ANR B Wesco, Inc. ( 2017 )


Menu:
  •                                            STATE OF VERMONT
    SUPERIOR COURT                                                    ENVIRONMENTAL DIVISION
    Environmental Division Unit                                          Docket No. 60-6-16 Vtec
    Agency of Natural Resources,
    Petitioner
    v.                                                  DECISION ON THE MERITS
    Wesco, Inc.,
    Respondent
    This matter arises out of Respondent Wesco, Inc.’s (Respondent) alleged release in 2011
    of gasoline (a hazardous material) into surface water, groundwater and land of the state;
    Respondent’s alleged failure to install appropriate overfill protection, failure to install cathodic
    protection, failure to make documents, records and report available, and failure to report a
    suspected release all at or relating to property at 56 Pearl Street, Essex Junction, Vermont. In a
    May 3, 2016 Administrative Order (AO),1 the Vermont Agency of Natural Resources (ANR) alleges
    violations of the Vermont Waste Management law, 10 V.S.A. § 6616, and Vermont’s
    Underground Storage Tank Rules (VUST Rules). The AO sets out factual allegations describing
    Respondent’s prohibited release and associated failures.              The AO does not seek further
    remediation; however, ANR seeks administrative penalties of $106,466.35 for the violations.2 On
    July 1, 2016, Respondent requested a hearing on the AO with this Court.
    The Court conducted a merits hearing at the Vermont Superior Court, Costello
    Courthouse in Burlington, Vermont on June 15 and 16, 2017. Appearing at the trial were Randy
    J. Miller, II, Esq. and John Zaikowski, Esq. representing the Agency of Natural Resources and
    Tristram J. Coffin, Esq. representing Respondent.
    1
    The AO was filed with the Court on June 24, 2016.
    2
    This includes $97,000 in penalties set out in the AO, in addition to $9,466.35 to cover the cost of
    enforcement.
    1
    Findings of Fact
    Based upon the evidence presented at trial, the Court renders the following Findings of
    Fact and Conclusions of Law.
    1.     Respondent owns the Champlain Farms fuel station and convenience store at 56 Pearl
    Street, Essex Junction, Vermont.
    2.     On May 24, 2011, the ANR Department of Public Safety’s Vermont Hazardous Materials
    Response Team was notified by the Essex Junction Fire Department that there was a concern of
    elevated gasoline vapors in the area of the Post Office Square Shopping Plaza off of Pearl Street
    in Essex Junction, Vermont.
    3.     Respondent’s technician had been dispatched to the site to investigate possible sources
    of inventory discrepancy.
    4.     Upon inspection, ANR discovered explosive levels of petroleum vapors within catch basins
    of a storm drain system on the Shopping Plaza property.
    5.     The Shopping Plaza occupants include retail and commercial businesses open to the
    public. There is also a post office at the Shopping Plaza.
    6.     The Fire Department evacuated the Shopping Plaza and closed the businesses due to the
    threat of explosion.
    7.     Agency personnel inspected the spill buckets for Respondent’s underground gasoline
    storage tanks.
    8.     By the end of the inspection, the owners of the Shopping Plaza had brought in a
    consultant and installed a ventilation system on the storm drain where the gasoline vapors had
    been detected.
    9.     On the morning of May 25, 2011, Thomas Unkles, an Agency representative, performed
    an inspection. Mr. Unkles was accompanied on the inspection by David McQuade, Wesco’s
    Director of Environmental Compliance.
    10.    In the afternoon, Respondent has its tanks and underground piping system inspected by
    a private contractor, Tanknology, Inc.
    11.    On May 26, 2011, Jerry Tanner, Wesco’s technician, performed a leak inspection.
    2
    12.      Agency personnel returned to the site and alleged that a faulty O-ring was the likely
    source of the release. Mr. Tanner, however, testified that based on his inspection the O-ring
    could not have been the cause of the release. Ultimately, no conclusive or compelling evidence
    was presented to indicate the cause or duration of the release.
    13.      On May 27, 2011, Respondent’s representatives reported to the Agency the inventory
    records.
    14.      On June 1, 2011, Agency personnel returned to the facility and observed the installation
    of additional monitoring wells by Respondent’s consultant.
