Williamson Plumbing v. Stockdale ( 2004 )


Menu:
  • Williamson Plumbing v. Stockdale, No. 1565-02 Cncv (Katz, J., Feb. 13,
    2004)
    [The text of this Vermont trial court opinion is unofficial. It has been
    reformatted from the original. The accuracy of the text and the
    accompanying data included in the Vermont trial court opinion database is
    not guaranteed.]
    STATE OF VERMONT                                      SUPERIOR COURT
    Chittenden County, ss.:                           Docket No. 1565-02 CnCv
    WILLIAMSON PLUMBING
    v.
    STOCKDALE
    FINDINGS OF FACT
    CONCLUSIONS OF LAW
    NOTICE OF DECISION
    Plaintiff commenced this action to recover amounts allegedly past
    due for plumbing installation work at defendants’ new home in Jericho.
    Defendants dispute the amounts claim, alleging breaches of contract,
    largely issues of workmanship. The matter was tried February 9, 2004.
    On the basis of the evidence presented, the following decision is
    announced.
    FINDINGS OF FACT
    1.       Homeowners accepted plumber’s proposal for work to be done, at
    a particular price, and work began. For the most part, the relationship
    went smoothly, with pre-printed invoice forms and prompt payments.
    Several disputes arose at the end of the job, which we will rule on
    individually.
    2.       Although there was an agreement that plumber could hang pipes
    in any manner that was most convenient to him within the “mechanical
    room” in the basement, subject only that the work be neat, there was no
    real discussion regarding pipe location outside that room.
    3.       In fact, plumber installed the water supply intake vertically,
    outside the perimeter wall, such that it intrudes into the room. Although
    the evidence was not explicit on the subject, it appears from the photos
    that this vertical pipe probably extends into the basement area about four
    inches. Based on the photo entitled “Ceiling” in defendants’ exhibit 13,
    this vertical pipe is near the “mechanical room” and the stairs to the
    garage. Were it to be boxed in, it would be minimally intrusive of the
    main basement area, and not unsightly. On the other hand, putting the
    vertical pipe within the wall, as the homeowners now suggest, would
    leave it with less insulation and therefore more prone to winter freezing.
    Coming from the ground, the well water would tend to start out very cold.
    Were the water not run for a number of hours, a pipe in the wall would
    seem prone to freezing.
    4.       There was no discussion between the parties regarding location of
    this pipe. There are no written specifications. Under all the
    circumstances, it was not poor workmanship to locate the pipe as it was.
    It’s location is not a breach of contract.
    5.       The same photo shows the plastic waste pipe hanging below the
    joists supporting the main floor. As such it tends to restrict ceiling height.
    However, the photo shows that pipe again in the vicinity of the
    mechanical room, where the plumber had been given a freer hand, because
    appearance was not the issue. There was no proof as to the waste pipe
    extending into the main basement area, to the diminution of effective
    ceiling height.
    6.       A one inch steel gas line was installed below the joists. It could
    have been run within the joists, thereby preserving ceiling height. It is not
    clear how long a section could have been fit through the joist openings, or
    if smaller sections would have had to have been joined, as this steel pipe
    has no real flexibility. There was no written contract specification calling
    for this pipe to be completely within the joists. It lies virtually against the
    outside wall. Hence, it could have been boxed out, or the wall brought out
    about four inches, and thereby avoided any ceiling height loss in the great
    expanse of the basement.
    7.      One pipe feeding upstairs heating units runs within the joists, but
    then dips down to avoid the large steel I-beam. Again, running under the
    I-beam causes an effective loss of height.
    8.       First, we find that the plumber was reasonable in declining to
    simply drill through the beam without clear prior authority. The beam is
    an obvious structural member. It must not be compromised. It may well
    be that a 1 ½ inch hole, drilled into a fourteen inch beam, would have
    minimal effect on strength or rigidity. But the plumber is not expected to
    know this. Not working for the general contractor, the plumber brought
    the issue to the attention of the homeowner, asking for a decision from
    engineer or architect. The homeowner did not get back to the plumber
    with a prompt answer, so the latter ran the pipe below the beam, as shown
    in photo “Ceiling 2.”
    9.      Second, we note from the photo that this is in the corner of the
