Sheffield Wind Project ( 2009 )


Menu:
  •                                    STATE OF VERMONT
    ENVIRONMENTAL COURT
    }
    In re Sheffield Wind Project            }       Docket No. 252-10-08 Vtec
    (Appeal of Brouha et al.)        }
    }
    Decision and Order on Pending Motions
    Appellants Carol Brouha, Paul Brouha, Greg Bryant, Don Gregory, the King
    George School, Linda Lavalle, Jane Rollins, Robert Tuthill, and David Zimmerman
    initially appealed from a decision of the Vermont Agency of Natural Resources (ANR)
    issuing individual stormwater discharge permit (No. 5535-INDC), covering the
    construction of the Sheffield Wind Project in Sheffield, Vermont. In late May of 2009,
    Appellants filed a notice of appeal from the amended individual stormwater discharge
    permit (No. 5535-INDC.A) for the same project. The parties agreed that the amended
    permit superseded the original one, and that it would be most efficient to incorporate
    the appeal of the amended permit in the ongoing case, allowing the parties to
    supplement their motion memoranda to address all issues from both appeals that still
    pertain to the amended permit
    Appellants are represented by Stephanie J. Kaplan, Esq.; Appellee-Applicants
    Signal Wind Energy, LLC and Vermont Wind, LLC are represented by Ronald A.
    Shems, Esq., Andrew N. Raubvogel, Esq., and Geoffrey H. Hand, Esq. The Vermont
    Agency of Natural Resources is represented by Judith L. Dillon, Esq.         Appellee-
    Applicants have moved to dismiss certain questions in the statement of questions. Both
    parties have moved for summary judgment.          The facts stated in this decision are
    undisputed unless otherwise noted.
    1
    Standards Applicable to the Present Motions
    Summary judgment is appropriate “only where, taking the allegations of the
    nonmoving party as true, it is evident that there exist no genuine issues of material fact
    and the movant is entitled to judgment as a matter of law.”             Fritzeen v. Trudell
    Consulting Engineers, 
    170 Vt. 632
    , 633 (2000) (mem.). When presented with cross-
    motions for summary judgment, the Court considers each motion independently and
    “afford[s] all reasonable doubts and inferences to the party opposing the particular
    motion under consideration.” In re Chimney Ridge Road Merged Parcels, No. 208-9-08
    Vtec, slip op. at 2 (Vt. Envtl. Ct. July 31, 2009) (Durkin, J.) (citing DeBartolo v.
    Underwriters at Lloyd’s of London, 
    2007 VT 31
    , ¶ 8, 
    181 Vt. 609
    ).
    In considering a motion for summary judgment, the trial court’s function is “not
    to make findings on disputed factual issues.” Blake v. Nationwide Ins. Co., 
    2006 VT 48
    ,
    ¶ 21, 
    180 Vt. 14
    ; Gettis v. Green Mountain Economic Development Corp., 
    2005 VT 117
    ,
    ¶ 19, 
    179 Vt. 117
    . In the context of summary judgment, the court does not adjudicate
    the credibility of the parties or their witnesses or the weight of the facts offered through
    the affidavits submitted on summary judgment. Provost v. Fletcher Allen Health Care,
    Inc., 
    2005 VT 115
    , ¶ 15, 
    179 Vt. 545
     (stating that summary judgment is not warranted
    simply because a movant offers facts that appear more plausible than those tendered in
    opposition, or if the opposing party appears unlikely to prevail at trial.)1
    Trial courts are cautioned that summary judgment “is not a substitute for a
    determination on the merits, so long as evidence has been presented which creates an
    issue of material fact, no matter what view the court may take of the relative weight of
    that evidence.” Fritzeen, 170 Vt. at 633 (internal citation omitted).
    1
    No responses to requests to admit have been submitted in the present case. See
    Gallipo v. City of Rutland, 
    2005 VT 83
    , ¶¶ 20–22, 
    178 Vt. 244
     (citing Freed v. Plastic
    Packaging Materials, Inc., 
    66 F.R.D. 550
    , 552 (E.D. Pa. 1975) (facts in a request to admit
    that are deemed admitted become undisputed and can serve as a basis for summary
    judgment).
