Dover Watch Timeshare Project ( 2007 )


Menu:
  •                                   STATE OF VERMONT
    ENVIRONMENTAL COURT
    }
    In re: Dover Watch Timeshare Project               } Docket No. 103-5-06 Vtec
    (Appeal of Dover Watch Owners Association) }
    }
    Decision and Order on Cross-Motions for Summary Judgment
    Appellant Dover Watch Owners Association, Inc., (Appellant Association) appealed
    from a decision of the Development Review Board (DRB) of the Town of Dover dated April
    20, 2006, upholding the Zoning Administrator’s decision that a municipal zoning permit
    is required for the work Appellant Association wishes to complete on the time share
    (interval ownership) project known as Dover Watch. Appellant Association, involving
    more than 300 purchasers of time shares in the project, is represented by Eric J. Anderson,
    Esq.; the Town is represented by Joseph S. McLean, Esq.
    Both parties have moved for summary judgment.              The following facts are
    undisputed1 unless otherwise noted.
    Appellant Association seeks to complete construction on one partially-completed
    building and to construct additional2 four-unit buildings in a time share (interval
    1
    It has been unduly difficult for the Court to determine the present scope of the
    project itself, as well as to determine the scope of the project that had been approved as of
    the adoption of zoning in Dover in 1988, because the parties have provided only the most
    recent of the many Act 250 permits or permit amendments applicable to this project, and
    have provided none of the permit applications. The one Act 250 permit decision supplied
    by the parties, the District 2 Environmental Commission’s Memorandum of Decision in
    #2W0543-R1N(Altered), issued on January 5, 2006, attached to the parties’ Stipulated Facts
    as Exhibit D, assumes knowledge of the prior history of the permit and the underlying facts
    not provided to this Court.
    2
    The Court cannot determine from the materials supplied whether Appellant
    Association wishes to construct a total of 52 units in 13 four-unit residential buildings,
    1
    ownership) project now known as Dover Watch, on property located northerly of Country
    Club Road in West Dover. The project was started by Appellant Association’s predecessor-
    in-interest, Eugene Ettlinger, and/or by corporations in which he had an interest. It appears
    that Appellant Dover Watch Owners Association is in continued litigation3 with one of
    those corporations,“Dover Watch at Mt. Snow, Ltd.,” over ownership of all or part of the
    project property.
    The parties have not provided any of the Act 2504 decisions or permits applicable
    to the property other than the most recent one issued in January 2006, ruling on a motion
    to alter regarding the scope of the –R1N decision which had been issued in November of
    2005. Accordingly, any of the permit history of this project as described in this decision
    derives from that decision or from the one Environmental Board decision on the project5
    available from the Natural Resources Board website.
    Mr. Eugene Ettlinger first applied to the District Commission in early 1982 for an Act
    250 permit to construct 96 two-bedroom residential units on 16.2 acres of land. After test
    wells had been dug on an adjacent 53.8-acre parcel, which were planned to provide a water
    including the existing buildings, or to construct a total of 88 units in 22 four-unit residential
    buildings, including the existing buildings, nor which non-residential buildings (such as
    a pool building and an administration building) are included in Appellant Association’s
    concept of the project.
    3
    The Court recognizes the parties’ frustration stemming from the delays in the
    Dover Watch time share project that may be related to this litigation; however, all that is
    before this Court in this appeal is the municipal zoning status of the project.
    4
    The Act 250 permit status of the project is relevant to the provisions of the Zoning
    Bylaw related to whether and when a project may be grandfathered.
    5
    In re: Eugene Ettlinger (Tara Interval), Land Use Permit #2W0543-EB, Findings of
    Fact, Concl. of Law and Order (Vt. Envtl. Bd., Dec. 8, 1982), available at
    http://www.nrb.state.vt.us/lup/decisions.htm
    2
    supply for the proposed project, a Vermont corporation controlled by Mr. Ettlinger
    (Environmental Consultants, Inc.) purchased the adjacent 53.8-acre parcel. However,
    neither the public notice of the Act 250 permit proceedings nor the permit application was
    amended to include the additional involved land. In September of 1982, the District
    Commission issued Act 250 Permit #2W0543 to Mr. Ettlinger to construct the 52 two-
    bedroom units in 13 buildings, and gave “conceptual” approval for the entire project,
    described as 88 two-bedroom units in 22 buildings. However, due to the lack of notice of
    the additional 53.8-acre parcel of “involved land,” a neighboring landowner appealed to
    the Environmental Board, which vacated the permit and remanded the application due to
    that lack of notice.
