Morrisville Hydroelectric Proj Water Quality ( 2017 )


Menu:
  • STATE OF VERMONT
    SUPERIOR COURT ENVIRONMENTAL DIVISION
    Docket No. 103-9-16 Vtec
    Morrisville Hydroelectric Project Water
    . Decision on Motions
    Quality
    This is an appeal from a water quality certification issued by the Agency of Natural
    Resources to Morrisville Water and Light for the Morrisville Hydroelectric Project located on the
    Lamoille River and its tributaries in north-central Vermont. Morrisville Water and Light applied
    for the certification as part of a separate licensing application with the Federal Energy Regulatory
    Commission. The Agency of Natural Resources issued the certification, and Morrisville Water
    and Light subsequently filed an appeal in this Court challenging various aspects of the
    certification as issued. American Whitewater and the Vermont Paddlers’ Club, the Vermont
    Natural Resources Council, and the Vermont Council of Trout Unlimited all filed cross-appeals.
    The matter is now before the Court on multiple motions to dismiss and motions for
    summary judgment.
    i. Motions under Review
    a. AW/VPC Motion for Partial Summary Judgment
    On February 3, 2017, American Whitewater and the Vermont Paddlers’ Club {(AW/VPC)
    moved for summary judgment on its amended Question 1.
    The Agency of Natural Resources (ANR) filed an Opposition to the motion on March 6,
    2017, and AW/VPC filed a response on March 21, 2017.1 AW/VPC is represented by Daniel P.
    Richardson, Esq. and Ryan P. Kane, Esq. ANR is represented by Leslie A. Welts, Esq. and Jennifer
    S. Duggan, Esq.
    * The response filed March 21, 2017 is missing a page. AW/VPC re-filed the response, including the missing
    page, on March 22, 2017.
    For the reasons set out below, AW/VPC’s motion for summary judgment on its amended
    Question 1 is DENIED.
    b. ANR Motion to Dismiss and Motion for Summary Judgment
    On February 3, 2017, ANR moved to dismiss, pursuant to civil rule 12(b)(6), a portion of
    Morrisville Water and Light (MWL) amended Question 6, and AW/VPC Questions 1 and 14. ANR
    also moved for summary judgment on MWL Questions 1, 2, and 3.
    MWL filed a motion for an extension for time to reply on February 9, 2017, and then filed
    an opposition to the motion to dismiss and motion for summary judgment on February 21, 2017.
    ANR filed a reply to this on March 8, 2017. AW/VPC filed an Opposition to the motion to dismiss
    on March 8, 2017, and ANR filed a reply on March 22, 2017.
    For the reasons set out below, ANR’s motion to dismiss AW/VPC amended Question 1 is
    DENIED, and its motion to dismiss AW/VPC amended Question 14 is GRANTED. ANR’s motion
    for summary judgment on part of MWL Question 3 is GRANTED, and ANR’s motions to dismiss
    and for summary judgment on MWL Questions 1, 2, and 6 are MOOT.
    c. VNRC and VTTU Motion to Dismiss MWL Questions
    On February 3, 2017, the Vermont Natural Resources Council (VNRC) and the Vermont
    Council of Trout Unlimited (VTTU) moved to dismiss Appellant Morrisville Water and Light’s
    (MWL) amended Questions 1, 2, 3, 6, and 8 pursuant to civil rule 12(b)(6).
    MWL filed an opposition to the motion on February 16, 2017. VNRC is represented by
    Jon Groveman, Esq.; VITU is represented by Robert J. Carpenter, Esq.; and MWL is represented
    by Gregory M. Eaton, Esq. and Clara E. Conklin, Esq.
    For the reasons set out below, VNRC AND VTTU’s motion to dismiss MWL Questions 1, 2,
    6, 8, and the portion of Question 3 not affected by ANR’s motion for summary judgment is
    GRANTED.
    d. VNRC and VTTU Motion for Summary Judgment on AW/VPC Questions
    On February 3, 2017, VNRC and VTITU moved for summary judgment on AW/VPC’s
    amended Questions 3, 4, 5, 7, 8, 9, 11, and 12.
    ANR filed a response in support of the motion on March 6, 2017. AW/VPC filed an
    opposition to the motion for summary judgment on March 8, 2017, and VNRC AND VTTU filed a
    response to the opposition on March 21, 2017. AW/VPC filed an additional response opposing
    the motion for summary judgment, and responding to ANR’s statement of facts, on March 21,
    2017. ANR filed a motion for leave to file a sur-reply, along with a sur-reply, on March 28, 2017.
    ANR filed its motion for leave to file a sur-reply in response to a specific, discrete assertion
    made by AW/VPC in its March 21, 2017 response. A party does not normally have a right to file
    a sur-reply. V.R.C.P. 78(b)(1). When new issues are raised in a response, however, the opposing
    party may be entitled to file a sur-reply. Champlain Parkway Wetland CU Determination, No.
    123-10-16 Vtec, slip op. at 3 (Vt. Super. Ct. Envtl. Div. Apr. 14, 2017) (Durkin, J.) (citations
    omitted). In the case now before us, AW/VPC’s March 21, 2017 response raises a new issue to
    which we find it appropriate to allow ANR to respond. We therefore GRANT ANR’s motion for
    leave to file a sur-reply.
    For the reasons set out in detail below, VNRC and VTTU’s motion for summary judgment
    on AW/VPC’s amended Question 3 is GRANTED, and VNRC and VTTU’s motion for summary
    judgment on AW/VPC’s amended Questions 4, 5, 7, 8, 9, 11, and 12 is DENIED.
    il. Legal and Regulatory Framework
    Section 401(a)(1) of the Federal Clean Water Act (CWA) requires an “applicant for a
    Federal license or permit for any activity... which may result in any discharge into... navigable
    waters” to present a water quality certification (§ 401 certification) to the licensing or permitting
    agency. 
    33 U.S.C. § 1341
    (a)(1). The purpose of the § 401 certification is to ensure that the activity
    to be licensed or permitted will comply with “effluent limitations and other limitations” required
    by the CWA and “any other appropriate requirement of State law.” 
    33 U.S.C. § 1341
    (d). The
    certifying agency can impose reasonable conditions and limitations in a § 401 certification to
    ensure compliance with these laws. PUD No. 1 of Jefferson Cty. v. Washington Dep’t of Ecology,
    
    511 U.S. 700
    , 712 (1994); 
    33 U.S.C. § 1341
    (d).
    In Vermont, the legislature has delegated the responsibility for administering § 401
    certification to ANR. 10 V.S.A. § 1004.
    The phrase “any other appropriate requirement of State law” has been only partly
    defined.
    Pursuant to CWA § 303, states are required to adopt water quality standards, which are
    then approved by the U.S. Environmental Protection Agency (EPA). 
    33 U.S.C. § 1313
     (calling for
    water quality standards); 40 C.F.R. Part 131 (EPA regulations guiding the establishment of water
    quality standards). The U.S. Supreme Court has held that state water quality standards adopted
    pursuant to CWA § 303 are among the “other limitations” that must be complied with for § 401
    certification, and that “limitations to assure compliance with state water quality standards” also
    fall into the category of “other appropriate requirement|s] of state law” required by § 401
    certification. PUD No. 1,511 U.S. at 713; 
    40 CFR § 121.2
    (a)(3) (indicating that a § 401 certification
    must give “reasonable assurance” that the activity will not violate state water quality standards).
    Vermont has adopted the Vermont Water Quality Standards (VWQS) pursuant to CWA
    § 303.2 In re Clyde River Hydroelectric Project, 
    2006 VT 11
    , 3, 
    179 Vt. 606
    . , Any § 401
    certification issued in Vermont must ensure that the activity to be certified will comply with the
    VWOQS. See PUD No. 1, 
    511 U.S. 700
    ; 
    40 CFR § 121.2
    (a)(3)
    The Supreme Court has declined to “speculate on what additional state laws, if any, might
    be incorporated by [the ‘other appropriate requirement of state law’] language” set out in CWA
    § 401. PUD No. 1,511 U.S. at 713.3
    In the case now before us, MWLis applying to the Federal Energy Regulatory Commission
    (FERC) for a license for the Morrisville Hydroelectric Project (the Project), and has applied to ANR
    for a § 401 certification as part of the FERC license application process. ANR issued a § 401
    certification, and MWL, AW/VPC, VNRC, and VTTU appealed that certification to the
    Environmental Division. See 10 V.S.A. § 8504(a).