    2
    In interpreting and applying administrative rules or regulations, such as the
    provisions of the Vermont Water Quality Standards (VWQS) at issue in this case, the
    Court approaches regulatory construction in the same manner as statutory
    interpretation.   In re Williston Inn Group, 
    2008 VT 47
    , ¶ 14, 
    183 Vt. 621
     (citing
    Conservation Law Found. v. Burke, 
    162 Vt. 115
    , 121 (1993)). The Court’s “overall goal is
    to discern the intent of the drafters,” first and foremost “by reference to the plain
    meaning of the regulatory language.” 
    Id.
     (citing Slocum v. Dep’t of Soc. Welfare, 
    154 Vt. 474
    , 478 (1990)). The other tools of statutory construction are also available “should
    the plain-meaning rule prove unavailing.” 
    Id.
    Section 1-05 of the Vermont Water Quality Standards also addresses the issue of
    their interpretation. That provision recognizes that ordinarily the Secretary of the ANR
    will apply and interpret the regulations in permit proceedings, but specifically states
    that:
    [w]here a de novo appeal is taken from the Secretary’s decision, the
    appellate decision-maker must make determinations and interpretations
    under these rules to achieve the purposes of both state and federal law.
    The decision-maker in a de novo appeal is not bound by any
    determinations or interpretations of these rules made by the Secretary
    relative to an application, provided that review of such determinations is
    within the scope of the appeal.
    VWQS § 1-05 (emphasis added).
    Although the Court is not bound by the Agency’s determinations or
    interpretations of the VWQS “relative to [a particular] application,” as in In re: Unified
    Buddhist Church, Inc., No. 253-10-06 Vtec, slip op. at 3 (Vt. Envtl. Ct. Jan. 25, 2008)
    (Wright, J.), “deference is to be given to the interpretation of regulations and to the
    construction of a statute by the agency responsible for its execution.” Id. (citing In re
    Appeal of Electronic Industries Alliance, 
    2005 VT 111
    , ¶7, 
    179 Vt. 539
    ).
    3
    References to the Numbering of Questions in the Statements of Questions
    Unfortunately, Appellants did not use a consistent numbering system between
    the statement of questions pertaining to the original permit (Statement of Questions
    filed January 5, 2009) and the statement of questions pertaining to the amended permit
    (Statement of Questions filed June 18, 2009). This decision will refer to the questions
    from the June Statement of Questions simply as “Question #,” and will refer to any
    distinctions between the questions from the January and June Statements of Questions
    as “January Question #” or “June Question #,” as necessary to minimize confusion.
    Issues That Are Moot or Otherwise Have Been Resolved
    January Question 2, regarding the project’s compliance with the provisions of
    federal regulation 
    40 CFR § 131.12
    , was not included in the June Statement of Questions.
    Accordingly, Applicants’ motions to dismiss or for summary judgment as to that
    question are moot. Question 2 from the January Statement of Questions is not an issue
    in the appeal from the amended permit, and will not be further discussed.
    January Question 13, regarding whether the project’s “plan to bury 3.1 miles of
    electricity collection cables complies with the acceptable practices in the Vermont
    Stormwater Management Manual,” was withdrawn by Appellants on May 11, 2009.
    Given that Appellants did not contest Applicants’ argument that the Stormwater
    Management Manual only applies to operational permits, and therefore does not apply
    to this construction permit, the reiteration of this question as June Question 12 seems to
    have been an inadvertent error. If it was intended to be included, summary judgment
    must be granted in favor of Applicants as to June Question 12 because Appellants have
    not put forth any evidence to contest Applicants’ factual contentions on this issue, as
    required for summary judgment.
    January Question 14, regarding whether Applicants “should be required to
    stabilize and protect from erosion and sedimentation all areas of earth disturbance
    4
    immediately in anticipation of storm events[,] and in any event within 24 hours,” was
    not included in the June Statement of Questions. Accordingly, Applicants’ motion for
    summary judgment as to that question is moot.            Question 14 from the January
    Statement of Questions is not raised as a separate issue in the appeal from the amended
    permit, and will not be further discussed.
    January Question 15 duplicated January Question 10; the June Statement of
    Questions eliminated the duplicate question and listed the issue as Question 9.
    Accordingly, any arguments originally submitted with reference to January Questions
    10 or 15 will be addressed in this decision with respect to June Question 9.
