Bethel Mills, Inc. J.O. 3-97 ( 2006 )


Menu:
  •                                   STATE OF VERMONT
    ENVIRONMENTAL COURT
    }
    Re: Bethel Mills, Inc.                    }          Docket No. 243‐11‐05 Vtec
    Jurisdictional Opinion #3‐97              }
    }
    Decision on Appellant’s Motion for Summary Judgment
    This  matter  concerns  an  appeal  by  Bethel  Mills,  Inc.  (Appellant)  from  a
    Jurisdictional Opinion (JO) of the District 3 Environmental Coordinator, dated October
    20, 2005.  The Coordinator concluded that an abutting 0.61‐acre parcel of land acquired
    by  Appellant  in  1998,  which  adjoins  Appellant’s  2.93‐acre  tract  of  land  containing  its
    lumber  yard  operations,  is  “involved  land”  to  which  Act  250  jurisdiction  is  attached.
    Bethel Mills is represented by C. Daniel Hershenson, Esq.  No other party has appeared
    in this proceeding.  Appellant has filed an unopposed motion for summary judgment.
    Factual Background
    The following facts are undisputed unless otherwise noted.
    1.      Appellant owns a 2.93‐acre parcel of land located on North Main Street in
    the Industrial zoning district of the Town of Bethel (Town).
    2.      Appellant  operated a sawmill on  the  2.93‐acre  parcel from 1781 until  the
    mid‐1970’s.
    3.      In the mid‐1970’s to mid‐1980’s, Appellant ceased operating a sawmill and
    made environmental and aesthetic improvements on the 2.93‐acre parcel.
    4.      From  the  early  1990’s  until  the  present  Appellant  has  used  the  2.93‐acre
    parcel for the operation of a lumber yard and retail hardware commercial use.
    5.      The 2.93‐acre parcel is wholly located in the Industrial zoning district.
    6.      Sometime in the 1980s, Appellant constructed improvements on the 2.93‐
    acre  parcel,  including  a  19,000‐square‐foot  warehouse,  wood  storage  racks  and  sheds,
    site  paving  and  related  infrastructure.    Appellant  did  not  seek  or  receive  an  Act  250
    permit for these improvements prior to construction.
    7.      At  some  time  thereafter  (a  specific  date  is  not  revealed  by  the  record  in
    this  appeal),  a  determination  was  made  that  the  improvements  Appellant  previously
    constructed  constituted  a  “substantial  change”  to  the  development  on  the  2.93‐acre
    parcel.  Thus, even though the former sawmill pre‐dated the implementation of Act 250,
    Appellant  was  required  to  obtain  an  Act  250  permit  for  the  previously  constructed
    improvements.    As  a  result  of  that  determination,  the  following  were  issued  by  the
    District Commission and the former Environmental Board:
    a.      Land  Use  Permit  #3W0898,  issued  by  the  District  Commission  on
    March 3, 2004;
    b.      Findings of Fact and Conclusions of Law, also issued by the District
    Commission on March 3, 2004, to accompany the above referenced
    Permit;
    c.      Memorandum  of  Decision  issued  by  the  District  Commission  on
    May 21, 2004, in which the Commission granted in part and denied
    in  part  Appellant’s  motion  to  alter  the  previously  issued  Permit,
    Findings and Conclusions.  On that same day, the Commission also
    issued its altered Permit, Findings and Conclusions.
    d.      Findings  of  Fact,  Conclusions  of  Law  and  Order  issued  by  the
    former Environmental Board on August 4, 2005.
    8.      At some point prior to 1998, Appellant purchased a half‐acre of land from
    an adjacent residential property owner, Richard Mills, to settle a boundary line issue.
    9.      In  1998,  Appellant  purchased  the  remaining  0.61‐acre  parcel  of  land
    owned  by  Richard  Mills  (the  “Mills  Parcel”).    The  Mills  Parcel  is  improved  with  a
    residential  structure  and  outbuilding.    The  total  area  of  Appellant’s  contiguous  land
    2
    holdings  is  4.04  acres,  including  the  lumber  yard,  the  Mills  Parcel,  and  the  half‐acre
    previously purchased from Richard Mills.