    In taking the appeal of the § 401 certification, our role is to determine whether the Project
    complies with the provisions of CWA specified in § 401, the VWQS, and any other appropriate
    ? The VWOQS state that they are intended to achieve the goals set out in the CWA and 10 V.S.A. § 1250,
    which is the first section of the Vermont Water Pollution Control Act. VWQS § 1-02.
    3 Prior to the Supreme Court’s decision in PUD No. 1, some state courts interpreted this provision broadly
    as “a congressional authorization to the states to consider all state action related to water quality in imposing
    conditions on section 401 certificates.” State, Dep’t of Ecology v. Pub. Util. Dist. No. 1 of Jefferson Cty., 
    849 P.2d 646
    , 653 (Wash. 1993), aff'd sub nom. PUD No. 1, 
    511 U.S. 700
     (1994) (citing Arnold Irr. Dist. v. Dep't of Envtl. Quality,
    
    717 P.2d 1274
    , 1280 (1986)). Others read this language more narrowly. Niagara Mohawk Power Corp. v. N.Y. State
    Dep’t of Envt!. Conservation, 
    624 N.E.2d 146
    , 150 (N.Y. Ct. App. 1993).
    state law; and whether any conditions or limitations should be imposed in the § 401 certification
    to ensure compliance with these laws. See 10 V.S.A. § 8504(h) (calling for de novo review).4
    IN. AW/VPC Question 1
    AW/VPC moves for summary judgment on its Question 1, and ANR moves to dismiss
    AW/VPC Question 1.
    a. Motion to Dismiss
    ANR moves to dismiss AW/VPC Question 1 for “failure to state a claim upon which relief
    can be granted.” V.R.C.P. 12(b)(6). When considering such a motion, we “must take the factual
    allegations in the complaint as true, and consider whether ‘it appears beyond doubt that there
    exist no facts or circumstances that would entitle the [moving party] to relief.’” Colby v. Umbrella,
    Inc., 
    2008 VT 20
    , 415, 
    184 Vt. 1
     (quoting Alger v. Dep’t of Labor & Indus., 
    2006 VT 115
    , 9 12, 
    181 Vt. 309
    ).
    As explained above, MWL applied for a § 401 certification to satisfy 
    33 U.S.C. § 1341
    (a)(1).
    Section 1341(a)(1) provides that if the certifying agency—here, ANR—“fails or refuses to act on
    a request for certification” within one year after receipt of the request, then “the certification
    requirements of this subsection shall be waived with respect to such Federal application.”
    AW/VPC Question 1 asks “[w]hether [ANR] waived issuance of a Water Quality
    Certification for the [Project] by failing to act on the application for Water Quality Certification
    ... Within one (1) year of receiving an application, in accordance with Section 401(a)(1) of the
    Clean Water Act, 
    33 U.S.C. § 1341
    (a)(1).”
    In its motion to dismiss, ANR argues that FERC, as the agency to which MWL is applying
    for a license, has exclusive authority to decide whether the certification requirement has been
    waived, and that ANR, and the Environmental Division on review, does not have authority to
    make this determination.> AW/VPC disputes this assertion.
    4 Although the VWQS were amended effective January 15, 2017, in the matter now before us we consider
    compliance with the VWQS that went into effect October 30, 2014. Under our vested rights doctrine, the earlier
    VWQS were in effect when the application in question was filed and therefore apply to this case. See Smith v.
    Winhall Planning Comm’n, 
    140 Vt. 178
    , 181 (1981); VWQS § 1-10(A)(2).
    5 At its base, this challenge asserts that the Environmental Division does not have jurisdiction, an assertion
    more properly raised pursuant to V.R.C.P. 12(b)(1). Regardless, the standards for reviewing 12(b)(6) and 12(b)(1)
    When a state agency issues a § 401 certification, state courts have jurisdiction to review
    the determinations made in that § 401 certification, while federal courts generally do not.
    Roosevelt Campobello Int’l Park Comm’n v. U.S. E.P.A., 
    684 F.2d 1041
    , 1056 (ist Cir. 1982); 
    40 C.F.R. § 124.55
    (e). This is because “the breadth of State authority under Section 401 results in
    most challenges to a [§ 401 certification] implicating only questions of State law.” Alcoa Power
    Generating Inc. v. F.E.R.C., 
    643 F.3d 963
    , 971 (D.C. Cir. 2011) (citing City of Tacoma, Wash. v.
    FERC, 
    460 F.3d 53
    , 67 (D.C. Cir. 2006)).
    While the federal licensing agency that the § 401 certification is issued for (in this case,
    FERC), and the D.C. Circuit Court on appeal from that agency’s decision, have no jurisdiction over
    § 401 certification challenges that implicate only questions of state law, they do have jurisdiction
    to determine whether the § 401 certification complies with the certification requirements set
    out in CWA § 401. Id. This is because whether a § 401 certification is invalid because the
    certifying state agency failed to “’act on a request for certification’ within the statutory one-year
    period” is a requirement set out in CWA § 401, and therefore “is a question of federal law.” Id.
    at 971-72 (quoting 
    33 U.S.C. § 1341
    (a)(1)).
    While federal courts have jurisdiction, this does not mean that state courts do not have
    jurisdiction over the same question. State courts generally have concurrent jurisdiction over
    federal claims. Gulf Offshore Co. v. Mobil Oil Corp., 
    453 U.S. 473
    , 478 (1981) (citations omitted).
    Congress can divest state courts of this concurrent jurisdiction either “by an explicit statutory
    directive, by unmistakable implication from legislative history, or by a clear incompatibility
    between state-court jurisdiction and federal interests.” 
    Id.
     The statute here simply states that if
    the certifying agency fails to act within one year, “the certification requirements of this
    subsection shall be waived with respect to such Federal application.” 
    33 U.S.C. § 1341
    (a)(1).
    Nothing in the statute indicates an intent to divest state courts of jurisdiction over determining
    whether the one-year timeline has been met. Indeed, at least one state supreme court decision
    considers whether a state certifying agency failed to comply with the one-year requirement in
    are sufficiently similar that our analysis would be the same under either standard. See Rheaume v. Pallito, 
    2011 VT 72
    , 7 2, 
    190 Vt. 245
    .
    CWA § 401. FPL Energy Maine Hydro LLC v. Dep’t of Envtl. Prot., 
    2007 ME 97
    , 14] 15-23, 
    926 A.2d 1197
    .6
    The one-year review requirement in the CWA is similar to a Vermont statute requiring
    municipal panels to render a decision within a certain period of time after holding a hearing ona
    permit application. 24 V.S.A. § 4464(b)(1). If the municipal panel fails to comply with this
    timeline, the application is deemed approved. Id. The purpose of deemed approval is to “remedy
    indecision and protracted deliberations on the part of zoning boards and to eliminate deliberate
    or negligent inaction by public officials.” In re Morrill House, LLC, 
    2011 VT 117
    , 1.8, 
    190 Vt. 652
    (mem.) (quoting In re Ashline, 
    2003 VT 30
    , | 13, 
    175 Vt. 203
    ); compare to Alcoa Power, 
    643 F.3d at 972
     (“In imposing a one-year time limit on States to ‘act,’ Congress plainly intended to limit
    the amount of time that a State could delay a federal licensing proceeding without making a
    decision on the certification request.”).”
    In cases where the issue of deemed approval is raised, we have jurisdiction to consider
    whether the municipal panel below complied with the statutory timeline in issuing a decision.
    See, e.g., Brisson Stone, LLC v. Town of Monkton, 
    2016 VT 15
    , 4] 25 (Vt. Feb. 12, 2016). Likewise,
    ® The question of whether the state court has jurisdiction over determining compliance with the one-year
    requirement is not addressed in the decision.
    In FPL Energy, the state certifying agency granted an application for a § 401 certification within one year of
    the application being filed. 
