Rock Pile Properties, LLC CU Permit - Decision on Motion ( 2022 )


Menu:
  • VERMONT SUPERIOR COURT
    Environmental Division                                                                   Docket No. 21-ENV-00102
    32 Cherry St, 2nd Floor, Suite 303,
    Burlington, VT 05401
    802-951-1740
    www.vermontjudiciary.org
    Rock Pile Properties, LLC CU Permit
    ENTRY ORDER
    Title:             Motion to Dismiss
    Filer:             Elizabeth Filosa, attorney for Applicant-appellee, Rock Pile Properties, LLC
    Filed Date:        November 19, 2021
    Memorandum in Opposition filed by Stephen L. Cusick, attorney for Appellant, Town of Barre,
    December 10, 2021
    The Town of Barre (“the Town”) appeals from a decision of its Development Review Board
    (“DRB”) granting a conditional use permit to Rock Pile Properties, LLC (“Applicant”). That permit
    authorized Applicant to convert the top two floors of a mixed-use building from four residential units
    to eight units. No other party has appealed the decision, although Linda and Mark Baker have entered
    appearances as interested parties.
    Applicant moves to dismiss the Town’s appeal, arguing that the Town lacks standing to bring
    the appeal for two reasons. The first is that the Town did not participate in the proceeding below, as
    is required to appeal a decision of that proceeding. See 24 V.S.A. § 4471. The second is that no
    interpretation of the town plan or bylaws is at issue in the arguments presented in the Town’s
    Statement of Questions, as is required for a Town to be an “interested person” under 24 V.S.A.
    § 4465(b). Because we agree with Applicant’s first argument, we need not reach its second.
    Challenges to an Appellant’s standing go to the Court’s subject matter jurisdiction. Brod v.
    Agency of Natural Resources, 
    2007 VT 87
    , ¶ 8, 
    182 Vt. 234
    . We therefore review this motion as one
    brought under V.R.C.P. 12(b)(1). When reviewing such a motion, this Court accepts all
    uncontroverted factual allegations as true and construes them in the light most favorable to the
    nonmoving party. Rheaume v. Pallito, 
    2011 VT 72
    , ¶ 2, 
    190 Vt. 245
    . This Court may consider
    evidence outside the pleadings if necessary to resolve such a motion. Conley v. Crisafulli, 
    2010 VT 38
    , ¶ 3, 
    188 Vt. 11
    .
    Applicant argues that the Town did not participate in the “proceeding” in which the decision
    under appeal was made, as that term is used in 24 VSA § 4471. The procedural history is not in
    dispute. Applicant initially submitted permit application CUP-21000004 (“CUP-004”) to undertake
    the conversion from four to eight residential units in June 2021. The DRB held a duly warned public
    hearing on July 14, 2021, which members of the Barre selectboard attended. At that hearing, the
    zoning administrator presented his view on the application. He noted that the applicant proposed
    Entry Regarding Motion                                                                                   Page 1 of 4
    Rock Pile Properties, LLC CU, No. 21-ENV-00102 (Vt. Super. Ct. Envtl. Div. Feb. 10, 2022) (Durkin, J.)
    fewer parking spaces than the Bylaws required, although the DRB had the authority under the Bylaws
    to grant a waiver to reduce the required number of parking spaces. The DRB decided to conduct a
    site visit to gain a better appreciation of parking options at and adjacent to the property and adjourned
    the hearing until August 11. On that day, members of the DRB, with the Town Manager present,
    conducted a site visit and then reconvened the continued hearing in the evening. The Town Manager
    and a member of the selectboard were also present at that hearing, at which the DRB denied the
    application “without prejudice.” The DRB “recommended” that the Applicant reapply with a detailed
    schematic of the planned parking lot, including locations of dumpsters and snow storage, if it still
    wished to pursue the development. Applicant Exhibit 2 at 22. At no time during, before, or after
    either of these hearings has it been suggested that the Town selectboard members or Manager offered
    oral or written testimony with evidence for the DRB’s consideration or a statement of concern.
    The next day, August 12, 2021, Applicant submitted a new permit application, CUP-21000006
    (“CUP-006”). The narrative portion of this application was identical to CUP-004, but instead of an
    aerial photograph of the property with tax parcel boundary lines and proposed parking spaces
    superimposed, applicant submitted a self-prepared parking plan demonstrating some of the
    dimensions of the parking lot and the locations of the proposed spaces. This plan also reduced the
    proposed number of parking spaces for tenants from nine to eight.1 See Town Exhibits A, C;
    Applicant Exhibit 3. The DRB held a duly-warned public hearing on CUP-006 on September 8. No
    representative of the Town submitted testimony ahead of or appeared at that hearing. At the hearing,
    the zoning administrator presented his staff report on the revised parking plan, including proposed
    conditions, should the Board grant the permit. Applicant Exhibit 3. Members of the DRB discussed
