Vt. 8
    , 10 (1987) (“The failure to effect a
    timely appeal extinguishes subject matter jurisdiction.” (citing Harvey v. Town of
    Waitsfield, 
    137 Vt. 80
    , 82 (1979))). The absence of a timely appeal prevents the DRB or
    the Court from considering the merits of an appeal, even if the administrative officer
    issued a permit in error or without the statutory or regulatory authority to do so. See In
    re Taft Corners Assocs., 
    162 Vt. 638
    , 639 (1994) (mem.) (If a timely appeal of a decision
    of the zoning administrator is not taken, the trial court is barred under 24 V.S.A.
    § 4472(d) from asserting jurisdiction “even if the administrator’s ruling was ultra vires.”
    (citing Town of Charlotte v. Richmond, 
    158 Vt. 354
    , 356 (1992); Levy v. Town of St.
    Albans, 
    152 Vt. 139
    , 142 (1989))); see also Tekram, 
    2005 VT 92
    , ¶ 8 (stating that courts
    have “‘strictly enforced’ [the] exclusivity-of-remedy provision to ensure timely review
    of all zoning disputes, thereby assuring parties of finality”); City of S. Burlington v.
    Dept. of Corrs., 
    171 Vt. 587
    , 588 (2000) (stating that the court has “recognized that the
    policy underlying the [exclusivity-of-remedy] statute is to assure parties of finality”).11
    10   In the alternative, Appellants also seem to claim that the failure to post, no matter
    how long ago, automatically renders the permits “null and void,” requiring remand to
    the DRB to consider the merits of those permits at a new public hearing. Appellants’
    Objection to Appellees’ Motion, at 7.
    11 It is important to note that, since the amendments to the zoning statute effective on
    July 1, 2004, the zoning statute provides that if an administrative officer issues a permit
    13
    Because Appellants filed their notices of appeal with the DRB years after the
    expiration of the appeal periods, both appeals are untimely and must be dismissed
    unless some other circumstance justifies the filing of a late appeal of either permit.
    Appellants argue that Appellees failed to post proper notice of the 2005 and 2008
    Zoning Permits, as required by 24 V.S.A. § 4449(b), and that they are therefore justified
    in filing the late appeals.
    First, material facts are in dispute as to if, where, and when Appellees posted the
    notices of the 2005 and the 2008 Zoning Permits, and therefore it is at least premature
    for the Court to undertake the analysis of whether deficient posting justifies the filing of
    a late appeal under these circumstances. However, if the Court finds that the notices of
    permit were not properly posted, then the remedy of allowing a four-year-late (or one-
    year-late) appeal is not an automatic result of this finding. Rather, if it is determined
    that the notices of permit were not properly posted, the Court would then need to
    analyze—based on further filings by the parties—the issue of “whether due process or
    fundamental administrative fairness requires that a party deprived of notice of a zoning
    permit be allowed to contest the permit, notwithstanding the strong policy interests in
    finality.” In re Hignite, 
    2003 VT 111
    , ¶ 8, 
    176 Vt. 562
     (mem.).12
    in error, and that permit becomes final, then the construction authorized under such a
    permit becomes a nonconformity that is thereafter governed by the regulatory
    provisions regarding nonconformities.         See 24 V.S.A. § 4303(13) (defining
    “nonconforming lots or parcels” as a lots or parcels “that do not conform to the present
    bylaws covering dimensional requirements but were in conformance [with prior
    bylaws], including a lot or parcel improperly authorized as a result of error by the
    administrative officer”); see also id. § 4303(14) (defining “nonconforming structure”
    similarly).
    12
    Echoing the United States Supreme Court, the Vermont Supreme Court has stated
    that “[a]n elementary and fundamental requirement of due process in any proceeding
    which is to be accorded finality is notice reasonably calculated, under all the
    circumstances, to apprise interested parties of the pendency of the action and afford
    them an opportunity to present their objections.” Town of Randolph v. Estate of White,
    14
    In addition to examining Applicants’ arguments regarding fundamental due
    process, any analysis of whether Appellants should be allowed to file a late appeal of
    either permit would also require the Court to address whether Appellants would have
    had standing as an “interested person” under 24 V.S.A. § 4465(b)(3) to appeal either
    permit at the time of the statutory appeal period for each permit, as they did not own or
    live in the adjacent property at the time of the 2005 Permit.13 In addition, the Court
    would also expect Appellants to present evidence as to the reasons why they did not
    attempt to file a late appeal of either permit during the time that construction was
    ongoing pursuant to the permit, or at the time at which they first became aware of that
    construction. Material facts are in dispute, or at least have not been provided to the
    Court, on all these points; however, the Court will not reach these issues until and
    unless it determines that notice of the zoning permits was not properly posted under 24
    V.S.A. § 4449(b) and addresses the issue of the effect of the Certificates of
    Occupancy/Compliance discussed in footnote 9.
