Allen Road Land Co. Act 250 Appeal ( 2011 )


Menu:
  • STATE OF VERMONT
    SUPERIOR COURT _ ENVIRONMENTAL DIVISION
    }
    In re Allen Road Land Co. Act 250 Permit } Docket No. 62-4-11 Vtec
    (appeal of Amended Act 250 } (appeal from District 4 Envtl.
    Permit No. 401232-1) } Commission determination)
    }
    ***~k********i:****~k*%**~k*'k'k****'k********k****'k**'k**'k~k'k**~k*~k*~k*‘k*****'k**i€*************~k*
    ' }
    _In re Allen Road Land Co. JO #4-226 } Docket No. 63-4-11 Vtec
    } (appeal from J.O. of District 4
    } Envtl. Commission
    } Coordinator)
    }
    Decision on Motions for Consolidation and Stay
    Appellants Sharon and Doug Carlson (“Appellants”) have appealed, in Docket
    No. 62-4~11 Vtec, a decision by the District 4 Environmental Commission (“District
    Commission”) approving an amendment to a state land use permit issued to Allen
    Road Land Company (“Applicant”) for the construction of 30 residential units, in four
    nevv three-story buildings, and of associated development in the City of South
    Burlington (“City”). The amendment authorizes Applicant to use blasting techniques
    to remove ledge in order to install a sewer line and to add decks and basements to the
    approved buildings. Appellants have also appealed, in Docket No. 63-4-11 Vtec, a
    Jurisdictional Opinion #4-226 (“JO”) issued by the District 4 Environmental
    Commission Coordinator (“District Coordinator”) determining that the use of a
    hydraulic jack hammer to remove ledge does not require a permit amendment,
    provided the noise it generates does not exceed a specified limit.
    Currently pending before the Court are Appellants’ motion to consolidate their
    two appeals and their motions to stay the underlying decisions in both dockets.
    Applicant has responded to these motions by filing a response in opposition to both
    pending motions. In both dockets, Appellants are represented by Jacob O. Durell,
    Esq. and Applicant is represented by Christina Jensen, Esq.
    Factual Background
    For the sole purpose of putting the pending motions into context, we recite the
    following facts, which we understand to be undisputed unless otherwise noted:
    1. On August 6, 2010, the District Commission issued a state land use permit,
    LUP No. 4C1232, to Applicant authorizing the following: (1) the construction of 30
    residential units in four new three~story buildings; (2) the retention of one existing
    residence; (3) the construction of 600 linear feet of new road; and (4) the construction
    of three carports. The permit covered development of a 4.99 acre parcel off Hinesburg
    Road (Vermont Route 1 16) in the City of South Burlington, Vermont.
    2. . In an application dated December, 2010, Applicant sought an amendment to its
    original permit for the use of blasting to remove ledge on its property in order to install
    the proposed sewer line. The amendment application also sought approval to use
    blasting to remove additional ledge Applicant might discover during construction and
    approval to add decks and basements to its buildings.
    3. On January 24, 2011, the District Commission held a public hearing on the
    application for a permit amendment and recessed the hearing in order to receive
    additional submissions from the parties. After receiving the additional submissions,
    the District Commission adjourned the hearing on March 15, 2011.
    4. On March 23, 2011, Applicant requested a jurisdictional opinion from the
    District Coordinator to determine whether it needed a permit amendment in order to
    use a hydraulic jack hammer to remove ledge on its property.
    5. On April 1, 2011, the District Coordinator issued the JO indicating that an
    amendment would not be necessary for Applicant to use a hydraulic jack hammer to
    remove ledge, provided that the`` noise generated by such use does not exceed 76
    decibels, measured as a weighted average over an eight-hour period.
    6. On April 14, 2011, the District Commission issued a permit amendment,
    No. 4C1232~1, to Applicant authorizing “blasting for installation of sewer line and the
    addition of decks and basements to the approved buildings.” (See Mem. in Opp’n to
    Mot. for Stay of Amendment to Act 250 Permit, Attach. 1, Land Use Perrnit
    Amendment, No. 4C1232~1 at 1, filed May 13, 2011.) The District Comrnission
    conditioned its approval on the Applicant following its “Blasting Plan” and limiting
    noise generation to 76 decibels, measured as a weighted average over an eight-hour
    period.
    7. On April 29, 2011, Appellants timely appealed both the District Coordinator’s
    decision in Docket No. 63-4-11 Vtec and the District Commission’s decision in Docket
    No. 62-4-11 Vtec.
