Nesti v. Vermont Agency of Transp. ( 2019 )


Menu:
  • Nesti v. Vermont Agency of Transp., No. 1096-12-18 Cncv (Toor, J., Aug. 20, 2019).
    [The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the
    accompanying data included in the Vermont trial court opinion database is not guaranteed.]
    VERMONT SUPERIOR COURT
    CHITTENDEN UNIT
    CIVIL DIVISION
    │
    FRANCES NESTI,                                                           │
    Plaintiff                                                               │
    │
    v.                                                                      │
    │
    VERMONT AGENCY OF                                                        │                 Docket No. 1096-12-18 Cncv
    TRANSPORTATION,                                                          │
    Defendant                                                               │
    │
    RULING ON DEFENDANTS’ MOTION TO DISMISS
    This case arises from the expansion of Route 7 at the South Burlington/Shelburne
    town line, and subsequent water damage to Plaintiff Frances Nesti’s nearby property from
    the rebuilt roadway drainage infrastructure. Plaintiff brings this action against the Agency
    of Transportation (“VTrans”)in connection with its reconstruction of Route 7.1 She alleges
    five claims: nuisance, trespass, takings, ejectment, and removal of lateral support.
    Defendants move to dismiss on grounds of statute of limitations and immunity. The court
    heard oral argument on August 5, 2019. Alexander J. LaRosa, Esq. represents Plaintiff.
    Robert F. McDougall and Ryan P. Kane, Esqs. represent Defendants.
    Alleged Facts
    The facts as alleged by Plaintiff are as follows. Plaintiff owns property located at 2
    Pine Haven Shore Lane in Shelburne, downhill and west of Route 7. Am. Compl. ¶ 1. Her
    claims arise from the State’s reconstruction of Route 7 in South Burlington and Shelburne
    1 Plaintiff also named the Agency of Natural Resources Department of Environmental Conservation, but at
    oral argument agreed to the dismissal of DEC from the case.
    in 2005 and 2006. Id. ¶¶ 28–42. The State significantly changed the pre-existing drainage
    of surface waters as part of the project, which resulted in stormwaters being redirected
    toward and through Plaintiff’s property. Id. ¶¶ 40–55.
    “Immediately after VTrans completed construction in . . . 2006, Plaintiff saw a
    massive increase in stormwater runoff” in the dry depression that ran through her
    property. Id. ¶ 53. She claims that this stormwater has carried pollutants from the road to
    her property and caused significant erosion. Id. ¶¶ 56–79. More specifically, Plaintiff
    alleges the stormwater has eroded what had been a “shallow depression” into a “20 foot
    wide, 20 foot deep[,] steep sided, eroded[,] and unstable ravine.” Id. ¶ 61. That ravine
    now threatens her house and driveway, under which Plaintiff’s utility lines are buried. Id.
    ¶¶ 62–79. The complaint includes numerous photographs that depict the extent of the
    erosion.
    Discussion
    Plaintiff asserts claims for nuisance, trespass, the taking of an easement without
    just compensation, ejectment, and removal of lateral support.2 The State moves to
    dismiss, arguing that (1) all the claims are time-barred and barred by sovereign immunity,
    and (2) the two new counts fail to state a claim under Rule 12(b)(6).
    I.      Statute of Limitations
    The original complaint was filed in December 2018. The State contends that the
    nuisance, trespass, and takings claims are all subject to the general six-year statute of
    limitations of 12 V.S.A. § 511. Because the amended complaint alleges that Plaintiff “saw
    a massive increase in stormwater runoff” on her property “[i]mmediately after VTrans
    2 The latter two counts, Counts IV and V, were added in the amended complaint.
    2
    completed construction in . . . 2006,” Am. Compl. ¶ 53, the State argues that the action
    accrued in 2006 and is now time-barred. Plaintiff contends that the 15-year statute of
    limitations for “action[s] for the recovery of lands” applies to those claims. See 12 V.S.A.
    § 501.
