Krull v. Town of Huntington ( 2017 )


Menu:
  • Krull v. Town of Huntington, No. 651-7-15 Cncv (Mello, J., Dec. 22, 2017).
    [The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the
    accompanying data included in the Vermont trial court opinion database is not guaranteed.]
    VERMONT SUPERIOR COURT
    CHITTENDEN UNIT
    CIVIL DIVISION
    │
    JEFFREY KRULL,                                                           │
    Plaintiff                                                               │
    │
    v.                                                                      │                 Docket No. 651-7-15 Cncv
    │
    TOWN OF HUNTINGTON and                                                   │
    JOHN SCOTT EXCAVATING, INC.,                                             │
    Defendants                                                              │
    │
    RULING ON PENDING MOTIONS
    Plaintiff Jeffrey Krull brings this action for negligence and trespass against the Town of
    Huntington and John Scott Excavating, Inc., following flooding events in 2011 and 2013 that
    resulted in substantial damage to his property. In essence, he alleges that Defendants negligently
    performed maintenance and repair work on a nearby road, and that Defendants’ negligence and
    trespass caused the property damage. Now before the court are numerous pending motions. The
    court heard oral argument on September 11, 2011. Jacob O. Durell, Esq. represents Plaintiff Krull.
    James F. Carroll, Esq. represents Defendant Town of Huntington. Gregory A. Weimer, Esq.
    represents Defendant John Scott Excavating, Inc.
    Since the summer, Defendants have raised concerns about serial, late filings by Plaintiff,
    while Plaintiff has continually sought to supplement his filings, sometimes even months after the
    applicable deadlines. Thus, preliminarily, the court clarifies that in ruling on the pending motions,
    it has considered materials filed up until September 15, 2017, as stated at the September 11th
    oral argument, but has not considered materials filed after that date.
    DEFENDANTS’ MOTIONS FOR SUMMARY JUDGMENT
    The Town of Huntington moves for summary judgment on the grounds that it is entitled to
    municipal sovereign immunity, and alternatively that the negligence and trespass claims both fail
    on the merits. Huntington also asserts that, to the extent the complaint alleges a conversion, that
    claim also fails on the merits. John Scott Excavating (“JSE”) similarly moves for summary
    judgment on the grounds that, as a government contractor, it is entitled to the Town’s immunity,
    and also that the tort claims fail on the merits. Furthermore, both Defendants move for summary
    judgment on certain categories of damages. They contend that Plaintiff cannot recover punitive
    damages and emotional distress damages in this case.
    Facts
    The following facts are undisputed for purposes of the motions for summary judgment,
    unless otherwise noted. In October 2008, Plaintiff purchased real property located at 310
    Economou Road in Huntington, Vermont. The property is roughly 21 acres and includes a 600
    square foot house. The property is on the western side of Economou Road, and the house is
    located on a small, flat spot of land, surrounded by steep hillsides to the south, west, and east. A
    creek or stream traverses the property and runs within a few feet to the west of the residence, but
    does not cross Economou Road in the vicinity of the property. Surface water from the steep slope
    to the west runs into the creek before reaching Plaintiff’s house. Surface water from the east and
    south is intended to be managed by a series of culverts and ditches to run into the creek without
    negatively impacting the residences along Economou Road, including Plaintiff’s residence.
    Economou Road is steep and narrow, in excess of 10 percent grade in some locations.
    Immediately to the south of Plaintiff’s property, the road becomes steep and increases rapidly
    with elevation, with a sharp curve in the road. The land is also very steep and increases rapidly
    in elevation across Economou Road from Plaintiff’s property to the east. This land is forested and
    undeveloped, with up to a 25 percent slope. As a result of the steep terrain sloping downwards to
    the flat spot where Krull’s house sits, the probable area draining to the property is about 20 acres.
    Krull’s expert, Blair Enman, P.E., observes that “[t]his is a significant drainage area capable of
    producing substantial runoff.”
    In late April 2011, a severe rainstorm hit Economou Road and the surrounding area. The
    creek did not overflow, but surface water from the surrounding area washed across the property,
    bringing with it rocks, rubble, gravel, and silt strewn across the entire house site. Parts of the road
    were washed out, including a large trench on the east side of the road near Krull’s property.
    Economou Road sustained significant damage both in the immediate vicinity of the property, and
    in a separate stretch further to the south. Following this rainstorm, Huntington hired John Scott
    Excavating (“JSE”) to repair the road, which consisted of digging out an existing ditch along the
    eastern side of the road and lining it with “rip rap,” digging up an existing culvert and shaking it
    out to clear it of sediment and replacing it in the same location, and delivering gravel that the
    Town used to repair and grade the road. When JSE’s work was complete, the Town reviewed
    and approved it. Prior to the April 2011 storm, JSE did not perform any work for the Town on
    Economou Road related to the location or sizing of culverts or drainage ditches, or the design of
    the road.
    At the time of the 2011 storm, Krull was in the process of substantially renovating his
    property. For that reason, he was not living there during that time, and was not on the property
    the day of the storm. As part of the renovations, he had removed some walls and siding from the
    house to open up access to the crawl space underneath. This space was open to the elements
    during the 2011 storm, and became flooded with water, rocks, and sediment. Krull returned to his
    property after the storm was over and took photographs. He did not observe the storm event as
    it progressed. A large amount of winter storm debris on the slope to the east of Economou Road
    was swept up in the April 2011 storm and caused the culverts to become unusually clogged with
    material.1
    On July 3, 2013, a severe storm again hit Economou Road and the surrounding area. An
    extremely large volume of rapidly moving water swept through Economou Road and significantly
    1 Plaintiff purports to dispute this, claiming that minutes for a June 27, 2017 Selectboard meeting indicate that fall
    maintenance was not done prior to snowfall, and that this was the cause of excess debris in the system. Plaintiff fails
    to indicate where these meeting minutes are in the record. See V.R.C.P. 56(c)(1)(A) (party asserting that a fact is
    genuinely disputed must file separate statement of disputed facts “with specific citations to particular parts of materials
    in the record”); Webb v. Leclair, 
    2007 VT 65
    , ¶¶ 4–6, 
    182 Vt. 559
     (Rule 56(c) is meant to avoid such “needle in a
    haystack” searches). The court accepts Huntington’s proffered fact as undisputed.
    2
    damaged the road. The creek on Krull’s land did not overflow, but surface water from the
    surrounding area again flooded through the property, bringing with it rocks, gravel, and sediment.
    Unlike during the April 2011 storm, Krull was at the property during the July 2013 storm. Krull
    states he was never in danger of physical injury during the 2013 storm.
    During the 2013 storm, the Huntington road foreman Clinton “Yogi” Alger was handling
    road troubles throughout the town. At some point during the storm, he went to Economou Road
    and saw that water was overrunning the culverts and ditches, and flooding across the road.
    Because Alger needed to address numerous issues throughout the town, he called John Scott of
    JSE for emergency assistance in addressing the flooding on Economou Road. Alger and Scott
    met at the base of Economou Road near Texas Hill Circle, and Alger requested that JSE clear a
    culvert at the intersection of Texas Hill and Economou, and then clear the ditches and culverts on
    Economou Road. Yogi then left to address other roads in town, and did not see or talk to Scott
    while JSE was working on Economou Road.2
    In an attempt to divert the water from Krull’s property and his home, JSE began clearing
    out the drainage ditch on the east side of the road. Water continued to rush over the road and
    toward the property. According to JSE, it attempted to divert this flow pattern by creating a “berm”
    across the road to direct the water toward a stream that runs behind Krull’s house, in hopes of
    preventing it from continuing to reach his house. JSE used a bucket loader to dig out a pathway
    for the water to follow on Krull’s side of the road as part of this effort. During this process, JSE
    asserts, it reached over the bank on to Krull’s property with the excavator. Then, JSE continued
    to attempt to clear the ditch on the east side of the road. Despite JSE’s efforts, water continued
    to flow across the road toward Krull’s property at roughly the same intensity until the storm wound
    down. As discussed below, Krull disputes this account of JSE’s actions. He contends that JSE
    went more than 60 feet onto his property. He also contends that JSE unnecessarily dug a ditch
    that resulted in the destruction of trees and vegetation, increased flow of water and road material
    to his house, and plainly would not have diverted the flow to the natural stream.
    Plaintiff’s property incurred extensive damage following the 2011 and the 2013 rainstorms.
    To this day, a significant amount of rocks, gravel, and sediment still covers parts of his property.