    January Question 16, regarding whether Applicants “can demonstrate that
    construction of the project will create no adverse impact to the Class III wetlands on the
    site,” as well as to all surface waters in the state, was not included in the June Statement
    of Questions. Accordingly, Applicants’ motions to dismiss or for summary judgment as
    to that question are moot. Question 16 from the January Statement of Questions is not
    an issue in the appeal from the amended permit, and will not be further discussed.
    June Question 5 (January Question 6), regarding any earth disturbance associated
    with modifications to access roads off the site, has also become moot. The off-site road
    improvements (other than improvements to Duck Pond Road along the frontage of the
    project property, which are in fact addressed in the permit) are the subject of a separate
    authorization (NOI Authorization 5535-9020.2) under General Permit 3-9020, which has
    become final without appeal, rendering Question 5 moot. Moreover, Appellants have
    not cited any section in the applicable statutes or regulations that would require off-site
    work to be covered by the same stormwater construction permit that covers the on-site
    construction work for this project.
    Prior to submission of the June Statement of Questions, while only the January
    Statement of Questions was pending, Appellants moved to amend January Question 8
    to clarify that the question related to the compliance of the project’s Erosion Prevention
    5
    and Sediment Control Plan with the state Standards and Specifications for Erosion
    Prevention and Sediment Control. The equivalent question in the June Statement of
    Questions, Question 7, contains the clarification. Accordingly, to the extent necessary,
    Appellants’ motion to amend January Question 8 is granted. However, as discussed
    above, the appeal will proceed as to the amended permit under the June Statement of
    Questions, and the Question will be addressed in this decision with respect to June
    Question 7.
    Issue Preclusion from PSB Decision
    Applicants argue that June Questions 1, 2, and 3 have been conclusively resolved
    by the Public Service Board’s (PSB) decision regarding the project’s Certificate of Public
    Good,2 and therefore those issues are barred by the doctrine of issue preclusion.
    Issue preclusion, or collateral estoppel, bars relitigation of an issue that has
    already been litigated and decided. Trickett v. Ochs, 
    2003 VT 91
    , ¶ 10, 
    176 Vt. 89
    . Issue
    preclusion is appropriate where: “(1) preclusion is asserted against one who was a party
    in the prior action; (2) the same issue was raised in the prior action; (3) the issue was
    resolved by a final judgment on the merits; (4) there was a full and fair opportunity to
    litigate the issue in the prior action; and (5) applying preclusion is fair.” In re Hartland
    Group North Ave. Permit, 
    2009 VT 92
    , ¶ 7 (citing Trickett, 
    2003 VT 91
    , ¶ 10).
    Administrative decisions, like those made by the Public Service Board, “can have
    preclusive effect in judicial proceedings when the administrative body has acted in a
    judicial capacity, resolving disputed issues of fact, and providing the parties with an
    adequate opportunity to litigate.”     In re Hartland Group, 
    2009 VT 92
    , ¶ 8 (citing
    Trickett, 
    2003 VT 91
    , ¶ 11). However, that does not hold true in this instance.
    2  On August 8, 2007, the Vermont Public Service Board, pursuant to 30 V.S.A. § 248,
    issued a Certificate of Public Good authorizing the construction of the Sheffield Wind
    Project.
    6
    Ridge Protectors, Inc. was a party to the PSB’s Certificate of Public Good
    proceedings. Although some, but not all, of the Appellants were members of or active
    in Ridge Protectors, Inc., Applicants have not shown that the parties were sufficiently
    the same or that there was a full and fair opportunity to litigate the issues raised in this
    appeal. In particular, five of the Appellants in this case were not members of Ridge
    Protectors, Inc., and therefore were not parties or members of a party before the PSB.
    Furthermore, there was not a full and fair opportunity to litigate the issues raised
    in this appeal. In particular, the applicability of the presumption of compliance found
    under 10 V.S.A. § 1246 and the overall effect that presumption has on compliance with
    the VWQS as a whole, including the anti-degradation policy, were issues not before the
    PSB.   Accordingly, Applicants motion to dismiss based on the doctrine of issue
    preclusion must be denied.
    Motion for Summary Judgment as to Question 4
    Question 4 relates to whether there will be discharges to tributaries of streams
    over 2,500 feet in elevation, and, if so, whether the application complies with the
    Vermont Water Quality Standards (VWQS)3 § 1-03(C) as to such waters, which are
    classified as Class A under 10 V.S.A. § 1253.