    that plan with the applicant and a neighbor, as well as other elements of the application, such as the
    envisioned number of residents per unit. The DRB voted to close the hearing on the application, and
    by a vote of 4-2 approved the application with conditions.
    The Town thereafter filed a timely appeal with this Court concerning the DRB’s approval of
    this second application.
    As part of the first step of our legal analysis, we must determine whether the facts presented
    show that the Town participated in the proceeding in which the decision on CUP-006 was issued.
    Although it is uncontroverted that representatives of the Town were present for the July 14 hearing
    and August 11 site visit and hearing concerning the first application, neither party has suggested, nor
    do the exhibits submitted establish, that those representatives “participated” as required by statute.
    The statute clearly defines participation as “offering, through oral or written testimony,
    evidence or a statement of concern related to the subject of the proceeding.” 24 V.S.A. § 4471. There
    has been no suggestion that the Town’s representatives offered such testimony at any point from the
    moment CUP-004 was submitted to the moment that application was denied. Nevertheless, Applicant
    appears to have accepted that the Town participated in these hearings, and we therefore do not reach
    our decision on this basis. See, e.g., Applicant’s Reply in Support of Motion to Dismiss at 2.
    Instead, we conclude that those hearings did not form part of the same proceeding in which
    the decision on CUP-006 was reached. The statute does not define the term “proceeding,” however
    1 In fact, the narrative portion of the application still referred to the property supporting a minimum of nine parking
    spaces. However, the new attached parking map only showed eight spaces. Town Exhibit C at 2, 5. At the hearing, the
    zoning administrator’s report analyzed the project assuming only eight parking spaces on the property were proposed, and
    the DRB approved the project on the condition that the parking map, which showed only eight spaces, was authoritative
    and binding. Applicant Exhibit 3 at 6–7.
    Entry Regarding Motion                                                                                        Page 2 of 4
    Rock Pile Properties, LLC CU, No. 21-ENV-00102 (Vt. Super. Ct. Envtl. Div. Feb. 10, 2022) (Durkin, J.)
    the Vermont Supreme Court has offered guidance on its meaning in In re Carroll, 
    2007 VT 19
    , 
    181 Vt. 383
    .
    Carroll concerned an application for subdivision approval in the Town of Jericho. The Town
    had adopted a multi-stage procedure for major subdivision review, as authorized by 24 V.S.A.
    § 4418(2)(B). That procedure required the developer to submit a preliminary plat and the DRB to
    hold a public hearing on that plat. If the DRB approved of the preliminary plat, the developer would
    need to submit a final plat which would be the subject of a further public hearing before a final DRB
    decision. Carroll, 
    2007 VT 19
    , ¶11. The appellant in Carroll had submitted written testimony ahead
    of the hearing on the preliminary plat but did not offer testimony ahead of or during the hearing on
    final plat approval. Reasoning that these were two distinct proceedings, the Environmental Court
    determined that the appellant did not have standing to appeal the final plat approval.
    The Supreme Court reversed. Accepting that appeal was available from the DRB’s decision
    on the preliminary plat approval for the sake of argument, see id. ¶ 16, the Supreme Court nevertheless
    held that the preliminary and final plat approvals formed part of the same proceeding. First, it quoted
    approvingly from Black’s Law Dictionary (8th) definition of “proceeding” as “[t]he regular and orderly
    progression of a lawsuit, including all acts and events between the time of commencement and the
    entry of judgment”). Id. ¶ 13. It concluded this definition supported viewing preliminary and final
    plat approval as all part of the same proceeding.
    Next, the Court looked to the legislature’s intent in enacting the requirement of participation
    by interested persons to appeal a land use decision, and creating the available procedures for multi-
    stage subdivision approval. It determined that it was consistent with this intent to allow someone
    who participated only in the preliminary plat approval to appeal the final plat approval, given that
    under the Jericho procedures, key features of subdivision design could be resolved at the preliminary
    stage through a “general agreement” reached by the DRB and developer. Id. ¶¶ 14-15. Finally, the
    Court reasoned that the mere issuance of an appealable decision, as may have been the case with the
    Jericho DRB’s approval of the preliminary subdivision plan, did not necessarily mark the end of one
    proceeding and the beginning of the next. Id. ¶ 16 (and going on to state, “[i]n fact, statutory language
    giving the right to appeal ‘a decision rendered in that proceeding’ suggests that there can be more than
    one appealable decision within a proceeding.”).
    The Town seizes especially on this latter statement to argue that Carroll requires us to view