    Discussion
    In Docket No. 62-4~1 1 Vtec, Appellants_are appealing the District Commission’s
    grant of an amended permit, No. 4C1232-1, to Applicant’s state land use permit for
    the construction of 30 residential units, in four new three-story buildings, and of
    associated construction and development, on a 4.99 acre parcel off I-Iinesburg Road in
    the City of South Burlington. Permit amendment No. 4C1232-1 authorizes Applicant
    to take the following steps not included in the original permit: to use blasting
    techniques, subject to a noise limitation, to remove ledge in order to install a sewer
    line and to add decks and basements to the approved buildings. ln Docket No. 63-4-
    11 Vtec, Appellants are appealing the District Commissioner’s issuance of the JO
    determination that the use of a hydraulic jack hammer to remove ledge does not
    require a permit amendment, provided the noise it generates does not exceed a
    Speciiied iimit. '
    Appellants now seek consolidation of their two appeals and ask for ma stay of
    both the District Commission’s decision granting permit amendment No. 4C1232-1
    and the District Coordinator’s JO indicating that no amendment is necessary for use
    of a hydraulic jack hammer.
    I. Motion to Consolidate
    Appellants’ motion to consolidate under V.R.E.C.P 2(b) is titled a “l\/lotion for
    Coordination of Proceedings,” which is an accurate description of their request. (See
    Mot. for Coordination of Proceedings, filed Apr. 29, 2011). Under V.R.E.C.P. 2(b),
    which is titled “Coordination of Proceedings,” when a “project involves multiple
    proceedings that have resulted or may result in separate hearings or appeals . . . the
    court may advance, defer, coordinate, or combine proceedings and may make other
    orders that will promote expeditious and fair proceedings and avoid unnecessary costs
    or delay.” This rule gives the Court a “ilexible case management tool,” allowing us to
    coordinate the conferences and hearings for multiple appeals concerning the same
    project. Reporter’s Notes, V.R.E.C.P. 2.
    Here, Appellants seek coordination of the proceedings for two appeals involving
    a single project, Applicant’s construction of 30 residential units in four new three~
    story buildings, and development associated with these buildings Applicant opposes
    Appellants’ request, arguing that the two pending appeals involve different substantive
    and procedural issues and addressing them together would not benefit the Court or
    the parties. We cannot agree with Applicant. Before us we have the appeals of
    decisions approving two different methods for removing ledge to provide for the
    construction of a single project. Although the legal issues that are raised in each
    appeal differ to some extent, there is some overlap of legal issues presented and an
    overlap of many of the relevant factual issues. It is our experience that the
    coordination of conferences and hearings for these types of related cases will save the
    Court and parties valuable resources. Consequently, we GRANT Appellants’ motion to
    consolidate.
    We note that Applicant’s opposition to Appellant’s request appears to be
    partially based on a misunderstanding of the request and the applicable procedural
    rule. This Court often uses the term “consolidate” as shorthand for the coordination
    of proceedings, which we regularly grant upon motion by one of the parties. See, e.g.,
    In re Rivers Dev. Conditional Use Appeal, Nos. 7~1-05 Vtec, 68-3-0'7 Vtec, 183-8-07
    Vtec, 248-11-0'7 Vtec, and 157-7-08 Vtec, slip op. at 7-11 (Vt. Envtl. Ct. Nov. 21,
    2008) (Durkin, J) (granting the appellant’s motion to consolidate despite opposition by
    some of the other parties). This type of consolidation is not the same as consolidating
    multiple actions (e.g., multiple appeals) into a single action. See Reporter’s Notes,
    V.R.E.C.P. 2 (“[V.R.E.C.P. 2(b)] does not address full consolidation of proceedings,
    which by virtue of V.R.C.P. 42(a) may be ordered only with the consent of the
    parties.”)1 The consolidation of actions involves the substitution of a single docket
    number for multiple actions, concludes with a single ruling, and requires the parties’
    consent. See V.R.C.P 42(a) (“[The court] may, with the consent of the parties, order all
    actions consolidated . . . .”); Mobbs v. Central Vt. RV., Inc., 
    155 Vt. 210
    , 215 & n.2
    (1990) (discussing V.R.C.P 42 and distinguishing a court order to hold a joint trial
    from an order merging “suits in a single cause of action”).
    Here, Appellants are not requesting consolidation of their two appeals into one;
    thus, Applicant’s consent is not necessary for us to grant Appellants’ motion. Because
    1 Federal Practice and Procedure provides a helpful description of the types of consolidation and serves as guidance
    here because of the similarity between V.R.C.P. 42(a) and Rule 42 of the Federal Rules of Civil Procedure. See ll
    Wright, Miller & Kane, Federal Practice and Procedure: Civil 3d § 2382; Mobbs v. Central Vt. RV., Inc., 
    155 Vt. 210
    , 215 (1990) (“Because V.R.C.P 42 is substantially Similar to Fed.R.Civ.P. 42, See Reporter’s Notes, V.R.C.P.