    2007 ME 97
    , 94. Following an appeal in state trial court by a group of non-governmental
    organizations, and more than one year after the application was filed, the state agency vacated its initial decision
    and denied the application for a § 401 certification. Id. 1] 4-6. FPL appealed that denial in state trial court, which
    affirmed, and then to the Maine Supreme Court. Id. 4 1.
    At the Supreme Court, FPL submitted that because the vacation and denial was issued outside of the one-
    year time period, the § 401 certification requirement was waived. Id. 4 1. In the parallel licensing matter, FERC
    disagreed, holding that there is “nothing in the language of section 401 to suggest that a State must not only act on
    the certification request but also take action on any appeals that might subsequently be filed within one year.” FPL
    Energy Maine Hydro LLC, 
    108 FERC 4
    ] 61261, 62431 (Sept. 21, 2004). FERC stayed the matter pending resolution of
    the § 401 certification appeal—which also raised other arguments—in state court. Id. Without deferring to FERC’s
    decision regarding the one-year time period, the Maine Supreme Court also disagreed with FPL, based largely on its
    conclusion that the legislative history of Section 401 shows “a congressional intent that an agency take action on an
    application within one year,” but not that “all in-state appeals ... be completed within the same one-year deadline.”
    FPL Energy, 
    2007 ME 97
    , 4] 23.
    In short, compliance with the one-year period was addressed by both FERC and the state court in this case.
    7 This analogy is imperfect because once a municipal permit application is deemed approved by the Court,
    the matter is concluded save for appeals. The § 401 certification is unlike a final permit, because it does not conclude
    the matter—instead, the § 401 certification is presented to the ultimate permitting agency, which then determines
    whether to grant the permit.
    we have jurisdiction here to consider whether ANR complied with the statutory timeline set out
    in Section 401. For this reason, we disagree with ANR’s argument that FERC—and not the
    Environmental Division—has exclusive authority to decide whether the certification requirement
    has been waived. ANR’s motion to dismiss AW/VPC Question 1 is therefore DENIED.?
    b. Motion for Summary Judgment
    We next turn to AW/VPC’s motion for summary judgment on its Question 1, and recite
    the following facts solely for the purpose of ruling on this motion.
    1. On April 22, 2013, Craig Myotte, Manager of MWL, sent an email to Jeff Crocker at ANR
    with a § 401 certification application attached. In the email, Mr. Myotte states, “I would
    appreciate it if you could review the document to see if it meets the ANR’s requirements.” The
    attached application is signed by Mr. Myotte, and dated April 19, 2013.
    2. On April 22, 2013, Mr. Crocker responded by email, stating that the § 401 certification
    application “will meet ANR requirements.” He notes that the application has the incorrect ANR
    address on it, further notes that he is in the process of updating ANR’s new address on the web
    site, and that “the application | sent you via email has the correct address. | just want to make
    sure you send the application to the Montpelier address.”
    3. On April 25, 2013, MWL applied to FERC for a license. An exhibit to the application states
    that MWL “has filed an application for Water Quality Certification with [ANR].”
    4. On June 14, 2013, FERC sent a letter to Mr. Myotte indicating that MWL’s FERC application
    had a number of deficiencies. On November 5, 2013, FERC issued notice that a complete
    application had been filed.
    8 In reaching this conclusion, we are aware that FERC has explained it “ha[s}] the authority to consider
    whether to accept conditions contained in late-filed” § 401 certification, and that it “routinely dof[es] so.” Cent.
    Vermont Pub. Serv. Corp., 
    113 FERC 4
    ] 61167, 61654 4 20 (Nov. 17, 2005); see also Puerto Rico Sun Oil Co. v. U.S.
    E.P.A., 
    8 F.3d 73
    , 79 (1st Cir. 1993) (giving deference to the EPA’s interpretation of its regulations and Section 401 to
    give it discretion to “declare a waiver” once the one-year deadline has passed, or to decide to accept a certification
    filed late).
    Because we sit in the position of the agency whose action we are reviewing, it is not within the scope of our
    review to consider whether FERC might accept a § 401 certification where the certifying agency has failed to comply
    with the one-year timeline. Furthermore, a footnote in the Central Vermont FERC decision indicates skepticism that
    a certifying state agency has the authority to extend the one-year deadline to act, given that the purpose of the
    deadline is “to preclude undue delay by the states.” Id. ] 16.15. Again, as we sit in the certifying agency’s place,
    that skepticism may be extended to any decision we might render regarding whether FERC might accept a § 401
    certification despite noncompliance with the one-year timeline.
    5. On January 15, 2014, FERC sent a letter to Mr. Myotte indicating that MWL was one week
    overdue in filing either a copy of a § 401 certification; a copy of the request for § 401 certification,
    including proof of the date the certifying agency received the request; or evidence of a waiver of
    the § 401 certification.
    6. On January 30, 2014, Mr. Crocker forwarded his April 22, 2013 email to Mr. Myotte,
    stating “Here was my response to your initial email in April indicating that you would need to
    mail a hard copy” of the § 401 certification application to ANR.
    7. Later that same day, Mr. Myotte emailed a § 401 certification application, dated January
    30, 2014, to Mr. Crocker. In a response email, Mr. Crocker indicated that the application looked
    complete, adding “Typically you would mail a copy of the application to us for processing and we
    issue a letter to you acknowledging its receipt and that it is complete. ! can accept the electronic
    copy of the application since your Final license application has been deemed complete by FERC,
    and will issue a letter that we have receive[d] the application.”
    8. A short time later, Mr. Crocker emailed Mr. Myotte, asking him to revise the application
    to include the Lake Elmore Development, which Mr. Myotte did and sent back to Mr. Crocker.
    The revised application is also dated January 30, 2014.
    9. On February 3, 2014, Mr. Crocker sent a letter to Mr. Myotte acknowledging the receipt
    of the § 401 certification application on January 30, 2014.
    10. On February 4, 2014, MWL filed with FERC the January 30, 2014 § 401 certification
    application and February 3, 2014 acknowledgement from ANR.
    11. On November 7, 2014, Mr. Myotte sent a letter to ANR via email stating that MWL was
    withdrawing its January 30, 2014 § 401 certification application and simultaneously re-applying
    for § 401 certification.
    12. In a September 9, 2015 letter to ANR, MWL stated that it was withdrawing its November
    7, 2014 application and re-applying for § 401 certification.
    13. ANR issued the § 401 certification on August 9, 2016.
    We grant summary judgment to a party “if the movant shows that there is no genuine
    dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
    V.R.C.P. 56(a), applicable here through V.R.E.C.P. 5(a)(2). “In determining whether there is a
    genuine issue as to any material fact, we will accept as true the allegations made in opposition
    to the motion for summary judgment, so long as they are supported by affidavits or other
    evidentiary material.” Robertson v. Mylan Labs., Inc., 
    2004 VT 15
    , 4] 15, 
    176 Vt. 356
     (citation
    omitted). In this case, AW/VPC and ANR have both submitted affidavits and other evidentiary
    material to support their statements of facts and responses.
    AW/VPC contends that Mr. Myotte emailed the § 401 certification application dated April
    19, 2013 to Mr. Crocker on April 22, 2013 intending it to be accepted as a complete application
    by ANR. ANR disputes this and characterizes the April 22, 2013 email as a preliminary
    communication between ANR and MWL to allow MWL to receive feedback on its § 401
    certification application. ANR argues that a formal application was not submitted until January
    30, 2014.
    On the record now before us, we are unable to conclude that the undisputed material
    facts entitle AW/VPC judgment as a matter of law on its Question 1. Instead, the evidence largely
    supports ANR’s interpretation of events.
    While somewhat vague, the April 22, 2013 email communication from Mr. Crocker
    suggests that a complete application must be sent by regular mail to ANR. There is nothing in
    the record indicating that this was done at that time.
    In addition, the April 19, 2013 application was incomplete, as it did not include the Lake
    Elmore Development. The second version of the January 30, 2014 was complete, as it did include
    this part of the Project. See In re Keystone Dev. Corp., 
    2009 VT 13
    , 4] 5, 
    186 Vt. 523
     (mem.)