    the hearings on CUP-004 as part of the same proceeding in which the decision on CUP-006 was
    reached. We disagree. We have previously remarked upon the “unique procedural continuity between
    preliminary and final plan subdivision approval processes.” In re Waitsfield Water System Prelim. &
    Final Plan Apps., Nos. 39-3-12 & 65-5-12 Vtec, slip op. at 3 (Vt. Super. Ct. Envtl. Div. July 20,
    2012)(Durkin, J.). While subdivision approval processes vary significantly from town to town, their
    uniqueness generally lies in the mixture of final decisions and guidance that the municipal panel is
    required or authorized to issue at preliminary stages of review, while any decision to finally approve a
    subdivision is reserved for the later stages. See In re Charron 13-Lot PUD Preliminary Plat, No. 24-
    2-19 Vtec, slip op. at 2–3 (Vt. Super. Ct. Envtl. Div. June 17, 2019) (Durkin, J.) (discussing subdivision
    review and the Court’s inquiry into what discrete issues, if any, a town’s bylaws authorize the municipal
    panel to finally decide at early stages of the process).
    That multi-stage review before the same planning body distinguishes subdivision approval
    from the conditional use approval process that Applicant faced before the DRB in this instance. When
    the DRB considered CUP-004, it had every authority (or so we are led to believe, as no copy of the
    Bylaws has been submitted into evidence) to issue the conditional use permit that Applicant sought.
    Entry Regarding Motion                                                                                   Page 3 of 4
    Rock Pile Properties, LLC CU, No. 21-ENV-00102 (Vt. Super. Ct. Envtl. Div. Feb. 10, 2022) (Durkin, J.)
    Instead, the DRB chose to deny the permit application without prejudice, ending that proceeding, and
    leaving it to Applicant to decide whether to re-apply and begin a new proceeding.
    We accept, as we must, Carroll’s holding that by rendering an appealable decision, a municipal
    body does not automatically draw a dividing line between one proceeding and the next. However, we
    believe that when the DRB is at a stage in a process where it has authority to grant final approval for
    a permit, then either granting or denying that permit does ordinarily complete those proceedings
    before that tribunal.
    The Town argues that the DRB “obtained critical information and knowledge in the first
    hearing and site visit and relied on that information in approving the application on September 8.”
    Even viewed in the light most favorable to Town as the non-moving party, we do not believe that the
    facts show that the Town relied on this information in a manner sufficient to merge two proceedings
    into one. The zoning administrator submitted a new staff report ahead of the DRB hearing on the
    second application and the record reflects that the DRB deliberated anew on that application at the
    end of the September 8 hearing. The reduction in the number of parking spaces to eight and the
    clearer understanding of vehicular circulation in the parking lot provided by the new parking plan,
    both of which were new in CUP-006, appear to have been critical to the DRB’s decision to grant the
    permit.
    Finally, we are wary of the precedent that accepting the Town’s argument would set. The
    Town was on ample notice both when the DRB denied the first application and when the DRB called
    a new hearing on the second application. It is, moreover, a sophisticated actor in the municipal land-
    use process. In light of those points, the Town could not have reasonably believed at the time that
    participation in hearings on the CUP-004 application would entitle it to an appeal of the DRB’s
    approval of the CUP-006 application. Given the minimal amount of effort required to participate in
    a municipal proceeding under 24 VSA § 4471, we cannot encourage a practice of haphazard
    participation followed by attempts to justify it using a stretched definition of “proceeding.” Doing so
    would contravene what we have deemed to be “[t]he primary purpose of the participation requirement
    . . . [namely] to provide sufficient notice of an opponent’s concerns about a development project while
    the municipal panel is considering the permit application.” Waitsfield Water System, Nos. 39-3-12 &
    65-5-12 Vtec at 5 (July 20, 2012).
    If the Town wished to preserve its right to appeal any decision on the CUP-006 application,
    it was required to participate in the proceeding during which that decision was rendered. Having
    concluded it did not, we must GRANT the present motion and dismiss the Town’s appeal.
    So Ordered.
    Electronically signed on February 10, 2022, at Brattleboro, VT pursuant to V.R.E.F. 9(d).
    ________________________________
    Thomas S. Durkin, Superior Judge
    Environmental Division
    Entry Regarding Motion                                                                                   Page 4 of 4
    Rock Pile Properties, LLC CU, No. 21-ENV-00102 (Vt. Super. Ct. Envtl. Div. Feb. 10, 2022) (Durkin, J.)
    

Document Info

Docket Number: 21-ENV-00102

Filed Date: 2/1/2022

Precedential Status: Precedential

Modified Date: 7/31/2024