    15.      On June 3, 2011, Agency personnel requested copies of inventory reconciliation records
    for the facility’s gasoline tanks for the period of January 2011 until June 3, 2011 be brought to a
    meeting scheduled for June 6, 2011.
    16.      On June 6, 2011, Agency personnel met with Respondent’s representative and consultant
    to discuss remedial steps at the facility.
    17.      On June 8, 2011, the Agency issued Respondent a Notice of Alleged Violation (NOAV) with
    compliance directives to immediately pump, empty and cease operation of the gasoline tanks at
    the facility, and to remove the underground storage tanks from the ground and allow contractors
    access to remove free product and petroleum contaminated soils from beneath and around the
    tanks.
    18.      On June 9, 2011, Agency personnel reviewed the boring log and monitoring well
    construction diagrams prepared and submitted by Respondent’s consultant. The Agency also
    applied for an Emergency Order (EO) ordering Respondent to immediately empty underground
    storage tanks and cease operation of dispensing activities, and within five days to remove
    underground storage tanks, contaminated soils, and free product, and to properly dispose of
    these materials.
    19.      On June 16, 2011, the Environmental Division issued the EO requested by the Agency.
    20.      In cooperation with the ANR and the Fire Department, Respondent emptied and removed
    all underground storage tanks from the facility, removed contaminated soils from beneath and
    around the tanks, and disposed of those materials.
    3
    21.    The Agency estimated that 2,600 gallons of product was released. But, this estimate was
    based entirely on inventory discrepancies, which may or may not be caused by a release. The
    Court therefore finds the estimate based on inventory records alone inconclusive.
    22.    In its “Site Investigation and Corrective Action Report,” Respondent’s environmental
    consultant noted that the amount of contaminant removed in the initial venting of the storm
    drain is unknown, but estimated that approximately 95.7 gallons of gasoline was removed in later
    venting. Ex. 28 at 12. The report also notes that contaminated liquids and solids were removed
    from the site in the initial response, but gives no estimate as to the amount of product removed
    at that time. Id. at 4. In addition, the report offers a high estimate of 1,592 gallons of gasoline
    removed from soils around the site. Id. at 18.
    23.    The site has been a gas station since the 1950’s and some of the contaminated soil
    samples contained MTBE, a compound that was used in gasoline for a period of time prior to
    2007. This suggests that some of the contamination occurred in the past. Determining what
    contamination is attributable to the release in 2011 and what was historic contamination
    complicates whether a significant release occurred.
    24.    It is also unclear when the 2011 release began.
    25.    ANR issued an administrative order (AO) dated May 3, 2016, alleging five violations
    related to the release.
    26.    ANR’s cost of enforcement included approximately $9,466.35, attributable to the time
    spent by the Agency’s environmental analysts, enforcement officer, and waste management and
    prevention representative.
    27.    Respondent has three prior violations of 10 V.S.A § 8003 or related rules, permits, orders
    or assurances of discontinuance in the prior seven years.
    Determining Violations and Penalty Assessment
    When a respondent requests a hearing on an AO, we have the authority to determine
    whether the alleged violation occurred. 10 V.S.A. § 8012(b)(1). ANR carries the burden of
    proving the alleged violations by a preponderance of the evidence. Id. § 8013(a). If ANR meets
    this burden, we are required to “determine anew the amount of a penalty” that should be
    assessed against the respondent challenging the ANR order. Id. § 8012(b)(4). We therefore
    4
    review the evidence before the Court and determine an appropriate penalty assessment,
    pursuant to the eight subsections of 10 V.S.A. § 8010(b)(1)–(8).
    ANR, and this Court in this proceeding, must consider seven factors when assessing a
    penalty:
    (1) the degree of actual or potential impact on public health, safety, welfare,
    and the environment resulting from the violation;
    (2) the presence of mitigating circumstances, including unreasonable delay
    by the Secretary in seeking enforcement;
    (3) whether the respondent knew or had reason to know the violation
    existed;
    (4) the respondent’s record of compliance;
    (5) [Repealed.]
    (6) the deterrent effect of the penalty;
    (7) the State’s actual costs of enforcement; and
    (8) the length of time the violation has existed.
    10 V.S.A. § 8010(b)(1)–(8). The maximum penalty for each violation is $42,500, plus $17,000 for
    each day a penalty continues. Id. § 8010(c)(1). Generally, ANR treats multiple violations of the
    same permit, or related violations generally, as one violation when calculating penalties. We take
    the same approach in this case, and analyze the five violations as a single violation.