    The permit does not authorize any discharges above 2,500 feet in elevation. It is
    undisputed, however, that elements of the project will be constructed above 2,500 feet
    in elevation. Applicants claim that there will be no discharges into waters above 2,500
    feet despite the construction above this elevation.        However, Appellants raise a
    disputed issue of fact as to whether a discharge from the construction of a project
    3  The parties did not provide a copy of the Vermont Water Quality Standards; the
    Court has used the electronic version of the VWQS available at:
    http://www.nrb.state.vt.us/wrp/publications/wqs.pdf.
    7
    element at 2,535 feet will occur. Because this fact is disputed, summary judgment is not
    appropriate.
    Motion for Summary Judgment as to Question 6
    Question 6 relates to whether the proposed culvert replacement and the
    installation of new culverts must be reviewed as part of the application for this permit.
    The parties do not dispute that the proposed culvert replacement and installation of
    new culverts were in fact reviewed as part of the application for this permit. Question 6
    is therefore resolved in the affirmative by summary judgment.
    Motion for Summary Judgment as to Question 8
    Question 8 relates to whether the On-Site Plan Coordinator required by the
    permit should be “independent” rather than “under the control of” the Applicants. The
    Amended Permit, as well as the statute and regulations, provides for ANR inspection
    and monitoring as well as the oversight provided by the On-Site Plan Coordinator and
    the EPSC Specialist. In addition, the ANR has independent inspection and investigation
    authority under 10 V.S.A. § 8005. Appellants have not shown as a matter of law that
    requiring or allowing the On-Site Plan Coordinator to be selected by Applicants will
    cause the project to violate the VWQS.
    Motion for Summary Judgment as to Question 9
    Question 9 asks whether the permit must provide for “public involvement in
    monitoring compliance and in enforcing permit conditions.”          Appellants, like any
    members of the public, are entitled to public access to all monitoring reports and
    records. The federal statute, 
    33 U.S.C. § 1251
    (e), requires public participation in the
    “development, revision, and enforcement” of regulations, standards, effluent
    limitations, plans, and programs. It does not on its face provide for public participation
    8
    in monitoring, nor is such a provision found in state statute or regulations. Because 
    33 U.S.C. § 1251
    (e) does require public participation in enforcement, it would be up to
    other appropriate proceedings to determine if the prerequisites for a federal Clean
    Water Act citizen suit are met, in the absence of such state provisions. As in ANR v.
    Montagne & Branon, No. 291-12-07 Vtec, slip op. at 10 (Vt. Envtl. Ct Apr. 9, 2008)
    (Durkin, J.), it is not for this Court to create a provision that does not exist in state
    statutes or regulations.
    Motion for Summary Judgment as to Question 10
    Question 10 asks whether Applicants should be required to post a bond to
    ensure that remediation and restoration funds will be available in the event that
    discharge from the construction of the project results in significant damages. Unlike
    under other environmental statutes, such as Act 250,4 or the Waste Management
    statute,5 Appellants have cited no specific statutory authority under the Water Pollution
    Control statute to require a bond as a condition of permit approval.
    However, at this time it would be an impermissible advisory opinion to
    determine whether a bond could be required under the language that “the permit shall
    contain additional conditions, requirements, and restrictions as the secretary deems
    necessary to achieve compliance” with the VWQS. 10 V.S.A. § 1264(e), (h).
    Motion for Summary Judgment as to Question 3
    Under 10 V.S.A. § 1264(g)(1), “[i]n any appeal under this chapter an individual
    permit meeting the requirements of [10 V.S.A. § 1264(f), providing for, among other
    4
    10 V.S.A. § 6068(c) (“A permit may contain such requirements and conditions . . .
    including . . . the filing of bonds to insure compliance.”).
    5 10 V.S.A. § 6611(a) (operator of waste management facility “shall provide evidence of
    . . . financial responsibility” to cover remedial work upon closure of the facility).
    9
    things, best management practices or BMPs], shall have a rebuttable presumption in
    favor of the permittee that the discharge does not cause or contribute to a violation of
    the Vermont water quality standards for the receiving waters with respect to the
    discharge of regulated stormwater runoff.” Under the final sentence of § 1264(g)(1), this
    presumption only applies to permits allowing discharge into impaired waters that are
    impaired for reasons other than regulated stormwater runoff.