    (explaining that “a permit applicant gains a vested right in the governing regulations in existence
    when a full and complete permit application is filed”) (citing Smith v. Winhall Planning
    Commission, 
    140 Vt. 178
    , 182 (1981)).
    Furthermore, MWL and ANR have conducted themselves in a manner consistently
    demonstrating that both parties believed the § 401 certification application was submitted on
    January 30, 2014. When FERC asked MWL for information on the status of the § 401 certification
    on January 15, 2014, MWL did not send FERC the April 19, 2013 § 401 certification application or
    the April 22, 2014 communication with MWL to support an assertion that its application had been
    filed at that time. Nor did MWL contact ANR for information on the status of the April 19, 2013
    10
    application. Instead, MWL submitted the January 30, 2014 application to ANR and then sent
    documents to FERC stating that the application was submitted on January 30, 2014. On
    November 7, 2014, MWL withdrew its January 30, 2014 application and simultaneously re-
    applied. In later withdrawals, MWL again referred to the application as being originally submitted
    on January 30, 2014. Throughout this entire course of events, both MWL and ANR treated the
    January 30, 2014 application as the official and complete application.
    Notably, while MWL has appealed parts of the § 401 certification, it does not argue that
    the § 401 certification is invalid for failing to comply with the one-year timeline. MWL has not
    weighed in on AW/VPC’s Question 1.
    For these reasons, we conclude, on the record now before us, that MWL submitted its
    § 401 certification application on January 30, 2014, and that, in light of subsequent withdrawals
    and re-applications, ANR complied with the one-year timeline in Section 401. We are therefore
    inclined to grant summary judgment in favor of ANR on AW/VPC Question 1. Because ANR has
    not filed a cross-motion on this question, however, we may not grant it summary judgment
    without giving all parties notice and an opportunity to respond. V.R.C.P. 56(f)(1). We hereby
    give all parties 30 days from the date of this decision to file briefs and supporting documents with
    the Court regarding the question of whether ANR complied with the one-year timeline in Section
    401.
    IV. AW/VPC Question 14
    ANR moves to dismiss AW/VPC amended Question 14 for failure to state a claim on which
    relief can be granted.?
    > AW/VPC argues that ANR’s motion to dismiss AW/VPC Question 14 should be converted to a motion for
    summary judgment pursuant to the following provision set out in V.R.C.P. 12(b):
    If, on a motion asserting the defense numbered (6) to dismiss for failure of the pleading to state a
    claim upon which relief can be granted, matters outside the pleading are presented to and not
    excluded by the court, the motion shall be treated as one for summary judgment and disposed of
    as provided in Rule 56, and all parties shall be given reasonable opportunity to present all material
    made pertinent to such a motion by Rule 56.
    AW/VPC suggests in its opposition that if the motion is converted to one for summary judgment, the parties should
    be allowed to complete discovery on whether the “flow alteration regime in the § 401 certification violate[s] the
    Anti-Degradation Policy in its Water Quality Standards.” From the pleadings, it is unclear how such discovery relates
    to resolving amended Question 14, which ANR appears to challenge by raising a purely legal question. Furthermore,
    11
    AW/VPC amended Question 14 asks “[t]o the extent that the [§ 401 certification] renders
    the project uneconomical and results in decommissioning, whether the Green River Dam should
    be removed due to its adverse impacts.”
    ANR contends that the question of decommissioning falls outside the scope of the matter
    on appeal. ANR notes that the issue before the Court is whether the Project complies with VWQS,
    other relevant state laws, and parts of the CWA. 
    33 U.S.C. §1341
    (a)(1), (d). Ultimately, the Court
    is tasked to either issue or deny a § 401 certification. ANR submits that decommissioning does
    not fall within the scope of this review, and the Environmental Division therefore has no
    jurisdiction to consider that issue. See 4 V.S.A. § 34 and 10 V.S.A. § 8504 (setting out the limited
    jurisdiction of the Environmental Division).
    AW/VPC disagrees, arguing that ANR is proposing a flow regime that does not comply
    with the VWQS. Because of this, AW/VPS argues, the Court essentially has two options: deny the
    § 401 certification application, which would mean that FERC would not be able to license the
    project and the dam would have to be decommissioned and removed; or grant the § 401
    certification application with the requirement that the project be operated in “true” run-of-river
    mode, which would render the dam uneconomical and therefore also require decommissioning.
    Although filed as a motion to dismiss pursuant to V.R.C.P. 12(b)(6), because the motion
    asserts a lack of subject matter jurisdiction over the substance of amended Question 14, we
    consider the motion pursuant to V.R.C.P. 12(b)(1). We review a 12(b)(1) motion by accepting “all
    uncontroverted factual allegations of the complaint... as true and constru[ing them] in the light
    most favorable to the nonmoving party.” Rheaume v. Pallito, 
    2011 VT 72
    , 7 2, 
    190 Vt. 245
     (citing
    Jordan v. State Agency of Transp., 
    166 Vt. 509
    , 511 (1997)).
    We agree with ANR that we do not have jurisdiction to determine “whether the Green
    River Dam should be removed due to its adverse impacts.”
    There are a number of procedures through which FERC may remove a dam. Michael T.
    Pyle, Beyond Fish Ladders: Dam Removal as a Strategy for Restoring America's Rivers, 
    14 Stan. Envtl. L.J. 97
    , 122 (1995). For example, if a dam becomes more expensive to maintain than to
    ANR has not presented any matters outside the pleadings in its motion that would call for converting the motion to
    dismiss. We therefore decline to convert this to a motion for summary judgment.
    12
    remove, a licensee may surrender their license. 
    Id. at 126
    ; 
    16 U.S.C. § 799
    . FERC can also include
    a decommissioning condition when issuing a new license, 
    id. at 129
    ; 129 n.191 (listing cases), and
    may also be able to directly order dam removal, 
    Id. at 133-37
    .
    While the § 401 certification might impact the economic feasibility of adam and therefore
    play into FERC’s decision regarding decommissioning or removal, the issue of decommissioning
    and removal is a subsequent step which falls outside of our immediate scope of review. For this
    reason, we conclude that we have no jurisdiction to address whether the dam should be
    decommissioned or removed. ANR’s motion to dismiss AW/VPC amended Question 14 is
    therefore GRANTED.
    V. MWL’s Amended Questions 1, 2, 3, 6, and 8
    VNRC and VTITU move to dismiss MWL amended Questions 1, 2, 3, 6, and 8 pursuant to
    civil rule 12(b)(6) for failure to state a claim upon which relief can be granted. ANR also moves
    to dismiss part of MWL Question 6, and for summary judgment on MWL Questions 1, 2, and 3.
    These questions generally ask whether the § 401 certification should take economic and
    social factors into account.!°
    *° We note that “economic and social” are broad terms. We use them ina general sense here to frame the
    discussion. The challenged questions read as follows:
    Question 1: “whether [ANR] failed to strike a balance between competing water uses in the public interest
    as required by ANR Streamflow Procedure in issuing the [§ 401 certification], including, but not limited to the policy
    of the State of Vermont to decrease Vermont’s dependence on non-renewable energy sources.”
    Question 2: “For all facilities, whether ANR failed to adequately consider any public benefits or detriments
    in issuing the [§ 401 certification], including any public benefits or detriments associated with increasing
    conservation flows for previously approved facilities, as required by ANR Streamflow Procedure, Part F.”
    Question 3: “Whether ANR was required by [VWQS], ANR Streamflow Procedure, and Vermont Statutes,
    such as 10 V.S.A. § 1421 and 10 V.S.A. § 1423(b)(3), to consider economic and social issues when issuing the [§ 401
    certification].”
    Question 6: “Whether ANR failed to give adequate consideration to the decreased flood protection, and
    the inability of MWL to perform emergency generation during an emergency of the New England Grid and peak
    demand hours, that would be caused by the drawdown and downstream flow conditions imposed in the [§ 401
    certification].”
    Question 8: “Regarding the Green River facility, whether ANR failed to give due consideration to the dam
    safety concerns posed by spillage that would result from the restrictions on reservoir drawdown and downstream
    flows.”