    Plaintiff’s argument, while creative, is ultimately unavailing. “[T]respass is an
    invasion of the plaintiff’s interest in the exclusive possession of his land, while nuisance
    is an interference with his use and enjoyment of it.” John Larkin, Inc. v. Marceau, 
    2008 VT 61
    , ¶ 8, 
    184 Vt. 207
     (quoting W. Keeton et al., Prosser and Keeton on the Law of Torts
    § 87, at 622 (5th ed. 1984)). A “taking” typically involves a “permanent physical
    occupation or temporary incursions . . . amounting to an easement . . . .” Regan v. Spector,
    
    2016 VT 116
    , ¶ 19, 
    203 Vt. 463
    ; see also Ondovchik Family Ltd. P’ship v. Agency of
    Transp., 
    2010 VT 35
    , ¶¶ 16–18, 
    187 Vt. 556
    . All of these causes of action are subject to the
    general six-year limitations period of 12 V.S.A. § 511. See Dep’t of Forests, Parks &
    Recreation v. Town of Ludlow Zoning Bd., 
    2004 VT 104
    , ¶ 6, 
    177 Vt. 623
     (“taking” or
    “inverse condemnation” claim, which accrues on “the date on which the government
    physically interferes with the access”); Alpstetten Ass’n, Inc. v. Kelly, 
    137 Vt. 508
    , 512–13
    (1979) (nuisance); Bostock v. City of Burlington, No. S1337-03 CnC, slip copy at 13–14,
    
    2010 WL 2259141
     (Vt. Super. Ct. Jan. 27, 2010) (Toor, J.) (nuisance and trespass); The
    Nature Conservancy v. Ames, No. 6-1-05 Excv, at 3, 
    2006 WL 7089440
     (Vt. Super. Ct.
    Apr. 25, 2006) (Cook, J.) (trespass).
    Plaintiff attempts to distinguish the above caselaw. She argues that Ludlow
    involved a regulatory taking rather than a physical invasion, but Ludlow clearly stated
    that the six-year limitations period applies to all “eminent domain and inverse
    condemnation proceedings.” 
    2004 VT 104
    , ¶ 6. She contends that Kelly did not contain a
    3
    claim for nuisance. However, the counterclaim-plaintiff in Kelly alleged a complete and
    wrongful interruption to his water supply, which the Court characterized as a “tortious
    act resulting in an interference with the use and enjoyment of his property,” the very
    definition of nuisance. Kelly, 
    137 Vt. at 513
    . Plaintiff further asserts that application of the
    15-year statute of limitations is consistent with Lorman v. City of Rutland, 
    2018 VT 64
    , a
    case filed in 2015 which involved sewage backups on plaintiffs’ property between 1983
    and 2014. Id. ¶ 37. The Court affirmed the trial court’s grant of summary judgment for
    the city on grounds of immunity and insufficient evidence to prove a taking, and never
    addressed the statute of limitations. Id. ¶¶ 23–24, 27–28, 33, 37. Plaintiff offers no
    persuasive basis for applying the 15-year statute of limitations in 12 V.S.A. § 501 to any of
    these claims.3 The claims are instead subject to the 6-year statute of limitations in section
    511.
    Plaintiff next asserts that, even if the six-year period applies, the trespass and
    nuisance claims are not time-barred due to the continuing tort doctrine. That doctrine
    “allows a plaintiff to support his or her cause of action with events that occurred outside
    of the limitations period by delaying the accrual of a claim until the date of the last injury
    or the date the tortious acts cease.” Gettis v. Green Mountain Econ. Dev. Corp., 
    2005 VT 117
    , ¶ 23, 
    179 Vt. 117
     (quotation omitted). The doctrine “requires at least two elements: a
    continuing wrong, and some action contributing to the wrong that occurred within the
    3 In a case not cited by Plaintiff, the South Dakota Supreme Court held that nuisance and takings claims
    alleging periodic flooding from storm sewer system were governed by the 20-year period for adverse
    possession, rather than the 6-year limitations period for trespass actions. City of Sioux Falls v. Miller, 
    492 N.W.2d 116
    , 120 (S.D. 1992). However, the South Dakota Court had previously held, on numerous
    occasions, that the 20-year period for adverse possession was applicable to both takings claims and “where
    property rights are damaged in the name of the public, regardless of the underlying tort claim.” 