    Nevertheless, the presumption also applies to the permit at issue in this appeal
    by virtue of § 1264(g)(2), which applies the presumption to individual construction
    permits issued under the federal NPDES program,6 and § 1264(h), which applies the
    presumption to unimpaired waters or “waters that meet the water quality standards of
    the state.” See also Re: CCCH Stormwater Discharge Permits, Permit Nos. WQ-02-11,
    WQ-03-05, WQ-03-06, & WQ-03-07, Findings of Fact, Concl. of Law, & Order, at 27 (Vt.
    Water Res. Bd. Oct. 4, 2004).
    Under both the federal Clean Water Act and Vermont law, discharge permits
    must comply with the VWQS. See 
    33 U.S.C. § 1313
    (a); 10 V.S.A. § 1264(e)(1). The
    Vermont Water Quality Standards include an anti-degradation policy in § 1-03.7
    Vermont’s anti-degradation policy requires that “[e]xisting uses of waters and the level
    of water quality necessary to protect those existing uses shall be maintained and
    6
    However, the presumption applies to NPDES permits “only to the extent allowed
    under federal law.” 10 V.S.A. § 1264(g)(2). For example, EPA has withdrawn approval
    for a provision of the VWQS, the limited duration activity (LDA) provision, as being
    inconsistent with federal law. See Letter from Stephen S. Perkins, Director, Office of
    Ecosystem Protection, U.S. EPA, to Peter Young, Chair, Vermont Natural Resources
    Board (July 11, 2007). Under the LDA provision, certain short-term exceedances of the
    VWQS associated with construction projects were permitted. EPA “disapprove[ed] the
    LDA provision as being inconsistent with federal law . . . [because] that provision had
    the effect of allowing variances from water quality standards to be granted without the
    safeguards essential to be consistent with federal law.” Id.
    7  See 
    40 C.F.R. § 131.6
    (d) (requiring states to include “[a]n antidegradation policy
    consistent with Section 131.12,” which contains EPA’s federal policy).
    10
    protected regardless of the water’s classification.” VWQS § 1-03(B)(1). Since the VWQS
    include the state’s anti-degradation policy, the statutory presumption extends to a
    permittee’s compliance with the anti-degradation policy. See Re: CCCH at 40, n.10.
    Because the presumption applies to VWQS § 1-03, in this appeal the Appellants
    bear the burden of rebutting the presumption that compliance with the permit will
    ensure that all VWQS standards have been met, including the anti-degradation policy’s
    requirements that existing uses and water quality of the receiving waters will be
    maintained and protected. 10 V.S.A. § 1264(g), (h); Re: CCCH at 40, n.10. 8
    However, the conclusion that the presumption is applicable does not resolve the
    issue in Question 3 as to whether the baseline determination of existing uses and
    existing water quality is required, pursuant to VWQS § 1-03(B)(1). Because the waters
    receiving discharge under this permit are high quality waters, § 1-03(C) requires that
    “such waters shall be managed to maintain and protect the higher water quality and
    minimize risk to existing and designated uses.”
    8
    Section 1264(e) “requires that any permit issued for a new stormwater discharge by
    the Secretary of ANR must, at a minimum, be consistent with the 2002 [Stormwater]
    Manual, as amended from time to time, by rule.” Re: CCCH at 30. Once it is shown
    that the permit is consistent with the Manual, which sets forth BMPs that can be used
    for a project, the presumption of compliance with all VWQS is applied. Id. The parties
    have not provided the documentation showing that the Vermont Standards and
    Specifications for Erosion Prevention and Sediment Control (Vermont EPSC Standards)
    have been adopted by rule as the Stormwater Manual for the construction phase of a
    project, but the ANR, which is charged with administering this program, states that to
    be the case in its memorandum. If the Vermont EPSC Standards establish the BMPs for
    construction permits, as the 2002 Manual establishes the BMPs for operational permits,
    then consistency with the Vermont EPSC Standards for construction-phase permits
    creates the statutory presumption of compliance with all VWQS. See Vermont Agency
    of Natural Resources Opposition to Appellants’ Motion for Summary Judgment, at 12
    (Mar. 17, 2009).