    13
    a. The Streamflow Procedure
    VNRC and VTTU contend that MWL amended Questions 1, 2, 3, 6, and 8 should be
    dismissed because they ask the Court to weigh economic and social factors, neither of which is
    within the Court’s authority to consider. Similarly, ANR argues for summary judgment on MWL
    Questions 1, 2, and 3 because the certifying agency does not have any authority to “take
    economic or social factors into account when setting limitations or conditions to ensure
    compliance with the VWQS.” ANR Mot. Dism. at 9.
    MWL counters that economic and social factors can, or must, be considered under ANR’s
    Agency Procedure for Determining Acceptable Minimum Stream Flows (the Streamflow
    Procedure) and 10 V.S.A. §§ 1421 and 1423(b)(3).
    We conclude that the Streamflow Procedure does not allow or require consideration of
    economic or social factors in this case, for two main reasons. First, the § 401 certification does
    not have to ensure compliance with the Streamflow Procedure, because, as explained below,
    that procedure is not an “appropriate requirement of state law.” 
    33 U.S.C. § 1341
    (d). Second,
    State and federal water quality laws do not authorize consideration of economic or social factors
    in this case; because the Streamflow Procedure was created pursuant to those laws, it cannot
    supersede them by allowing consideration of economic or social factors.
    i. The CWA does not require compliance with the Streamflow Procedure
    because it is not an appropriate requirement of state law
    As explained above, the purpose of a § 401 certification is to satisfy requirements of the
    CWA. 
    33 U.S.C. § 1341
    (a)(1). A § 401 certification must “set forth effluent limitations and other
    limitations, and monitoring requirements to ensure” that the applicant for a federal license will
    comply with standards set out in the CWA and “any other appropriate requirement of state law.”
    Id. § 1341(d). The VWQS are one such appropriate requirement of state law, in part because the
    VWOQS are adopted pursuant to a mandate set out in the CWA. PUD No. 1, 511 U.S. at 712-13.
    The Vermont Administrative Procedure Act (VAPA) distinguishes rules from procedures.
    3 V.S.A. § 801. Under VAPA, a rule applies generally to “implement|[], interpret], or prescribe[]
    law or policy,” and is adopted through a process involving notice and comment. Id. §§ 801(9)
    and 836-44. Courts alternatively refer to rules as “regulations.” See, e.g., C&S Wholesale
    14
    Grocers, Inc. v. Dep’t of Taxes, 2016 VT 77A, 14. Agency rules and regulations “have the force
    and effect of law.” 3 V.S.A. § 845(a).
    A procedure is a practice that is maintained in the public records. Id. §§ 801(8) and 835.
    A practice is “a substantive or procedural requirement of an agency, affecting one or more
    persons who are not employees of the agency, which is used by the agency in the discharge of
    its powers and duties.” Id. § 801(7). “Agency protocols and procedures... do not have the force
    or effect of a statute or... regulation. Rather, they provide officials with guidance on how they
    should perform those duties which are mandated by statute or regulation.” King v. Gorczyk, 
    2003 VT 34
    , 7] 22, 
    175 Vt. 220
     (quoting Wanzer v. Dist. of Columbia, 
    580 A.2d 127
    , 133 (D.C. Ct. App.
    1990)). “An internal agency ‘practice or procedure’ is primarily directed toward improving the
    efficient and effective operations of an agency, not toward a determination of the rights [or]
    interests of affected parties.” 
    Id.
     {| 25 (quotation omitted); see also In re Woodford Packers, Inc.,
    
    2003 VT 60
    , If] 13-17, 
    175 Vt. 579
     (mem.) (holding that ANR could change its methodology for
    determining floodways without notice, because that methodology was a “practice” and not a
    “rule”).
    The VWQS are rules or regulations that carry the force of law. It is partly for this reason
    that they are “appropriate requirement[s] of state law” to be considered by an agency issuing a
    § 401 certification. See PUD No. 1, 511 U.S. at 713. The Streamflow Procedure does not carry
    the force of law, however, and therefore cannot be an “appropriate requirement of state law.”
    ANR is therefore not required to follow the Streamflow Procedure when determining whether to
    issue a § 401 certification or in determining limitations or conditions to be included in a § 401
    certification.
    ii. The Streamflow Procedure was created to give effect to state and federal
    water laws, and cannot be interpreted in a way that goes against or
    beyond those laws.
    As explained above, the purpose of the § 401 certification is to ensure that a proposed
    activity complies with the CWA, the VWQS, and any other appropriate state laws. 
    33 U.S.C. § 1341
    (d). PUD No. 1,511 U.S. at 713.
    The Streamflow Procedure appears to have been put in place to facilitate the
    implementation of the VWQS and its Hydrology Policy. See Streamflow Procedure at 1 (stating
    15
    that it is intended to serve the state water quality policies set out in 10 V.S.A. § 1250, and an
    executive order calling for a decrease in Vermont’s dependence on non-renewable sources of
    energy"’); VWQS § 1-02 (stating that the VWQS are rules intended to achieve the goals set out in
    10 V.S.A. § 1250 and the CWA); In re Clyde River Hydroelectric Project, 
    2006 VT 11
    , 4 13, 
    179 Vt. 606
     (indicating that the Streamflow Procedure was created under the authorization of, and to
    implement the purposes of, the VWQS Hydrology Policy).
    Because the Streamflow Procedure is not a rule or regulation, it is subsidiary to, and
    cannot supersede, the VWQS, CWA, and Vermont water quality policy that it was created to
    implement. Cent. Laborers’ Pension Fund v. Heinz, 
    541 U.S. 739
    , 748 (2004) (“neither an
    unreasoned statement in [a] manual nor allegedly long-standing agency practice can trump a
    formal regulation with the procedural history necessary to take on the force of law”).
    The VWQS only require consideration of social and economic factors when regulating
    high-quality waters. VWQS 1-02(C). The parties agree that high-quality waters are not at issue
    in this case, and therefore this provision of the VWQS does not apply. Other sections of the VWQS
    that deal with flow values do not authorize consideration of economic or social factors. See, e.g.
    VWOQS §§ 1~02(E)(1), 2-02.
    In addition, the state water quality policy says nothing about balancing water quality
    against social and economic considerations. 10 V.S.A. § 1250.
    Because the Streamflow Procedure was created to carry out the purposes of state and
    federal water quality laws, and those laws do not authorize balancing water quality protection
    against economic and social considerations, we conclude that the Streamflow Procedure cannot
    be interpreted to authorize or require ANR to consider economic and social concerns when
    issuing a § 401 certification.
    We note that the Water Resources Board reached the same conclusion over 20 years ago
    in holding that economic and “so-called societal impacts” of a proposed activity are not to be
    considered in determining whether to issue a § 401 certification, because those impacts are not
    “germane to determining whether the Project meets the [VWQS] and other applicable state law
    1 The Streamflow Procedure does not specify which executive order this is.
    16
    pertaining to water quality concerns.” In re Lamoille River Hydroelectric Project § 401
    Certification, No. WQ-94-03 and -04, Preliminary Rulings (Water Res. Bd. Aug. 15, 1995).22
    We are further convinced that consideration of economic considerations is not
    appropriate by referring to decisions addressing the CWA National Pollutant Discharge
    Elimination System (NPDES) permits, which also look to whether an activity complies with state
    water quality standards. See In re Stormwater NPDES Petition, 
    2006 VT 91
    , 4 6, 
    180 Vt. 261
    ; In
    re Entergy Nuclear Vermont Yankee Discharge Permit 3-1199, 
    2009 VT 124
    , 4 45, 
    187 Vt. 142
    .
    Courts have held in NPDES cases that economic factors are not to be considered or balanced
    against compliance with water quality standards. E.g., Montpelier WWTF Discharge Permit, No.
    22-2-08 Vtec, slip op at 21 (Vt. Envtl. Ct. Jun. 30, 2009) (Durkin, J.).
    Because the CWA, the Vermont state water quality policy, and the VWQS do not allow
    economic and social considerations to be taken into account when regulating water quality, and
    the Streamwater Procedure was adopted pursuant to these statutes and regulations, the
    Streamflow Procedure also cannot allow economic and social factors to be considered.
    b. 10V.S.A. § 1421 and 1423(b)(3)
    MWL argues that 10 V.S.A. § 1421 and 1423(b)(3) fall into the “appropriate requirement
    of state law” provision and must be considered; and that they require a § 401 certification to take
    social and economic factors into account.