    Id.
     (citing
    prior cases). The Vermont Supreme Court has never made such a holding.
    4
    limitations period.” Id. ¶ 25. The Vermont Supreme Court has neither adopted nor
    rejected the continuing tort doctrine. Id. ¶ 24.4 This court discussed the doctrine in
    Bostock, where the plaintiffs claimed that the City of Burlington flooded their property
    with water, pollutants, and sewage due to construction of a highway connector, wildlife
    sanctuary, and stormwater project. No. S1337-03 CnC, slip copy at 5–6. The court ruled
    there that even assuming the doctrine is available, plaintiffs did not meet their summary
    judgment burden to produce evidence showing that the doctrine applied in that case. Id.
    at 17–18.5
    Assuming the continuing tort doctrine is available in Vermont, the key inquiry
    becomes whether the alleged trespass or nuisance is continuous or permanent. See D.
    Dobbs, The Law of Torts § 57 (2d ed. June 2019 update) (“If the defendant’s trespass or
    nuisance continues to cause harm to the plaintiff’s interests in land, courts usually begin
    by classifying the invasion as either permanent (completed) or temporary (continuing).”).
    Dobbs writes:
    In theory, if a nuisance is deemed permanent, there is only
    one unceasing invasion of the plaintiff’s interests and only one
    cause of action. This necessarily arises when the invasion first
    began or was first manifest. The statute of limitations on the
    one cause of action must, then, begin running from the time it
    became manifest. In contrast, if the nuisance or trespass is
    “temporary,” or “continuous,” a new cause of action arises day
    by day or injury by injury, with the result that the plaintiff in
    such a case can always recover for such damages as have
    accrued within the statutory period immediately prior to suit.
    4 The Court discussed the concept of “continuing trespass” in S. L. Garand Co. v. Everlasting Mem’l Works,
    Inc., 
    128 Vt. 359
     (1970) and Canton v. Graniteville Fire Dist. No. 4, 
    171 Vt. 551
    , 552 (2000) (mem.), although
    neither the “continuing tort doctrine” nor the statute of limitations were at issue.
    5 This court also declined to conclude that the Gettis requirement that a wrongful act occur within the
    limitations period was dispositive, even though there was no such act within the limitations period in
    Bostock. No. S1337-03 CnC, slip copy at 15. The court observed that the Gettis Court had not analyzed the
    continuing tort doctrine in the specific context of trespass and nuisance claims, which was an unsettled area
    of law, and that the plaintiffs had pointed to differences between negligence claims and trespass and
    nuisance claims that might obviate the Gettis requirement. 
    Id.
     at 15–16.
    5
    D. Dobbs, Remedies § 5.4, at 343 (1973) (footnotes omitted). Courts have reached varying
    and sometimes conflicting conclusions as to what is “permanent” and what is
    “temporary.” See D. Dobbs, The Law of Torts § 57, at 115–16 (2001) (“Conflicting
    decisions and factual variety make statement of a general rule perilous. . . . It is not easy
    to find harmony in the case results.”). For example, some courts focus on the tortious
    conduct or act, while other focus on the nature of the nuisance or trespass. Compare
    Carpenter v. Texaco, Inc., 
    419 Mass. 581
    , 583, 
    646 N.E.2d 398
    , 399 (Mass. 1995) (“a
    continuing trespass or nuisance must be based on recurring tortious or unlawful conduct
    and is not established by the continuation of harm caused by previous but terminated
    tortious or unlawful conduct”) with Jacques v. Pioneer Plastics, Inc., 
    676 A.2d 504
    , 507
    (Me. 1996) (“we have defined a nuisance as continuing when the thing that constitutes
    the nuisance is not of such a permanent nature that it can not readily be removed and
    thus abated”) (quotation omitted).