    As a result, he has been unable to make full use of his property, has incurred additional expenses
    for alternative living arrangements, and has had difficulty financing potential projects on his land.
    Plaintiff brought this action on July 6, 2015.
    Discussion
    I.       Town of Huntington’s Municipal Immunity
    The doctrine of municipal sovereign immunity “protects municipalities from tort liability in
    cases where the municipality fulfills a governmental rather than a proprietary function.” Graham
    v. Town of Duxbury, 
    173 Vt. 498
    , 499 (2001).3 Activities such as “[b]uilding and maintaining
    2 While JSE frequently does work for Huntington, Scott is not a town employee. Alger also delegated work to several
    other contractors to assist with other parts of Huntington during the 2013 storm.
    3 The following A.L.R. comment summarizes the general principles underlying the municipal immunity doctrine:
    (1) the supposed immunity of the sovereign from suit, which is extended to the
    municipality as the representative or agency of the sovereign, (2) the idea that it is
    more expedient that scattered individuals suffer than that the public in general be
    inconvenienced, and (3) the considerations of public policy involved in the theory
    3
    streets, and the accompanying drainage system, are generally government functions, and no
    liability for injuries suffered as a result of such activities may attach.” Id.; see also Dugan v. City
    of Burlington, 
    135 Vt. 303
    , 304 (1977) (street); Sanborn v. Village of Enosburg Falls, 
    87 Vt. 479
    ,
    482 (1914) (drainage system for street); O’Connor v. City of Rutland, 
    172 Vt. 570
    , 570–71 (2001)
    (assuming that city was negligent in failing to maintain adequate crosswalks and street lighting in
    case where plaintiff’s daughter was struck and killed by motorist while crossing street, city was
    immune from suit because those were governmental functions). Defendants’ acts alleged here
    plainly fall into this category of maintenance of streets and the accompanying stormwater
    drainage system, and therefore constitute governmental functions protected from tort liability
    under municipal sovereign immunity.
    The court recognizes that the application of municipal immunity may lead to a harsh result,
    particularly in cases where the municipality would otherwise be liable for tortious conduct, and
    where the plaintiff would be left with no remedy for the damages he or she sustained resulting
    from the municipality’s actions. The Vermont Supreme Court has recognized the “harsh results”
    and “arbitrariness” of general municipal immunity and its “governmental/ proprietary” distinction,
    and has observed that “Vermont is one of a minority of states that retains the governmental-
    proprietary distinction, which has been criticized by courts and commentators for many years as
    unworkable.” Hudson v. Town of E. Montpelier, 
    161 Vt. 168
    , 178 n.3 (1993).4 Indeed, Justice
    Johnson wrote that she “would abolish general municipal immunity along with the
    governmental/proprietary distinction” and adopt Restatement (Second) of Torts § 895C (1979).
    Hillerby v. Town of Colchester, 
    167 Vt. 270
    , 282, 291 (1997) (Johnson, J., dissenting). In that
    same case, in a separate dissent, Justice Dooley agreed with Justice Johnson that the
    governmental/proprietary distinction was inappropriate and should be abandoned. 
    Id. at 276
    (Dooley, J., dissenting).
    Yet, a majority of the Supreme Court declined to take action:
    Our refusal to abolish the governmental/proprietary distinction
    should not be read as an endorsement of that distinction. We point
    out, as we did in Hudson, 
    161 Vt. at
    177-78 n. 3, that many courts,
    legislatures, and commentators have strongly criticized this method
    of determining municipal liability. Yet we believe that our role in
    addressing this issue, at this time, is not to reform the rules of
    municipal immunity, but to give the Legislature the initial opportunity
    that governmental agents will perform their duties more effectively if not hampered
    by fear of tort liability.
    Comment Note, Municipal Immunity from Liability for Torts, 
    60 A.L.R.2d 1198
    , § 2 (originally published in 1958).
    4 The Restatement aptly summarizes this history of criticism:
    The immunity of local governments has long been under attack, and the
    justifications that have been offered for it have been condemned as unsound. All
    of them can be found to have been rejected at one time or another in the decided
    cases. The current of criticism has been that it is better that the losses due to the
    tortious conduct of officers and employees should fall upon the municipality rather
    than upon the injured person and that the torts of public employees are properly to
    be regarded, as in other cases of vicarious liability, as a cost of the administration
    of government and should be borne by the public.
    Restatement (Second) of Torts § 895C cmt. (d) (1979).
    4
    to fashion a more reasonable and workable doctrine. Its fact-finding
    and problem-solving process is better suited for the task in this area
    of the law.
    Hillerby, 
    167 Vt. at 276
    ; see also O’Connor, 172 Vt. at 570–71 (declining to overturn Hillerby in
    2001 when it was still “recent precedent,” and noting that the “considerations that underlie Hillerby
    also weigh against overturning it”). Thus, the Court suggested a willingness to revisit the issue if
    the legislature declines to fashion “a more reasonable and workable doctrine.” Perhaps, given
    that the Legislature has now had an “initial opportunity” to rework the municipal immunity doctrine
    and that it has apparently not done so in the 20 years after Hillerby, the Court might now be
    inclined to reform the doctrine on its own. However, in light of the Court’s relatively recent refusal
    to abrogate the doctrine despite full knowledge of the doctrine’s criticisms and potential for harsh
    results, this court does not see how it can do so now.
    Plaintiff contends that the immunity doctrine does not apply here because this case
    involves a “sewer.” It is true that an exception to municipal immunity exists with respect to
    maintenance of sewers, which is considered to be a proprietary function. See Dugan v. City of
    Burlington, 
    135 Vt. 303
    , 304–05 (1977) (“The building and maintenance of streets and sidewalks
    are governmental functions, while the maintenance of sewers is considered proprietary.”)
    (citations omitted); Sanborn v. Vill. of Enosburg Falls, 
    87 Vt. 479
    , 482 (1914). But the material
    facts in this case do not relate to a sewer. The allegation is that Defendants negligently maintained
    or repaired a road and its accompanying stormwater drainage system, which was not connected
    to any sewer system. See Graham v. Town of Duxbury, 
    173 Vt. 498
    , 499 (2001) (building and
    maintaining a street’s “accompanying drainage system” is a governmental function); Sanborn v.
    Vill. of Enosburg Falls, 
    87 Vt. 479
    , 482 (1914) (“it is clear from the case that the sluice, catch-
    basin, and tile in question were not sewers and were no part of any sewer system”) (emphasis
    added). Nor does a sewer system exist anywhere in Huntington. There is absolutely no evidence
    that the street drainage system at issue here is a “sewer.”
    Another limited exception to municipal immunity involves natural streams. See Graham v.
    Town of Duxbury, 
    173 Vt. 498
    , 500 (2001) (“a town may be liable for subsequent damage to
    surrounding property after receiving notice of a problem concerning a natural stream”) (citing
    Sargent v. Town of Cornwall, 
    130 Vt. 323
    , 328 (1972); Haynes v. Town of Burlington, 
    38 Vt. 350
    ,
    362 (1865)). Like the sewer exception, the natural stream exception is also inapplicable here. A
    natural stream does cross into Plaintiff’s property to the west of his house, but there is no
    allegation or evidence that the stream overflowed or otherwise damaged Plaintiff’s property as a
    result of any actions taken by Defendants.
    Although a municipality waives sovereign immunity by purchasing liability insurance, 29
    V.S.A. § 1403, the Supreme Court has explicitly held that “[s]uch waiver does not occur when
    insurance or reinsurance is acquired through participation in an intermunicipal insurance
    agreement such as VLCT PACIF.”5 McMurphy v. State, 
    171 Vt. 9
    , 15–16 (2000) (citing 24 V.S.A.
    §§ 4942, 4946). Huntington has submitted evidence that it did not purchase its own liability
    insurance coverage at any time related to the subject flooding events, and instead was a member
    5 VLCT PACIF refers to the Property and Casualty Intermunicipal Fund (PACIF), which is managed by the Vermont
    League of Cities and Towns (VLCT). See McMurphy v. State, 
    171 Vt. 9
    , 15 (2000).
    5
    of PACIF. This fact is undisputed.6 Huntington did not waive its municipal sovereign immunity by
    purchasing liability insurance.
