In re: Appeal of Patrick Simoneau and William Penrod (Decision and order on Appellants' Motion for Summary Judgment) ( 2001 )


Menu:
  •                                      STATE OF VERMONT
    ENVIRONMENTAL COURT
    In re: Appeal of Patrick           }
    Simoneau and William Penrod        }
    } Docket No. 210-9-00 Vtec
    }
    }
    Decision and Order on Appellants= Motion for Summary Judgment
    Appellants Patrick Simoneau and William Penrod appealed from a decision of the Planning
    Commission of the Town of Colchester approving Appellee-Applicant Winooski Valley Park
    District= s application for site plan approval. Appellants are represented by Liam L. Murphy,
    Esq.; Appellee-Applicant is represented by Scot L. Kline, Esq.; the Town is represented Richard
    C. Whittlesey, Esq. Appellants have moved for summary judgment on Question 1 of their
    Statement of Questions: whether Appellee-Applicant= s application for site plan approval is an
    impermissible successive application.
    The following facts are undisputed unless otherwise noted.
    On publicly-owned lands surrounding Colchester Pond, Appellee-Applicant has sought in
    several stages to extend or improve a loop trail for pedestrian traffic. Appellants own properties
    contiguous to the southerly portion of the circumference, the only portion without an improved
    trail.
    In 1996, Appellee-Applicant had received site plan approval to construct a 610' gravel access
    drive and 60' by 100' parking area. The parking area is located near Appellants= properties.
    Appellants were concerned that pedestrians who walked the trail would trespass over Appellants=
    properties to return to the parking area rather than retracing their steps around the pond.
    Condition #6 of the 1996 site plan provided that any future construction of trails around the south
    end of the pond would require A review and approval by the Planning Commission as a Site Plan
    application.@ The 1996 site plan approval and conditions was not appealed and hence became
    final.
    The Zoning Administrator issued to Appellee-Applicant a notice of violation dated July 7, 1998,
    citing as the violation: A [s]pecifically you have constructed a trail around the south end of the
    pond, in violation of the Planning Commission= s 1996 approval,@ making reference to condition
    #6 as set forth above. Appellee-Applicant appealed the Notice of Violation to the Zoning Board
    of Adjustment, which upheld it, and then appealed to the Environmental Court, which issued a
    summary judgment decision. In re: Appeal of Winooski Valley Park District, Docket No. 201-
    11-98 Vtec (Vt. Envtl. Ct., June 14, 1999). The appeal eventually was withdrawn.
    On June 22, 1998, Appellee-Applicant submitted an application for site plan approval, describing
    the project as:
    placement of a boardwalk through about 400 l[inear] f[eet] of wetlands, to complete a 22 mile
    path around Colchester Pond. An informal path exists. The proposed improvements would
    clearly delineate existing foot traffic. Proposed development to include (1) Two 16' x 4' bridges
    (2) removable 8' x 4' footbridges (3) a wooden stairway (4) fencing and (5) signs.
    The Planning Commission denied site plan approval in a written decision dated October 14,
    1998, on the basis that the project would adversely affect the character of the area. The 1998
    Planning Commission decision describes the project as a A series of boardwalks[,] bridges,
    fencing, and a staircase through the southwest corner of the pond.@ It specifically noted that A
    [t]his application does not include the construction of the footpath.@ The 1998 Planning
    Commission decision was not appealed and hence became final.
    On June 13, 2000, Appellee-Applicant submitted an application for site plan approval, describing
    the project as:
    establishment of a footpath, about 1400' long x 2' wide, which would complete a 22 mile loop
    trail around Colchester Pond. Path within publicly-owned parkland. No structures proposed. No
    fill.@
    While the earlier denied proposal sought to complete the trail around the south end of the pond
    by constructing a boardwalk near and at times through the wetlands, the 2000 application
    proposes no structures and substantially reroutes the planned trail away from sensitive wetlands
    onto property previously thought to be outside the park-owned land. The Planning Commission
    first voted to consider this a new application as compared to the one denied in 1998, and then
    approved the site plan with conditions in its August 15, 2000 decision, on appeal in the present
    case.
    In the present motion, Appellants argue that the current site plan application is an impermissible
    successive application and hence should be denied outright on res judicata or collateral estoppel
    grounds. A Planning Commission need not consider a successive application for a project
    rejected in a prior application unless either the application or some other circumstance has
    changed. In re Application of Carrier, 
    155 Vt. 152
    , 158 (1990), citing (cf.) In re Crescent Beach
    Assn., 
    126 Vt. 140
    , 141, (1966); applied by the Environmental Court in, e.g., Appeal of Addison
    County Eagles, Docket No. 13-1-00 Vtec (Vt. Envtl. Ct., May 7, 2001); Appeal of 31 Hyde St.
    Assn., Docket No. 218-11-98 Vtec (Vt. Envtl. Ct., March 27, 2000); Appeals of Miserendino,
    Docket Nos. 85-5-99 Vtec and 191-10-99 Vtec (Vt. Envtl. Ct., Jan. 13, 2000).
    The applicant must demonstrate that the successive application is different in content or that
    changed circumstances have intervened. See In re Crescent Beach Ass= n, 
    126 Vt. 140
    , 141
    (1966); In re Application of Carrier, 
    155 Vt. 152
    , 158 (1990). The Planning Commission, and
    hence this Court, may consider a successive application particularly if A the modified proposal is
    sufficiently changed to satisfy concerns that prevented approval of the prior application.@ Carrier,
    155 Vt. at 158-59. See also, e.g., In re: Appeal of Wesco, Inc., Docket No. 4-1-99 Vtec (Vt.
    Envtl. Ct., Aug. 23, 1999) (changes in new application, though perceptibly small, sufficient to
    warrant review because they addressed court= s earlier ruling).
    The 1998 application did not propose to create or make any changes to the footpath, but rather to
    construct a boardwalk through the wetlands, with an associated stairway, fencing and signage. It
    was denied largely due to objections to the construction of a boardwalk through the wetlands.
    Appellee-Applicant= s 2000 application proposes a footpath featuring no structures whatsoever
    and routed away from the wetlands. The 2000 application before the Court in the present case is
    sufficiently different from the 1998 application to warrant consideration on its merits by the
    Planning Commission, and hence this Court.
    Accordingly, based on the foregoing, Appellants= Motion for Summary Judgment is DENIED
    and summary judgment is entered in favor of Appellee-Applicant on Question 1 of the Statement
    of Questions. We will hold a telephone conference on June 1, 2001 to determine whether and
    when the remainder of the case should be scheduled for a hearing.
    Done at Barre, Vermont, this 21st day of May, 2001.
    ___________________
    Merideth Wright
    Environmental Judge
    

Document Info

Docket Number: 210-9-00 Vtec

Filed Date: 5/21/2001

Precedential Status: Precedential

Modified Date: 4/24/2018