    The “permanent” versus “temporary” determination often involves a number of
    factors, including whether the invasion can be terminated or abated, and whether the cost
    of termination is wasteful or oppressive. Dobbs, The Law of Torts § 57 at 117–18. One of
    the better discussions of this analysis comes from Maine’s high court:
    In determining the distinction between “permanent” and
    “continuing” one commentator has considered the following
    three factors:
    (1) is the source of the invasion physically
    permanent, i.e., is it likely in the nature of
    things, to remain indefinitely? (2) is the source
    of the invasion the kind of thing an equity court
    would refuse to abate by injunction because of
    its value to the community or because of
    relations between the parties? (3) which party
    6
    seeks the permanent or prospective measure of
    damages?
    Dan B. Dobbs, Handbook on the Law of Remedies § 5.4, p.
    338 (1973). Professor Dobbs goes on to state that “a nuisance
    or trespass is usually not regarded as a permanent one unless
    it is physically permanent or likely to continue
    indefinitely.” Id. Likewise, many courts have considered the
    question of abatability to be the deciding factor in their
    determination of whether a nuisance or trespass is continuous
    or permanent.
    Jacques v. Pioneer Plastics, Inc., 
    676 A.2d 504
    , 507–08 (Me. 1996) (citing Beatty v.
    Washington Metro. Area Transit Auth., 
    860 F.2d 1117
    , 1122 (D.C. Cir. 1988) (continuing
    nuisance one which is abatable, or intermittent or periodical); Reynolds Metals Co. v.
    Wand, 
    308 F.2d 504
    , 508 (9th Cir. 1962) (aluminum plan’s emissions permanent
    nuisance because unlikely they would be abated or enjoined); City of Sioux Falls v.
    Miller, 
    492 N.W.2d 116
    , 119 (S.D. 1992) (periodic flooding from storm sewer system
    permanent nuisance because unlikely to be enjoined due in part to value to
    community); Racine v. Glendale Shooting Club, Inc., 
    755 S.W.2d 369
    , 374 (Mo. Ct. App.
    1988) (recognizing that distinguishing feature between permanent and temporary
    nuisance is its abatability)).
    In the summary judgment ruling in Bostock, this court held that plaintiffs “failed
    to come forward with evidence that their alleged injury is abatable, or that the cost of
    terminating the alleged nuisance or trespass is neither wasteful nor oppressive.” Bostock,
    No. S1337-03 CnC, slip copy at 17. Unlike Bostock, however, this case is still at the
    pleading stage. Plaintiff alleges that “a number of options exist[] to abate the damage to
    [her] property,” the damage is “not necessary,” and that “[a]lternatives exist to reduce
    flows, redirect stormwater[,] and abate pollution.” Am. Compl. ¶¶ 85, 101. On a motion to
    dismiss, the court must accept these allegations as true. They are sufficient to create a
    7
    question of fact regarding whether the invasion of water can be terminated or abated, and
    the reasonableness of the cost involved in such termination. Whether an invasion “can be
    abated” is not an exclusive factor, but it is “central” to the temporary versus permanent
    determination. Dobbs, The Law of Torts § 57. At this stage, the court cannot definitively
    resolve this question.
    At oral argument, VTrans argued that if an invasion is the result of lawful authority,
    socially beneficial, and intended to be permanent, that ends the inquiry, citing Hoery v.
    United States, 
    64 P.3d 214
    , 220 (Colo. 2003). However, further discussion in that case
    makes clear that the issue is not so simple. For example, Hoery cited cases in which courts
    have found continuing torts when the impacts were continuing despite the fact that the
    defendant’s actions took place years before, including cases involving government
    defendants. Id. at 221.