    ANR responds that § 1421 sets out policy goals directed at the state, and that § 1423(b)(3)
    is part of a directive to ANR to create a water resources plan, and are therefore not applicable to
    MWL.
    10 V.S.A. § 1421 reads:
    To aid in the fulfillment of the State’s role as trustee of its navigable waters and to
    promote public health, safety, convenience, and general welfare, it is declared to
    be in the public interest to make studies, establish policies, make plans, make
    rules, encourage and promote buffers adjacent to lakes, ponds, reservoirs, rivers,
    and streams of the State, encourage and promote protected river corridors
    adjacent to rivers and streams of the State, and authorize municipal shoreland and
    river corridor protection zoning bylaws for the efficient use, conservation,
    %2 When ruling on an appeal, we give Water Resources Board decisions the same weight and consideration
    as prior Environmental Division decisions. 10 V.S.A. § 8504(m).
    17
    development, and protection of the State’s water resources. The purposes of the
    rules shall be to further the maintenance of safe and healthful conditions; prevent
    and control water pollution; protect spawning grounds, fish, and aquatic life;
    control building sites, placement of structures, and land uses; reduce fluvial
    erosion hazards; reduce property loss and damage; preserve shore cover, natural
    beauty, and natural stability; and provide for multiple use of the waters in a
    manner to provide for the best interests of the citizens of the State.
    10 V.S.A. § 1423(b)(3) reads:
    The Secretary shall prepare a comprehensive plan relating to water resources as
    a guide for the preparation of a State, regional, or municipal land use or
    development plan. The plan shall be based on the classification of waters pursuant
    to chapter 47 of this title. The plan shall to the extent possible give consideration
    to any existing regional or municipal plans which are compatible with the interests
    of the State. The primary purpose of the plan shall be for the preventive control
    of pollution, giving due consideration to necessary development and growth. The
    plans shall be governed by the following general standards .... Areas in which the
    existing or potential economic value of public, recreational or similar uses exceeds
    the existing or potential economic value of any other use shall be classified
    primarily on the basis of the higher economic use value.
    We conclude that these statutes do not have to be considered in a § 401 certification.
    Unlike the VWQS, which are applicable to § 401 certification as discussed above, these statutes
    set out broad directives for the state and a state agency. These statutes do not appear to be
    relevant to the matter at hand—appropriate requirements of state law, in other words— because
    there is no way that one could say whether a hydroelectric facility could comply with, or violate
    them. As such, we conclude that these are not “appropriate requirement|s] of state law” to be
    taken into account in a § 401 certification.
    c. Motions to Dismiss and for Summary Judgment
    VNRC and VITU move to dismiss MWL amended Questions 1, 2, 3, 6, and 8 pursuant to
    civil rule 12(b)(6) for failure to state a claim upon which relief can be granted. ANR also moves
    to dismiss the part of MWL Question 6 that relates to electricity generation, and for summary
    judgment on MWL Questions 1, 2, and 3.
    Because the Streamflow Procedure, 10 V.S.A. § 1421, and 10 V.S.A. § 1423(b)(3) are not
    “appropriate requirement[s] of state law” to be taken into account in a § 401 certification and,
    insofar as ANR is to apply the Streamflow Procedure, it cannot be interpreted to allow social or
    economic factors to be considered in a § 401 certification, VNRC and VTTU’s motion to dismiss
    18
    MWL Questions 1, 2, and the part of Question 3 that deals with the Streamflow Procedure, 10
    V.S.A. §§ 1421 and 1423(b)(3) is GRANTED.
    Because there is no “appropriate requirement of state law” that allows consideration of
    economic and social factors, and MWL Questions 6 and 8 raise social and economic concerns
    insofar as they raise concerns related to flooding, safety, and ability to generate electricity, VNRC
    and VTTU’s motion to dismiss MWL Questions 6 and 8 is also GRANTED.
    We grant summary judgment if the “movant shows that there is no genuine dispute as to
    any material fact and the movant is entitled to judgment as a matter of law.” V.R.C.P. 56(a).
    Regarding the part of Question 3 addressing the VWQS, the one undisputed material fact is that
    the Project does not affect any high-quality waters, which means that the VWQS do not allow for
    consideration of social and economic factors. Because the VWQS do not permit social or
    economic factors to be considered, ANR’s motion for summary judgment on MWL Question 3 is
    GRANTED. By granting VNRC and VTTU’s motion to dismiss MWL Questions 1, 2, and 6, ANR’s
    motions to dismiss and for summary judgment on those questions is MOOT.
    Vi. AW/VPC’s amended Questions 3, 4, 5, 7, 8, 9, 11, and 12
    VNRC and VITU move for summary judgment on AW/VPC’s amended Questions 3, 4, 5,
    7,8, 9,11, and 12. ANR supports the motion, and also challenges AW/VPC’s amended Question
    6 and a portion of Question 10. *
    *3 ANR does not, however, formally move for summary judgment on AW/VPC’s amended Questions 6 and
    10.
    The challenged questions are:
    Question 3: “Whether whitewater boating on the Green River during natural high flow events and during
    scheduled recreational releases is a designated use protected under Section 3-04(A}(6} of the [VWQS] for Class B
    waters, and if so, whether the Water Quality Certification should ensure the continued opportunity for whitewater
    boating on the Green River during natural high flow events and during scheduled recreational releases.”
    Question 4: “Whether the Water Quality Certification for the Green River Development must achieve and
    maintain a high level of quality that fully supports whitewater boating as required by Section 3-04(B)(7) of the
    [VWQS] for Class B waters.”
    Question 5: “Whether the Water Quality Certification should be conditioned in order to ensure the full
    support of whitewater boating as required by Section 3-01(C)({1) of the [VWQS] for Class B waters.”
    Question 6: “Whether ANR has conducted any site specific flow studies documenting the impact of
    whitewater boating in compliance with Section 3-01(C) and Section 1-02(E) of the [VWQS] and if not whether any
    determination by ANR regarding impacts of whitewater boating is entitled to deference by the Court.”
    19
    AW/VPC amended Question 3 asks whether whitewater boating on the Green River is a
    designated use.
    AW/VPC amended Question 4 refers to a section of the VWQS that provide for the
    protection of conditions for boating, and presumes that this would also specifically protect
    whitewater boating. This appears to rest on the assumption that whitewater boating is an
    existing or designated use. AW/VPC amended Question 5 refers to a section of the VWOQS that
    refers to requirements to ensure the full support of uses. While boating is a use designated in
    the VWQS, this question assumes that whitewater boating is also an existing or designated use.
    AW/VPC amended Question 6 refers to sections of the VWQS that require site-specific flow
    studies to ensure the full support of uses; again, this assumes that whitewater boating is an
    existing or designated use.
    AW/VPC amended Question 7 asks whether whitewater boating on the Green River is an
    existing use. AW/VPC amended Questions 8, 9, 11, and 12 rest on the assumption that
    whitewater boating is an existing use.
    Question 7: “Whether whitewater boating on the Green River is an existing use protected by the ANR
    Interim Anti-Degradation Implementation Procedure and Section 1-03 of the [VWQS] and if not whether any
    determination by ANR regarding impacts of whitewater boating is entitled to deference by the Court.”
    Question 8: “If whitewater boating on the Green River is such a protected existing use, whether the Water
    Quality Certification should be conditioned to maintain natural high flow events and include scheduled recreation
    releases in order to protect that use in accordance with Section VIII of the ANR Interim Anti-Degradation
    implementation Procedure and Section 1-03 of the [VWQS].”
    Question 9: “If whitewater boating on the Green River is a protected existing use under Section VIII of the
    ANR Interim Anti-Degradation Implementation Procedure and Section 1-03 of the [VWQS], whether scheduled
    whitewater boating releases are compatible with the fisheries management goals, as that term is used in the Water
    Quality Certification on appeal . . . for the Green River, will not result in any violation of the [YWQS], and should be
    included in the Water Quality Certification.”