    
    166 Vt. 280
    , 283 (1997) (citing Mullane v. Cent. Hanover Bank & Trust Co., 
    339 U.S. 306
    ,
    314 (1950)). Notice that does not meet this standard does “not comport with due
    process requirements.” Id. at 284 (quoting Memphis Light, Gas & Water Div. v. Craft,
    
    436 U.S. 1
    , 14 (1978)). In order to determine what process is due to an interested party,
    and therefore whether the notice given to such a party is sufficient, the Vermont
    Supreme Court has applied the three-factor balancing test set forth in the U.S. Supreme
    Court case of Mathews v. Eldridge: “(1) the private interest affected by the official
    action, (2) the risk of an erroneous deprivation of the interest under the procedures
    used, and (3) the governmental interests involved, including fiscal and administrative
    burdens.” Estate of White, 166 Vt. at 284 (citing Mathews, 
    424 U.S. 319
    , 334–35 (1976)).
    13
    Under 24 V.S.A. § 4465(b)(3), Appellants would be required, among other things, to
    demonstrate that the work proposed under the permit sought to be appealed has “a
    physical or environmental impact on the [their] interest”; that impact is measured as of
    the appeal period.
    15
    Enforcement of the Terms of Either Zoning Permit or of the Zoning Regulations
    Appellants argue that they have also brought an appeal of the Zoning
    Administrator’s refusal to take enforcement action against Appellants, although it is not
    clear whether they sought enforcement of the terms of the permits, sought enforcement
    of the zoning ordinance, or seek some other relief.
    If such a request was in fact made by Appellants and was then denied by the
    Zoning Administrator, that “decision or act” could be appealed to the DRB under 24
    V.S.A. § 4465(a). See also, e.g., In re Charlotte Farm & Mills, 
    172 Vt. 607
    , 608 (2001)
    (stating that “the finality and exclusivity doctrines embodied in § 4472(d) do not
    preclude an interested person from taking action to ensure compliance with the terms
    of a zoning permit” and “[t]he fact that no one timely appealed the initial permit
    granted to [applicant] did not preclude neighboring property owners from later seeking
    review of the zoning administrator's decision that [applicant’s] activities were within
    the scope of its permit” (citations omitted)); In re Sardi, 
    170 Vt. 623
    , 626 (2000) (mem.)
    (“The zoning administrator is authorized to enforce zoning bylaws by appropriate
    actions,” and “interested persons . . . may appeal to the board of adjustment in the event
    the administrator fails to act on their complaints.” (citations omitted)).     However,
    material facts are in dispute, or at least have not been provided to the Court, as to
    whether or when Appellants requested the Zoning Administrator to enforce the terms
    of the permits, or to take any other enforcement action under the authority of 24 V.S.A.
    §§ 4451 and 4452.14 If such a request was made, was denied, and the denial was sought
    14
    The enforcement authority available to municipalities to enforce their zoning
    ordinances and the terms of zoning permits issued by the zoning administrative officer
    is distinct from the enforcement authority provided in § 4470(b), which is available both
    to municipalities and to individuals, but only authorizes individuals and municipalities
    to enforce decisions of the municipal panel—in the present case, the DRB. In the
    present case, Appellants do not seek enforcement of any decision of the DRB. It is
    important to understand that 24 V.S.A. § 4470(b) “does not provide for individuals to
    16
    to be appealed to the DRB, then the request to enforce is also before the Court in these
    appeals, independently of whether a late appeal of either zoning permit is allowed.
    Appellants assert that they requested some type of enforcement when they met
    with the Town representatives on September 24, 2009. See Appellants’ Supplemental
    Objection, at 1 (stating that Appellants “provided . . . information as to various zoning
    violations on [Appellees’] property”); Appellant’s Reply to Town’s Memorandum, at 3
    (stating that “the content of their discussion with the Town administrators on
    September 24, 2009[,] and written submission to them at that time” make clear
    Appellants’ intent to “provide notice of the violations and seek enforcement of the
    zoning laws”). Appellants further argue that the Town Attorney’s October 8, 2009 letter
    operated as the zoning administrator’s denial of their request for enforcement, so that it
    was within the scope of their appeal to the DRB. Appellants’ Supplemental Objection,
    at 1–2; Appellant’s Reply to Town’s Memorandum, at 2.
    However, material facts are in dispute, or at least have not been provided to the
    Court, regarding Appellants’ oral presentation at the September 24, 2009 meeting,
    regarding their written submission at that meeting, and regarding the notices of appeal
    they filed with the DRB on October 15, 2009. Accordingly, the Court cannot determine
    at this time whether any type of enforcement request by Appellants is properly within
    the scope of the present appeal.
    Request for Revocation of Permits
    Appellants also appear to argue that the Town should revoke the 2005 and 2008
    Zoning Permits due to material misstatements or omissions of fact in the applications
    bring direct enforcement actions for asserted violations of zoning ordinances,” and that
    such enforcement actions can only be brought by a municipality. Whitmore v. Phillips,
    No. 18-1-09 Vtec, slip op. at 3 (Vt. Envtl. Ct. Mar. 12, 2009) (Wright, J.).
    17
    for both permits.15 However, material facts are in dispute, or at least have not been
    provided to the Court, regarding whether Appellants ever requested the Zoning
    Administrator to seek revocation of either permit based on material misrepresentations
    and omissions, whether the Zoning Administrator denied such a request, or whether
    Appellants appealed such a “decision or act” to the DRB under 24 V.S.A. § 4465(a).
