In re: Appeal of John Larkin City of South Burlington v. John Larkin, Gerald Milot, Larkin-Milot Partnership, and Michael and Kathryn Luciano ( 2001 )


Menu:
  •                                      STATE OF VERMONT
    ENVIRONMENTAL COURT
    In re: Appeal of John Larkin        }
    }
    } Docket No. 159-9-99 Vtec
    }
    }
    City of South Burlington,
    Plaintiff,
    }
    v                                   }
    } Docket No. 244-10-00 Vtec
    John Larkin, Gerald Milot,          }
    Larkin-Milot Partnership, and       }
    Michael and Kathryn Luciano,
    Defendants.
    Decision and Order on Second Motion for Summary Judgment
    In Docket No. 159-9-99 Appellant appealed from a decision of the then-Zoning Board of
    Adjustment (ZBA) of the City of South Burlington regarding the height limit on Lot 49 in the
    Pinnacle subdivision. In May, 2000, the Court remanded the matter for the ZBA (now the DRB)
    to act on the merits of Appellant= s appeal of the June 1999 Notice of Violation, as in the original
    decision the ZBA had treated it as a request for a variance. On remand, the ZBA upheld the
    notice of violation in July 2000. In Docket No. 244-10-00, in October 2000, the City filed an
    enforcement action to compel Defendants, among other things, to lower the building= s height.
    The matters have been consolidated for hearing. The City has filed a second motion for partial
    summary judgment in Docket No. 159-9-99 Vtec.
    Appellant-Defendant Larkin is represented by Carl H. Lisman, Esq.; the City is represented by
    Joseph S. McLean, Esq. The 1999 Notice of Violation was addressed to Mr. Milot and Mr.
    Larkin, as individuals. Mr. Milot has not appealed or entered an appearance in Mr. Larkin= s
    appeal of the Notice of Violation, Docket No. 159-9-99 Vtec. None of the five Defendants,
    including Mr. Larkin, has filed an answer in Docket No. 244-10-00 Vtec.
    First, the City argues that Appellant Larkin failed to appeal the July 11, 2000 decision of the
    DRB, after this Court had remanded the matter to the DRB. However, Appellant did originally
    attempt to appeal from the then-ZBA= s action on his appeal of the notice of violation. The reason
    it was remanded by this Court is that the ZBA had improperly treated his appeal of the notice of
    violation as an application for a variance. By remanding the matter, the Court did not divest itself
    of jurisdiction to consider the appeal of the notice of violation; rather, the Court merely provided
    for an orderly appeal by requiring the DRB to act on the matter in the first instance. Accordingly,
    the Court still has jurisdiction of Appellant= s appeal of the notice of violation.
    The City also has moved for summary judgment on Questions 1 and 2 of the Statement of
    Questions in Docket No. 159-9-99 Vtec, that is, to establish the methodology under the Zoning
    Regulations for measuring the height of the building in question, and to establish the height1 of
    the building in question.
    The parties agree that ' 25.113 governs building height, which is measured from the A average
    preconstruction grade adjoining such structure.@ It sets a limit of 40 feet for pitched roofs and 35
    feet for any other structure, and provides for DRB approval of increase in height above those
    limits under subsections (b), (c) and (g).
    Preconstruction grade is defined as the grade existing on the property as of the date of an
    application for development approval, unless another grade has been established under ' 25.117
    as the preconstruction grade. Section 25.117 allows the DRB approve the placement or the
    removal of 20 or more cubic yards of fill. Removal or addition of less than that amount is
    unregulated by the Zoning Regulations.
    The problem with applying these definitions to the lot in question is that the preconstruction
    grade is shown on the plan only by one contour line, at 389 feet above sea level. Even with the
    assumptions suggested by the City, an average grade cannot be established by a single contour
    line. Moreover, the City will need to establish which topographic reference point was used in the
    recorded plans.
    Second, material facts are in dispute as to whether the preconstruction grade was raised by an
    unregulated addition of less than 20 cubic yards of fill.
    Third, the approved plan also contains a notation that the allowed first floor elevation (FFE) is
    394 feet above sea level, but does not indicate how far above the grade that first floor elevation
    was to be placed, although it may be possible to answer that question by measuring the plan to
    scale. If the actual first floor elevation as built is located at 394 feet above sea level, and if it can
    be ascertained from the approved plans how much the approved plans for the house extended
    above that approved first floor elevation, then it may be that the as-built height of the house
    conforms with the approved plans, whether or not it conforms to a 28-foot height as measured by
    the definition in the Zoning Regulations.
    Accordingly, material facts are in dispute, even regarding the measurement of the as-built height
    of the house. Accordingly, all remaining issues in this matter must be set for trial. When the May
    3 hearing was continued, the parties agreed that the matter could be set for a hearing in July.
    Please advise the Court of any dates on which the attorneys or witnesses are unavailable in July
    and August, as well as whether the matter can be concluded in a half day.
    If it can, it will probably be set for July 12. In the interim, Docket No. 244-10-00 Vtec may be
    subject to a motion for default as to any party not filing an answer to it.
    Done at Barre, Vermont, this 16th day of May, 2001.
    ___________________
    Merideth Wright
    Environmental Judge
    Footnotes
    1.
    As the City notes, the height standards in the Zoning Regulations are distinct from the
    maximum permitted elevation standards for buildings in the Dorset Park View Protection Zone
    under §22.40 of the Zoning Regulations.
    

Document Info

Docket Number: 159-9-99 Vtec

Filed Date: 5/16/2001

Precedential Status: Precedential

Modified Date: 4/24/2018