    Because the Town is entitled to municipal immunity, the court need not consider the
    arguments regarding Plaintiff’s negligence and trespass claims against the Town. For the sake of
    completeness, however, the court notes briefly in dicta that the record appears to lack genuinely
    disputed material facts indicating that the Town was negligent. Plaintiff’s theory of negligence is
    that the Town breached a duty of care by not performing a hydraulic analysis for any of the culverts
    or ditches on Economou Road, in violation of the town Road Standards and the VTrans Hydraulics
    Manual, and that at least one of the culverts was too small (15 inches instead of the required 18
    inches) in violation of a VTrans highway standard. A hydraulic analysis, he argues, would
    demonstrate that insufficient culvert and ditch capacity exists to meet the regulatory standard of
    care for preventing runoff from a once-in-25-year rainstorm. Aside from the fact that Plaintiff’s
    expert has not undertaken a hydraulic analysis (and has requested that the Town pay for one),
    the evidence undisputedly shows that a hydraulic design was not required for any of the culverts
    or ditches on Economou Road, and that the Town therefore could not have breached the cited
    Road Standards or Hydraulics Manual by not performing such an analysis. Furthermore, the
    culvert that Plaintiff contends is too small because it is 15 inches is, in fact, undisputedly 18 inches.
    Moreover, it is far from clear that there was even an actionable duty, as generally there is no
    private right of action for failure to comply with a municipal standard. See generally Corbin v.
    Buchanan, 
    163 Vt. 141
     (1994).
    Plaintiff further contends that municipal immunity does not apply because he has asserted
    a state law “takings” claim. That argument is addressed below with respect to the motion to amend
    his complaint. To the extent Plaintiff asserts that there is evidence of gross negligence or
    recklessness, and that this evidence provides another exception to the application of the
    municipal immunity doctrine, the court finds no such admissible evidence in the summary
    judgment record. “[G]ross negligence is ‘more than an error of judgment, momentary inattention,
    or loss of presence of mind’; rather, ‘it amounts to a failure to exercise even a slight degree of
    care’ and an ‘indifference to the duty owed [to another].’” Hardingham v. United Counseling Serv.
    of Bennington Cty., Inc., 
    164 Vt. 478
    , 481 (1995) (quoting Rivard v. Roy, 
    124 Vt. 32
    , 35 (1963));
    see also Shaw v. Moore, 
    104 Vt. 529
     (1932) (“Gross negligence is substantially and appreciably
    higher in magnitude and more culpable than ordinary negligence. [It] is equivalent to the failure
    to exercise even a slight degree of care.”). Plaintiff has offered no admissible evidence of ordinary
    negligence by the Town, let alone gross negligence or recklessness.
    II.      Government Contractor Immunity
    The court must also consider whether the Town’s immunity extends to its contractor, John
    Scott Excavating, which the Town hired to perform road and culvert repairs on Economou Road.
    While the Vermont Supreme has apparently not addressed this issue, other courts have extended
    governmental immunity to private entities who carry out governmental directives. The general rule
    with respect to extending governmental immunity to private contractors has been described as
    follows:
    6 Plaintiff purports to dispute this fact only by asserting that “PACIF may constitute insurance.” Under clearly established
    law, PACIF does not constitute insurance for purposes of waiving municipal immunity. See McMurphy, 171 Vt. at 15–
    16; 24 V.S.A. § 4946.
    6
    [W]here the act, or failure to act, which causes an injury is one which
    the contractor was employed to do, and the injury results not from
    the negligent manner of doing the work, but from the performance
    thereof or failure to perform it at all, the contractor is entitled to share
    the immunity from liability which the public enjoys, but that the
    contractor is not entitled to the immunity of the public body from
    liability where the injury arises from the tortious manner of
    performing the work.
    Thus, the courts are practically unanimous in holding a public
    contractor liable for his negligence, or his wilful torts, and in holding
    him not liable for necessary or incidental damages.
    Annot., Right of Contractor with Federal, State, or Local Public Body to Latter’s Immunity to Tort
    Liability, 
    9 A.L.R.3d 382
    , § 2(a) (originally published in 1966) (collecting cases). The New Jersey
    Supreme Court has observed two principles underlying the extension of municipal immunity to
    governmental contractors: (1) that “the immunity of the entity itself would become meaningless if
    contractors complying with its design were liable in tort for defects in that design”; and (2) that it
    would be “fundamentally unfair to hold a contractor liable” for injury caused by defective plans,
    where that contractor was bound to “specifications that are provided by a public entity and over
    which it has no control” in the absence of a “blatant, obvious danger that the contractor should
    have brought to the attention of the public entity.” Vanchieri v. New Jersey Sports & Exposition
    Auth., 
    514 A.2d 1323
    , 1326 (N.J. 1986).
    Under this general rule, then, JSE would be liable for its own negligence or intentional
    torts that resulted in injury, but would be entitled to share in the Town’s immunity for “incidental
    injuries necessarily involved in the performance of the contract” not resulting from its own
    negligence or other tortious conduct, or ultrahazardous methods. 
    Id.
     § 3; see also, e.g., Boyle v.
    United Techs. Corp., 
    487 U.S. 500
    , 512–13 (1988) (adopting a “government contractor defense”
    and holding that it could bar the estate of a military helicopter pilot from suing the manufacturer
    for alleged design flaws if the challenged design choice was made by military officials); Estate of
    Lyons v. CNA Ins. Companies, 
    558 N.W.2d 658
    , 663 (Wis. Ct. App. 1996) (adopting “a form of
    governmental contractor immunity applicable to parties who contract with municipal or state
    authorities and are directed to perform certain tasks under that contract” and holding that bridge
    designer was entitled to immunity); Vanchieri v. New Jersey Sports & Exposition Auth., 
    514 A.2d 1323
    , 1326 (N.J. 1986) (“When a public entity provides plans and specifications to an independent
    contractor, the public contractor will not be held liable for work performed in accordance with those
    plans and specifications.”). JSE would also be entitled to share in the Town’s municipal immunity
    if Plaintiff’s damages resulted from some design flaw in the roads or culverts, and if JSE had
    merely followed specifications given by the Town. Because tortious conduct by JSE in the
    performance of its work would not be immune, the court must examine the merits of the
    negligence and trespass claims asserted against JSE.
    III.     Negligence of John Scott Excavating
    There is no evidence of negligence by JSE in performing its contracted tasks in response
    to the 2011 rainstorm. As to the 2013 storm, Plaintiff’s own expert, Blair Enman, says nothing
    7
    remotely critical of JSE in his report, affidavit, or deposition.7 However, Plaintiff offers some
    evidence of negligence by JSE in his own affidavit, in the form of eyewitness testimony.8
    Plaintiff’s version of the events of July 3, 2013, as recounted in his affidavit, differs from
    the account offered by John Scott Excavating. JSE contends that it merely reached over onto
    Plaintiff’s property with its excavator, while Plaintiff asserts that he saw JSE go at least 60 feet
    onto his property. JSE also contends that it attempted to redirect the flow of water to a natural
    stream that runs behind Plaintiff’s house by creating a berm across the road and digging a ditch
    on Plaintiff’s side of the road. Plaintiff, however, asserts that this action was negligent, as detailed
    in his affidavit:
    The excavator had . . . dug a ditch across the road focusing all of
    the runoff from approximately .5 miles of road uphill on the east side
    of the road directly to the “South Site” [part of Plaintiff’s property].
    This diverted most of the water, rock, and debris from . . . across
    the road and began flooding water over the [neighbors’] driveway
    and onto the South Site . . . .
    .       .      .
    On this day, JSE destroyed at least two dozen trees and other
    plants on my property.
    .     .      .
    In addition to the substantial flooding . . . and other damage that
    JSE caused on the South Site, the Home Site suffered again a
    similar magnitude of damage as the 2011 event . . . .
    7 Plaintiff points to Enman's deposition, where he explains that he “did not concentrate the effort on [JSE],” that he
    “ha[d] not done enough research to say to what extent that would have or could have further impacted the Krull
    property,” and that his report “largely dealt with the municipal aspect of the infrastructure,” which he admitted was “a
    long way of saying no” to the question of whether there was anything in his written report that was critical of anything
    JSE did or did not do. Enman depo. at 159:16--160:12. At a later point in his deposition, when asked whether it was
    “customary,” in his experience, “for a road foreman or contractor who is working on a municipal road to dig on a property
    to divert water” during a road storm, and if that was a technique he would suggest, he responded: “No.” 