    10.     The  Mills  Parcel  is  located  entirely  within  the  Village  Residential  zoning
    district.    It  appears  that  the  common  boundary  between  the  Mills  Parcel  and
    Appellant’s  remaining  land  may  also  form  the  boundary  line  between  this  residential
    zoning district and the Industrial zoning district.
    11.     On  November  28,  2000,  the  Town  Development  Review  Board  denied
    Appellant’s request to utilize the Mills Parcel for industrial use, on the ground that such
    use is not allowed in the Village Residential zoning district.
    Procedural Background
    The  issue  of  whether  Act  250  jurisdiction  attaches  to  the  Mills  Parcel  has  been
    addressed several times by others, including the District 3 Environmental Commission,
    the Environmental Board, and the District 3 Environmental Coordinator, whose opinion
    is the subject of this appeal.
    On  March  3,  2004,  the  District  Commission  issued  Land  Use  Permit  (LUP)
    #3W0898,  together  with  Findings  of  Fact  and  Conclusions  of  Law,  for  the  previously
    completed removal of the sawmill and construction of a storage building, wood storage
    racks  and  sheds, site  paving, and  related infrastructure.  LUP  #3W0898 states (in  bold
    type)  that  “[j]urisdiction  shall attach to  the  entire 4.04‐acre tract of land,  including the
    residential lot.”
    In that first application, Appellant requested that the District Commission  limit
    jurisdiction, so that the Mills Parcel would not be encumbered by the LUP.  Appellant’s
    request  was  apparently  based  on  the  Environmental  Board’s  2001  decision  in  Re:
    Stonybrook Condominium Owners Assoc., Declaratory Ruling #385 (Vt. Envtl. Bd., May
    18,  2001)  (“Stonybrook”),  in  which  the  Environmental  Board  ruled  that  under  certain
    circumstances the scope of the permitted project should be restricted to “something less
    3
    than  the  entire  tract,”  Stonybrook  at  18.    The  District  Commission  denied  Appellant’s
    request  to  limit  jurisdiction,  concluding  that  “the  buildings  on  the  residential  lot  [i.e.:
    the Mills Parcel] serve to buffer the noise and the light produced on the lumber storage
    lot,” District Commission Findings and Conclusions dated March 3, 2004, at 13, and that
    “the  ‘aura’  of  the  lumber  storage  lot  spills  onto  the  residential  lot.”    The  Commission
    used this rationale to deny the Applicant’s request to limit jurisdiction.  Id.
    On  March  18,  2004,  Appellant  filed  with  the  District  Commission  a  motion  to
    alter  LUP  #3W0898  by,  inter  alia,  adding  a  condition  stating  that  the  “property
    purchased by Bethel Mills from Richard Mills in 1998 . . . is hereby removed from the
    jurisdiction  of  this  permit  in  accordance  with  [Stonybrook].”    District  Commission
    Memorandum  of  Decision  dated  May  21,  2004,  at  5.    The  Commission  denied
    Appellant’s request to add such a condition, stating that:
    It  is  the  permittee’s  burden  to  produce  evidence  convincing  the
    Commission there is no “nexus” between the two tracts of land regarding
    the  residential  and  commercial  lot.    There  is  a  “nexus,”  a  functional
    relationship,  between  the  two  tracts  of  land,  relating  directly  to  the
    production of noise and lighting on the industrial lot.  The residential lot
    clearly  provides  a  buffer  for  the  residential  neighborhood  to  the  north.
    The  permittee  may  not  have  purchased  the  residential  lot  with  this  in
    mind, but the “nexus” exists.
    Id. at 3.
    The  District  Commission’s  May  21,  2004  Memorandum  of  Decision  was
    accompanied  by  LUP  #3W0898(Altered),  together  with  amended  Findings  and
    Conclusions.   The altered Permit retained  jurisdiction  over  the  entire  4.04‐acre tract of
    land, with the Commission stating in the introduction to its Findings that the “tract of
    land  consists  of  4.04  acres  with  4.04  acres  involved  in  the  project  area.”    Id.  at  1.    The
    altered Findings repeated the Commission’s earlier finding as to the residential lot, and
    the  Commission  again  denied  Appellant’s  request  that  it  limit  jurisdiction  so  as  to
    exclude the Mills Parcel from the Permit’s jurisdiction.