    Moreover, while the State focuses on the fact that the Route 7 road project is lawful,
    beneficial, and intended to be permanent, Nesti argues that the increased flow of
    stormwater is the act the court should focus on. In other words, can the court say at this
    stage of the proceedings that the stormwater discharged is itself “beneficial,” as opposed
    to the road? Given the lack of clarity in the law in this area, these are issues not
    appropriate for resolution at this stage of the case based solely on the pleadings. See
    Montague v. Hundred Acre Homestead, LLC, 
    2019 VT 16
    , ¶ 11 (“We are particularly wary
    of dismissing novel claims because ‘[t]he legal theory of a case should be explored in the
    light of facts as developed by the evidence, and, generally, not dismissed before trial
    because of the mere novelty of the allegations.’”) (quoting Ass’n of Haystack Prop.
    Owners, Inc. v. Sprague, 
    145 Vt. 443
    , 447 (1985)).
    8
    In sum, the takings claim is barred by the six-year statute of limitations, but the
    court cannot determine whether the trespass and nuisance claims are “continuing torts”
    for limitations purposes on the current record.
    II.     Sovereign Immunity
    The State asserts that, even if the trespass and nuisance claims are not time-barred,
    they are barred by the doctrine of sovereign immunity to the extent they seek money
    damages.6 “Sovereign immunity bars suits against the State unless immunity is expressly
    waived by statute.” Sabia v. State, 
    164 Vt. 293
    , 298 (1995) (citing LaShay v. Department
    of Social & Rehabilitation Servs., 
    160 Vt. 60
    , 67 (1993)). The State has waived its
    immunity to certain types of suits under the Vermont Tort Claims Act:
    The state of Vermont shall be liable for injury to
    persons or property . . . caused by the negligent or wrongful
    act or omission of an employee of the state while acting within
    the scope of employment, under the same circumstances, in
    the same manner and to the same extent as a private person
    would be liable to the claimant . . . .
    12 V.S.A. § 5601(a). The primary purpose of the tort claims act is “to waive sovereign
    immunity for recognized causes of action, particularly for common law torts.” Zullo v.
    State, 
    2019 VT 1
    , ¶ 18 (citing Kennery v. State, 
    2011 VT 121
    , ¶ 26, 
    191 Vt. 44
    ). There are,
    however, exceptions to the waiver. 12 V.S.A. § 5601(e). If an exception applies, then the
    State remains immune. “In order to bring a tort claim for damages against the State, the
    plaintiff must demonstrate that . . . no exception to the State’s waiver of sovereign
    6 At oral argument, the State conceded that sovereign immunity applies only to claims for money damages,
    but not to claims for equitable relief. See, e.g., Coleman v. Court of Appeals of Maryland, 
    566 U.S. 30
    , 35
    (2012) )“[a] foundational premise of the federal system is that States, as sovereigns, are immune from suits
    for damages, save as they elect to waive that defense.”) (emphasis added); Wool v. Menard, 
    2018 VT 23
    , ¶
    8 (“Sovereign immunity protects the State and its components from liability for money damages unless
    immunity is waived by statute.”) (emphasis added); Am. Trucking Associations, Inc. v. Conway, 
    152 Vt. 363
    ,
    376 (1989) (holding that immunity not applicable because “this is not a suit for money damages against the
    state”). Thus, the immunity question before the court relates only to money damages.
    9
    immunity applies.” Wool v. Menard, 
    2018 VT 23
    , ¶ 9 (citing Mellin v. Flood Brook Union
    Sch. Dist., 
    173 Vt. 202
    , 218–19 (2001)). Here, the State argues that two of these exceptions
    preserve its immunity.
    A. Discretionary Function Immunity
    The State first points to the discretionary function exception, which protects the
    State from any claim “based upon the exercise or performance or failure to exercise or
    perform a discretionary function or duty on the part of a State agency or an employee of
    the State, whether or not the discretion involved is abused.” 12 V.S.A. § 5601(e)(1). The
    purpose of that exception is “to assure that courts do not invade the province of coordinate
    branches of government through judicial second guessing of legislative or administrative
    policy judgments.” Lorman v. City of Rutland, 
    2018 VT 64
    , ¶ 13 (citing Estate of Gage v.
    State, 
    2005 VT 78
    , ¶ 4, 
    178 Vt. 212
    ).