    room. Again, it could have been boxed out, without any significant harm
    to aesthetics or the overall ceiling height.
    10.      Homeowner next asserts that the wall-hung hot water heater was
    improperly installed. The manufacturer’s instruction sheet calls for the
    heater to have 36 inches clearance beneath any combustible or non-
    combustible surface. In fact, it was installed very close to one floor joist,
    and perhaps only a foot beneath the subflooring above. The plumber’s
    experienced foreman testified that the 36" clearance is an old
    specification, no longer recommended by the manufacturer. In support of
    this belief, he brought to court a manufacturer’s spec sheet. In fact, that
    sheet both calls for a six inch clearance, which in part this installation did
    not enjoy, and it relates to a different model (2532) than the one installed
    (2402).
    11.    Only two weeks before trial, the heater was ruined by freezing.
    Apparently, cold air entered the concentric exhaust/air inlet pipe, and
    cracked the copper heating vessel. Homeowner believes that had there
    been a longer rise, resulting from a lower installation, the cold air might
    not have penetrated as it actually did. We note however that the
    manufacturer does not specify any minimum rise in the specification
    sheet/installation instructions. In the end, it is merely speculation that a
    lower installation would have made a difference. The plumber was
    persuasive that the mere length of the pipe outside may have exposed it to
    too much cold air. There was no proof that the first installation caused the
    freeze damage. Further, the manufacturer replaced the unit free. The
    replacement unit was installed lower than the original. The manufacturer
    did not pay for installation of the second unit, which cost homeowners
    $526. But a significant portion of that would have had to have been paid
    merely to reinstall the second unit identically to the first. The cost of
    lowering the second unit must only have been a part of that cost.
    12.      In the end, we are persuaded that the plumber should have
    followed the spec sheet for this particular model, although we cannot find
    that the freeze damage was caused by any failure to follow that sheet. It
    was therefore reasonable for the homeowner to have the replacement unit
    installed at a lower height.
    13.      Upstairs, a trim plate for an “inner 45º” corner of the baseboard
    heating was never installed. Homeowners purchased the item and
    installed it themselves. No price was put in evidence.
    14.      A pedestal sink in the downstairs bathroom was never installed.
    A small $1.50 part was required, and homeowner did not obtain the part
    until the plumbers left the job. But it was clearly understood that, with
    homeowners supplying fixtures, they were responsible for all parts.
    Under these circumstances it is not reasonable to expect the plumber to
    make a separate trip, whenever the homeowner finally comes up with the
    necessary small part. There never was a time when the homeowner had
    the part, together with any other “punch list” work, such that the plumber
    should have been expected to return to the site.
    15.       Rough in plumbing, within the cellar slab, was never part of the
    contract. Hence, it is an appropriate extra. After that plumbing was
    already in place, the proposal was modified to include the cellar bathroom.
    But the price in the contract proposal, accepted as the contract, was
    merely running plumbing to the bathroom and hooking up fixtures. It did
    not include the slab work. As the slab work involved an extra trip to the
    site, the plumber’s cost is a reasonable one.
    16.     Homeowners have two estimates for “correcting” work of which
    they complain, particularly rerouting pipes. The two average out to about
    $1,300. We have, however, already noted that some of the work
    complained about was not unreasonable, under the circumstances.
    CONCLUSIONS OF LAW
    17.      In order to recover, homeowners must not only show a breach, but
    also that they were harmed by that breach.
    18.     When there is no written specification on a particular point, the
    law will examine plumbing decisions in light of the prevailing standard of
    workmanship in the area. 13 Am. Jur. 2d Building and Construction
    Contracts § 12. Hence, the decision to have the water supply pipe
    alongside, rather than within the cellar wall was reasonable within this
    standard, as was the decision to have the long, rigid gas line immediately
    below the joists and adjacent to the wall. The decision to go under the I-
    beam, instead of through it without an engineer’s approval, was
    reasonable given the potential for liability and damage the plumber faced