    Thus, the first valid Act 250 Permit for the project was #2W0543–R1, issued by the
    District Commission in early 1983 (the 1983 Act 250 Permit) for the construction of 13 four-
    unit buildings containing 52 two-bedroom units, as well as the conversion of what seems
    to have been an existing 40' by 40' building on the property for use as an “administration
    building.” The parties have not supplied sufficient information to determine whether this
    original Act 250 Permit contemplated the buildings on a 16.2-acre parcel, with some
    provision for water supply on the adjacent parcel of involved land, or whether the project
    property ever merged to consist of a 70-acre parcel of land. Nor can the Court determine
    from the documents that have been supplied whether the 1983 Act 250 Permit discussed
    “conceptual” approval for any additional buildings beyond the initial thirteen.
    By some time in the 1980s, three of the thirteen four-unit buildings authorized by
    Act 250 Permit #2W0543–R1 were completed. The parties have not provided any of the
    applications to or decisions of the District Commission prior to the –R1N decision issued
    in January of 2006; that decision outlines the permitting history of the project as it pertained
    to the issues in the then-motion to alter, and does not mention the –R1B, –R1C, –R1D,
    –R1G, or –R1I amendments. However, it appears from the description of the Act 250
    3
    permitting history in that decision that on November 10, 1988, the –R1E Act 250 Permit
    extended the construction completion date to October 1, 1990 for the entire project, the last
    extension decision that addressed the entire project as originally permitted. On May 31,
    1988,6 the – R1F Act 250 Permit first approved the construction of the pool building; it was
    to be completed by October 15, 1989.
    When the project obtained the 1983 Act 250 Permit, the Town of Dover had not yet
    adopted a zoning bylaw. It may have adopted an interim bylaw in April7 of 1988; in any
    event it adopted a zoning bylaw effective on November 8, 1988 (the 1998 Zoning Bylaw8).
    The project property appears to be located9 in the Valley Walls (District C) zoning district.
    In this district, under the 1988 Zoning Bylaw, a multiple-unit residential project was a
    permitted use if applied for as a Planned Residential Development (PRD) subject to the
    requirements of Article 6 of the Zoning Bylaw.          §330.   However, for any Planned
    Residential Development, §620(B) limited its overall density to the number of residential
    units that would be permitted if the land were subdivided into lots in accordance with the
    zoning requirements for the particular zoning district. If the project had been a PRD on 16
    6
    If the -R1E Act 250 Permit date of November 10, 1988 is correct, then this date for
    the subsequent -R1F Act 250 Permit is probably May of 1989 rather than 1988. This
    discrepancy may easily be checked from the records of the District Commission, but has
    not been provided to the Court in connection with the present motions.
    7
    This is suggested by the fact that April 1988 rather than (or as well as) November
    1988 dates appear in the grandfathering-related sections of the Zoning Bylaw.
    8
    The Zoning Bylaw was subsequently amended in 1992, 1993, 1994 and in 1996;
    however, neither party suggests these later amendments were pertinent to the issues in this
    appeal.
    9
    The parties have not provided any indication as to the zoning district of the
    property, except to argue that the project would not now qualify for a zoning permit due
    to the one-unit-per-five-acres density required in the district; the Valley Walls (District C)
    zoning district is the only one with a five-acre density, which is the same in the 1988 and
    the 2005 Zoning Bylaw.
    4
    acres, it would have been limited to three residential units (or, if on 70 acres, it would have
    been limited to fourteen residential units).
    Section 202 of the 1988 Zoning Bylaw provided that any “construction started prior
    to April 26, 1988 may be completed as long as it is a permitted use within the District
    without obtaining a Zoning Permit,” provided that the property owner complies with all
    other applicable permits and files a site plan showing the location of the proposed
    structures, a sketch showing their height, a statement of the proposed use, and proof that
    construction was started prior to November10 1988. Because the 1988 Zoning Bylaw would
    not have allowed the proposed 52-unit project as a permitted use (that is, as a PRD), the
    original project would not have qualified for this exemption.
    Section 150 of the 1988 Zoning Bylaw provided that if “modifications are to be made
    to a valid Act 250 . . . permit which was issued before April 26, 1988, which change the
    design or specification of the original project, a zoning permit shall be required if any of the
    following criteria are met.” The six criteria in §150 cover circumstances in which the
    changes to the project (1) reduce any distance to the nearest road, property boundary or
    stream; (2) increase the height of any building or structure; (3) increase the footprint of a
    structure; (4) increase the square footage of a structure; (5) create additional dwelling or
    commercial units, buildings or accessory structures; or (6) create additional lots.
    Construction on a fourth project building known as “Quad-IV” must have been
    commenced and partially completed at some time prior to March of 1993,11 as on March 15,
    1993, the –R1H Act 250 Permit extended the construction completion date for the Quad IV
    building to October 1, 1995. In the application for that extension the then-applicant stated
    10
    See footnote 7, above.