    11
    While the rebuttable presumption establishes that the BMPs in place in the
    permit will achieve the requirements of § 1-03(C), that presumption can be rebutted by
    evidence brought forward by Appellants. However, an agreed or otherwise established
    benchmark of the existing uses and existing quality of the receiving waters is necessary
    against which to measure that evidence.           Such a benchmark is also necessary to
    determine during the life of the permit whether the requirements of the permit and the
    anti-degradation policy are being met. See Amended Permit, § J.
    The anti-degradation policy creates a three-tiered system of protection.          See
    § 1-03(B)–(D); Re: CCCH at 39; In re: Stormwater NPDES Petition, No. 14-1-07 Vtec, slip
    op. at 16 (Vt. Envtl. Ct. Aug. 28, 2008) (Durkin, J.); see also 
    40 C.F.R. § 131.12
    . The first
    of these, § 1-03(B), requires that existing uses of all waters be maintained and protected,
    whether the waters are impaired or unimpaired, and lays out the factors to be
    considered in making the “existing uses” determination. Section 1-03(B) allows the
    determination of existing uses to be made either on a case-by-case basis during the
    permit process or during the basin planning process.9 The third tier, § 1-03(D), protects
    “outstanding resource waters,” not applicable to this appeal.
    The second tier, found in § 1-03(C), addresses “Protection and Maintenance of
    High Quality Waters,” which are waters “the existing quality of which exceeds any
    applicable water quality criteria.” For such unimpaired waters, the anti-degradation
    policy requires that, except as provided in § 1-03(C)(2), “such waters shall be managed
    to maintain and protect the higher water quality and minimize risk to existing and
    designated uses.” § 1-03(C)(1). Section 1-03(C)(2) allows a “limited reduction in the
    existing higher quality of such waters,” under certain circumstances, but not so far as to
    jeopardize the maintenance of “the level of water quality necessary to maintain and
    protect all existing uses as well as applicable water quality criteria” required to be
    9 No party has argued that the determination of existing uses was done during a basin
    planning process in the present case.
    12
    maintained “in all cases” by the final sentence of § 1-03(C)(1).        See also In re:
    Stormwater NPDES Petition at 16.
    Thus, for such high quality waters, the plain language of the anti-degradation
    policy found in § 1-03(C) requires that the existing higher level of water quality be
    maintained, unless a § 1-03(C)(2) reduction in existing quality has been allowed. Even if
    a reduction is allowed, the plain language of the anti-degradation policy requires in all
    cases both that whatever level of higher water quality necessary to protect existing uses
    must be maintained and that the applicable water quality criteria in Chapter 3 of the
    VWQS must continue to be met.
    Section 1-03 “does not include an implementation procedure explaining how and
    under what circumstances anti-degradation review of a proposed discharge [is to] be
    undertaken.” Re: CCCH at 39. The VWQS do not define whether all discharges must
    undergo anti-degradation analysis, or “whether a distinction can be drawn between
    construction-phase and operational-phase discharges or between impaired and
    unimpaired receiving waters.”      RE: CCCH at 39–40.      Until a rule or procedure is
    adopted that clarifies how the anti-degradation policy should be implemented and to
    which types of discharges it applies,10 this Court can only determine what is required by
    the plain language of the statute and applicable regulations, including the VWQS,
    applying the recognized rules of statutory construction.
    10  The former Water Resources Board noted that “an anti-degradation implementation
    procedure . . . could help clarify when careful inventory and assessment of a receiving
    water’s existing uses and the imposition of additional terms and conditions to monitor
    and modify projects to assure compliance with all provisions of the VWQS, not just
    numerical criteria, is required.” Id. at 32 (emphasis in original). The Board expressed
    its concern over the potential “danger that water quality in . . . now un-impaired waters
    may be incrementally degraded over time if the . . . ANR relies solely on [the use of
    BMPs] to authorize additional new discharges of collected stormwater into these
    waters.” Id.
    13
    Motion for Summary Judgment as to Question 7
    Question 7 presents two separate issues. It first asks whether the Applicants’
    Erosion Prevention and Sediment Control Plan (EPSC Plan) complies with specific
    sections of the Vermont Standards and Specifications for Erosion Prevention and
    Sediment Control (Vermont EPSC Standards).11 The specific sections of the Vermont
    EPSC Standards listed in Question 7 are Section A on page 3.7, Section 3 on page 3.8,
    and Section 3.3 on pages 3.19–3.21. Material facts are in dispute, or at least have not
    been provided to the Court, to allow the Court to determine whether the EPSC Plan
    complies with the EPSC Standards, as the Standards were not provided either
    electronically or in hard copy. See footnote 11 below.