    4
    On June 21, 2004, Appellant appealed the altered Permit and amended Findings
    to the former Environmental Board (Board), alleging that the Commission had erred by
    declining  to  exclude  the  Mills  Parcel  from  the  permitted  project.    The  Board  denied
    Appellant’s request to limit the scope of the permitted project, stating that “[n]oise and
    light  from  the  Project  do  affect  the  residential  land,  and  the  house,  outbuildings  and
    vegetation  on  the  Mills  Parcel  provide  some  screening—both  visual  and  aural—of  the
    Project.  Accordingly, the Board cannot grant Bethel Mills’ request to reduce the scope
    of  the  permitted  project  under  Stonybrook.”    Envtl.  Bd.’s  Findings,  Conclusions,  and
    Order in LUP #3W0898(Altered)‐EB, at 16 (Vt. Envtl. Bd., Aug. 4, 2005).
    The Board did not stop there, however, but went on to say that “[a]lthough it is
    beyond the scope of this permit appeal, the Board notes that the question of whether the
    Mills Parcel is involved land has not been addressed in any jurisdictional opinion . . . .
    Whether  the  Mills  Parcel  constitutes  involved  land  under  EBR  2(F),  or  whether  it
    formerly  did  but  no  longer  does,  could  be  addressed  by  the  appropriate  district
    environmental coordinator upon request by Bethel Mills.”  Id.
    Appellant subsequently requested a jurisdictional opinion (JO) from the District
    3  Environmental  Coordinator.    On  October  20,  2005,  the  Coordinator  issued  the
    requested  JO,  concluding  that  “because  the  Mills  parcel  is  contiguous  to  the  lumber
    yard, was purchased prior to the issuance of the Land Use Permit and serves a purpose
    for blocking light, noise and screening from the nearby residential homes, it is involved
    land and Act 250 jurisdiction attaches.”  Jurisdictional Opinion #3‐97 Bethel Mills, Inc.,
    at 4 (District 3 Envtl. Coordinator, Oct. 20, 2005).  This appealed followed.1
    1  Between the time Appellant appealed the District Commission’s March 18, 2004, Decision to the former
    Environmental  Board  and  the  District  Coordinator  issued  her  JO,  jurisdiction  over  such  appeals  was
    transferred to this Court.  10 V.S.A. § 8504(a).
    5
    Discussion
    We note at the outset that the Commission’s introductory statement in the May
    21, 2004 Permit that the “tract of land consists of 4.04 acres with 4.04 acres involved in
    the  project  area”  is  not  determinative  of  the  question  of  whether  the  Mills  Parcel  is
    “involved  land”  under  Environmental  Board  Rule  2(F)(1).    EBR  (2)(F)(1)  states  in  its
    entirety:
    (F) “Involved Land” includes: (1) The entire tract or tracts of land, within a
    radius  of  five  miles,  upon  which  the  construction  of  improvements  for
    commercial or industrial purposes will occur, and any other tract, within a
    radius  of  five  miles,  to  be  used  as  part  of  the  project  or  where  there  is  a
    relationship  to  the  tract  or  tracts  upon  which  the  construction  of
    improvements will occur such that there is a demonstrable likelihood that
    the  impact  on  the  values  sought  to  be  protected  by  Act  250  will  be
    substantially  affected  by  reason  of  that  relationship.    In  the  event  that  a
    commercial or industrial project is to be completed in stages according to
    a  plan,  or  is  part  of  a  larger  undertaking,  all  land  involved  in  the  entire
    project shall be included for the purpose of determining jurisdiction.
    There is no evidence that the permitted lumber yard is part of a staged plan or
    larger undertaking, which could involve the Mills Parcel under the somewhat circular
    definition  in  the  final  clause  of  EBR  (2)(F)(1)  (“all  land  involved”  shall  be  included  as
    involved  land).    In  fact,  the  current  undisputed  facts  reveal  an  absence  of  a  “staged
    plan.”  There now can be no commercial or industrial uses on the Mills Parcel, because
    it is located entirely within the Village Residential zoning district, where such uses are
    not allowed.  See the November 28, 2000 DRB denial of Appellant’s request to utilize the
    Mills Parcel for industrial use, on the ground that such use is not allowed in the Village
    Residential zoning district.