    11
    If the parties know when that building was commenced in relation to the April
    26, 1988 date used in §150 of the 1988 Zoning Bylaw, they have not provided that
    information to the Court in connection with the present motions.
    5
    that the Quad IV building “is standing; exterior covered; roof, windows and doors in
    place” and that “90% of the firewall” between the four townhouses was in place. On
    September 13, 1993, the –R1J Act 250 Permit extended the construction completion date for
    Buildings 5 and 6 to October 1, 1995; however, there is no indication that construction on
    either of these buildings was commenced prior to the expiration of the extended 1995 date
    or that any further extension was sought for either of these buildings.
    On November 5, 1996, the –R1K Act 250 Permit extended the construction
    completion date for the Quad IV building to October 1, 2000. The –R1L Act 250 Permit
    extended the construction completion date for the pool building to October 15, 2000. On
    April 23, 2001, the –R1M Act 250 Permit extended the construction completion date for the
    both the Quad IV building and the pool building to October 15, 2005.
    On November 22, 2005, the –R1N(Altered) Act 250 Permit extended the construction
    completion dates for the Quad IV building and the pool building to October 15, 2008. On
    January 5, 2006, the District Commission denied Appellant Association’s motion further
    to alter that decision, which appears to have requested a ruling that the –R1N extension
    application was meant to apply to “the original 52-unit project.”
    The total possible number of unit weeks for the sixteen units in the four completed
    (or partially-completed) buildings is 832 (computed as sixteen units x 52 weeks/year).
    Appellant Association acquired 220 of these unit weeks of the time share project in 2004
    through a foreclosure action in Windham Superior Court against the corporation, Dover
    Watch at Mt. Snow, Ltd.12 The partially-completed Quad-IV building is reported by
    12
    The action was originally filed against Mr. Ettlinger as well as the corporation, but
    in the Judgment, Order and Decree of Foreclosure (Revised) entered by the Windham
    Superior Court in Docket No. 381-8-03 WmC on January 8, 2004, Mr. Ettlinger’s name was
    deleted from the caption and the text. The minutes of the DRB meeting as described in the
    DRB decision on appeal reflect some disagreement between Appellant Association’s
    attorney and the corporation’s attorney as to the ownership of the undeveloped land.
    6
    Appellant Association to be in a state of considerable disrepair; nevertheless, “dozens” of
    time share unit weeks have been sold for units in that building.
    Appellant Association seeks to complete the time share project as originally
    proposed, although the Court cannot determine whether the project which Appellant
    Association seeks to complete consists of a total of 52 units in 13 buildings on a 16.2 parcel
    of land, or a total of 96 units (twenty additional four-unit buildings), or whether it is on a
    total of 70 acres of land.
    Effective October 25, 2005,13 the Town again amended its Zoning Bylaw. The 2005
    Bylaw amendments eliminated §§150 and 202. Section 130 of the 2005 Bylaw provides that
    the Zoning Bylaw “is not intended to repeal, annul or in any way impair any State or local
    regulations, [or] valid permits (including Act 250 and existing subdivisions as defined in
    10 V.S.A. Section 6081) previously adopted or issued.”
    In the present proceeding Appellant Association asked the District Commission to
    alter the discussion section of its November 22, 2005 decision in -R1N (Altered) “to
    recognize that Applicant needs to have the completion date for the entire project extended
    and not simply the completion date for Quad IV and the pool building.” District 2
    Environmental Commission Memorandum of Decision in #2W0543-R1N(Altered) (January
    5, 2006) at p.2. In its January 5, 2006 Memorandum of Decision, the District Commission
    concluded that Appellant Association had not abandoned the Act 250 permit and permit
    amendments for the partially completed “Quad-IV” building or the pool building; that
    completion of those two buildings does not require further review under Act 250; that the
    remainder of the project requires a new Act 250 application and review under the Act 250
    criteria, because the last amended construction completion date has “long since” expired
    13
    Effective July 1, 2004, 24 V.S.A. §4449(d) provided that amended zoning
    regulations are to be applied as of the date on which they are proposed. The date on which
    the 2005 Zoning Bylaw was proposed for public comment has not been provided to the
    Court.
    7
    and circumstances may have changed; and that, if Appellant Association wished to extend
    the construction completion date for the entire project, it would need to file a new Act 250
    application addressing changes in circumstances, changes in the proposed project, and the
    Act 250 criteria. That decision stated that the “only portions of the project [other than the
    three completed buildings] which still have a valid, unexpired construction completion
    date are the pool building and Building Quad IV (Units 13 – 16).”