    Id.
     at 181:21–
    182:2. However, that exchange continued:
    Q. And it's not something that you have seen before?
    A.   I have seen it.
    Q. You have seen it?
    A.   Sure.
    Q. How many instances of that have you seen?
    A.   Couldn't count.
    
    Id.
     at 181:3–181:10. Nothing in the deposition testimony creates a disputed material fact as to whether JSE breached
    a duty of care in performing work on Economou Road.
    8 The court grants Huntington’s motion to strike Plaintiff’s “Statement of Disputed Facts by Pl.’s Expert in Opp’n to
    Summ. J.” This document is not a pleading; it was written and signed by Plaintiff’s expert, and violates V.R.C.P. 11(a).
    The court considers only the later statement of facts submitted by Plaintiff and signed by counsel, as well as his expert’s
    affidavit and Plaintiff’s own affidavit with supporting materials.
    8
    It did not appear to me on July 3, 2013 that JSE was attempting to
    dig a ditch to the brook as he would have had to have gone much
    further across the property, for water to reach the brook. In addition,
    a simple assessment, from out of the excavator, of the land slope
    shown in Exhibit 3, would confirm that the slope in that area would
    direct runoff toward the house site, rather than towards the stream.
    .      .        .
    In addition to the damages to the South Site, the Home Site suffered
    similar damage as it had in 2011 due to ongoing maintenance and
    repair issues on Economou Rd., and because of JSE’s actions that
    day up the road from my home.
    Pl.’ Aff. ¶¶ 10(d)–(f), 11, 14. Additionally, Plaintiff attaches a number of photographs that he took
    during and immediately after the 2013 rainstorm, showing the runoff, tracks in the mud from the
    excavator, and the damage to his property. He also incorporates into his affidavit a narrative,
    which he wrote in the month following the 2013 rainstorm, and which he asserts is a true and
    accurate reflection of what happened at the time. Therein, he describes how the excavator arrived
    and did work on the opposite side of the road from his, and that mud, silt, sediment, and stone
    flowed across the road into his driveway and house site, “but was limited to the area of previous
    damage.” That narrative then continues, in pertinent part:
    About an hour or so later another crew arrived with the owner of the
    excavating company, who was operating the excavator. He began
    excavating the trench created by the first crew, and worked his way
    up to the bend in the road. At this point water only was flowing
    across and into the undamaged portion of the house site. The
    existing berm was filtering muddy water, and the intentional
    hemlock stand and vegetation were catching stone and silt. At the
    bend in the road, where a deluge of water and material was flowing
    into the trench just created, the operator then drove the machine
    onto our property, through the berm, and dug a trench up the bank
    and across the road killing a dozen or so hemlocks and releasing
    all of the water and material flowing down the road into the
    previously undamaged portion of the house site. I went up the road
    as he did so. And urgently suggested he needed to repair what was
    just done and get the flow back on its previous course. He
    responded, “I think you[’]r[e] right and began to fill in his ditch as
    water and road material ripped through the now broken trees and
    scared [sic] hillside.
    Ex. 10 to Pl.’s Aff. at 2. Viewing the evidence in the light most favorable to the non-moving party,
    as the court must in deciding a motion for summary judgment, Plaintiff’s affidavit and
    accompanying materials demonstrate a genuinely disputed material fact as to whether JSE was
    negligent in its actions on July 3, 2013, and whether that alleged negligence was a proximate
    cause of the damages to Plaintiff’s property. It is for the finder of fact to make credibility
    determinations and settle the discrepancy between Plaintiff’s and John Scott Excavating’s
    competing versions of events.
    9
    Again, the court acknowledges that Plaintiff’s expert, Blair Enman, says nothing about
    whether JSE was negligent. However, the court is satisfied that Plaintiff himself has sufficient
    expertise to opine that JSE was negligent, and that its negligence caused his property damage.
    In the narrative incorporated by reference into his affidavit, Plaintiff states that he is a designer
    and builder by trade, has a B.A. in architecture, and has worked consistently in the fields of
    architecture, landscape design, construction, and project management. He worked for four
    months in Belize following two hurricanes, where he implemented a $1 million erosion control
    project, and has 20 years of experience in “various land repair and erosion control projects.”
    Plaintiff’s affidavit is sufficient for him to survive JSE’s motion for summary judgment.
    JSE’s potential liability is limited, however, to damages incurred as a result of its actions
    taken during the 2013 rainstorm, as detailed in Plaintiff’s affidavit. There is no evidence that it was
    negligent at any other time.
    IV.     Trespass by John Scott Excavating
    In addition to the negligence claim, Plaintiff also brings a claim for trespass. Trespass is
    an invasion of one’s interest in the exclusive possession of his or her land. John Larkin, Inc. v.
    Marceau, 
    2008 VT 61
    , ¶ 8, 
    184 Vt. 207
     (citing W. Keeton et al., Prosser and Keeton on the Law
    of Torts § 87, at 622 (5th ed.1984); Restatement (Second) of Torts § 158 cmt. c, at 277 (1965)).
    “Liability for trespass arises when one intentionally enters or causes a thing to enter the land of
    another.” See Canton v. Graniteville Fire Dist. No. 4, 
    171 Vt. 551
    , 552 (2000) (citing Restatement
    (Second) of Torts § 158(a)). The Vermont Supreme Court has recognized that “one who causes
    water to enter the land of another is liable for trespass. Id.; see also S.L. Garand Co. v. Everlasting
    Memorial Works, Inc., 
    128 Vt. 359
    , 360–62 (1970) (treating diversion of water onto another’s land
    as act of trespass). However, “mere entry onto another’s land does not in itself constitute a
    trespass because such entry can be privileged: ‘Trespass involves the unprivileged entry on to
    the land in possession of another. By definition, trespass involves conduct that the trespasser has
    no right to engage in . . . .’” Ondovchik Family Ltd. P'ship v. Agency of Transp., 
    2010 VT 35
    , ¶ 10,
    
    187 Vt. 556
     (quoting Wild v. Brooks, 
    2004 VT 74
    , ¶ 17, 
    177 Vt. 171
    ) (emphases in original); see
    also Restatement (Second) of Torts § 158 cmt. e (“Conduct which would otherwise constitute a
    trespass is not a trespass if it is privileged.”); id. §§ 176–211.
    Plaintiff appears to argue that the entry of water, mud, sediment, and gravel from the
    roadway onto his land, as well as JSE’s entry onto his land in performing their contract with the
    town, both constitute a trespass. Through Plaintiff’s affidavit, there is evidence that JSE physically
    entered Plaintiff’s land, and that it invaded Plaintiff’s property by permitting water or road material
    to enter his land. To the extent JSE intentionally entered Plaintiff’s land or diverted water or road
    material through his land, JSE contends that those actions were privileged. See Ondovchik, 
    2010 VT 35
    , ¶ 10; Restatement (Second) of Torts § 211. In Ondovchik, the Court held that snowplows
    are engaged in privileged, lawful conduct when plowing roads, because the State has a duty
    under federal law to remove snow and engage in other routine maintenance of state highways.
    Ondovchik, 
    2010 VT 35
    , ¶ 11. The Court relied on section 211 of the Restatement, which provides:
    A duty or authority imposed or created by legislative enactment
    carries with it the privilege to enter land in the possession of another
    for the purpose of performing or exercising such duty or authority in
    so far as the entry is reasonably necessary to such performance or
    exercise, if, but only if, all the requirements of the enactment are
    fulfilled.
    10
    Restatement (Second) of Torts § 211. Similarly, here, no one can rationally dispute that the Town
    has a duty to maintain its roads and culverts during rain storms, including Economou Road. See
    19 V.S.A. § 310(a) (“A town shall keep its class 1, 2, and 3 highways and bridges in good and
    sufficient repair during all seasons of the year . . . .”).
    But this case contains an important distinction from Ondovchik. Here, there is evidence
    that the actions taken by JSE were not reasonably necessary to such performance of the Town’s
    duty to keep Economou Road in good and sufficient repair. Plaintiff’s assertion in his affidavit is
    that there was no reason for JSE to come 60 feet onto his property and dig a ditch that ended up
    diverting the runoff directly toward the undamaged portion of his house, and that this action plainly
    could not have diverted the runoff to the natural stream. Plaintiff has presented evidence which,
    if believed, could entitle him to relief for a trespass claim.
