Inland Empire Dry Wall Supply Co. v. W. Sur. Co. ( 2018 )


Menu:
  •                                                  This opinion was filed for record
    rruE
    IN CLERKt OFFICE
    8UPRBE COURT,STKIE OF VIMSHNQTOli
    at.        (Xk on i/.UV /y 7£}1^ J
    DATE   JAN 1 8
    GHIEFJUSTKE                                    SUSAN L. CARLSON
    SUPREME COURT CLERK
    IN THE SUPREME COURT OF THE STATE OF WASHINGTON
    INLAND EMPIRE DRY WALL
    SUPPLY CO., a Washington corporation,                No. 94118-1
    Respondent,
    V.                                         En Banc
    WESTERN SURETY COMPANY
    (Bond No. 58717161),
    Petitioner.
    Filed    JAN 1 8 ?niS
    JOHNSON,J.—This case involves the issue of whether the purchaser of a
    lien release bond is an indispensable party in an action under chapter 60.04 ROW
    by a lien claimant against the surety of the release bond. The Court of Appeals, in a
    divided opinion, reversed the trial court's grant of summary judgment in favor of
    the surety and held that a claim against a lien release bond could be pursued solely
    against the surety. We affirm.
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    Facts and Procedural History
    Inland Empire Dry Wall Supply Company is a supplier of drywall materials.
    Inland Empire entered into an agreement to supply drywall materials to Eastern
    Washington Drywall & Paint(EWD&P).EWD&P contracted with Fowler General
    Construction to work on an apartment complex project in Richland, Washington.
    Inland Empire claims to have supplied $124,653.05 worth of drywall for the
    apartment complex project work that EWD&P was performing.
    Inland Empire claims EWD&P never paid it for the materials supplied. To
    pursue payment, Inland Empire filed a preclaim notice and timely recorded a
    mechanics' lien against the construction project under RCW 60.04.091. To release
    the project property from the lien. Fowler obtained a lien release bond in the
    amount of$186,979.57 from Western Surety Company. The lien release bond
    identifies Fowler as the "Principal," Western as the "Surety," and Inland Empire as
    the "Obligee." Clerk's Papers(CP)at 23. After Fowler recorded the lien release
    bond. Inland Empire filed an action asking for "judgment in the principle sum of
    $124,653.05" plus interest, costs, and attorney fees, and for "an order foreclosing
    [its] claim against Defendant Western Surety's Bond . . . and an Order directing the
    penal sum be paid to [it]." CP at 5, 6. The complaint named Western Surety—but
    not Fowler, the principal on the bond—as a party to the action. In its answer.
    Western raised several affirmative defenses, including the affirmative defense that
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    Inland Empire failed to name and include Fowler as a necessary and indispensable
    party, and that Inland Empire had not satisfied the statute of limitations under
    chapter 60.04 RCW.Inland Empire and Western then filed cross motions for
    summary judgment.
    The trial court granted summary judgment in favor of Western. It ruled that
    under RCW 60.04.141, Inland Empire was required to sue and serve both Western
    as surety and Fowler as principal in the action to foreclose on a lien release bond. It
    reasoned that because the bond, rather than the apartment complex property, was
    now the property subject to the claim of lien. Fowler, as purchaser of the bond,
    together with Western became owners ofthe subject "property." The trial court
    therefore dismissed the lawsuit because Inland Empire failed to name and to serve
    Fowler as a party within the 90 days required under RCW 60.04.141.
    Division Three ofthe Court of Appeals in a divided opinion reversed, the
    majority holding that RCW 60.04.161 controlled under these circumstances and
    that Inland Empire was only required to name Western, the bond surety, as the
    defendant to its bond foreclosure action. Inland Empire Dry Wall Supply Co. v. W.
    Sur. Co., 
    197 Wash. App. 510
    , 519, 
    389 P.3d 717
    , review granted, 
    188 Wash. 2d 1002
    ,
    
    393 P.3d 785
    (2017). Chief Judge Fearing dissented.
