Comtuck LLC East Tract Rd JO - Decision on Motion ( 2019 )


Menu:
  •                                         STATE OF VERMONT
    SUPERIOR COURT                                                           ENVIRONMENTAL DIVISION
    Docket No. 54-5-17 Vtec
    Comtuck LLC East Tract Act 250 JO Appeal
    ENTRY REGARDING MOTION
    Title:          Motion for Reconsideration (Motion 12)
    Filer:          Comtuck, LLC
    Attorney:       Jon T. Anderson
    Filed Date:     November 16, 2018
    Response in Opposition filed on 11/30/2018 by Attorneys Elizabeth Lord, Catherine Gjessing,
    and Gregory J. Boulbol for the Vermont Interested Persons Natural Resources Board and
    the Vermont Agency of Natural Resources
    Reply filed on 12/11/2018 by Attorney Jon T. Anderson for Appellant Comtuck, LLC
    The motion is GRANTED IN PART and DENIED IN PART.
    Comtuck, LLC (“Comtuck”) appeals Jurisdictional Opinion #2-305 (“JO”) issued by the
    District #2 Environmental Commission Coordinator (“District Coordinator”) in response to a
    request submitted by Comtuck. In our ruling on the parties’ cross-motions for summary
    judgment, the Court disposed of the matter in a November 2, 2018 decision. The decision
    concluded, generally, that Comtuck proposed a material change to a previously permitted project
    which potentially impacted criteria enumerated in the parcel’s umbrella permit (“the 1985
    Permit”).1 Therefore, it was required to seek additional approvals for the project as currently
    proposed and present evidence on all Act 250 criteria. Comtuck presently seeks reconsideration
    of that decision.
    Pursuant to V.R.C.P. Rule 59(e), the Court has broad power to alter or amend a previous
    judgment. In re SP Land Co., LLC, 
    2001 VT 104
    , ¶ 16, 
    190 Vt. 418
     (citation omitted). The Court
    can respond to a Rule 59(e) motion by “revis[ing] its initial judgment if necessary to relieve a
    party against the unjust operation of the record resulting from the mistake or inadvertence of
    the court and not the fault or neglect of a party.” Rubin v. Sterling Enters., Inc., 
    164 Vt. 582
    , 588
    (1996) (citing In re Kostenblatt, 
    161 Vt. 292
    , 302 (1994)). However, granting a motion to
    reconsider is an “extraordinary remedy” that should be used sparingly. In re Bennington Wal-
    Mart Demolition/Constr. Permit, No. 158-10-11 Vtec, slip op. at 4 (Vt. Super. Ct. Envtl. Div. Aug.
    1
    This project has a very lengthy permitting history. For a detailed record of this, please refer to our
    accompanying Revised Decision on Motions.
    In re Comtuck, LLC E. Tract Act 250 JO Appeal, No. 54-5-17 Vtec (EO on Mot. to Reconsider) 3-29-2019 Page 2 of 4
    17, 2012) (Walsh, J.); In re Bouldin Camp – Nobel Rd., No. 278-11-06 Vtec, slip op. at 1 (Vt. Envtl.
    Ct. Sept. 13, 2007) (Wright, J.).
    We have identified four reasons for this Court to grant a Rule 59(e) motion: “to correct
    manifest errors of law or fact on which the decision was based, to allow the moving party to
    present newly discovered or previously unavailable evidence, to prevent manifest injustice, or to
    respond to an intervening change in the controlling law.” In re Vanishing Brook Subdivision, No.
    223-10-07 Vtec, slip op. at 4 (Vt. Envtl. Ct. July 10, 2008) (Wright, J.) (quoting 11 C. Wright, A.
    Miller, & M. Kane, Federal Practice and Procedure: Civil § 2810.1 (2d Ed. 1995). Importantly, Rule
    59(e) does not provide parties with the opportunity to relitigate matters already decided by this
    Court. S. Vill. Communities, LLC, No. 74-4-05 Vtec, slip op. at 2 (Vt. Envtl. Ct. Sept. 14, 2006)
    (Durkin, J.) (quoting Wright et al., supra, § 2810.1).
    Comtuck presents essentially two arguments supporting its motion. First, it asserts that
    the 1985 Permit can only be reopened if Comtuck proposes a material change to the originally
    permitted project affecting the criteria resolved in that decision. Therefore, it argues that
    because it is not proposing to develop new land or to make a material change to the previously
    permitted project that would affect any criteria resolved by the 1985 Permit, it should not be
    required to present any evidence on criteria resolved by that permit.
    Based upon the factual representations and legal arguments previously presented, we
    reached the exact opposite conclusions that Comtuck now suggests. In our November 2, 2018
    decision, we concluded that Comtuck proposes a material change to the previously permitted
    project. In re Comtuck, LLC E. Tract Act 250 JO Appeal, No. 54-5-17 Vtec, slip op. at 13 (Vt. Super.
    Ct. Envtl. Div. Nov. 2, 2018) (Durkin, J.). We further concluded that the project was “wholly