    going through a support beam without the engineer’s approval.
    19.      Findings cannot be based upon speculation. See, e.g., Pratt v.
    Dep’t of Social Welfare, 
    145 Vt. 138
    , 143–44 (1984) (invalidating board’s
    findings as based on speculation and conjecture). The belief that the water
    heater froze because of being installed too high is not supported by solid
    evidence. It is plausible, but tends to be rebutted by the manufacturer’s
    failure to specify a minimum rise on the exhaust. Given a different cellar
    configuration, the unit could be in the same location relative to the
    ground, yet 36" below the floor joists, and still have suffered the same
    freeze.
    20.      The charge of two per cent per month interest, although
    apparently called for in the proposal (copy of third page not included
    among exhibits) is not permitted. 9 V.S.A. § 41a. Under 9 V.S.A. § 50
    there are two potential penalties. The first is to reduce the interest rate to
    the legal limit and return, with interest, anything paid above and beyond
    this rate. 9 V.S.A. § 50(a). The second is to strike all interest and forgive
    one half of the principal, when the “lender” exceeds the permitted rate. 9
    V.S.A. § 50(b). To apply the second, harsher penalty, we are required to
    make a finding that the lender deliberately intended to violate Vermont
    usury laws. Crocker v. Brandt, 
    130 Vt. 349
    , 357–58 (1972). We are not
    persuaded that plumber here intended to do anything of the sort. The rate
    of interest at issue was part of a pre-printed form that plumber purchased,
    most likely at an office supply store. It was probably printed out of state
    and neither plumber, printer, nor Staples realized it was in contravention
    to Vermont interest rate law. As such, this rate is best classified as and
    “innocent act” and therefore properly subject only to the limit imposed by
    § 50(a). Additionally, plumber here was not a lender in the sense of § 50.
    He did not enter into this relationship actually lending money and never
    had the expectation that he would lend money. Instead, he is in the
    position of having provided services, and then not been paid his bill. As
    such, he is still limited by the legal rate, but should not suffer the harsh
    penalties imposed upon lenders who intend from the start of the
    transaction to lend money and commit usury.
    21.      On the basis of the foregoing, the sum of $3,784 was reasonably
    billed by plumber to homeowners. We are persuaded, however, they are
    entitled to a $320 credit against that sum for replumbing the wall-hung
    water heater to comply with manufacturer’s specification. The balance of
    their recent bill would have been due merely for replacing a unit which
    had been properly installed, but nevertheless was damaged by freezing.
    22.      We are not persuaded by the balance of homeowners’ contentions
    regarding the piping issues. First the plumber made reasonable decisions
    in the absence of clear instructions. Second, the reasonable homeowner
    faced with the pipe-below-the-joists situation here involved would
    probably not have lowered the entire ceiling, would not have paid $1,300
    to raise the pipes, but would, instead have boxed out the offending
    protrusions, located as they are to the side and in the corner.
    23.      Plaintiff requests attorneys fees through a contractual provision.
    The general rule in Vermont is the “American Rule,” which means that
    parties pay their own legal fees absent contractual agreement or statute.
    D.J. Painting, Inc. v. Baraw Enters., 
    172 Vt. 239
    , 246 (2001). As a
    derogation to the general rule, we will only accept such contract language
    that justifies such a departure. Bruntaeger v. Zeller, 
    147 Vt. 247
    , 255
    (1986); see also Concord Gen. Mut. Ins. Co. v. Woods, 
    2003 Vt. 33
    , at ¶
    18. If attorney fees are included in the contract between the parties,
    plaintiff claimed more than it was due, particularly because of excessive
    interest, defendant was justified in not paying that demand. As such, we
    conclude that plaintiff is not the prevailing party, such that it should be
    awarded attorneys fees. See Union of Needletrades, Indus. & Textile
    Employees v. I.N.S., 
    336 F.3d 200
    , 205–08 (2d Cir. 2003) (defining the
    high standards for prevailing and substantially prevailing).
    NOTICE OF DECISION
    Plaintiff is entitled to judgment in the amount of $3,484, plus
    interest at the legal rate from May 15, 2002, and costs. A proposed
    judgment should be submitted.
    Dated at Burlington, Vermont, _________________, 2004.
    __________________________
    Judge
    

Document Info

Docket Number: S1565

Filed Date: 2/13/2004

Precedential Status: Precedential

Modified Date: 4/24/2018