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    Analysis
    This case raises the issue of whether under chapter 60.04 RCW the
    purchaser of a lien release bond is an indispensable party who must be named and
    joined in an action on the lien release bond; this is an issue of statutory
    interpretation. Construction of a statute is a question oflaw that this court reviews
    de novo. State v. Wentz, 
    149 Wash. 2d 342
    , 346,68 P.3d 282(2003). Where a
    "statute's meaning is plain on its face, then the court must give effect to that plain
    meaning as an expression of legislative intent." Dep't ofEcology v. Campbell &
    Gwinn, LLC, 
    146 Wash. 2d 1
    , 9-10, 43 P.3d 4(2002). Such meaning "is discerned
    from all that the Legislature has said in the statute and related statutes which
    disclose legislative intent about the provision in question," and if the statute
    remains susceptible to more than one reasonable meaning, this court resorts to aids
    of construction, including legislative history. Campbell & 
    Gwinn, 146 Wash. 2d at 11
    , 12.
    Chapter 60.04 RCW creates a cause of action for suppliers of labor,
    materials, or equipment to a construction project. The statute is often referred to as
    the "construction lien" statute. Before chapter 60.04 RCW was enacted, material
    and equipment providers and laborers were limited in pursuing unpaid claims
    under contract principles and generally could bring suit against only the purchaser
    of the materials or person (or entity) contracting for labor. In the absence ofsome
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    equitable or contractual theory, no claim existed against the property, property
    owner, or others. Construction lien statutes such as chapter 60.04 RCW were
    enacted to create a cause of action and remedy under certain circumstances in the
    construction industry. The enactment of chapter 60.04 RCW created a limited
    cause of action, allowing a claim to be filed against the property and property
    owner, so long as strict statutory time requirements were followed. As we have
    previously noted, the statute is construed liberally to protect persons who fall
    within its provisions. See Williams v. Athletic Field, Inc., Ill Wn.2d 683, 696-97,
    
    261 P.3d 109
    (2011).
    RCW 60.04.021 allows "any person furnishing labor, professional services,
    materials, or equipment for the improvement of real property" to place a lien on the
    construction project property as a method of securing payment for services
    rendered. A lien claimant, here Inland Empire, is required to give the property
    owner and the prime contractor written notice ofthe lien claim and to record the
    notice in the county where the subject property is located. RCW 60.04.031,.091.
    The statutory scheme includes strict time limits in which to act.
    RCW 60.04.141 describes procedures a lien claimant must follow once the
    lien has been recorded. It provides, in relevant part:
    No lien created by this chapter binds the property subject to the lien
    for a longer period than eight calendar months after the claim cif lien
    has been recorded unless an action is filed by the lien claimant within
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    that time in the superior court in the county where the subject property
    is located to enforce the lien, and service is made upon the owner of
    the subject property within ninety days of the date of filing the action .
    . . and in case the action is not prosecuted to judgment within two
    years after the commencement thereof, the court, in its discretion, may
    dismiss the action for want of prosecution, and the dismissal of the
    action or a judgment rendered thereon that no lien exists shall
    constitute a cancellation of the lien.
    RCW 60.40.141. The statutory language makes it clear that RCW 60.04.141
    requires "the owner ofthe subject property" to be named in actions where no
    release bond has been filed. This makes legal and practical sense: while the
    foreclosure suit seeks to enforce payment, if payment is not made,the property
    owner's interest in the property may be foreclosed, i.e., forfeited. Based on this
    potential remedy, the statute—^RCW 60.04.141—requires joinder of the property
    owner. Failure to comply with these statutory provisions results in the loss by the
    lien claimant of the right to the lien. See Bob Pearson Constr., Inc. v. First Cmty.
    Bank, 
    111 Wash. App. 174
    , 179, 
    43 P.3d 1261
    (2002). The type of action created
    under RCW 60.04.141 is a quasi in rem type of action where the object, or res, is
    the real property.
    RCW 60.04.161 authorizes a property owner or contractor, subcontractor,
    lender, or lien claimant who disputes the correctness or validity of the claim of lien
    to post a lien release bond. The real property then is released from the claim and
    becomes unreachable, and the bond purchaser instead posts the bond as security.
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    The purpose of the lien release bond is twofold. First, the bond protects the
    property owner by removing the lien from the real property, thus providing the
    owner with clear marketable title. Second, the bond "protects the lien claimant by
    taking the place of the property and serving as a form of substitute security should
    the lien claimant ultimately prevail." The Law OF Miscellaneous and
    Commercial Surety Bonds 155(Todd C. Kazlow & Bruce C. King eds., 2001);
    see also CalPortland Co. v. LevelOne Concrete, LLC, 
    180 Wash. App. 379
    , 387, 
    321 P.3d 1261
    (2014). Fowler, the general contractor on the project here, obtained a
    lien release bond to free up the construction project property. As the Court of
    Appeals correctly recognized,"Once a lien release bond is recorded, the procedural
    statute shifts from RCW 60.04.141 to RCW 60.04.161." Inland Empire, 197 Wn.