    V.      Conversion
    To the extent the Complaint also alleges a conversion, see Compl., Count II, ¶ 6
    (“Defendants’ trespass to at least some of Plaintiff’s property amounted to conversion . . . .”), that
    claim fails. To establish a claim for conversion, the property owner must show “that another has
    appropriated the property to that party’s own use and beneficial enjoyment, has exercised
    dominion over it in exclusion and defiance of the owner’s right, or has withheld possession from
    the owner under a claim of title inconsistent with the owner’s title.” Montgomery v. Devoid, 
    2006 VT 127
    , ¶ 12, 
    181 Vt. 154
     (quoting P.F. Jurgs & Co. v. O'Brien, 
    160 Vt. 294
    , 299 (1993)); see also
    Hegarty v. Addison Cty. Humane Soc., 
    2004 VT 33
    , ¶ 9, 
    176 Vt. 405
    ; Restatement (Second) of
    Torts § 222A (1965) (“Conversion is an intentional exercise of dominion or control over a chattel
    which so seriously interferes with the right of another to control it that the actor may justly be
    required to pay the other the full value of the chattel.”). The admissible evidence comes nowhere
    close to demonstrating that Defendants appropriated Plaintiff’s property for their own use and
    enjoyment, exercised dominion over it in exclusion of Plaintiff’s right, or withheld possession under
    an inconsistent claim of title.
    VI.     Damages
    Defendants contend that Plaintiff is not entitled to punitive damages or emotional distress
    damages. Punitive damages require “outrageously reprehensible” conduct accompanied by
    “malice”. See, e.g., Fly Fish Vermont, Inc. v. Chapin Hill Estates, Inc., 
    2010 VT 33
    , ¶ 18, 
    187 Vt. 541
    . There is no evidence of such conduct. Moreover, it appears that Plaintiff concedes that he
    is not entitled to punitive damages.
    As for emotional distress damages, the general rule is that such damages are not allowed
    for claims of ordinary negligence, absent physical impact or substantial bodily injury or sickness.
    Vincent v. DeVries, 
    2013 VT 34
    , ¶¶ 10–12, 25, & n.2, 
    193 Vt. 574
    . There is no such evidence of
    physical impact or substantial bodily injury or sickness. In fact, Plaintiff testified that he was never
    in physical danger during the July 2013 rainstorm. Krull depo. at 161:6–15.
    PLAINTIFF’S MOTION TO AMEND COMPLAINT
    Plaintiff seeks to amend his complaint. His motion, in addition to numerous stylistic and
    technical changes that have no potential to affect the court’s ruling on summary judgment,
    proposes five “primary” amendments: (1) the addition of a “spoliation” claim; (2) the addition of a
    Public Records Act claim; (3) the addition of a claim for injunctive relief; (4) the substitution of the
    11
    State of Vermont as a defendant; and (5) the addition of a state law “takings” or inverse
    condemnation claim.9
    The Supreme Court and the civil rules have recognized a liberal policy for permitting
    amendments to the pleadings. See, e.g., V.R.C.P. 15(a); Lillicrap v. Martin, 
    156 Vt. 165
     (1991);
    Hunters, Anglers and Trappers Ass’n of Vermont, Inc. v. Winooski Valley Park Dist., 
    2006 VT 82
    ,
    ¶ 17, 
    181 Vt. 12
     (quoting Bevins v. King, 
    143 Vt. 252
    , 254-55 (1983)). However, “‘denial of a
    motion under Rule 15(a) may be justified based upon a consideration of the following factors: (1)
    undue delay; (2) bad faith; (3) futility of amendment; and (4) prejudice to the opposing party.’”
    Prive v. Vermont Asbestos Group, 
    2010 VT 2
    , ¶ 13, 
    187 Vt. 280
    , 286–87 (2010) (quoting Colby
    v. Umbrella, 
    2008 VT 20
    , ¶¶ 12–13, 
    184 Vt. 1
    ).
    Delay and Prejudice
    Here, delay and prejudice provide ample grounds to deny the motion to amend. This case
    has been pending since July of 2015, yet Plaintiff waited approximately two years—after the close
    of discovery, and only in response to Defendants’ motions for summary judgment—to file his
    motion to amend. Plaintiff offers no compelling reason or good cause for the delay. In fact, he
    concedes that counsel mentioned his “takings” theory to Defendants’ counsel long before the
    motions for summary judgment motions were filed, but never moved to add that as a claim until
    July 2017. “[A] motion to amend should be made as soon as the necessity for altering the pleading
    becomes apparent. A party who delays in seeking an amendment is acting contrary to the spirit
    of the rule and runs the risk of the court denying permission because of the passage of time.”
    Wright & Miller, 6 Fed. Prac. & Proc. Civ. § 1488 (3d ed. (Apr. 2017 update). The proposed
    amendment would patently prejudice Defendants because it would necessitate an additional
    round of dispositive briefing after discovery has already closed and motions for summary
    judgment have been filed. Id. (“As a general rule, the risk of substantial prejudice increases with
    the passage of time. . . . [P]laintiffs have been denied leave to amend to add new claims or
    theories when the amendment is sought after the case has been pending for some time, discovery
    has closed, and the court is about to rule on defendant’s summary-judgment motion.”); see also
    Gauthier v. Keurig Green Mountain, Inc., 
    2015 VT 108
    , ¶ 47, 
    200 Vt. 125
     (concluding that trial
    court did not abuse its discretion in denying motion to amend filed almost one year after initiation
    of suit and two weeks after defendant had moved for summary judgment, where trial court found
    that plaintiff’s proffered justification for delay was not basis for proposed new claims, and that
    defendant “had already marshaled its resources to respond to the allegations made in the existing
    complaint”) (quotations omitted).
    Futility
    Moreover, the motion to amend can also be denied because the proposed amendment is
    futile, with one exception noted below. Generally, to decide whether a proposed amendment is
    “futile,” the court must examine whether plaintiff’s amended complaint would survive a Rule
    12(b)(6) motion to dismiss. Prive v. Vermont Asbestos Grp., 
    2010 VT 2
    , ¶ 13, 
    187 Vt. 280
    .
    However, courts need not always assess proposed amended pleadings on a 12(b)(6) standard.
    “In evaluating the futility of amendment, a number of courts have held that a summary judgment
    standard may be applied and leave to amend denied outright should the party seeking
    amendment fail to satisfy that standard.” Oneida Indian Nation of New York State v. Cty. of
    Oneida, N.Y., 
    199 F.R.D. 61
    , 88 n.23 (N.D.N.Y. 2000) (quoting Republic Nat’l. Bank v. Hales, 75
    9 Plaintiff also appears to argue that his proposed amendment merely clarifies that his negligence and trespass claims
    already constitute a “takings” claim, rather than adding a totally new “takings” cause of action.
    
    12 F. Supp. 2d 300
    , 308 (S.D.N.Y. 1999)). “Other courts . . . have at times allowed amendment, but
    simultaneously evaluated the amended pleading under the standards governing motions brought
    pursuant to Rule 56.” 
    Id.
     (quoting Hales, 75 F. Supp. 2d at 309); see also Wright & Miller, 6 Fed.
    Prac. & Proc. Civ. § 1487 (3d ed. Apr. 2017 update) (“several courts have held that if a complaint
    as amended could not withstand a motion to dismiss or summary judgment, then the amendment
    should be denied as futile”) (emphasis added); Montalvo v. Sun Roc Corp., 
    179 F.R.D. 420
    , 424
    (S.D.N.Y. 1998); Azurite Corp. v. Amster & Co., 
    844 F. Supp. 929
    , 939 (S.D.N.Y. 1994), aff’d, 
    52 F.3d 15
     (2d Cir. 1995); Schare v. Six Flags Theme Parks, No. 96 CIV. 9377 (RWS), 
    1998 WL 24361
    , at *6 (S.D.N.Y. Jan. 23, 1998) (“Where an amended claim would fail on a summary
    judgment motion, the court has discretion to treat the opposition to the amendment as a motion
    for summary judgment and to consider matters outside the pleadings in resolving the motion.”);
    Rogen v. Scheer, No. 86 Civ. 2058 (MJL), 
    1991 WL 33294
    , at *3 (S.D.N.Y. Feb.22, 1991).
    Virtually all of Plaintiff’s proposed amendments are futile, as explained below.
    I.       Spoliation
    First, the Supreme Court has never recognized spoliation as an independent cause of action in
    Vermont. Naylor v. Rotech Healthcare, Inc., 
    679 F. Supp. 2d 505
    , 511 (D. Vt. 2009) (“As an issue
    of first impression, this Court finds no separate cause of action exists under Vermont law for
    spoliation of evidence.”). A discovery sanction is the proper remedy for spoliation. Id.; cf. Felis v.