    The State may also “recapture economic benefit” that the violator may have derived from
    the violation, up to the total maximum penalty allowed of $170,000. Id. § 8010(c)(2).
    In an effort to standardize penalties and ensure a fair process, ANR enforcement officers
    use a form that is based on the seven factors. They rate the severity of the violations from 0 to
    3 for factors (1), (3), (4) and (8), and come up with an initial penalty score. The highest possible
    initial score is a 15, which equates to an initial penalty of $42,500 for a Class I violation, the
    maximum allowed. Classes II, III, and IV carry lower maximum penalties of $30,000, $10,000 and
    $3,000 respectively. The initial penalty can then be adjusted based on penalty factors (2), (6) and
    (7). If the violator signs an Assurance of Discontinuance, agreeing not to dispute the action, the
    final penalty may be reduced by 25%.
    Number of Violations
    At the outset of the Court’s penalty assessment, we recognize that the Administrative
    Order at issue in this matter alleges five violations: 1) the prohibited release of hazardous
    5
    materials into the surface, groundwater or land of the state – 10 V.S.A. § 6616; 2) failure to install
    appropriate overfill protection – VUST Rules § 8-406(b)(1)(C); 3) failure to install cathodic
    protection – VUST Rules § 8-405(a)(1)(B); 4) failure to make documents, records, and reports
    available – VUST Rules § 8-502(e); and 5) failure to report a suspected release – VUST Rules § 8-
    506(b)(2).
    ANR, and therefore this Court on appeal, has discretion to calculate and assess one
    penalty for events that result in more than one violation or to calculate and assess a separate
    penalty for each violation stemming from the same activity. In the AO at issue, ANR considered
    the five alleged violations in three separate penalty assessments (one for the alleged release (10
    V.S.A. § 6616), one for the alleged failure to report a release (VUST Rules § 8-506(b)(2)), and one
    for the remaining alleged violations). Because the alleged violations regard the Pearl Street
    Station only and relate to the same proximate time, we conduct a single penalty assessment.
    Additionally, we take this approach because the evidence does not clearly establish each
    separate violation having independent cause for environmental or human health concerns.
    The parties do not dispute the core facts of the violations. Respondent offers that the
    release at issue was unknown, had a short duration, and a well-intended remedial response by
    Respondent. Thus, Respondent contests the amount of ANR fine.
    Class of Violation(s)
    We conclude that the release in this matter present a Class II violation. A Class II violation
    includes violations which present more than a minor violation of a statute listed in 10 V.S.A.
    §8003(a) or a rule promulgated under statute listed in 10 V.S.A. §8003(a). ANR suggested that
    the events presented a Class I violation as a threat of substantial harm to the public health, safety,
    or welfare or to the environment. As detailed below, the release of petroleum did not result in
    a threat of substantial harm and we therefore decline to classify the violations as Class I.
    6
    Calculation of Base Penalty:
    Penalty Factor 1: Actual or Potential Impact on Public Health, Safety, Welfare and the
    Environment
    Subsection (1) of 10 V.S.A. § 8010(b) requires consideration of “the degree of actual or
    potential impact on public health, safety, welfare and the environment resulting from the
    violation.”
    In considering ANR’s penalty calculation form, we assign a value of “1” to the degree of
    impact on public health, safely, and welfare (ANR form Question 1) as we conclude there was
    evidence of minor actual impact or moderate potential impact from the release and response.
    The moderate potential impact on public health, safety and welfare stemmed from the risk of
    ignition or explosion as well as human exposure to gasoline product and fumes. The potential of
    these risks was moderate due to the volume of gasoline release and path that the product
    migrated over. The minor actual impact was the closing and evacuation of the Shopping Plaza.
    We assign a value of “1” to the degree of impact on the environment (ANR form Question
    2) as we conclude there was minor actual impact and moderate potential impact to the
    environment from the release.       Petroleum was released from the facility, migrating via
    groundwater towards the Shopping Plaza property. The credible evidence supports a conclusion
    that the violation caused minor actual impact that harmed the environment.