    Question 7 also asks whether, even if the EPSC Plan does meet the Vermont
    EPSC Standards, more stringent requirements should be imposed to meet the VWQS.
    Material facts are in dispute as to whether any more stringent requirements are
    necessary to meet the requirements of the VWQS. Appellants may present evidence at
    trial both directed at overcoming the presumption, and as to the merits of whether any
    more stringent requirement is necessary to meet any specific standard in the VWQS, as
    referenced in the more specific statement of Question 2 required below.
    Motion for Summary Judgment as to Question 11
    Question 11 relates to whether restrictions imposed by the permit on
    construction during the late fall/winter/spring period, which is a period defined as from
    11
    The parties did not provide a copy of the Vermont Standards and Specifications for
    Erosion Prevention and Sediment Control. The Court attempted to access an electronic
    copy available at: http://www.anr.state.vt.us/cleanandclear/erosion.htm. However, the
    link provided brings up a notification that “this page cannot be found.”
    14
    October 15 to April 15, should be extended to May 15 because of the high elevations and
    late spring snowmelt in the project area.
    Material facts are in dispute as to whether the characteristics of the project area
    warrant extending the late fall/winter/spring period restrictions of § G(2) of the
    Amended Permit and of the Erosion Prevention and Sediment Control Plan to May 15.
    Those restrictions include the potential for the Secretary to suspend or prohibit
    construction activities if such construction “is determined to present a significant risk to
    water quality.” Amended Permit, § G(2). Appellants may present evidence at trial both
    directed at overcoming the presumption, and as to the merits of whether extending this
    period to May 15 is necessary for compliance with the VWQS.
    Motions to Dismiss12 or for Summary Judgment as to Questions 1 and 2
    Appellee-Applicants are correct that the parties are entitled to “a statement of
    questions that is not vague or ambiguous, but is sufficiently definite so that they are
    able to know what issues to prepare for trial.” In re Unified Buddhist Church, Inc.
    Indirect Discharge Permit, No. 253-10-06 Vtec, slip op. at 5 (Vt. Envtl. Ct. May 11, 2007)
    (Wright, J.). Questions 1 and 2 pertaining to the Amended Permit are more specific
    than the corresponding questions relating to the original permit, but they are still too
    broad to allow the parties to prepare for trial.
    On the other hand, to the extent that Questions 1 and 2 encompass the issues
    raised in the other questions in the Statement of Questions, material facts are in dispute
    at the present time to preclude summary judgment, except as to the following legal
    issue embedded in Appellants’ Motion for Summary Judgment regarding the turbidity
    12
    Applicants initially moved to dismiss January Questions 1, 2, 3, 4, and 16; January
    Questions 2 and 16 are no longer at issue in the present appeal. Therefore, only June
    Questions 1, 2, and 3 (formerly January Questions 1, 3, and 4) remain. Question 3 was
    addressed earlier in this decision.
    15
    standard in § 3-04(B)(1).       Appellants have conflated the Amended Permit’s 25
    nepholometric turbidity units (NTU) limit for stormwater as it leaves the construction
    site with the § 3-04(B)(1) in-stream limit of 10 NTU. It will be for trial to determine
    whether or not the action level set for the runoff at the construction site is sufficient to
    achieve the in-stream turbidity standard.
    Question 1 raises the project’s compliance with 10 V.S.A. §§ [1251],13 1263, and
    1264.    From the totality of the filings submitted by Appellants, the Court cannot
    determine that Appellants actually challenge any aspects of the proposal’s compliance
    with the Water Pollution Control statute, other than as raised by the more specific
    Questions 3 through 12, which have been addressed above. Accordingly, on or before
    October 9, 2009, Appellants shall file a more specific statement of Question 1, stating
    specifically if the issues raised as to the project’s compliance with the three statutory
    sections are limited to those raised by the other questions in the Statement of Questions.