    Downs Rachlin Martin PLLC, 
    2015 VT 129
    , ¶ 19, 
    200 Vt. 465
     (“Although a court can vacate a
    judgment based on a finding of fraud on the court, a party cannot bring a private cause of action
    for tort under this theory.”).
    II.        Public Records Act
    Plaintiff’s proposed Public Records Act claim similarly fails. This claim is apparently based
    only on the allegation that the Town did not create certain records or data. The Act, however,
    applies only to records already in existence. See 1 V.S.A. § 317(b) (“‘public record’ or ‘public
    document’ means any written or recorded information, regardless of physical form or
    characteristics, which is produced or acquired in the course of public agency business”). It does
    not mandate the creation of new records.
    III.       Substitution of State of Vermont as Defendant/”Huntington is Not a Town” Argument
    Plaintiff next seeks to substitute the State of Vermont as a Defendant in this action on the
    grounds that Huntington is not a real town. Plaintiff contends that Huntington was never
    incorporated nor chartered as a Vermont municipality and, therefore, is an unincorporated
    municipality for which the State is liable. See McCord v. City of Pueblo, 
    5 Colo. App. 48
    , 53, 
    36 P. 1109
    , 1110 (1894) (“The unincorporated agencies occupy the same positions as the state, and
    are protected to the same extent; but, when any state agency becomes a municipal corporation,
    it thereby acquires an identity distinct from the state, and is made liable for its own negligence.”).
    In effect, Plaintiff challenges the legal existence of the Town of Huntington.
    According to McQuillin:
    An inquiry into the legal existence of a municipality is in general
    reserved to the state in a proceeding by quo warranto or other direct
    proceeding. With few exceptions, a private person cannot
    ordinarily, either directly or indirectly, usurp this function of
    13
    government. Private individuals, as taxpayers or otherwise, cannot
    maintain an action challenging the legality of a municipal
    corporation, nor can they collaterally attack its existence where it is
    at least a de facto corporation. However, private parties may [have]
    standing in cases involving attacks on municipal incorporations and
    annexations only when the action complained of is void, rather than
    merely voidable, because the municipality exceeded its authority.
    Still, the law does not favor collateral attack on a municipal
    corporation in the exercise of police powers, and the court in such
    case need only ascertain its existence de facto.
    1 McQuillin Mun. Corp. § 3:107 (“Attack on corporate existence”) (3d ed. July 2017 update).
    Historical research reveals that 23,040 acres making up “New Huntington” was chartered
    to Edward Burling and 65 others on June 7, 1763, from Benning Wentworth, governor of the New
    Hampshire province, under the authority of King George III. State Papers of New Hampshire,
    26:232–35. New Huntington’s first settlers arrived in 1786, and the town was organized and its
    first town meeting was held on March 29, 1790. Hamilton Child, Gazetteer and Business Directory
    of Chittenden County, 218–19 (1882). Jehial Johns was elected to represent New Huntington in
    the General Assembly in 1791. Journal of the Proceedings of the General Assembly of the State
    of Vermont (Oct. 13, 1791), reprinted at State Papers of Vermont, 3(5): 5. The town has had a
    representative in the Legislature ever since. Leonard Dening, Catalogue of the Principal Officers
    of Vermont, 34–46 (1851). In 1794, the General Assembly recognized New Huntington’s elected
    town officers. Laws of 1794, “An Act Establishing the Town Officers in the Town of Burlington,
    Williston, New Huntington and Jericho” (Oct. 29th, 1794), reprinted at State Papers of Vermont,
    15:316. On October 27, 1795, the Vermont General Assembly changed its name from “New
    Huntington” to “Huntington.” Laws of 1795, “An Act Altering the Name of New Huntington to that
    of Huntington” (Oct. 27, 1795), reprinted at State Papers of Vermont, 15:425.
    The above historical sources conclusively demonstrate that Huntington was chartered as
    a municipal corporation in 1763, and has been treated as such by the state legislature since the
    founding of Vermont. Even assuming there were insufficient evidence of incorporation, it is clear
    that, at the very least, Huntington is a de facto corporation, subject to challenge only in a direct
    action by the State. 1 McQuillin Mun. Corp. § 3:107. The court further observes that the Vermont
    Supreme Court has implicitly recognized that Huntington is an incorporated town, with the ability
    to sue and be sued. See, e.g., Town of Jericho v. Town of Huntington, 
    79 Vt. 329
     (1906); Town
    of Huntington v. Chesmore, 
    60 Vt. 566
     (1888); Town of Starksboro v. Town of Huntington, 
    50 Vt. 599
     (1878); Town of Huntington v. Town of Charlotte, 
    15 Vt. 46
    , 50 (1843). Moreover, Vermont
    has 237 towns, 9 cities, 5 unincorporated towns, and 4 gores. Of the 246 incorporated cities and
    towns, only about 60 have municipal charters that are codified in the appendix to Title 24. Under
    Plaintiff’s logic, approximately three quarters of Vermont’s cities and towns are unincorporated
    municipalities, for which the State is liable. The court rejects this logic. Huntington and about 190
    other municipalities that are not listed in the Title 24 appendix can rest assured knowing that they
    are, in fact, municipal corporations.
    Plaintiff’s attempt to add the State as a party appears to be based only on the false premise
    that Huntington is not an incorporated municipality. The court could join the State if there were
    some independent basis by which the State could be liable. However, Plaintiff has provided no
    such evidence. Because the motion to join the State (# 21) arises from the same argument raised
    in the motion to amend, the motion to join is also denied.
    14
    IV.     Takings/Inverse Condemnation Claim
    Plaintiff seeks to add a state law “takings”/inverse condemnation claim. See Vt. Const. ch.
    I, art. 2 (“[P]rivate property ought to be subservient to public uses when necessity requires it,
    nevertheless, whenever any person’s property is taken for the use of the public, the owner ought
    to receive an equivalent in money.”). Plaintiff pursues this approach presumably because the
    “doctrine of immunity from liability does not apply where the injury complained of is the taking of
    private property for public use without compensation.” Griswold v. Town Sch. Dist. of Town of
    Weathersfield, 
    117 Vt. 224
    , 226 (1952). Liability under the constitutional takings provision “is not
    dependent on negligence but on the taking of private property and this unlawful taking gives the
    right of action.” 
    Id. at 227
    .
    The purpose of the Takings Clause is “to bar Government from forcing some people alone
    to bear public burdens which, in all fairness and justice, should be borne by the public as a whole.”
    Armstrong v. United States, 
    364 U.S. 40
    , 49 (1960). Thus, a property owner subject to a taking is
    entitled to just compensation. However, “not every ‘invasion’ of private property resulting from
    government activity amounts to an appropriation.” Ondovchik Family Ltd. P’ship v. Agency of
    Transp., 
    2010 VT 35
    , ¶ 16, 
    187 Vt. 556
     (citing Ridge Line, Inc. v. United States, 
    346 F.3d 1346
    ,
    1355 (Fed. Cir. 2003)). Instead, the Supreme Court has outlined a two-part test to determine when
    government conduct amounts to a potential taking: (1) “a property loss compensable as a taking
    only results when the government intends to invade a protected property interest or the asserted
    invasion is the direct, natural, or probable result of an authorized activity and not the incidental or
    consequential injury inflicted by the action,” 
    id.
     (citing Ridge Line, 
    346 F.3d at 1355
    ); and (2)
    “[e]ven where the effects of the government are predictable, to constitute a taking, an invasion
    must appropriate a benefit to the government at the expense of the property owner, or at least
    preempt the owners[’] right to enjoy his property for an extended period of time, rather than merely
    inflict an injury that reduces its value.” Regan v. Spector, 
    2016 VT 116
    , ¶ 18 (citing Ridge Line,
    346 F.3d at 1355–56). The Court has further emphasized that: (1) “temporary, repeated incursions
    can sometimes rise to the level of a taking, but only in instances where the incursions amount to
    the taking of an easement”; (2) “courts generally find a taking of an easement only when the
    government requires an ‘onerous’ dedication of property”; and (3) “[w]hen the intrusion is ‘limited
    and transient’ in nature and occurs for legitimate governmental reasons, it does not amount to a
    taking.” 
    Id.
     (citing Ondovchik, 
    2010 VT 35
    , ¶ 18); see also Ridge Line, 
    346 F.3d at 1354
    (recognizing that intermittent flooding of private land can in some circumstances constitute taking
    of an easement).