    Penalty Factor 3: Whether the Respondent Knew or Had Reason to Know the Violation
    Existed
    Subsection (3) of 10 V.S.A. § 8010(b) requires consideration of “whether the respondent
    knew or had reason to know the violation existed.” The ANR penalty calculation form includes
    two parts related to this subsection: 3a, knowledge of the requirements, and 3b, knowledge of
    the facts of the violation.
    Respondent knew or should have known about their legal requirements under the Waste
    Management statute and the facts of the violation. 10 V.S.A § 6616 is only two sentences long
    and clearly states that the release of hazardous material to surface or groundwater is prohibited.
    Thus, in considering ANR’s penalty calculation form, we assign a value of “1” for Respondent’s
    knowledge of requirements (ANR form Question 3a, which assigns a “1” where respondent “had
    reason to know about violated requirement”).
    7
    As to Respondent’s knowledge of the facts of the violations we assign a value of “1,”
    concluding there is evidence that Respondent “could not have reasonably known that the
    violation existed” (ANR form Question 3b). There is not clear evidence that Respondent knew or
    should have known about the release before it was discovered. Respondent’s technician had
    been dispatched to the site to investigate possible sources of inventory discrepancy. Respondent
    alleges that numerous state inspections, in addition to the Tanknology inspections, did not reveal
    a faulty O-ring or the other alleged violations. Because the cause of the release remains unknown
    today, we cannot conclude that Respondent should have been aware of the release sooner.
    Penalty Factor 4: Respondent’s Record of Compliance
    Subsection (4) of 10 V.S.A. § 8010(b) requires consideration of “the respondent’s record
    of compliance.” The evidence presented shows that Respondent had three previous violations
    of ANR’s regulations. In considering ANR’s penalty calculation from, we assign a value of “3” for
    this subsection (ANR form Question 4).
    Penalty Factor 8: Length of Time the Violation Existed
    Subsection (8) of 10 V.S.A. § 8010(b) requires consideration of “the length of time the
    violation has existed.” From the evidence, the Court is unable to determine when the release
    began. Respondent immediately began responsive action the day it was informed of petroleum
    vapors emanating from the storm drain and began working with the Agency to develop an
    appropriate response. After an inspection of the facility, the owners of the Shopping Plaza
    brought in a consultant and installed a ventilation system on the storm drain where the gasoline
    vapors had been detected. The ventilation system was effective at removing significant gasoline
    vapors from the storm drain system. Disputed evidence was offered at trial concerning the
    discovery of a faulty O-ring, and the details of Respondent notifying the Agency. Respondent
    complied with the Agency and pumped all underground storage tanks at the facility, emptied and
    ceased operation of gasoline and diesel dispensing activities, removed all underground storage
    tanks from the facility, removed free product and petroleum contaminated soils from beneath
    and around the tanks, and properly disposed of those materials.
    Additionally, the results of the remediation call into question the scale of the release that
    occurred in 2011. Evidence from the remediation clearly indicate there were releases that
    8
    predated May 2011. The site has been a gas station since the 1950’s and some of the soil samples
    contained MTBE, a compound that was used for a period of time prior to 2007. Determining what
    contamination is attributable to the release in 2011 and what was historic contamination
    complicates whether a significant release occurred.
    In considering ANR’s penalty calculation form, we assign a value of “1”, concluding that
    this violation existed for a very short duration (ANR form Question 5).
    In adding the above penalty scores we arrive at a base score of 7 which equates to a base
    penalty of $12,000 for a Class II violation. See ANR form Question 6.
    Penalty Adjustments:
    We next consider appropriate adjustments to the base penalty.
    Penalty Factor 2: Mitigating Circumstances
    Subsection (2) of 10 V.S.A. § 8010(b) requires consideration of “the presence of mitigating
    circumstances, including unreasonable delay by the secretary in seeking enforcement.” The
    release occurred in 2011. ANR issued Respondent a NOAV on June 8, 2011 and an EO on June 16,
    2011. ANR waited until May 2016—nearly five years—to initiate enforcement proceedings. The
    consequences of the delay are notable. The State acknowledges that many of the documents
    related to this case have been destroyed. The Essex Junction Fire Department no longer has its
    notes from the incident. The substantial delay in prosecution has significantly disadvantaged both
    parties, particularly Respondent’s ability to present an adequate defense.
    Furthermore, Respondent responded promptly and attempted to bring the subject
    property into compliance voluntarily including by emptying and removing all underground
    storage tanks from the facility, removed contaminated soils from beneath and around the tanks,
    and properly disposed of those materials. This evidence weighs heavily against the timeliness of
    ANR’s actions.