    Question 2 raises the project’s compliance with §§ 1-02, 1-03, 1-04, 3-01, 3-02, and
    3-04 of the VWQS. From the totality of the filings submitted by Appellants, the Court
    cannot determine that Appellants actually challenge any aspects of the proposal’s
    compliance with §§ 1-02, 1-03, or 1-04, other than as raised by the more specific
    Questions 3 through 12, which have been addressed above. As to the Water Quality
    Criteria found in §§ 3-01, 3-02, and 3-04, many of those criteria are inapplicable to the
    present proposal, but it is up to Appellants to specify which, if any, are the subject of
    the appeal. It is not for the Court or the other parties to make assumptions about which
    ones are of concern. Accordingly, on or before October 9, 2009, Appellants shall file a
    more specific statement of Question 2, stating specifically if the issues raised as to the
    project’s compliance with §§ 1-02, 1-03, and 1-04 are limited to those raised by the other
    questions in the Statement of Questions, and, stating with specificity the subsections of
    13   There is no § 1250; § 1251 contains the statutory definitions.
    16
    §§ 3-01, 3-02, and 3-04 that are asserted to be at issue in this appeal, and on which
    Appellants propose to present evidence.
    Appellee-Applicants’ motions to dismiss Questions 1 and 2 are DENIED at this
    time, with leave to renew after the more specific filings have been made.
    Accordingly, based on the foregoing, it is hereby ORDERED and ADJUDGED as
    follows:
    As discussed above, January Questions 2, 14, and 16, and June Questions 5 and
    12, are moot. Appellee-Applicants’ motions to dismiss Questions 1 and 2 are DENIED
    at this time, with leave to renew, as discussed above.
    Summary judgment is DENIED as to Questions 1, 2, 4, 7, and 11, as material facts
    are in dispute. Summary judgment is DENIED as to Question 10, as it calls for an
    impermissible advisory opinion in the present posture of the case.
    Summary judgment is GRANTED to both parties as to Question 6, in that the
    proposed culvert replacement and the installation of new culverts must be reviewed as
    part of the application for this permit, but also that the proposed culvert replacement
    and the installation of new culverts have in fact been reviewed in connection with the
    application for this permit.
    Summary judgment is DENIED to Appellants, and is GRANTED to Appellee-
    Applicants, as to Questions 8 and 9.
    Summary judgment is GRANTED in part to Appellee-Applicants as to Question
    3, in that the rebuttable presumption of compliance with the VWQS applies to the anti-
    degradation policy components of the VWQS, but is GRANTED in part to Appellants as
    to Question 3, in that the existing uses, and the existing water quality (if higher than the
    VWQS), must be established in this case for the receiving waters at issue in this permit.
    Please be prepared to discuss at the scheduled conference this task and whether any
    facts are in dispute as to it.
    17
    This matter is set for trial on October 15 and 16, to continue on November 5 if
    necessary. Given those trial dates, ordinarily the Court would give the parties until
    approximately November 17 to file requests for findings and memoranda of law, and,
    given the Thanksgiving weekend, would give the parties until approximately December
    1 to file any responses. Appellants have moved to extend the trial dates due to the
    timing of this decision on the pending motions.        That motion will be argued and
    decided at the conference now scheduled for October 5 (see enclosed notice).
    If the trial dates are extended, the Court will establish a schedule to avoid any
    corresponding delay in the issuance of the Court’s decision, by requiring the parties’
    requests for findings and memoranda of law to be filed by November 17, and by
    requiring any responses and supplemental requests to be filed by December 1 or by
    three business days after the final trial date, whichever occurs later. At the conference
    already scheduled for October 5, 2009, the parties should be prepared to discuss the
    following dates, which are available in the Court’s schedule: November 5 (already
    scheduled), 12*, 13, 19, and 20*, and December 2, 3, 4, 8, 9, and 10. The Court recognizes
    that the dates in November marked with an asterisk were not available in certain of the
    parties’ calendars as of the date the trial was originally scheduled, but has listed them
    for the parties’ information as being available in the Court’s schedule.
    Please be prepared to discuss which dates are available for specific witnesses, as
    the Court may schedule specific dates for witnesses on specific topics, including the use
    of some of the originally scheduled trial dates if appropriate. By the time of the October
    5 conference, the Court should be able to advise the parties as to which of those dates
    are available in St. Johnsbury and which are available in Berlin.
    Done at Berlin, Vermont, this 29th day of September, 2009.
    _________________________________________________
    Merideth Wright
    Environmental Judge
    18