    Question 10, in part: “Whether allowing [MWL] to operate in a store-and-release mode . . . during the
    “winter” .. . will reduce opportunities for whitewater boating that would occur under natural flow conditions as
    though the hydroelectric dam did not exist.”
    Question 11: “Whether the Water Quality Certification may be conditioned to eliminate or substantially
    interfere with existing whitewater boating opportunities in order to create a habitat that would not otherwise exist
    under natural flow conditions as though the hydroelectric dam did not exist.”
    Question 12: “Whether the Water Quality Certification may be conditioned such that it will eliminate or
    substantially interfere with existing whitewater boating opportunities in order to support other uses beyond what
    is required by the [VWQS] for class B waters.”
    20
    The first part of AW/VPC amended Question 10 asks the court to consider how a portion
    of the § 401 certification would reduce opportunities for whitewater boating. ANR suggests that
    this need not be considered unless whitewater boating is an existing or designated use.
    Of all the challenged questions, Questions 3, 4, 7, 8, and 9 specifically refer to the Green
    River.
    The common issue raised by all of the challenged questions is whether whitewater
    boating, or whitewater boating on scheduled releases as they currently exist on waters affected
    by the Project, are existing uses or designated uses that must be maintained or protected in the
    § 401 certification. AW / VPC argues that whitewater boating is an existing or designated use,
    while VNRC, VTTU, and ANR argue that it is not.
    We grant summary judgment to a party “if the movant shows that there is no genuine
    dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
    V.R.C.P. 56(a), applicable here through V.R.E.C.P. 5(a)(2). “In determining whether there is a
    genuine issue as to any material fact, we will accept as true the allegations made in opposition
    to the motion for summary judgment, so long as they are supported by affidavits or other
    evidentiary material.” Mylan Labs., 
    2004 VT 15
    , 4] 15 (citation omitted).
    a. Undisputed Material Facts
    The following facts are set out solely for the purpose of deciding the summary judgment
    motion now before the Court.
    1. The Green River is a Class B water and has not been assigned a water management type.
    2. The designated uses for the Green River are aquatic biota, wildlife, and aquatic habitat;
    acceptable as a source for a public water supply with filtration and disinfection; aesthetics;
    swimming and other primary contact recreation; boating, fishing and other recreational uses;
    and irrigation and agricultural uses. VWQS § 3-04(A).
    3. Whitewater boaters have been running the rapids on the Green River for years during
    natural high-water events.
    4. MWL has for the past five years also provided scheduled recreational releases specifically
    to allow for whitewater boating. Scheduled releases are done on short notice at the request of
    AW/VPC.
    21
    5. MWL uses the releases to generate power.
    6. The § 401 certification issued to MWL would eliminate all scheduled whitewater releases,
    and would significantly limit or eliminate naturally occurring whitewater boating opportunities.
    7. In the § 401 certification issued to MWL, ANR identified two existing uses at the Green
    River Development: aquatic biota, wildlife and aquatic habitat; and recreation. Certification
    finding {| 255. The certification appears to include angling and boating in the broader
    “recreation” use. Id. 4] 256.
    8. The § 401 certification also states that one of the conditions in the certification “will help
    to restore the frequency of natural high flow events and allow for whitewater boating when
    natural flows are compatible with boating. This certification is being conditioned such that the
    downstream flow regime will provide waters of a high quality that is suitable for and compatible
    with boating.” Id. 4] 239.
    9. The 2016 Tactical Basin Plan for the Lamoille Basin includes “Appendix F: Existing Uses in
    the Lamoille Basin.” 2016 Lamoille Basin Plan at 197, available at
    http://dec.vermont.gov/sites/dec/files/wsm/mapp/docs/2016-12-
    30_Lamoille_Tactical_Plan_FINAL.pdf. This appendix “presents the current list of Existing Uses
    determined for the Lamoille Basin.” Id. at 135.
    10. Appendix F includes sub-headings for the following uses: swimming, recreational boating,
    recreational fishing, and public water sources.
    11. Under the sub-heading “Recreational Boating,” Appendix F mentions whitewater boating,
    and flat water canoeing and kayaking. Id. “Table F2: Recreational Boating as an Existing Use of
    Specific Waters within the Lamoille Watershed” lists the Green River as a location with a “highly
    important” rating, noting under “characteristics that support the use”: “Class IV-V, outstanding
    scenery and rapids, used by expert paddlers, only river in State with potential to support
    recreational dam releases on a steep creek.” Id. at 199.
    12. A study of whitewater boating on the Green River conducted by MWL for its FERC
    application concluded that “the Green River can provide a quality whitewater boating experience
    that includes a variety of advance paddler challenges with an above average length run in a
    picturesque setting.” Green River Whitewater Study for the Morrisville Project (undated)
    22
    available at
    http://elibrary.ferc.gov/IDMWS/common/downloadOpen.asp?downloadfile=20120306%2D502
    6%2826972336%29%2Epdf&folder=358109&fileid=12909002&trial=1.
    b. Discussion
    i. Whitewater boating is not a designated use.
    AW/VPC amended Question 3 asks whether whitewater boating is a designated use.
    Questions 4, 5, and 6 assume that whitewater boating is a designated use or an existing use. 14
    The CWA and EPA regulations require states to identify designated uses in their water
    quality standards. 
    33 U.S.C. § 1313
    (c)(2)(A) (new or revised standards “shall consist of the
    designated uses of the navigable waters involved and the water quality criteria for such waters
    based upon such uses”); 
    40 C.F.R. § 131.10
     (setting out guidelines for “designation of uses”).
    EPA regulations define designated uses as “those uses specified in water quality standards
    for each water body or segment whether or not they are being attained.” 
    40 C.F.R. § 131.3
    (f).
    The VWQS define a designated use as “any value or use, whether presently occurring or
    not, that is specified in the management objectives for each class of water as set forth in §§ 3-
    02(A) [Class A(1) waters], 3-03(A) [Class A(2) waters], and 3-04(A) [Class B waters] of these rules.”
    VWaQsS § 1-01(B)(14).
    States have discretion to make designated uses more or less specific, as long as they are
    at least as specific as the uses identified in the CWA: drinking water supply; protection and
    propagation of fish, shellfish, and wildlife; recreation; agricultural; industrial; and navigation. 
    33 U.S.C. §§ 1251
    (a) (setting out goals and policy of CWA), 1313(c) (stating that water quality
    standards must take into consideration and protect CWA purposes); 
    40 C.F.R. § 131.10
    (c)
    (allowing, but not requiring, states to designate sub-categories of uses); U.S. Envt’l. Prot. Agency,
    4 ANR suggests that Question 4 refers to a section of the VWQS relating to management objectives for
    designated uses, not existing uses, and the question therefore depends on whitewater boating being a designated
    use. See VWQS § 3-04(B){7). It is not clear to the Court that this section, titled “Water Quality Criteria for Class B
    Waters,” applies only to designated uses and not to existing uses.
    ANR further suggests that Questions 5 and 6 refer to the VWQS Hydrology Policy (§ 1-02(E)) and Hydrology
    Criteria (§3-01(C)) also depend on whether whitewater boating is a designated use; again, we see no reason why
    these sections would not apply if whitewater boating is an existing use.
    23
    Water Quality Standards Handbook §§ 2.3, 4.4.1 (1994) available at https://www.epa.gov/was-
    tech/water-quality-standards-handbook [hereinafter EPA Handbook].
    Once a use is designated, the state is required to manage the water “to achieve and
    maintain a level of quality that fully supports” the use. VWAQS § 3-04(A); see also 
    40 C.F.R. § 131.10
    (a) (designated uses are “to be achieved and protected”). There is no requirement to
    support more specific uses that have not been designated.
    A state may not remove a designated use from its water quality standards unless the use
    isnot an “existing use” and the use is not feasible under specific criteria set out in EPA regulations.
    
    40 C.F.R. § 131.10
    (g); EPA Handbook § 2.7.
    In summary, designated uses are those specified by the authorized agency—here, ANR—
    regardless of whether the use is actually occurring, and the agency has discretion to designate
    uses in a general or specific manner.