    However,  prior  precedent  suggests  that  the  Mills  Parcel,  being  a  contiguous
    parcel  under  common  ownership,  is  part  of  the  “entire  tract  or  tracts  of  land”  on  a
    portion  of  which  commercial  improvements  have  been  constructed,  even  though  no
    6
    construction  has  occurred  on  the  Mills  Parcel  itself.    See  Costello  Garage,  
    158  Vt.  655
    ,
    656  (1992)  (Mem.)  (“the  Board  was  reasonable  in  determining  that  two  contiguous
    parcels  were  a  ’tract’”);  Stokes  Communications,  
    164  Vt.  30
    ,  37  (1995)  (stating  that  the
    “Board  has  construed  a  ‘tract  of  land’  for  jurisdictional  purposes  to  include  all
    contiguous  land  in  common  ownership,  regardless  of  the  functional  relationship
    between  the  parcels;”  and  citing  Costello  for  the  proposition  that  “contiguous  parcels
    held in common ownership are involved land under Rule 2(F)(1).”).
    The  Costello  and  Stokes  Communications  precedent  could  lead  to  a  conclusion
    that  the  Mills  Parcel  is  involved  land,  simply  because  it  is  part  of  the  “entire  tract  or
    tracts  of  land,  within  a  radius  of  five  miles,  upon  which  the  construction  of
    improvements for commercial or industrial purposes will occur,” without reaching the
    “any  other  tract”  clause  of  the  definition.    This  would  amount  to  a  very  broad  rule
    providing that “if it is contiguous, it is involved,” whereas the “any other tract” clause
    requires use as part of the project or a relationship to the improved tract.2  We decline to
    subscribe to so broad a rule in this opinion.  However, we conclude that the Mills Parcel
    fits the more narrow “involved land” rule relating to “any other tract” because it bears a
    relationship to the lumber yard that has been demonstrated in the proceedings below,
    and  that  relationship  is  likely  to  substantially  affect  the  aesthetic  values  sought  to  be
    protected by Act 250.
    The Mills Parcel is involved land, because it qualifies as “any other tract, within a
    radius of five miles, to be used as part of the project or where there is a relationship to
    the  tract  or  tracts  upon  which  the  construction  of  improvements  will  occur  such  that
    there is a demonstrable likelihood that the impact on the values sought to be protected
    by Act 250 will be substantially affected by reason of that relationship.”  EBR (2)(F)(1).
    2     But  see  Costello,  
    158  Vt.  655
    ,  656  (1992)  (“Board  Rule  2(F)(1),  defining  ‘involved  land,’  omits  the
    criterion of a functional relationship between contiguous parcels of land.”).
    7
    One  of  the  values  sought  to  be  protected  by  Act  250  is  aesthetics,  see  10  V.S.A.
    § 6086(a)(8)  (Act  250  Criterion  8)  (“Before  granting  a  permit,  the  district  commission
    shall  find  that  the  subdivision  or  development:  .  .  .  [w]ill  not  have  an  undue  adverse
    effect  on  the  scenic  or  natural  beauty  of  the  area,  aesthetics,  historic  sites  or  rare  and
    irreplaceable natural areas.”).
    The  Mills  Parcel,  with  its  residential  structure  and  outbuilding,  sits  between  a
    commercial  lumber  yard  and  several  residential  properties.    The  evidence  presented
    shows  that  the  Mills  Parcel  marks  the  end  of  the  Industrial  zoning  district  and  the
    beginning  of  the  Village  Residential  district.    Thus,  the  Mills  Parcel  acts  as  a  buffer,
    which  Appellant  owns  and  controls,  between  its  industrial  development  and  the
    adjoining residences in the Village Residential district.
    Appellant owned the Mills Parcel when it applied for its Act 250 permit, and the
    District Commission noted Appellant’s ownership of the Mills Parcel several times in its
    March  3,  2004  Findings  and  Conclusions  under  Act  250  Criterion  8.3    Those  Findings
    included  a  discussion  of  noise  monitoring  that  was  conducted  by  Appellant  on  the
    residential property abutting the Mills Parcel on the side furthest from the lumber yard.
    The  District  Commission  concluded  that  the  noise  levels  on  the  residential  property
    abutting  the  Mills  Parcel  were  mitigated  by  the  interposing  residential  structure  and
    outbuilding on the Mills Parcel.
