Brisson Subdivision Application ( 2007 )


Menu:
  •                                  STATE OF VERMONT
    ENVIRONMENTAL COURT
    }
    In re: Brisson Subdivision Application   }       Docket No. 198-9-05 Vtec
    (Appeal of Call)                 }
    }
    Decision and Order on Pending Motions
    Appellant Elizabeth Call appealed from a decision of the Planning Commission of
    the Town of Weybridge, granting approval to Appellee-Applicants Armond and Ramona
    Brisson of an 8-lot1 subdivision. Appellant is represented by Andrew Jackson, Esq.;
    Appellee-Applicants Brisson are represented by Eben Punderson, Esq. The Town of
    Weybridge did not enter an appearance in this matter. or ck if it was in through ZA
    This appeal was placed on inactive status by agreement of the parties while litigation
    proceeded in Addison Superior Court regarding the scope of an easement also at issue in
    the present subdivision appeal. The Addison Superior Court case was resolved in favor
    of Appellee-Applicants Brisson, and has been appealed to the Supreme Court. On June 1,
    2007, trial was scheduled in the above-captioned appeal for Thursday, November 8, 2007,
    at the Addison Superior Court, in the Mahady Courthouse in Middlebury. A revised
    stipulated discovery and trial preparation schedule was entered as a scheduling order by
    the Court.
    Appellant had initially filed a Statement of Questions containing four questions cast
    in terms of whether the Planning Commission had acted properly or within its authority.
    After a telephone conference in early 2007 at which the parties discussed with the Court
    1
    The proposal consists of seven building lots, labeled as Lots 8 through 14 on the
    plans, and the remaining land, labeled as Lot 1, which appears to include the project
    roadway and utility easements. All of the proposed development is located in the Town
    of Weybridge, some of Lot 1 is located in the Town of New Haven.
    1
    the de novo nature of these proceedings, Appellant filed a revised Statement of Questions
    reading in full as follows:
    1)    Does the specific application for subdivision submitted by [Appellee-
    Applicants], which proposes a multi-unit residential housing development
    without road frontage, meet the requirements of the Weybridge zoning and
    planning ordinances or regulations with no direct access to a town highway
    and which claims only access over a right of way on the property of
    [Appellant].
    2)    Does the application for subdivision submitted by [Appellee-
    Applicants], which proposes a multi-unit residential housing development
    without road frontage provide adequate protection for safety, visual and
    auditory issues created by approval of the right of way?
    Appellee-Applicants moved in limine that the Court’s review of the subdivision
    application be limited to the right-of-way and not to the subdivision generally. The Court
    ruled orally that Question 2 is limited to the effect of the right-of-way for the subdivision
    on the “safety, auditory and visual” issues stated in that question, but that because
    Question 1 was cast in terms of whether the application meets the requirements of the
    regulations, it potentially went beyond issues related to the right of way. However,
    Appellant was required to provide a more definite statement of Question 1, as it was not
    possible to tell from that Question what defects Appellant asserted in the application.
    V.R.E.C.P. 5(f)
    In this de novo proceeding, the Court sits in place of the Planning Commission to
    consider this subdivision application, but only on the issues properly raised by the
    Appellant in the Statement of Questions. V.R.E.C.P. 5(f) (“a statement of the questions that
    the appellant desires to have determined”); 10 V.S.A. § 8504(h) (“on those issues which
    have been appealed”). It has been difficult to determine what issues Appellant seeks to
    contest in this matter, based on Appellant’s various filings.
    Appellant’s April 30, 2007 filing after the Court required a more definite statement
    of Question I provided an extensive list of deficiencies in the application asserted by
    2
    Appellant. That is, Appellant’s revised Question I continues to challenge whether the
    application materials (including the proposed subdivision plat) are adequate under many
    listed sections of the Subdivision Regulations relating to the preliminary application (§ 300)
    and final plat (§ 310) for the subdivision, and the planning and design standards applicable
    to the subdivision from Article IV.
    Appellant’s Question 1 originally related to Appellant’s asserted deficiencies in the
    subdivision application; as revised it continues to be stated in terms of asserted lack of
    information and asserted deficiencies in the application materials, including in the
    proposed subdivision plat itself. Accordingly, Appellee-Applicants’ Motion to Dismiss
    those portions of revised Question 1 unrelated to deficiencies in the application is
    GRANTED. On or before October 11, 2007, the parties shall file with the Court either an
    agreed redacted version of Question 1 or, if they cannot agree, shall each file their own
    proposed redacted version of Question 1. Appellee-Applicants’ renewed Motion in Limine
    to limit Question 1 only to the right-of-way is DENIED.
    Of course, because the application is being considered de novo by the Court, we do
    not yet have before us the application materials and the final subdivision plat for which
    Appellee-Applicant is seeking approval. If they had been submitted in connection with a
    motion for summary judgment, it is possible that many of the subsections of Question I
    could have been determined prior to trial.
    Therefore, under the circumstances, the trial will commence as usual with Appellee-
    Applicant’s presentation of the application to the Court, including any cross-examination
    of Appellee-Applicant’s witnesses. At the close of Appellee-Applicant’s case, we will
    expect the parties to confer and report to the Court as to whether any of the subsections of
    Question I are no longer at issue, based on the application and subdivision plan as
    presented at trial, and to make any related motions orally on the record, before proceeding
    to hear the remainder of the evidence to be presented by Appellants’ witnesses.
    3
    From the materials provided by the parties in connection with their motions, it
    appears that the Planning Commission had before it, during its hearings on the subdivision
    application, a “sketch plan,” dated February 11, 2005, and, later, a revised “preliminary
    plat,” dated April 11, 2005, and that all it considered was the application for the proposal
    as a “major subdivision.” Although Appellee-Applicant referred to the proposal, in the
    narrative attached to the subdivision application, as a “PRD-style” subdivision, the parties
    have not claimed that the Planning Commission ruled on the application as a PRD, or that
    it conducted site plan approval analysis as a PRD. See, generally, §305 of the Zoning
    Regulations. Moreover, the original subdivision application represents that the project will
    also require Act 250 approval and a permit for the water supply and wastewater disposal
    systems from the Agency of Natural Resources. Although many if not most applicants
    prefer to have a single trial in Environmental Court covering all appeals of all necessary
    state and local approvals, it is entirely up to the applicant whether to proceed first on only
    a single required local application.
    The trial remains scheduled for November 8, 2007. Accordingly, in the pretrial
    conference now scheduled for October 18, 2007 (see enclosed notice), the parties should be
    prepared to discuss their understanding that the trial will only cover the application for
    subdivision approval as a major subdivision, and that the Court does not now have
    jurisdiction of any appeals of applications for PRD approval, site plan approval, Act 250
    approval or ANR permit approval.
    Done at Berlin, Vermont, this 4th day of October, 2007.
    _________________________________________________
    Merideth Wright
    Environmental Judge
    4
    

Document Info

Docket Number: 198-09-05 Vtec

Filed Date: 10/4/2007

Precedential Status: Precedential

Modified Date: 4/24/2018