    On February 5, 2006, Appellant Association’s architect wrote to the Zoning
    Administrator to request a letter confirming that the property “as approved” in the 1983
    Act 250 Permit is “grandfathered” under the Zoning Bylaw. The Zoning Administrator’s
    response stated that “the Dover Watch project is not ‘grandfathered’ under the Town of
    Dover’s Zoning Bylaw in a manner that would exempt it from obtaining local zoning
    approvals for any new land development.” Appellant Association appealed the Zoning
    Administrator’s decision to the DRB, which issued a decision on April 20, 2006 upholding
    the Zoning Administrator’s decision that a zoning permit is required. This de novo appeal
    followed.
    Appellant Association seeks a determination that the project “as approved” by the
    1983 Act 250 Permit “is still allowable” under the municipal Zoning Bylaw. At the outset,
    we note that any construction or development not addressed in the 1983 Act 250 permit is
    beyond the scope of this appeal.
    As the Zoning Administrator’s and DRB’s decision also implicitly recognized,
    construction of elements of the project approved in the 1983 Act 250 permit was
    grandfathered for whatever construction or site work was begun before the Town’s
    adoption of its first Zoning Bylaw in 1988, under the vested rights doctrine, and may be
    completed without the need for a new zoning permit unless by lapse of time it is
    considered to have expired or been abandoned under the Zoning Bylaw applicable at the
    8
    time. (See §§ 250 and 255 of the 1988 Zoning Bylaw). See, generally, discussion of vested
    rights doctrine in In re Jolley Associates, 
    2006 VT 132
    , and in In re Appeal of Taft Corners
    Associates, Inc., 
    171 Vt. 135
    , 139–144 (2000). The elements of the project in this category
    include the three completed buildings, assuming construction on them began before the
    date of the first interim Zoning Bylaw (which may be April 26, 1988) and may also include
    the partially completed Quad-IV building, if construction on it was begun before the
    applicable date.
    Construction of elements of the project approved in the existing Act 250 permit,
    which did not require a modification of the then-existing Act 250 permit and which was
    begun between April 26, 1988 and the date on which the 2005 Zoning Bylaw was proposed
    for public comment, is also grandfathered under the terms of §150 of the prior Zoning
    Bylaw. It may also be completed without the need for a new zoning permit, unless by lapse
    of time it is considered to have expired or been abandoned. The partially completed Quad-
    IV building may fall within this category if construction on it was begun between the stated
    dates.
    Construction of elements of the project which required a modification of the then-
    existing Act 250 permit, if that modification was applied for between April 26, 1988 and the
    date on which the 2005 Zoning Bylaw was proposed for public comment, needs a zoning
    permit under §150 of the prior Zoning Bylaw, regardless of the fact that §150 was later
    repealed. Construction of the pool building appears to have required a modification of the
    existing Act 250 permit; if that modification was sought between the stated dates (see
    footnote 6, above), then the pool building may fall within this category and will require a
    zoning permit.
    Finally, construction of any element of the project which was not begun prior to the
    date on which the 2005 zoning bylaw was proposed, but which was permitted under a
    then-valid Act 250 permit, is not grandfathered, but must be analyzed under § 130 of the
    9
    2005 Bylaw. It will require a zoning permit even if it has a valid Act 250 permit, and, if it
    is proposed as a PRD, may also require conditional use approval and site plan approval
    under the current Zoning Bylaw.
    Accordingly, based on the foregoing, it is hereby ORDERED and ADJUDGED that
    the Town’s Motion for Summary Judgment is GRANTED in PART, in that Appellant
    Association must obtain local zoning approval for the construction of any structure which
    was not begun prior to the date on which the 2005 zoning bylaw was proposed and for the
    construction of any structure which required a modification of the then-existing Act 250
    permit, if that modification was sought after April 26, 1988. Appellant Association’s
    Motion for Summary Judgment is GRANTED in PART, in that local zoning approval is not
    necessary for the completion of any structure upon which construction was begun before
    April 26, 1988, or for any construction or development approved in the Act 250 permit
    which was begun between the stated dates that did not require a modification of the
    existing Act 250 permit.
    A telephone conference has been scheduled (see enclosed notice) to discuss whether
    any issues remain for a hearing on the merits of this appeal, and to discuss whether any of
    the information not provided to the Court is nevertheless undisputed.
    Done at Berlin, Vermont, this 19th day of April, 2007.
    _________________________________________________
    Merideth Wright
    Environmental Judge
    10
    

Document Info

Docket Number: 103-05-06 Vtec

Filed Date: 4/29/2007

Precedential Status: Precedential

Modified Date: 4/24/2018