    42, We look to federal case law for guidance.”)
    it has been proven that the coordination of conferences and hearings for multiple
    appeals involving a single development project, as presented here, improves the
    efficiency of this Court’s operation and reduces costs, we GRANT Appellants’ motion to
    consolidate.
    II. Motion to Stay
    'I``urning to Appellants’ motions to stay, we note that decisions of district
    environmental coordinators or commissions are not automatically stayed upon their
    appeal, but this Court has authority to issue a stay, and set its terms and conditions,
    when it is “necessary to preserve the rights of the parties.” V.R.E.C.P. 5(e); cf. V.R.C.P.
    62(d)(2). ln determining whether the equities weigh in favor of issuing a stay of the
    two decisions now on appeal, we consider four factors: “(1) the likelihood of success of
    the appealing party on the merits, (2) whether the party seeking the stay will suffer
    irreparable injury if the stay is not granted, (3] whether the issuance of a stay will
    substantially harm other parties, and (4) the location of the best interests of the
    public.” N. Cmtv. Inv. Corp. Conditional Use Application, Nos. 123-6-07 Vtec, 128-6-
    07 Vtec, and 152-7-07 Vtec, slip op. at 2 (Vt. Envtl. Ct. Aug. 30, 2007) (Durkin, J)
    (quoting In re Tariff Filing of New England Tel. 85 Tel. Co., 
    145 Vt. 309
    , 311 (1984)).
    We note that our determination here of whether to issue a stay in either appeal does
    not govern our eventual determination of the merits in these appeals.
    Turning to the first factor, in their request for a stay of the District
    Commission’s issuance of permit amendment No. 4C1232-1, Appellants argue that
    they are likely to succeed because they can show that the use of blasting to remove
    ledge will violate criterion 8 of 10 V.S.A., Chapter 151 (commonly known as “Act 250”).
    See 10 V.S.A. § 6086(a)(3). That is, they argue that noise and vibrations produced by
    the blasting will have an undue adverse aesthetic impact. In examining the evidence
    Appellants discuss in their motion, we are not convinced they are likely to succeed on
    this issue. Appellants express concern that the foundations and structures on their
    property will be damaged from the scheduled blasting, but they do not support this
    assertion with evidence. T he evidence Appellants do discuss does not call into
    question the conclusion reached by the District Commission that any adverse impacts
    will not be undue. See In re Times & Seasons, LLC, 
    2008 VT 7
    , ‘|] 8, 
    183 Vt. 336
    (indicating that a decision-making body applying criterion 8 first determines if a
    project will cause an adverse aesthetic impact and then, if so, examines whether the
    adverse impact is undue); (See Mem. in Opp’n to Mot. for Stay of Amendment to Act
    250 Permit, Attach. 2, Allen Road Land Co., No. 4C1232-1, F``indings of Fact,
    Conclusions of Law, and Order, at 3-10, filed May 13, 2011). While we stress that our
    determination here is not equivalent to a ruling on the merits, for the purposes of
    ruling on Appellants’ request for a stay of the District Commission’s issuance of permit
    amendment No. 4C1232-1 in Docket No. 62-4-11 Vtec, we find that Appellants have
    not shown that they are likely to succeed.
    We reach the same conclusion for Appellants’ request for a stay in their appeal
    of the JO issued by the District Coordinator. There, the applicable question is
    whether Appellants have made reference to sufficient evidence to show that it is likely
    we would ultimately find that the use of a hydraulic jack hammer to remove ledge
    constitutes a “material change” to their original permit and therefore requires an
    amendment, See Act 250 Rule 34(A) (describing the circumstances triggering the need
    for a permit amendment). Act 250 Rule 2(C)(6) defines material change as a “change n
    to a permitted development or subdivision which has a significant impact on any
    finding, conclusion, term or condition of the project’s permit or which may result in a
    significant adverse impact with respect to any of the criteria [in Act 250].” Appellants
    appear to presume that the use of a hydraulic jack hammer will have an adverse
    impact upon the original permit or criterion 8, but they do not present evidence that
    provides a foundation for this Court to reach either of those legal conclusions. In the
    absence of such evidence, this Court is unable now, and will be unable at a de novo
    hearing on the merits, to conclude that the use of a hydraulic jack hammer, as
    proposed and as conditioned, constitutes a “material change.” Thus, we conclude that
    Appellants have not shown, at this juncture, that they are likely to succeed in their
    appeal of the District Coordinator’s JO in Docket No. 63-4-11 Vtec.
    In assessing the second factor in our analysis, whether Appellants will suffer
    irreparable injury, should a stay not be granted for either permit amendment No.