    Vermont law in this area has evolved. In Timms v. State, the landownder’s well was
    destroyed by the state’s non-negligent salting of roads, and the Supreme Court held that to be a
    taking, noting that “[p]ermanent physical damage to property to the point of depriving the owner
    of its beneficial use constitutes a taking.” 
    139 Vt. 343
    , 344–45 (1981) (citing Griswold, 
    117 Vt. at 226
    ; Sanborn v. Village of Enosburg Falls, 
    87 Vt. 479
    , 483–84 (1914)). Nearly three decades
    later, the Court overruled Timms, observing that it had become an outlier, and that the Timms
    Court had improperly failed to draw a distinction between “permanent physical occupation” and
    “more temporary invasion” in finding a taking “based upon the consequential damages of lawful
    salting activities that the government performed on its own property.” Ondovchik Family Ltd.
    P’ship v. Agency of Transp., 
    2010 VT 35
    , ¶ 15, 
    187 Vt. 556
     (citing T. Goger, Annot., Salting for
    Snow Removal as Taking or Damaging Abutting Property for Eminent Domain Purposes, 
    64 A.L.R.3d 1239
     (1975); Loretto v. Teleprompter Manhattan CATV Corp., 
    458 U.S. 419
    , 428 (1982))
    see also Loretto, 
    458 U.S. at 428
     (“[T]his Court has consistently distinguished between flooding
    cases involving a permanent physical occupation, on the one hand, and cases involving a more
    15
    temporary invasion, or government action outside the owner’s property that causes consequential
    damages within, on the other. A taking has always been found only in the former situation.”).
    The facts of Ondovchik bear some similarity to the present case. There, the landowner
    alleged damage to its building from snow throw and contaminated water runoff resulting from
    defendant’s snowplowing of the highway, which it argued constituted a taking. Id. ¶¶ 1, 4. The
    Court rejected this argument and affirmed the trial court’s dismissal of the inverse condemnation
    claim, stating:
    Here, landowner does not claim that defendant has authorized a
    permanent occupation, intrusion, or appropriation of landowner's
    property such that it permanently ousts landowner from possession.
    Rather, landowner alleges that legitimate governmental activities
    outside of landowner’s property occasionally intrude upon and
    damage landowner’s property. Any damages from such activities
    are purely consequential, and landowner’s complaint therefore
    lacks any facts or circumstances that would allow for recovery
    under a claim of inverse condemnation. Even when viewing the
    facts in the light most favorable to landowner, there is no allegation
    that defendant has created a permanent physical occupation of
    landowner’s property.
    Id., ¶ 17 (citing Ridge Line, 346 F.3d at 1355–56) (emphasis in original). The Court further
    observed that the landowner made “no claim . . . that defendant [took] an easement by allowing
    snow throw to intermittently and temporarily intrude on landowner’s property.” Id. ¶ 18.
    Applying the test articulated in Ondovchik and Regan here, the court first notes there is
    no evidence that the Town intended to invade Krull’s protected property interest. The operative
    question, instead, is whether the “invasion” of gravel, mud, and sediment from the road onto Krull’s
    property is the “direct, natural, or probable result of an authorized activity” or the “incidental or
    consequential injury inflicted by the action.” Regan, 
    2016 VT 116
    , ¶ 18; Ondovchik, 
    2010 VT 35
    ,
    ¶ 16. Under this distinction, the court cannot conclude that the “invasion” asserted here was the
    “direct, natural, or probable result” of the Town’s actions. Without diminishing the magnitude and
    severity of the damage sustained by Krull’s property, the court must conclude that this damage
    was incidental or consequential to the Town’s actions in maintaining Economou Road. The
    caselaw compels this result. See Omnia Commercial Co. v. United States, 
    261 U.S. 502
    , 510
    (1923) (“for consequential loss or injury resulting from lawful governmental action the law affords
    no remedy”). The proposed takings claim fails as a matter of law and, accordingly, amending the
    complaint to add that claim would be futile. Assuming the complaint already states a takings claim
    and that the proposed amendment merely provides clarification, as Plaintiff contends, there is no
    evidence of a constitutional taking sufficient to survive summary judgment.
    To the extent Plaintiff alleges a regulatory taking, that claim would also be futile. “The
    application of a general zoning law to particular property effects a taking if the ordinance does not
    substantially advance legitimate state interests or denies an owner economically viable use of his
    land.” Chioffi v. City of Winooski, 
    165 Vt. 37
    , 41 (1996) (quoting Agins v. City of Tiburon, 
    447 U.S. 255
    , 260 (1980)). Plaintiff has not identified any actual land-use regulation that negatively affected
    or affects his property.
    Finally, to the extent that Plaintiff’s proposed takings claim is alleged against JSE in
    addition to the Town, it is also futile. A takings claim can be brought only against a government
    16
    entity with the power of eminent domain, not against a private entity. Plaintiff’s remedy against
    JSE, if any, falls within the realm of tort law (i.e., his negligence and trespass claims, discussed
    above). Nor can any potential negligence by JSE be imputed to the Town to form the basis for a
    takings claim.10
    V.       Declaratory and Injunctive Relief
    Plaintiff also seeks to add a claim for what he calls “Injunctive & Declaratory Relief on All
    Counts.” Pl.’s Proposed Am. Compl. ¶¶ 67–73. “‘Injunctive relief’ is not an independent cause of
    action, but a request for a particular remedy that is dependent on some valid, underlying cause
    of action.” Albertine v. Churchview Estates, LLC., No. 591-5-14 Cncv, 
    2016 WL 9403907
    , *3 n.4
    (Vt. Super. Aug. 12, 2016) (Toor, J.), motion to reconsider granted on other grounds, 
    2016 WL 5816181
     (Sept. 28, 2016) (Mello, J.); see also In re Joint E. & S. Dist. Asbestos Litig., 
    14 F.3d 726
    , 731 (2d Cir. 1993) (emphasis supplied); see also Alabama v. U.S. Army Corps of Eng’rs,
    
    424 F.3d 1117
    , 1127 (11th Cir. 2005); Springfield Hosp. v. Hofmann, No. 5:09-CV-254, 
    2011 WL 3421528
    , at *2 (D. Vt. Aug. 4, 2011), aff’d, 
    488 F. App’x 534
     (2d Cir. 2012) (“a request for injunctive
    relief is not a separate cause of action”). Similarly, declaratory relief also requires the existence
    of some valid, underlying substantive claim. See Vermont State Employees’ Ass’n, Inc. v.
    Vermont Criminal Justice Training Council, 
    167 Vt. 191
    , 194 (1997) (Declaratory Judgment Act
    “does not increase or enlarge the jurisdiction of the court over any subject matter or parties”);
    Williams v. State, 
    156 Vt. 42
    , 60 (1990) (“[T]he availability of declaratory relief turns on whether
    the facts alleged, under all the circumstances, show that there is a substantial controversy,
    between parties having adverse legal interests, of sufficient immediacy and reality to warrant the
    issuance of a declaratory judgment. A mere abstract question or hypothetical threat is not a
    sufficient basis for a declaratory judgment.”) (citation and quotation omitted); Chiste v. Hotels.com
    L.P., 
    756 F. Supp. 2d 382
    , 406 (S.D.N.Y. 2010) (“Declaratory judgments and injunctions are
    remedies, not causes of action.”).
    Plaintiff’s proposed amended complaint states that he seeks declaratory and injunctive
    relief to “ensure the prevention of future temporary or permanent takings by requiring that certain
    minimum care is taken with respect to water runoff management in the area of Plaintiff’s home . .
    . .” Pl.’s Proposed Am. Compl. ¶ 73. His request for injunctive relief includes the following specific
    practices:
    (1) requiring the completion of an engineering analysis and report before any road
    grading or culvert or ditch repair or replacement;
    (2) that any such report shall provide recommendations of repairs needed to ensure
    systems can handle at least once-in-25-year rain events;
    (3) that any such recommendations shall be followed;
    (4) that engineering reports, evidence of work performed, and all related materials
    shall be retained for at least 25 years; and
    (5) that Defendants shall provide appropriate compensation when the road cannot be
    properly managed without a taking or other infringement of property rights.
    10 The court concludes that a site visit is not necessary to rule on Plaintiff’s takings claim, or on any of the other claims.
    The court can make a sufficiently informed decision based on the materials submitted by the parties, including the
    various photographs and maps of the property. Plaintiff’s motion for a site visit is denied.
    17
    Id. ¶ 73(a)–(e).
