ANR v. Stratton Gardens, LLC ( 2006 )


Menu:
  •                                   STATE OF VERMONT
    ENVIRONMENTAL COURT
    }
    Secretary, Vermont Agency of Natural Resources,          }
    Petitioner,                                       }
    }
    v.                                                       }      Docket No. 30‐2‐06 Vtec
    }
    Stratton Gardens, LLC,                                   }
    Respondent.                                       }
    }
    Decision and Order on Application for Intervention
    The Secretary of the Vermont Agency of Natural Resources (the Agency) issued an
    Administrative Order in this matter on November 18, 2005.  The Administrative Order
    imposed a monetary penalty and required Respondent to stop work on a subdivision until
    it had obtained all necessary permits and “all approved stormwater treatment systems and
    erosion control measures are in place and functioning.”  An exception to the stop work
    order allowed the installation of stormwater controls on lots to which title had passed prior
    to the issuance of the Administrative Order.  The parties agree that the project does not
    require either an Act 250 permit or any municipal permit.
    Respondent entered an appearance; however, the parties requested that the hearing
    on the merits of the matter be postponed as they were in negotiations  and were working
    on preparation of an Assurance of Discontinuance to resolve the matter.  Respondent has
    filed for bankruptcy, so that any payment of money in connection with resolution of this
    environmental violation must first be approved by the Bankruptcy Court.  The Bankruptcy
    Court hearing is scheduled for Tuesday, May 16, 2006.
    Joel Lutzker and Christine Lutzker, owners of one of the eight lots already sold in
    1
    the  subdivision,  have  moved  to  intervene  in  the  Environmental  Court  proceeding,
    pursuant to 10 V.S.A. §8012(d) and V.R.E.C.P. 4(d)(3).  We held an in‐person hearing on
    May 11, 2006 to enable the parties to present evidence, if they wished to do so,  as well as
    to make their arguments as to whether the Lutzkers are adequately represented by the
    existing parties.
    All that would be before the Court, if the Administrative Order were to go forward
    to  trial,  would  be  whether  there  was  a  violation,  and,  if  so,  what  penalty  would  be
    appropriate and whether work should stop until Respondent had applied for and obtained
    the required permits.
    Any  application  for  any  required  permit  would  not  be  before  the  Court  in  this
    proceeding; rather, the Lutzkers and any other interested parties would be able to comment
    on such a permit application during the administrative application process, and to appeal
    it to this Court in the future if they qualify as aggrieved parties and were dissatisfied with
    some aspect of the decision.  10 V.S.A. §8503(a)(1)(E).
    Just as the Agency could have negotiated an Assurance of Discontinuance with
    Respondent in advance of and instead of issuing the Administrative Order, the Agency
    remains  free  to  withdraw  the  Administrative  Order  and  to  negotiate  an  Assurance  of
    Discontinuance with Respondent without regard to any other potential party.  Once an
    Assurance of Discontinuance is presented to the Court, 10 V.S.A. §8007, rather than  §8012,
    governs the procedure before the Court.  There is no provision for intervention in relation
    to an Assurance of Discontinuance under §8007; rather, it is for the Office of Attorney
    General, rather than any potentially aggrieved parties, to challenge the sufficiency of an
    Assurance of Discontinuance to carry out the purposes of the Uniform Environmental
    Enforcement Act (10 V.S.A. Ch. 201). 10 V.S.A. §8007(c).
    If the Administrative Order were to go forward, we would at that time determine
    whether the Lutzkers qualify for party status to provide evidence and legal arguments only
    2
    in relation to the sufficiency of the Administrative Order.  10 V.S.A. §8012(d).  To the extent
    their concern with the penalty is that it should instead be spent on others of Respondent’s
    financial obligations, such issues may be more usefully presented to the Bankruptcy Court
    in tomorrow’s hearing.  We note that if this Court were considering the penalty de novo
    in the Administrative Order case, we could be limited to considering the statutory penalty
    factors in 10 V.S.A. §8010(b),  as informed by the factors in §8001.
    Accordingly, the Lutzkers’ motion to intervene is denied at the present time, without
    prejudice  to  its  renewal  if  the  anticipated  settlement  through  an  Assurance  of
    Discontinuance does not occur and the matter is set for trial, or if the anticipated settlement
    through  an  Assurance  of  Discontinuance  is  offered  to  this  Court  in  settlement  of  the
    Administrative Order, without the concurrent dismissal of the underlying Administrative
    Order.
    To assist the Lutzkers in keeping track of the Environmental Court proceedings, we
    will put them on the service list for court documents as an informational party, and request
    the other parties to send them a courtesy copy of any Assurance of Discontinuance (and/or
    any withdrawal of the Administrative Order) for their information.
    Done at Berlin, Vermont, this 15th day of May, 2006.
    _________________________________________________
    Merideth Wright
    Environmental Judge
    3
    

Document Info

Docket Number: 30-02-06 Vtec

Filed Date: 5/15/2006

Precedential Status: Precedential

Modified Date: 4/24/2018