    Based on these facts, the Court reduces Respondent’s penalty based on mitigating
    circumstances in the amount of $3,000.
    Penalty Factor 6: The Deterrent Effect
    Subsection (6) of 10 V.S.A. § 8010(b) requires consideration of “the deterrent effect of
    the penalty.” The Secretary may increase the penalty amount up to the maximum allowed in the
    9
    class of violation if the Secretary determines that a larger penalty is reasonably necessary to deter
    the respondent and the regulated community from committing future violations. Id. In this
    matter the maximum penalty is $30,000 and the base penalty we have calculated is $12,000,
    allowing for a maximum deterrent of $18,000.
    In reviewing the importance of establishing a penalty that will have a deterrent effect
    upon Respondent, we consider that Respondent was cooperative with ANR throughout the
    investigation and remediation of the release. Furthermore, we conclude that the short period of
    time that the violations existed once Respondent was on notice, and Respondent’s prompt and
    complete remediation of the release does not warrant a deterrent portion to be added to the
    initial base penalty.
    Penalty Factor 7: State’s Actual Costs of Enforcement
    Subsection (7) of 10 V.S.A. § 8010(b) requires that we consider “the state’s actual cost of
    enforcement.” The value of the time that all ANR personnel committed to responding to
    Respondent’s violations, totals $9,466.35. We direct Respondent to reimburse these costs as an
    additional penalty for the violations.
    Economic Benefit
    The Secretary may recapture any economic benefit Respondent may have gained by
    violating its permit. 10 V.S.A. § 8010(c).
    While we believe that recapturing economic gain from a violation is appropriate, we
    conclude that based on the evidence before the Court, it appears that Respondent did not realize
    a gain or economic benefit from the violations. Thus, we decline to impose any amount of
    additional penalty relating to economic gain.
    Reduction for Settlement
    Finally, ANR may reduce a respondent’s penalty when the respondent admits the
    violation and enters an Assurance of Discontinuance fully resolving the compliance issue. Such a
    reduction is not warranted in this matter as Respondent did not resolve their dispute by
    settlement.
    The Court therefore decreases the base penalty of $12,000 by subtracting mitigation for
    ANR’s delay in initiating enforcement and Respondent’s prompt investigation and remediation in
    10
    the amount of $3,000 and adds $9,466.35 as reimbursement of ANR’s costs of enforcement. The
    total penalty in this case is $18,466.35.
    Conclusion
    For the reasons stated above, we conclude that for the five violations at issue within the
    May 3, 2016 AO, Respondent shall be liable for a total penalty in these proceedings of $18,466.35.
    Rights of Appeal (10 V.S.A. § 8012(c)(4)–(c)(5))
    This Decision and the accompanying Judgment Order will become final if no appeal is
    requested within 10 days of the date this Decision is received. All parties to this proceeding have
    a right to appeal this Decision and Judgment Order. The procedures for requesting an appeal are
    found in the Vermont Rules of Appellate Procedure (V.R.A.P.) subject to superseding provisions
    in Vermont Rule for Environmental Court Proceedings (V.R.E.C.P.) 4(d)(6). Within 10 days of the
    receipt of this Order, any party seeking to file an appeal must file the notice of appeal with the
    Clerk of the Environmental Division of the Vermont Superior Court, together with the applicable
    filing fee. Questions may be addressed to the Clerk of the Vermont Supreme Court, 111 State
    Street, Montpelier, VT 05609-0801, (802) 828-3276. An appeal to the Supreme Court operates
    as a stay of payment of a penalty, but does not stay any other aspect of an order issued by this
    Court. 10 V.S.A. § 8013(d). A party may petition the Supreme Court for a stay under the
    provisions of the Vermont Rules of Civil Procedure (V.R.C.P.) 62 and V.R.A.P. 8.
    Electronically signed on November 13, 2017 at 11:05 AM pursuant to V.R.E.F. 7(d).
    _________________________________________
    Thomas G. Walsh, Judge
    Superior Court, Environmental Division
    11
    

Document Info

Docket Number: 60-6-16 Vtec

Filed Date: 12/15/2017

Precedential Status: Precedential

Modified Date: 7/31/2024