    4C1232-1 or the JO, we ask if Appellants have made a case that such injuries are
    likely and if they would have an adequate remedy at law, should the injuries they
    allege actually occur. The injuries discussed by Appellants include damage to the
    structures on their property and the fixtures in their home, the potential for lost wages
    and vacation days should they stay home to protect their property to accommodate a
    non-specific blasting schedule, and the disruption to their lives from avoiding going
    outside during blasting and from being near loud noise and vibrations. Again,
    Appellants sincerely express fears but provide no evidence upon which this Court can
    rely to conclude that these injuries are likely to occur. See ln re Route 103 Quarrv,
    No. 205-10-05 Vtec, slip op. at 3-4 (Vt. Envtl. Ct. Sept. 14, 2007) (Durkin, J)
    (concluding there was not “sufficient evidentiary foundation . . . to link [the
    applicant’s] proposed future blasting practices and the harm that [the neighbors]
    anticipated”). Further, while Appellants argue that it may be inconvenient for them to
    seek monetary compensation for any injuries they should actually suffer, and that the
    quantification of such compensation may be difficult, they do not argue that they
    would have no legal recourse for seeking such compensation in the event that they
    should suffer such unfortunate injuries.
    We find that Appellants have not provided sufficient evidence to show that they
    will suffer irreparable injury justifying a stay in either appeal. However, to relieve
    Appellants of some of their concerns, we find it appropriate to require that, if Applicant
    does choose to use blasting while the appeal in Docket No. 62-4-1 1 Vtec is pending, it
    must provide notice to Appellants at least two business days prior to each day it
    undertakes such blasting.2
    Examining the third factor, whether the issuance of a stay will substantially
    harm Applicant, the parties’ filings lead us to conclude that Applicant will not be
    harmed by a stay restricting it from commencing ledge removal. Appellants argue that
    the removal of ledge is only one part of a larger development project and that Applicant
    can continue with the remainder of the development in the midst of a stay addressing
    removal of ledge. Applicant does not directly refute this contention; instead, Applicant
    expresses concern about the appeals generally and Appellants’ motive for seeking a
    stay for both appeals. Thus, we conclude that third factor weighs in Appellants’ favor,
    or in favor of granting a stay of both permit amendment No. 4C1232-1 and the JO.
    Whether the public interest will be best served by a stay is the fourth factor we
    consider, and we find it inconclusive for both appeals. Applicants are seeking to
    create a private development with multiple residential units, and the injuries
    Appellants allege are mainly to their real and personal property. T he parties’ filings
    are not helpful in our assessment of this factor, and we conclude that, if anything,
    2 We recognize that Applicant may already plan to do this since Applicant represents in it’s response in opposition
    to the motion to stay in Docket No. 62-4-11 Vtec that blasting will be “scheduled in advance, with ample notice
    given to neighbors.” (See Mem. in Opp’n to Mot. for Stay of Amendment to Act 250 Permit 9.)
    Appellants have failed to show that a stay of either permit amendment No. 4C1232-1
    or the JO will favor the public interest.
    Taking into consideration our conclusions under the four factors discussed
    above, we find that the equities favor Applicant and that a stay is not warranted for
    either permit amendment No. 4C1232-1 or the JO. Consequently, we DENY
    Appellants’ requests for a stay of the District Commission’s decision granting permit
    amendment No. 4C1232-1 authorizing the use of blasting to remove ledge, Docket No.
    62-4-11 Vtec, and the District Coordinator’s JO indicating that no amendment is
    necessary for use of a hydraulic jack hammer to remove ledge, Docket No. 63-4-11
    Vtec. We do, however, find it appropriate to require that Applicant provide notice to
    Appellants at least two business days prior to each day it undertakes blasting if it
    elects to do so while the appeal in Docket No. 62-4-11 Vtec is pending. We wish to
    emphasize that, to the extent that Applicant goes forward with using either blasting or
    a hydraulic jack hammer to remove ledge, techniques that the Court will be examining
    in the two pending appeals, Applicant does so at its own peril, since the Court may
    ultimately overturn the decisions authorizing the use of these techniques by Applicant.
    Conclusion
    For all o.f the reasons more fully discussed above, we GRANT Appellants’ motion
    to consolidate their two appeals so that the proceedings are coordinated in accordance
    with V.R.E.C.P. 2(b). We DENY Appellants’ motions to stay in both dockets, Docket
    Nos. 62-4-11 Vtec and 63-4-11 Vtec, although we require Applicant to provide notice
    to Appellants at least two business days prior to each day it undertakes blasting. We
    stress that if Applicant does undertakes ledge removal with either blasting or a
    hydraulic jack hammer while these appeals are pending, it does so at the risk that its
    authorization may ultimately be revoked.
    Done at Newfane, Vermont, this 6th day of July 2011.
                                

Document Info

Docket Number: 62-4-11 Vtec

Filed Date: 7/6/2011

Precedential Status: Precedential

Modified Date: 4/24/2018