Moran Site Plan and Major Impact Development ( 2012 )


Menu:
  •                                STATE OF VERMONT
    SUPERIOR COURT - ENVIRONMENTAL DIVISION
    Moran Plant Site Plan &                                                Docket No. 4-1-12 Vtec
    Major Impact Development
    Judgment Order
    On January 9, 2012, nine (9) individuals (Appellants) appealed the City of Burlington
    (City) Development Review Board’s (DRB) August 17, 2010 approval of a project known as the
    Moran Plant Site Plan and Major Impact Development (Moran Plant Project). Along with the
    appeal, Appellants filed a Motion for Party Status with a proffer of evidence; however, they
    provided no evidence through affidavits or otherwise. Appellants’ basis for their right to file
    the appeal well beyond the 30-day deadline is that the City failed to provide notice pursuant to
    24 V.S.A. Section 4464(a)(2).
    In response, the City filed a Motion to Dismiss the appeal and an Opposition to Party
    Status. The City supported its filings with affidavits and exhibits.
    On February 9, 2012, the Court held an initial status conference followed immediately by
    a motions hearing. The hearing was held at the Superior Court, Civil Division, Burlington,
    Vermont; Judge Thomas G. Walsh presiding. Attorney Samuel Hoar, Jr. appeared on behalf of
    Appellants. Attorneys Kimberlee J. Sturtevant and Gregg Mayer appeared on behalf of the
    City.
    At the hearing, the City called two witnesses who provided testimony and further
    evidence relating to issues of notice and adjoining landowner identification.         None of the
    Appellants appeared, testified or provided evidence. Counsel for Appellants offered argument
    and cross-examined the City’s witnesses.
    At the conclusion of the evidentiary hearing, the Court took a brief recess to conduct its
    research and deliberations. Judge Walsh returned to the courtroom to announce his findings of
    fact and conclusions of law on the record of the hearing. This Judgment Order memorializes
    the legal determinations made at the hearing.
    The Court concluded that Appellants’ appeal of the DRB’s August 17, 2010 decision
    approximately 477 days after the decision was rendered was beyond the 30-day deadline. Thus,
    Appellants had the burden of proving that their late appeal should be allowed. The Court
    noted Vermont’s strong policy favoring finality in land use permitting. The Court recognized
    Attorney Hoar’s proffer that Appellants received no notice of the 2010 DRB proceedings as
    required by 24 V.S.A. §4464(a)(2). The Court noted that as the 2010 DRB approval was for
    conditional use, notice was required under 24 V.S.A §4464(a)(1). The Court then found, based
    upon the evidence in the parties’ pleadings and presented at the hearing, that the City complied
    with the notice requirements of 24 V.S.A. §4464(a)(1).     With respect to Appellant Vera B.
    Brodman, whose written notice was returned undeliverable, the City sent this written notice to
    Ms. Brodman’s address on record at the City, and therefore the Court found that the City had
    undertaken reasonable efforts to give notice in compliance with 24 V.S.A. §4464(a)(5). Thus, the
    Court concluded that Appellants received adequate notice. As such, the Court concluded that
    Appellants’ appeal of the August 17, 2010 DRB approval was out of time. The Court DENIED
    Appellants’ Motion for Party Status and GRANTED the City’s Motion to Dismiss, thereby
    concluding the case.
    This completes the proceedings before this Court in this matter.
    Done at Berlin, Vermont this 15th day of February, 2012.
    Thomas G. Walsh,
    Environmental Judge
    

Document Info

Docket Number: 4-1-12 Vtec

Filed Date: 2/15/2012

Precedential Status: Precedential

Modified Date: 4/24/2018