Secretary, Vermont Agency of Natural Resources v. Thomas L. O'Brien and Nancy J. O'Brien (Decision and Order on Motion to Reconsider Decision Denying Request for Jury Trial) ( 2002 )


Menu:
  •                                      STATE OF VERMONT
    ENVIRONMENTAL COURT
    Secretary, Vermont Agency of
    Natural Resources, Plaintiff       }
    }
    v                                  } Docket No. 166-8-02 Vtec
    }
    Thomas L. O= Brien and Nancy       }
    J. O= Brien, Respondents.
    Decision and Order on Motion to Reconsider Decision Denying Request for Jury Trial
    Respondents are represented by Jack Long, Esq.; the Secretary of the Agency of Natural
    Resources is represented by Gary Kessler. Respondents have moved the court to reconsider its
    denial of Respondents= request for a jury trial. This decision and order reiterates portions of the
    earlier order for the convenience of the parties, as well as addressing Respondents= new
    arguments.
    First, the Court recognizes that Respondents= request is based in the Vermont Constitution;
    nevertheless, federal cases as well as cases from Vermont and from other states can assist the
    Court in applying the Vermont Constitution= s guarantee of jury trial for issues of A fact, proper
    for the cognizance of a jury.@ Indeed, Respondents= original memorandum relied on Tull v.
    United States, 
    481 U.S. 412
     (1987) for that very purpose, as did State v. Sears, Roebuck &
    Company, No. S471-83 (Vt., Wash. Sup. Ct., Mar. 26, 1984), cited by Respondents in support of
    their motion.
    The analysis of whether a jury trial is required for any portion of this case must begin with a look
    at the administrative process established by the legislature for this proceeding. The Uniform
    Environmental Enforcement Act (10 V.S.A. Chapter 201), authorizing the Administrative Order
    issued to Respondents, is distinct from 10 V.S.A. ' 8221, which provides for civil penalties and
    equitable enforcement in superior court, and is also distinct from the various criminal penalties
    preserved by 10 V.S.A. ' 8003(b). Chapter 201 of Title 10 created a new system of
    administrative orders, which may include monetary penalties, to be issued in the first instance by
    the Secretary of the Agency of Natural Resources.
    The Uniform Environmental Enforcement Act provided for prompt judicial review of these
    administrative orders in the then-newly-created Environmental Court, upon request of a
    respondent or the Attorney General. 10 V.S.A. ' 8012. The scope of that review is de novo with
    respect to a penalty amount. See, e.g., Vermont Agency of Natural Resources v. Duranleau, 
    159 Vt. 233
     (1992). However, with respect to remedial orders issued under ' 8008(5), the Court= s
    authority is more limited, so that certain types of remedial orders must be remanded to the
    Agency as opposed to being modified by the Court. See 10 V.S.A. ' 8012(b)(2) and (b)(3).
    The Administrative Order issued by the Agency to Respondents imposed a monetary penalty,
    and also required Respondents to perform remedial work. 10 V.S.A. ' 8008. Respondents do not
    contest the fact that a violation or violations occurred, and Respondents do not request a jury trial
    with respect to the remedial work required by the Administrative Order. They argue that they are
    nevertheless entitled to a jury trial with respect to A all issues associated with the penalty phase of
    the action,@ characterizing the penalty as an action for A the collection of civil penalties,@ and
    citing Hodgdon v. Mt. Mansfield Co., 
    160 Vt. 154
     (1992) and State v. Sears, Roebuck &
    Company, No. S471-83 (Vt., Wash. Sup. Ct., Mar. 26, 1984). See the Seventh Amendment to the
    U.S. Constitution; and Chapter I, Article 12 and Chapter II, Article 38 of the Vermont
    Constitution.
    However, the administrative order was not an action for the > collection= of civil penalties that
    can be reduced to a defined amount, and is therefore was not equivalent to an action > in debt=
    and known at the common law (as contrasted with the equitable action formerly known as >
    assumpsit= ). Nor is it analogous to a nuisance action, nor are damages available.
    An action by a private party (or by a state on behalf of a private party) to enforce a private right,
    by suing to recover damages or a defined amount of statutory civil penalty, may require a jury
    trial if it can be seen as an action sounding in debt and therefore one of a type > known at the
    common law,= as discussed by the Vermont Supreme Court in Hodgdon, by the U.S. Supreme
    Court in Tull v. United States, 
    481 U.S. 412
     (1987) and Granfinanciera, S.A. v. Nordberg, 
    492 U.S. 33
     (1989), by the Superior Court in State v. Sears, Roebuck & Company, No. S471-83 (Vt.,
    Wash. Sup. Ct., Mar. 26, 1984), and by the Rhode Island court in Bendick v. Cambio1, 
    558 A.2d 941
     (R.I. 1989).