    After a zoning permit has become final, a municipality is authorized to seek
    invalidation or revocation of such a permit under 24 V.S.A. § 4455.16 That provision
    allows a municipality to petition this Court to revoke a permit, after which the Court
    must provide “notice and opportunity for hearing” and may revoke the permit if it
    determines either “that the permittee violated the terms of the permit” or that the
    permittee “obtained the permit based on misrepresentation of material fact.” 24 V.S.A.
    § 4455.     However, that section does not authorize either a municipal panel or an
    15
    Appellants claim that both applications submitted by Appellees contained material
    misstatements of fact and omitted several material facts, and they argue that “if the
    material facts had been fully disclosed in the 2005 and 2008 Applications, the Town
    would have been warranted in denying the building permits.” Appellants’ Objection to
    Appellees’ Motion, at 11. See id. at 7–11 (describing several purported misstatements
    and omissions of material fact in the 2005 and 2008 Permit Applications, such as
    “contradictory” statements regarding the size and extent of the proposed work and a
    failure to disclose that the proposed work included “alteration of grade or earth
    removal” and “construction of a retaining wall”).
    16 Prior to the time at which a permit becomes final, an administrative officer or
    municipal panel has the inherent authority to recall a permit or other decision to
    remedy an error; however, “any attempted unilateral reopening or alteration of an
    issued permit must be done by the issuing authority within the time allotted for appeal
    of that permit (that is, 15 days in the case of a zoning administrator’s action, and 30 days
    in the case of the ZBA).” In re: Appeal of Addison County Eagles, No. 13-1-00 Vtec, slip
    op. at 3 (citing In re Appeal of Dunn, No. 2-1-98 Vtec, slip op. at 3–6 (Vt. Envtl. Ct. Mar.
    8, 1999); Nash v. Warren Zoning Bd. of Adjustment, 
    153 Vt. 108
    , 114 (1989)). In the
    present appeals, any request to the Town to revoke the permits occurred, if at all, after
    the expiration of the appeal period for both permits.
    18
    administrative officer unilaterally to revoke a final permit.       Rather, it requires the
    municipality to file a petition in this Court seeking such revocation.
    Prior to the adoption of 24 V.S.A. § 4455, effective on June 1, 2009, this Court had
    upheld a zoning administrator’s authority “to revoke a permit for misrepresentation, at
    least where the permit form warns the applicant that misrepresentation voids the
    permit,” because “[t]o conclude otherwise would be to invite unscrupulous applicants
    to misrepresent the size, intended use, or location of a project on a permit application, to
    succeed in obtaining a permit without alerting potential opponents or the zoning
    administrator to problems with the project under the zoning ordinance.” In re: Appeal
    of Hurlburt, No. 27-2-98 Vtec, slip op. at 4 (Vt. Envtl. Ct. Feb. 12, 1999) (Wright, J.); see
    also Addison County Eagles, No 13-1-00 Vtec, slip op. at 6 (reciting the same principle
    established in Hurlburt).17
    Appellants do not explicitly claim that they requested the Zoning Administrator
    to seek revocation of either permit, or that they appealed a denial of that request to the
    DRB and hence to this Court, although they do argue that the permits are “null and
    void” and should be remanded for consideration by the DRB. Appellants’ Objection to
    Appellees’ Motion, at 7. Material facts are in dispute, or at least have not been provided
    to the Court, regarding whether Appellants made any such request at all and, if so,
    whether it was made before or after the effective date of 24 V.S.A. § 4455. Therefore, the
    17 Appellants rely on these two cases in arguing that the Zoning Administrator should
    unilaterally revoke both zoning permits under § 11.08 of the Zoning Regulations, which
    allows the Zoning Administrator unilaterally to revoke a permit “at any time,” based on
    an applicant’s “[o]mission or misstatement of any material fact . . . stated on the
    application or at any hearing, which could have warranted refusing the permit.” Even
    if the subsequent change in the enabling statute—setting out a procedure in this Court
    for any such revocations under 24 V.S.A. § 4455—does not supersede the analysis made
    in these two cases, the application forms used for both permits in the present appeals
    did not “warn[] the applicant that misrepresentation voids the permit,” Hurlburt, No.
    27-2-98 Vtec, slip op. at 4, so that the analysis in Hurlburt and Addison County Eagles
    would not necessarily apply.
    19
    Court cannot determine at this time whether any type of request to revoke either permit
    may be within the scope of the present appeal.
    Accordingly, based on the foregoing, it is hereby ORDERED and ADJUDGED
    that Appellees’ Motion to Dismiss or for Summary Judgment is DENIED at this time as
    material facts are in dispute. At the scheduled telephone conference (see enclosed
    notice), the parties should be prepared to discuss whether they wish to provide the
    missing information discussed in this decision through renewed motions for summary
    judgment, and should be prepared to discuss setting a schedule for mediation and for
    trial.
    Done at Berlin, Vermont, this 16th day of June, 2010.
    _________________________________________________
    Merideth Wright
    Environmental Judge
    20