    Because all of Plaintiff’s underlying claims against the Town of Huntington fail as a matter
    of law, he is not entitled to any injunctive or declaratory relief against the Town. Indeed, to the
    extent he seeks declaratory relief, his proposed claim is futile, as it would effectively result in the
    court issuing an impermissible advisory opinion. See Williams, 156 Vt. at 59–60 (“Without such
    justiciable controversy being present, the declaratory judgment can provide no more than an
    advisory opinion, which our State judiciary does not have the constitutional power to render.”).
    The only proposed request for injunctive or declaratory relief that could conceivably apply
    to John Scott Excavating is the request to “provide appropriate compensation when the road
    cannot be properly managed without a taking or other infringement of property rights.” Assuming
    that this could be a proper type of declaratory or injunctive relief, it is duplicative and adds nothing
    to the case. If Plaintiff proves that JSE is liable for some infringement of property rights as part of
    his negligence or trespass claim, appropriate compensation in the form of damages is the remedy.
    The court does not see what purpose the proposed declaratory or injunctive relief would serve.
    VI.     Other Proposed Amendments
    For the sake of completeness, the court also briefly addresses additional proposed
    amendments sought by Plaintiff, and which were not fully briefed by Defendants. It appears that
    Plaintiff attempts to add a claim under the Common Benefits Clause of the Vermont Constitution.
    See Vt. Const. ch. I, art. VII (“That government is, or ought to be, instituted for the common benefit,
    protection, and security of the people, nation, or community, and not for the particular emolument
    or advantage of any single person, family, or set of persons, who are a part only of that community
    . . . .”). A constitutional tort action under Article 7 “is not designed to review the discretionary
    decisions of another branch of government but to remedy harms caused when a governmental
    body acts in a wholly arbitrary and unjustified manner in violation of Article 7.” In re Town Highway
    No. 20, 
    2012 VT 17
    , ¶ 38, 
    191 Vt. 231
    . Thus, it is “not sufficient” for a Common Benefits Clause
    plaintiff “simply to show that he or she lacks a remedy adequate to vindicate the interest asserted.”
    Id. ¶ 37. The plaintiff must also show the denial of a common benefit accompanied by “disparate
    and arbitrary treatment when compared to others similarly situated,” that “the denial directly favors
    another particular individual or group,” and that “the decision was wholly irrational and arbitrary
    [and] actuated by personal motives unrelated to the duties of the defendant's official position,
    such as ill will, vindictiveness, or financial gain.” Id. Simply stated, there is no admissible evidence
    in the record that any actions taken by the Town were “motivated solely by an actual desire to
    harm the plaintiff or by other unjustified personal motives such as self-enrichment or the
    enrichment of others.” Id. ¶ 38; see also id. ¶ 45 (finding Article 7 violation by town selectboard in
    light of “relentless bias” and “invidious[] discriminat[ion]” against landowner and in favor of others,
    which denied plaintiff access to his property for many years).
    Plaintiff also adds factual allegations concerning stress and anxiety suffered by his
    daughter as apparently contributing to his own emotional distress. Pl.’s Proposed Am. Compl.
    ¶ 44. As discussed above in addressing Defendants’ summary judgment motions, this
    amendment would be futile. See Vincent v. DeVries, 
    2013 VT 34
    , ¶¶ 10–12, 25, & n.2, 
    193 Vt. 574
    .
    Additionally, Plaintiff seeks to amend his complaint by adding a claim under the timber
    trespass statute, 13 V.S.A. § 3606. That statute provides:
    18
    In addition to any other civil liability or criminal penalty allowed by
    law, if a person cuts down, fells, destroys, removes, injures,
    damages, or carries away any timber placed or growing for any use
    or purpose whatsoever, or forest products standing, lying, or
    growing belonging to another person, without permission from the
    owner of the timber or forest product, or cuts out, alters, or defaces
    the mark of a log or other valuable forest product, the party injured
    may recover of such person, in an action on this statute, treble
    damages for the value of the timber or forest product, and any
    damage caused to the land or improvements thereon as a result of
    such action.
    13 V.S.A. § 3606(a). The goal of the statute, which applies only to trespassers, see Masters v.
    Stone, 
    134 Vt. 529
    , 532 (1976), is “to deter intentional trespass and the wrongful taking of
    another’s timber.” Stanley v. Stanley, 
    2007 VT 44
    , ¶ 12, 
    181 Vt. 527
     (citing State v. Singer, 
    2006 VT 46
    , ¶ 11, 
    180 Vt. 104
    ). The Supreme Court has described the “intended targets” of the timber
    trespass statute as “those ‘tree pirates’ and “arboreal rustlers’ who trespass on another’s property
    and remove timber to which they have no right.” 
    Id.
     (quoting Singer, 
    2006 VT 46
    , ¶ 11).
    While the plain language of the statute is broad, it is inapplicable in this case. There is
    evidence that John Scott destroyed several trees on Plaintiff’s property, and that this caused
    increased water flow toward Plaintiff’s house. But John Scott Excavating is clearly not a “tree
    pirate” or “arboreal rustler” within the meaning of the timber trespass statute. Id. ¶ 12. Again, the
    purpose of the statute is “to deter intentional trespass and the wrongful taking of another’s timber.”
    Id. There is no evidence that JSE entered Plaintiff’s land for the purpose of destroying or taking
    his timber. The evidence instead reflects, at most, negligent destruction of several of Plaintiff’s
    trees while trying to divert the flow of water and road materials during a rainstorm. This is not the
    type of situation to which the timber trespass statute was intended to apply. Moreover, if the finder
    of fact concludes that JSE is liable to Plaintiff for negligence, Plaintiff would likely be awarded
    damages for destruction of the trees in any event. The addition of a claim under the timber
    trespass statute would be futile.
    The remaining proposed amendments represent an attempt to beef up the factual
    allegations, or are merely stylistic in nature. As Plaintiff states, these amendments are “largely
    not substantive, or perhaps even necessary at this time, but are being provided out of caution,
    and to better inform the parties of Plaintiff’s position.” Pl.’s Mot. to Am. Compl. at 1. Given that
    discovery ended months ago, it is not clear that these proposed amendments would change
    anything. As these remaining amendments appear to serve no purpose and are, in Plaintiff’s own
    words, “not . . . even necessary,” they are futile.
    PLAINTIFF’S MOTION FOR PARTIAL SUMMARY JUDGMENT
    Plaintiff moves for partial summary judgment on 3 of the 19 total affirmative defenses
    raised by Huntington in its Answer: (1) the two-year statute of limitations under 12 V.S.A. § 514;
    (2) the limitation of damages under 19 V.S.A. § 985; and (3) the failure to provide notice under 19
    V.S.A. § 987. Because the court has decided above that all of Plaintiff’s claims against the Town
    fail as a matter of law and that Huntington’s motion for summary judgment will be granted, it
    appears that Plaintiff’s Motion for Partial Summary Judgment as to the Town’s affirmative
    defenses is moot. For the sake of completeness, however, the court notes that the parties already
    agreed on the inapplicability both section 985 and 987, which apply only to a person injured while
    travelling over a defective bridge or culvert, see Thompson v. Town of Stannard, 
    125 Vt. 140
    , 143
    19
    (1965), and that the court would have denied Plaintiff’s motion as to § 514 for failure to establish
    undisputed material facts in support of his motion.
    Order
    Defendant Town of Huntington’s motion for summary judgment (# 10) is granted.
    Defendant John Scott Excavating’s motion for summary judgment (# 12) is granted in part
    and denied in part. The motion is denied as to actions taken by John Scott Excavating during the
    rainstorm on July 3, 2013 (as discussed above), which the court concludes raise a disputed
    material fact as to the negligence and trespass claims. The motion is granted in all other respects.
    Plaintiff’s motion to amend his complaint (# 13) is denied.
    Plaintiff’s motion for partial summary judgment (# 15) is moot.
    Plaintiff’s motion to join the State of Vermont (# 21) is denied.
    Plaintiff’s motion for a site visit (# 25) is denied.
    The clerk will schedule a pre-trial conference, for the purpose of setting a trial date and
    addressing any other necessary issues. As neither party has requested a jury trial, this matter will
    be decided at a bench trial.
    SO ORDERED this 22nd day of December, 2017.
    _____________________________
    Robert A. Mello
    Superior Court Judge
    20
    

Document Info

Docket Number: 651-7-15 Cncv

Filed Date: 12/22/2017

Precedential Status: Precedential

Modified Date: 7/31/2024