Woodchip Power Plant A250 JO 2-234 ( 2007 )


Menu:
  •                                       STATE OF VERMONT
    ENVIRONMENTAL COURT
    }
    Woodchip Power Plant Appeal                            }           Docket No. 91-4-06 Vtec
    (Act 250 Jurisdictional Opinion #2-234)                }
    }
    Decision and Order
    Appellant Access Ludlow Clean Energy, LLC (“Appellant”), as proponent of a proposed
    woodchip-burning electric generation plant, appealed from a Jurisdiction Opinion of the District
    Coordinator for the District 2 Environmental Commission dated February 16, 2006, determining
    that Appellant’s proposed energy plant in the Town of Ludlow will require amendments to
    existing Act 250 permits. Appellant is represented by Edward V. Schwiebert, Esq.; the Natural
    Resources Board (“NRB”) intervenes and is represented by John H. Hasen, Esq.; and the
    Department of Public Service (“DPS”) intervenes and is represented by Aaron Adler, Esq.
    Now pending before the Court is Appellant’s unopposed motion for summary judgment
    on Questions 4 and 5 of its Statement of Questions. DPS joins in Appellant’s motion for
    summary judgment. NRB has advised that it does not intend to file a memorandum in response
    to Appellant’s motion. For the reasons stated below, we conclude that Appellant’s motion
    should be granted.
    Factual and Regulatory Background
    The following facts are uncontested.1
    1.      Appellant proposes to construct an electric generating facility fueled by
    woodchips in the Town of Ludlow, on a 20± acre tract of land located on the southerly side of
    Soapstone Brook, a tributary to the Black River.
    2.      For the purposes of the instant motion, the proposed project site is assumed to be
    part of the Dean Brown Industrial Park, located northerly of Soapstone Brook.
    3.       The Dean Brown Industrial Park is subject to Land Use Permits #2S0232 and
    #2SO467 and amendments thereto.
    1Both NRB and DPS have informed the Court by separate filings that they do not oppose Appellant’s statement of
    material facts.
    4.       The construction and operation of the proposed woodchip power plant will
    require the issuance of a certificate of public good by the Public Service Board pursuant to 30
    V.S.A. § 248.
    5.       For the purposes of the instant motion, the proposed project is assumed to
    constitute a material change to the previously permitted Dean Brown Industrial Park.
    Discussion
    Appellant moves for summary judgment on Questions 4 and 5 of its Statement of
    Questions. Question 4 asks:
    Whether Act 250 jurisdiction exists over a project that specifically constitutes the
    construction of improvements for an electric generation facility that requires a
    certificate of public good under 30 V.S.A. § 248 and, therefore, is excluded from
    the definition of “development” [under] 10 V.S.A. § 6001(3)(D)?
    Question 5 asks:
    Whether the District Coordinator erred in concluding that Act 250 jurisdiction
    exists in the present circumstances involving a project that specifically constitutes
    the construction of improvements for an electric generation facility that requires a
    certificate of public good under 30 V.S.A. § 248 and, therefore, is excluded from
    the definition of “development” [under] 10 V.S.A. § 6001(3)(D)?
    The instant motion presents essentially the same legal issue that was before this Court in
    Glebe Mountain Wind Energy, LLC, Docket No. 234-11-05 Vtec (Vt. Envtl. Ct., Aug. 3, 2006).2
    Indeed, the Jurisdictional Opinion appealed from here states that “[t]he issue of the need for both
    an Act 250 permit and a certificate of public good [under 30 V.S.A. § 248] . . . has recently been
    raised in the Glebe Mountain wind project. . . . The [Glebe Mountain] jurisdictional opinion is
    now on appeal before the Environmental Court and it will likely be some time before a final
    jurisdictional ruling is issued.” Jurisdiction Opinion #2-234, at 1.
    The issue presented by both Glebe Mountain and the instant motion is this: does the
    construction of a § 248 project on lands already encumbered by Act 250 permit conditions
    require an Act 250 permit amendment pursuant to former Environmental Board Rule (EBR) 34,3
    2
    Our original decision in Glebe Mountain was issued on May 18, 2006. We subsequently granted in part NRB’s
    motion to reconsider and issued a Revised Decision on Cross-Motions for Summary Judgment on August 3, 2006,
    removing advisory dicta regarding secondary impacts. All citations to Glebe Mountain in the present Decision are
    to the Aug. 3rd Revised Decision on Cross-Motions for Summary Judgment.
    3
    The former Environmental Board Rules have been supplanted by the Act 250 Rules promulgated by the Natural
    Resources Board, effective May 1, 2006. We look to the former Environmental Board Rules as they existed on
    Page 2 of 3.
    where such construction will cause material or substantial changes to development previously
    permitted under Act 250.
    This Court addressed the above issue at length in Glebe Mountain. We do not see the
    need to repeat that analysis here. Because the District Coordinator’s Jurisdictional Opinion in
    the instant appeal was issued prior to our decision in Glebe Mountain, the District Coordinator
    could not benefit from our conclusion that “Act 250 jurisdiction under EBR 34 does not attach to
    electric generation facilities that are located on lands encumbered by pre-existing Act 250
    permits.” Glebe Mountain at 15. That conclusion applies as well to the uncontested facts of this
    appeal. Therefore, Appellant’s Question 4 must be answered in the negative and Appellant’s
    Question 5 must be answered in the affirmative.
    Accordingly, it is hereby ORDERED and ADJUDGED that Appellant’s motion for
    summary judgment is GRANTED as to Questions 4 and 5 in Appellant’s Statement of
    Questions. In so ruling, we specifically conclude that Act 250 jurisdiction does not exist over the
    construction of improvements for an electric generation facility requiring a certificate of public
    good under 30 V.S.A. § 248.
    Appellant has preserved eight other issues for our review by its Statement of Questions.
    However, our determination on Questions 4 and 5, that the proposed electric generation project is
    exempt from Rule 34 amendment jurisdiction, renders moot the remaining factual and legal
    issues posed by Appellant.         We therefore conclude that Jurisdictional Opinion #2-234 is
    REVERSED, thereby concluding this appeal.
    Pursuant to the discretion conferred by V.R.C.P. 58, the undersigned directs that this
    Decision shall also constitute the Judgment Order in this appeal.
    Done at Berlin, Vermont this 30th day of January, 2006.
    __________________________________________
    Thomas S. Durkin, Environmental Judge
    February 16, 2006, because we are required to apply the substantive standards that were applicable before the
    tribunal appealed from, pursuant to 10 V.S.A. § 8504(h).
    Page 3 of 3.
    

Document Info

Docket Number: 91-04-06 Vtec

Filed Date: 1/30/2007

Precedential Status: Precedential

Modified Date: 4/24/2018