    Appellant  looks  to  the  Supreme  Court  case  of  In  re:  Audet,  
    176  Vt.  617
      (2004),
    and  the  Environmental  Board’s  decision  in  Okemo  Realty,  Application  #900033‐2‐EB
    (May  2,  1996)  to  support  its  argument  that  the  Mills  Parcel  is  not  involved  land.    In
    Audet,  the Court held that Act 250 jurisdiction did not attach to a parcel of land where
    the owner had begun and then quickly abandoned a use on the parcel that would have
    triggered Act 250 jurisdiction, had the use been continued.  The parcel in question was
    3     See District Commission Findings and Conclusions dated March 3, 2004, at 5, 6, and 8.
    8
    separated  by  three‐tenths  of  a  mile  from  two  other  parcels  owned  by  the  same  party.
    The  two  other  parcels  were  contiguous,  and  were  treated  as  one  tract  by  the  Court.
    However,  the  contiguous  parcels  together  occupied  less  than  one  acre.    Thus,  Act  250
    jurisdiction  would  not  attach  unless  the  third  non‐contiguous  parcel  was  included  as
    involved land.
    The Audet Court based its holding on a finding that the “village business [on the
    contiguous parcels] occupies less than one acre, and has no connection with any other
    parcel.”  Audet,  176  Vt.  at  621.    Here,  however,  the  Mills  Parcel  is  connected  to  the
    business use, both by sharing a common boundary and because the residential structure
    and  outbuilding  screen  the  commercial  lumber  yard  from  the  other  residential
    properties  in  the  adjoining  zoning  district.    In  addition,  the  question  in  Audet  was
    whether  Act  250  jurisdiction  would  attach  at  all  to  any  of  the  parcels  under  common
    ownership,  whereas  here  Act  250  jurisdiction  has  already  attached  to  the  lumber  mill
    project area.
    In Okemo Realty, the Board concluded that:
    the  Kondracki  parcel  does  not  constitute  involved  land  [under  10  V.S.A.
    § 6001(3)  and  EBR  2(F)],  based  on  all  of  the  following  circumstances:  (a)
    this  is  a  renewal  application;  (b)  the  Applicant  acquired  the  Kondracki
    parcel  almost  two  decades  after  the  Original  Permit  was  issued;  (c)  this
    application  concerns  the  Project,  which  is  only  a  portion  of  the
    Subdivision; and (d) the Applicant proposes no activity for the Kondracki
    parcel.
    Okemo  Realty,  Application  #900033‐2‐EB  (May  2,  1996)  (emphasis  added).    Here,
    however,  Appellant  purchased  the  Mills  Parcel  in  1998,  and  subsequently  applied  for
    and  received  Land  Use  Permit  #3W0898  in  2004  for  the  previously  constructed
    improvements.    The  Commission  took  Appellant’s  ownership  of  the  Mills  Parcel  into
    account  in  issuing  the  March  3,  2004  Permit  and  May  21,  2004  Altered  Permit.
    Appellant’s ownership of the Mills Parcel thus provided Appellant with a buffer from
    9
    the  nearby  residential  properties  which  contributed  to  the  Commission  rendering
    positive findings under Criterion 8.4
    Although  Appellant’s  motion  is  unopposed,  our  procedural  Rules  provide  that
    “summary  judgment  when  appropriate  may  be  rendered  against  the  moving  party.”
    V.R.C.P. 56(c)(3).  We conclude that such a result is appropriate in this case.  The Mills
    Parcel constitutes involved land  under EBR (2)(F)(1).  It is therefore subject to Act 250
    jurisdiction.    The  consequence  of  this  determination  is  that  the  pending  appeal  is
    DISMISSED.
    Done at Berlin, Vermont, this 19th day of April, 2006.
    __________________________________________
    Thomas S. Durkin, Environmental Judge
    4    Had  Appellant  not  owned  the  Mills  Parcel  at  the  time  it  applied  for  its  Act  250  approval  of  the
    previously constructed improvements, we are left to wonder what adverse impacts the then Mills Parcel
    owner could have asserted before the District Commission.
    10
    

Document Info

Docket Number: 243-11-05 Vtec

Filed Date: 4/19/2006

Precedential Status: Precedential

Modified Date: 4/24/2018