    The Court established a two-part test for applying the discretionary function
    exception, asking whether “the acts involved [were] discretionary in nature, involving an
    element of judgment or choice” and if so, “whether that judgment involved considerations
    of public policy which the discretionary function exception was designed to protect.”
    Lorman v. City of Rutland, 
    2018 VT 64
    , ¶ 14 (citing Estate of Gage, 
    2005 VT 78
    , ¶ 5). When
    a government agent is authorized to exercise discretion, “it must be presumed that the
    agent’s acts are grounded in policy when exercising that discretion.” Searles v. Agency of
    Transp., 
    171 Vt. 562
    , 563 (2000) (mem.) (quoting United States v. Gaubert, 
    499 U.S. 315
    ,
    324 (1991)). “For a complaint to survive a motion to dismiss, it must allege facts which
    would support a finding that the challenged actions are not the kind of conduct that can
    be said to be grounded in . . . policy . . . .” 
    Id.
     (quoting Gaubert, 
    499 U.S. 315
    , 324–25).
    10
    The State contends that “the facts in the Amended Complaint are sufficient” to
    determine that the discretionary function exception applies. State’s Reply at 13. The court
    disagrees. To determine whether a decision is “grounded in policy,” the court needs to
    know what decision we are talking about, and who made it. See, e.g., Johnson v. Agency
    of Transp., 
    2006 VT 37
    , ¶ 13, 
    180 Vt. 493
     (mem.) (quoting Gaubert, 499 U.S. at 335–36)
    (Scalia, J., concurring) (“The dock foreman’s decision to store bags of fertilizer in a highly
    compact fashion is not protected by this exception because, even if he carefully calculated
    considerations of cost to the Government vs. safety, it was not his responsibility to ponder
    such things; the Secretary of Agriculture’s decision to the same effect is protected,
    because weighing those considerations is his task.”) (emphasis in original). It may also be
    significant whether the decision was guided by mandatory policies or not. Id. ¶ 6. At this
    stage of the case, the court has insufficient information with which to resolve this
    question.
    B. Highway Planning and Design Exception
    The second exception to which the State points is that for “[a]ny claim arising from
    the selection of or purposeful deviation from a particular set of standards for the planning
    and design of highways.” 12 V.S.A. § 5601(e)(8). This language “means that the State is
    immune from claims arising from the State’s choice of highway design standards or its
    conscious decision to depart from the requirements of chosen standards,” but it does not
    provide the State with “comprehensive immunity for highway design . . . .” McMurphy v.
    State, 
    171 Vt. 9
    , 12 (2000). As the Court elaborated:
    Whereas subsection (e)(8) shelters the State from liability for
    all of its deliberate design decisions, allowing it to design
    highways in the manner that it sees fit, the statute preserves
    liability in circumstances where the State has unintentionally
    failed to comply with the chosen design standards. Thus, if a
    11
    plaintiff can prove that the State intended to comply with
    certain standards, but failed to do so, the State would be
    liable for any injury caused if the plaintiff can also prove that
    the noncompliance was negligence.
    Id.; see also Vanderbloom v. State, Agency of Transp., 
    2015 VT 103
    , ¶ 6, 
    200 Vt. 150
    (emphasis added).
    Plaintiff’s claims clearly allege a deliberate highway design decision by VTrans to
    “alter[] the flow of water so as to collect and funnel a large amount onto Plaintiff’s
    property.” Compl. ¶ 94; see also id. ¶¶ 95, 105. However, while some of the language in
    McMurphy is perhaps unintentionally broad, see McMurphy, 
    171 Vt. at 12
     (“all . . .
    deliberate design decisions”), the statutory exception to the State’s waiver of immunity
    applies only to claims “arising from the selection of or purposeful deviation from a
    particular set of standards for the planning and design of highways.” 12 V.S.A.