    different than that originally proposed and permitted” project and “has the potential to impact
    many of the Act 250 criteria, including those enumerated in the 1985 Permit.” Id. at 14.
    Therefore, we concluded that, should Comtuck seek to develop the project as now proposed, it
    must submit a permit amendment application and the criteria enumerated in the 1985 Permit
    may be addressed. Id.
    Comtuck’s motion in this respect seeks to merely relitigate these two conclusions by
    contesting that the present proposal does not represent a material change generally and does
    not reflect a material change that has the potential to affect the criteria enumerated in the 1985
    Permit such that evidence must be presented on these issues. These attempts to relitigate issues
    already addressed by the Court are precisely the types of arguments that are not grounds for the
    Court to grant a motion to reconsider. As such, we decline to reconsider these conclusions and
    DENY Comtuck’s motion in this respect.
    Comtuck further asserts that it does not propose to change the access road to the project
    and the Court’s inclusion of this fact in its decision is in error. In their reply in opposition ANR
    and NRB stated that they had no reason to contest the accuracy of this statement. Because of
    this, we GRANT Comtuck’s motion to alter the decision for the limited purpose of striking
    references to the change in access from our decision to protect the parties from the unjust
    operation of the record.
    In re Comtuck, LLC E. Tract Act 250 JO Appeal, No. 54-5-17 Vtec (EO on Mot. to Reconsider) 3-29-2019 Page 3 of 4
    We note, however, that even with this language stricken, our legal overall conclusions
    remain unchanged. This is because of other project changes that we have concluded are
    material, such as the new lot configurations and the siting of on-site water supply and
    wastewater facilities. Therefore, we DENY Comtuck’s motion to revisit these conclusions even in
    granting its motion in this limited respect.
    The Court hereby strikes the following language:
    1. On page 3, we strike from Fact #6 the language beginning with “Comtuck also proposes
    to change” and ending with “opposite side of the proposed development.”
    2. On page 10, we strike from the last sentence in the first paragraph: “a new access road
    and.”
    3. On page 12, we strike the language beginning with “The new proposal also seeks” and
    ending with “Comtuck has thus far disclosed.”
    4. On page 12 we strike the language “neither . . . nor the new access was.” The sentence is
    rewritten as “The new lot reconfigurations were not disclosed or contemplated during
    the original permit proceedings.”
    5. On page 12, we strike the language “a newly proposed access road.”
    6. On page 12, we strike the language “nor a different access.”
    7. On page 14, we strike the language “change the East Tract’s access road.”
    All other aspects of our decision remain unchanged. A Revised Decision on Motions and
    Revised Judgment Order accompanies this Entry Order.
    So Ordered.
    Electronically signed on March 29, 2019 at 02:22 PM pursuant to V.R.E.F. 7(d).
    ________________________________
    Thomas S. Durkin, Superior Judge
    Environmental Division
    Notifications:
    Jon T. Anderson (ERN 1856), Attorney for Appellant Comtuck, LLC
    Elizabeth Lord (ERN 4256) and Catherine Gjessing (ERN 4310), Attorneys for
    the Interested Person Vermont Agency of Natural Resources
    Edward G. Adrian (ERN 4428), Attorney for Interested Person Town of Wilmington
    Gregory J. Boulbol (ERN 1712), Attorney for the Vermont Interested Person Natural Resources
    Board
    Interested Persons Michael P. and Kirby
    Interested Person Mary Ann Kirby
    Interested Person Renato Grella
    Interested Person Richard M. Arsenault
    Interested Person Stephanie R. Arsenault
    In re Comtuck, LLC E. Tract Act 250 JO Appeal, No. 54-5-17 Vtec (EO on Mot. to Reconsider) 3-29-2019 Page 4 of 4
    Interested Person Dennis R. Johnson
    Interested Person Laurette Wanko
    Interested Person Steven L. Bate
    Interested Person Daniel J. Fitzgerald
    Interested Person Alexandra Fitzgerald
    Interested Person Donna Fitzgerald
    Interested Person Kathryn Palmesi
    Interested Person Edward Greco
    Interested Person Mindy Lissner
    Interested Person Edwin F. Collins
    Interested Person Mary E. Krieg
    Interested Person Brett W. and Flodine
    Interested Person Linda C. Flodine
    Interested Person Meredith Musick
    Interested Person Monet E. Bossert
    efilosa
    

Document Info

Docket Number: 54-5-15 Vtec

Filed Date: 4/1/2019

Precedential Status: Precedential

Modified Date: 7/31/2024