    However, in contrast to the statutes discussed in those cases, Vermont= s Uniform Environmental
    Enforcement Act presents a distinctly different sort of statutory scheme, in which the existence
    of the violation (liability) and the penalty amount, as well as any remedial action, are first
    determined by administrative agency action. Only if a respondent requests a hearing are these
    issues even brought before the court, where they are then subject to judicial review. Once the
    penalty issue is before the court, the court must perform a discretionary determination of the
    amount of penalty de novo, by applying the eight equitable criteria laid out in the statute. 10
    V.S.A. ' 8010(b); and see also ' 8001. Even in Tull v. United States, 
    481 U.S. 412
     (1987), in
    which the statute did not assign the matter in the first instance to an administrative body, and in
    which a majority of the Court held that a jury trial was required to determine liability, the Court
    reiterated that the trial judge, sitting without the jury, should make the discretionary
    determination of the amount of civil penalty.
    In Granfinanciera, S.A. v. Nordberg, 
    109 S. Ct. 2782
    , 2795 (1989), the U.S. Supreme Court
    followed its decision in Atlas Roofing Co. v. Occupational Safety and Health Review Comm'n,
    
    430 U.S. 442
    , 454-55 (1977) that Congress may create new statutory public rights and assign
    their adjudication to tribunals without authority to conduct jury trials, without violating the
    constitutional requirement that jury trial be preserved. If the new statutory cause of action
    inheres in or lies against the government in its sovereign capacity and involves public rights, the
    legislature may provide an administrative scheme for its initial adjudication, and may provide for
    judicial review of that action in a judicial branch court without a jury trial. See, e.g.,; Texas Ass=
    n of Business v. Texas Air Control Board, 
    852 S.W.2d 440
    , 449-50 (Tex. 1993). Similarly, in
    Connecticut the state Supreme Court held that jury trials were not required because there was not
    a sum certain for the penalty, because courts had discretion in setting the penalty, and because
    the stated goals of the environmental enforcement statutes were equitable and restitutionary in
    nature. Commissioner of Environmental Protection v. Connecticut Bldg. Wrecking Co., Inc., 
    629 A.2d 1116
    , 1122 (Conn. 1993); compare 10 V.S.A. ' ' 8001 and 8010(b).
    The Vermont Supreme Court has taken the same approach under the Vermont Constitution: that
    a jury trial is not required for appeals and hearings unknown to the common law and which have
    no common law analogy. State of Vermont Department of Taxes v. Tri-State Industrial
    Laundries, Inc., 
    138 Vt. 292
    , 297 (1980); Shaw v. District Court, 
    152 Vt. 1
    , 6 (1989). This
    analysis is equally applicable to proceedings under the Uniform Environmental Enforcement
    Act. Proceedings for judicial review of a civil penalty in Vermont Environmental Court under 10
    V.S.A. ' 8012, even though the standard of review is de novo, do not require a jury as they
    involve proceedings by the government in its sovereign capacity to enforce public rights; they
    originate in an administrative agency proceeding; they are equitable in nature; and they were
    unknown at the common law. Further, as judicial review of agency action, rather than a suit
    brought directly in a judicial branch court, they have no common law analogy. See, also,
    Vermont Agency of Natural Resources v. Lyndonville Savings Bank & Trust Co., Inc., Docket
    No. 40-3-99 (Vt. Envtl. Ct., August 24, 1999); Vermont Agency of Natural Resources v. Towne,
    Docket No. E97-065 (Vt. Envtl. Ct., July 10, 1997).
    Accordingly, Respondents= request for reconsideration of this Court= s denial of their motion for
    a jury trial on the penalty issues is itself DENIED. This matter remains scheduled for trial on
    October 9 and 10, 2002, in Newfane. Although the parties had agreed that any prefiled testimony
    was to be filed so that it is received at the Court by October 4, 2002, no such prefiled testimony
    has been filed. At a telephone conference held today, the parties agreed that any written requests
    for findings or memoranda of law on issues relating to the existence of the violations and any
    remedial orders are to be filed at trial on October 9, 2002; and that oral argument on these issues
    will be held on the record at the close of the evidence. Written requests for findings, memoranda
    of law, and any argument on issues relating to a penalty are to be filed on or before October 21,
    2002, or on such other schedule as may be agreed by the parties at trial, with any responses filed
    on or before October 29, 2002 ( or on such other schedule as may be agreed by the parties).
    Done at Barre, Vermont, this 7th day of October, 2002.
    ___________________
    Merideth Wright
    Environmental Judge
    Footnotes
    1.
    Decided under prior Rhode Island statute; modified and distinguished in National Velour
    Corp. v. Durfee, 
    637 A.2d 375
    , 378-81 (R.I. 1994), which held that penalty assessment could be
    assigned to an administrative agency without a jury, and that an appeal could be assigned to
    superior court (at least in an on the record appeal) without a jury, based on the ‘public rights’
    analysis discussed below.