    § 5601(e)(8) (emphasis added). The amended complaint references no particular set of
    planning and design standards. Instead, the claims deal with a highway design decision
    to divert stormwater onto Plaintiff’s property. The planning and design exception does
    not provide the State with “comprehensive immunity for highway design . . . .” McMurphy,
    171 Vt. at 12.
    The court is unable to conclude at this stage whether the discretionary function or
    highway planning and design exception applies. Accordingly, sovereign immunity is not
    grounds for dismissal of Plaintiff’s claims for monetary damages.7
    7 Plaintiff also argues that regardless of whether one of the exceptions might otherwise apply, there
    can be no immunity for the trespass and nuisance claims alleged here because they are intentional torts.
    However, the cases on which she relies involved municipal sovereign immunity, rather than state sovereign
    immunity. State and municipal immunity are distinct. See McMurphy v. State, 
    171 Vt. 9
    , 19 (2000) (“The
    Vermont Legislature treats state and local governments differently with respect to immunity.”) (citing
    Hillerby v. Town of Colchester, 
    167 Vt. 270
    , 273–74 (1997)). While municipal immunity is generally
    determined by looking to the common law governmental/proprietary distinction, the State’s immunity
    under the Tort Claims Act is determined by the private-analog test and the various statutory exceptions in
    the Act. Id.; see also 12 V.S.A. § 5601. The Tort Claims Act waives the State’s immunity from liability “for
    12
    III.    New Claims in Amended Complaint: Ejectment and Lateral Support
    In response to the State’s motion to dismiss, Plaintiff filed an amended complaint
    with two new claims: Count IV, for ejectment, and Count V, alleging the withdrawal of
    lateral support. Count IV, titled “Ejectment,” is framed as an action for the recovery of
    lands under 12 V.S.A. § 501. Plaintiff alleges that the “incursion from . . . stormwater is
    not temporary or intermittent,” but that “it is continuous, open, [] notorious[,] and
    without permission” and “has not occurred for 15 years.” Am. Compl. ¶¶ 119–21. Plaintiff
    asks for an “order of ejectment directing VTrans’ stormwater elsewhere” and a
    “declaratory ruling that the State has not obtained an easement by prescription . . . .” Id.
    ¶ 123.
    The State asserts that Count IV is an attempt to salvage the potentially time-barred
    trespass claim by reframing it as a claim for ejectment, and that the claim fails because
    the State does not have “possession” of Plaintiff’s land. State’s Reply at 13–14. The Court
    injury to persons or property . . . caused by the negligent or wrongful act or omission of an employee of the
    State while acting within the scope of employment . . . .” 12 V.S.A. § 5601(a) (emphasis added). As the State
    correctly asserts, the statute provides no distinction between claims based on negligence and claims based
    on intentional acts. While the result might be different for a municipal defendant, the defendants here are
    state entities, and Plaintiff offers no persuasive basis for applying the reasoning of Lorman and Tarbell to
    the doctrine of state sovereign immunity.
    Plaintiff also contends that immunity does not apply to any case involving damage to land by the
    State’s invasion. Pl.’s Opp’n at 20–21. Plaintiff cites Makela v. State, which states the unremarkable
    proposition that “[t]he doctrine of immunity from liability does not apply where the injury complained of
    is the taking of private property for public use without compensation.” 
    124 Vt. 407
    , 409 (1964). However,
    the State does not contend that immunity bars the takings claim. The Makela court continued: “This rule is
    also recognized in cases having to do with damage to property but not with the taking thereof.” 
    Id.
     (citing
    Haynes v. Town of Burlington, 
    38 Vt. 350
    , 360 (1865); Sanborn v. Vill. of Enosburg Falls, 
    87 Vt. 479
    , 484
    (1914)). Plaintiff infers from this that the immunity doctrine is also inapplicable to the trespass and
    nuisance claims, because they allege damage to her land.