    Here, ANR has set boating—and not whitewater boating—as a designated use in the
    Green River. Although windsurfing, tugboating, and gondola rowing also could be considered
    subcategories of boating, ANR has not specified them as designated uses on the Green River,
    Class B waters, or any other waters. The state therefore has no duty to achieve, support, or
    protect them as designated uses. The same is true for whitewater boating.
    Because whitewater boating is not a designated use, VNRC and VITU’s motion for
    summary judgment on AW/VPC Question 3 is GRANTED.
    ii. The Court is unable to determine at this time whether whitewater boating
    on the Green River is an existing use.
    AW/VPC Question 7 asks whether whitewater boating is an existing use on the Green
    River. Questions 4, 5, and 6 assume that whitewater boating is a designated use or an existing
    use. Questions 8, 9, 11, and 12 assume that whitewater boating is an existing use.
    Existing uses are relevant to two provisions in EPA regulations. First, existing uses are
    relevant in determining whether a designated use is also an existing use, and therefore cannot
    be removed from state water quality standards. 
    40 C.F.R. § 131.10
    (g). Second, existing uses are
    relevant insofar as states are required to adopt antidegradation policies that protect and
    24
    maintain “[e]xisting instream water uses and the level of water quality necessary to protect . . .
    existing uses.” 
    40 C.F.R. § 131.12
    (a)(1).
    EPA regulations define existing uses as “those uses actually attained in the water body on
    or after November 28, 1975, whether or not they are included in the water quality standards.”
    
    40 C.F.R. § 131.3
    (e). The VWQS provide a similar definition: “Existing use means a use which has
    actually occurred on or after November 28, 1975, in or on waters, whether or not the use is
    included in the standard for classification of the waters, and whether or not the use is presently
    occurring.” WWAQS § 1-01(B)(18). The U.S. Supreme Court has explained that the CWA
    antidegradation policy is intended to protect “existing beneficial uses of navigable waters,
    preventing their further degradation.” PUD No. 1, 511 U.S. at 705 (emphasis added).
    The EPA interprets the phrase “existing uses are those uses actually attained” to mean
    that “the use and water quality necessary to support the use... have been achieved.” Letter
    from Denise Keener, Director, Standards and Health Protection Division, EPA, to Derek Smithee,
    Chief, Water Quality Programs Division, Oklahoma Water Resources Board (Sep. 5, 2008), part
    (1) available at https://www.epa.gov/sites/production/files/2014-10/documents/existinguse-
    smithee-letter.pdf [hereinafter Smithee letter] (emphasis added).
    The EPA has explained that the prohibition on removing existing uses is not intended to
    prevent removal of an existing use when doing so “would result in improving the condition of a
    waterbody, i.e., facilitate[] attainment of a use closer to those supported by minimally impacted
    conditions.” Id. For example, “if a state . . . stocks trout (a coldwater species) into a natural
    warmwater fishery, the existing use provision would not prevent removal of that stocked trout
    fishery use because a natural warm water fishery is closer to the minimally impacted condition.”
    Id.
    Unlike designated uses, states are not required to specify existing uses in their water
    quality standards. See 
    40 C.F.R. § 131.10
    . Nevertheless, according to the EPA Water Quality
    Standards Handbook, a state “selects the level of specificity it desires for identifying recreational
    existing uses,” as long as they are as specific as the designated uses and the uses listed in CWA
    §§ 101(a) and 303(c). EPA Handbook § 4.4.1. The Handbook goes on to explain that:
    If the use classification system in a State is defined in broad terms such as...
    boating, then it is a State determination whether to allow changes in the type of
    25
    ... boating activity that would occur on a specific water body as long as the basic
    use Classification is met. For example, if a State defines a use simply as "boating,"
    it is the State's decision whether to allow something to occur that would change
    the type of boating from canoeing to power boating as long as the resulting water
    quality allows the "boating" use to be met.
    The VWOQS call for existing uses to be identified as part of the basin planning process, or
    on a case-by-case basis “during consideration of an application.” VWQS §§ 1-03(B)(1), 1-02(D)(2)
    and (4). In determining existing uses, the VWQS instruct ANR to consider:
    a. Aquatic biota and wildlife that utilize or are present in the waters;
    b. Habitat that supports existing aquatic biota, wildlife, or plant life;
    c. The use of the waters for recreation or fishing;
    d. The use of the water for water supply, or commercial activity that depends
    directly on the preservation of an existing high level of water quality; and
    e. ... regarding... the factors considered under paragraphs (a) and (b) above,
    evidence of the use’s ecological significance in the functioning of the ecosystem
    or evidence of the use’s rarity.
    VWOQs § 1-03(B)(1).
    AW/VPC argues that whitewater boating, and whitewater boating on scheduled releases,
    are existing uses on the Green River in the sense that they have taken place. AW/VPC further
    contends that the state has recognized whitewater boating on the Green River as an existing use
    by including it in the 2016 Lamoille Basin Plan list of existing uses.
    VNRC, VTTU, and ANR counter that ANR has discretion to define existing uses broadly or
    narrowly, and that here ANR has defined the broader use of recreational boating—and not the
    narrower use of whitewater boating—as an existing use. ANR contends that whitewater boating
    on the Green River is listed in the 2016 Lamoille Basin Plan only as an example of a type of
    recreational boating, not as a standalone existing use.
    Whether the 2016 Lamoille Basin Plan designates whitewater boating on the Green River,
    and if so, to what degree, is a disputed material fact that we are not able to resolve on the record
    now before us. Furthermore, while existing uses may be identified in the basin planning basis,
    *5 While not all of AW/VPC’s amended questions specifically reference the Green River, its briefings appear
    to focus on that water body.
    26
    they also may be determined by ANR on a case-by-case basis “during consideration of an
    application.” VWQS § 1-03(B)(1). The matter now before the Court is an application for a § 401
    certification, and the Court is sitting in the place of ANR in considering that application. 10 V.S.A.
    § 8504(h). Even if the 2016 Lamoille Basin Plan does not identify whitewater boating on the
    Green River as an existing use, that would not be dispositive, because we would have the power
    to identify it as an existing use.
    Because we are unable to determine at this time whether whitewater boating on the
    Green River (or other waters affected by the Project) is an existing use, VNRC and VTTU’s motion
    for summary judgment on AW/VPC amended Questions 4, 5, 7, 8, 9, 11, and 12 is DENIED.
    Because there has been no formal motion for summary judgment on AW/VPC amended
    Questions 6 and 10, we reserve judgment on those questions.
    ORDER
    1. AW/VPC’s motion for summary judgment on its amended Question 1 is DENIED.
    2. ANR’s motion to dismiss AW/VPC amended Question 1 is DENIED, and ANR’s motion to
    dismiss AW/VPC amended Question 14 is GRANTED.
    3. We are inclined to grant summary judgment to ANR on AW/VPC Question 1. Because
    ANR has not filed a summary judgment motion on this question, however, we may not
    grant it summary judgment without giving all parties notice and an opportunity to
    respond. V.R.C.P. 56(f)(1). We hereby give all parties 30 days from the date of this
    decision to file briefs and supporting documents with the Court regarding the question
    of whether ANR complied with the one-year timeline in Section 401.
    4. ANR’s motion for summary judgment on part of MWL Question 3 is GRANTED.
    5. VNRC and VTTU’s motion to dismiss MWL Questions 1, 2, 6, 8, and the portion of Question
    3 not affected by ANR’s motion for summary judgment is GRANTED.
    6. ANR’s motions to dismiss and for summary judgment on MWL Questions 1, 2, and 6 are
    MOOT.
    7. ANR’s motion for leave to file a sur-reply is GRANTED.
    27
    8. VNRC and VITU’s motion for summary judgment on AW/VPC’s amended Question 3 is
    GRANTED. VNRC and VITU’s motion for summary judgment on AW/VPC’s amended
    Questions 4, 5, 7, 8, 9, 11, and 12 is DENIED.
    Electronically signed on June 13, 2017 at 02:37 PM pursuant to V.R.E.F. 7(d).
    To Wye
    Thomas G. Walsh, Judge
    Superior Court, Environmental Division
    28
    

Document Info

Docket Number: 103-9-16 Vtec

Filed Date: 6/13/2017

Precedential Status: Precedential

Modified Date: 7/31/2024