    While the latter sentence quoted from Makela is confusing when taken out of context, it does not
    support Plaintiff’s argument. It seems to refer to indirect takings, such as where the government does not
    take a property in its entirety, but the property nonetheless suffers damages or a loss in value from the
    government’s actions. See Sanborn, 
    87 Vt. at 484
     (“The subjection of land to an easement of the character
    of a highway is a taking as much as though the absolute title passed.”). In any event, neither Makela,
    Sanborn, nor Haynes suggest that the immunity doctrine does not apply to the tort claims of trespass and
    nuisance.
    13
    agrees. “To recover in ejectment, the plaintiff must prove the defendant in possession of
    the premises at the commencement of the action.” Lynch v. Town of Rutland, 
    66 Vt. 570
    ,
    573 (1894). “[E]jectment does not lie” for uses which “do[] not carry the right of exclusive
    possession . . . .” Scampini v. Rizzi, 
    106 Vt. 281
    , 287 (1934). Plaintiff does not allege any
    possessory interest or claim of title by the State. Any relief to which Plaintiff might be
    entitled from the State’s redirection of stormwater through her land must come through
    the nuisance or trespass claims.
    In Count V, Plaintiff alleges that VTrans’ stormwater “is taking away the naturally
    necessary lateral support of [her] land,” which is “causing harm to [her] land and things
    placed on said land.” 
    Id.
     ¶¶ 131–32. She seeks “compensation” and “an order requiring
    VTrans to restore and stabilize Plaintiff’s land . . . .” Id. ¶ 132.
    Plaintiff’s lateral support claim also fails as a matter of law. Under the lateral
    support doctrine, “[t]he owner of any land is entitled to have that land supported and
    protected in its natural condition by the adjoining land,” and “[a] landowner who
    withdraws such support will be held liable for damages.” Domina v. Moore, No. 99-163,
    slip op. at 3 (Vt. May 10, 2000) (unpub. mem.) (citing 9 R. Powell & P. Rohan, Powell on
    Real Property § 698 (1999)). This court has looked to the Restatement in considering
    lateral support claims. See Bostock, No. S1337-03 CnC, slip copy at 18–22 (citing
    Restatement (Second) of Torts §§ 817, 819 (1979)).
    “One who withdraws the naturally necessary lateral support of land in another’s
    possession or support that has been substituted for the naturally necessary support, is
    subject to liability for a subsidence of the land of the other that was naturally dependent
    upon the support withdrawn.” Restatement (Second) of Torts § 817(1). However, as the
    14
    State correctly points out, the Restatement makes clear that the facts of the amended
    complaint do not fall within the lateral support doctrine:
    This Chapter states the liabilities of a person who withdraws
    the support furnished by one tract of land to a tract of land in
    possession of another person insofar as these liabilities arise
    from an invasion of the interests of the other in the support of
    his land . . . . It does not state the liability of a person who, as
    a trespasser upon a tract of land, removes the support of
    some part of the land. (The liability for trespass on land is
    stated in §§ 157- 166.) The damages for that harm are
    recoverable as part of the damages for the trespassing act.
    Interests of a possessor of land other than his interest in the
    support of his land may be invaded by the acts involved in
    withdrawing support, but the liabilities for these invasions are
    not within the scope of this Chapter.
    Restatement (Second) of Torts, Ten 39 Scope Note (emphasis added). Plaintiff alleges
    that the State’s trespassory flow of water onto her land has caused subsistence by creating
    a large ravine across her land. This is essentially another attempt to reframe her trespass
    claim. The allegations of the amended complaint do not give rise to a claim for the
    withdrawal of lateral support.
    Order
    The motion to dismiss is granted as to the takings claim (Count III), ejectment
    claim (Count IV), and lateral support claim (Count V), but denied as to the nuisance and
    trespass claims (Counts I and II). The State shall file its answer within 14 days and the
    parties shall file a discovery schedule within 30 days. The court urges the parties to engage
    in an early mediation.
    Dated at Burlington this 13th day of August, 2019.
    ___________________
    Helen M. Toor
    Superior Court Judge
    15
    

Document Info

Docket Number: 1096-12-18 Cncv

Filed Date: 8/20/2019

Precedential Status: Precedential

Modified Date: 7/31/2024