    App. at 516. Unlike RCW 60.04.141, the language ofRCW 60.04.161 refers to the
    liability of the surety and does not mention either the bond purchaser or property
    owner in that context. RCW 60.04.161, of course, necessarily refers to the owner
    of the property as one of several entities that may dispute a lien and record a bond.
    But aside from that reference, it simply states that "[t]he condition ofthe bond
    shall be to guarantee payment of any judgment upon the lien in favor ofthe lien
    claimant entered in any action to recover the amount claimed in a claim of lien, or
    on the claim asserted in the claim of lien." RCW 60.04.161 (emphasis added). It
    further provides:
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    The effect ofrecording a bond shall be to release the real property
    described in the notice of claim of lien from the lien and any action
    brought to recover the amount claimed. Unless otherwise prohibited
    by law, if no action is commenced to recover on a lien within the time
    specified in RCW 60.04.141, the surety shall be discharged from
    liability under the bond. If an action is timely commenced,then on
    payment of any judgment entered in the action or on payment ofthe
    full amount of the bond to the holder ofthe judgment, whichever is
    less, the surety shall be discharged from liability under the bond.
    RCW 60.04.161 (emphasis added). The real property owner and the real property
    subject to the claim of lien are no longer subject to the claim. The bond becomes
    the only available source for the lien claimant to turn to in seeking to collect the
    amount owed, and the bond purchaser under RCW 60.04.161 therefore need not be
    treated the same way as the property owner under RCW 60.04.141. Nothing in the
    statute suggests that the bond purchaser gets the bond back if the claim fails for
    any reason. The Court of Appeals majority correctly recognized that
    [tjhis substitution of the "surety" in RCW 60.04.161 for the "owner of
    the subject property," as used in RCW 60.04.141, indicates the
    legislature's plain intent that when a lien release bond is filed, the
    surety shall be substituted for the property owner as the entity that
    must be sued to recover on a lien.
    Inland 
    Empire, 197 Wash. App. at 516-17
    .
    Western argues that suing only the surety on a release bond does not satisfy
    RCW 60.04.161 and RCW 60.04.Mi's procedural requirements "because a
    surety's liability is fully conditional and not triggered and absolute until the lien
    claimant successfully litigates with the principal to establish the disputed lien's
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    correctness and validity." Pet. for Review at 10. The statutory language Western
    relies on does not expressly state against whom the action to foreclose on the lien
    must be brought.
    The main premise of Western's argument is that until the validity of the lien
    claim has been adjudicated as between the principal and the lien claimant, no
    obligation exists on its part to pay. It is true that the lien claimant must prove the
    validity and the right to recover the claimed amount, whether its claim is against
    the property and its owner or the bond. But that does not answer the question of
    who must be named as a party. That issue is resolved by looking at the statutory
    provisions. To that end, nothing in the language of RCW 60.04.161 stating that
    "any judgment upon the lien in favor ofthe lien claimant entered in any action to
    recover the amount claimed ... or on the claim asserted in the claim of lien"
    requires that the lien claimant must first proceed against the principal.(Emphasis
    added.)
    Western argues that the provisions ofthe lien release authorization of RCW
    60.04.161 must be read in conjunction with the general provisions of RCW
    60.04.141, which set forth the procedures for bringing an action to foreclose the
    original lien as against the real property. It maintains that the procedural
    requirements of RCW 60.04.141, and specifically the language that service is to be
    made on the "owner of the subject property," should be and have been interpreted
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    to require that both the principal and the surety be joined in the action to foreclose
    on the bond. But reading these provisions together does not support the result that
    Western wants. Western reads more into the statutory language than what is
    actually there.
    While RCW 60.04.161 expressly states that the action to recover the amount
    claimed has to be commenced within the time specified in RCW 60.04.141, it does
    not transpose any other requirements contained in RCW 60.04.141 on the lien
    claimant seeking to commence an action on the bond. Instead, it states that unless
    an action to recover on a lien is timely commenced,the surety must be discharged
    from liability under the bond. It further states that if the action is timely
    commenced,then on payment of any judgment entered in that action or on
    payment of the full amount ofthe bond to the judgment holder, the surety's
    liability will be discharged. RCW 60.04.161.
    As the Court of Appeals here noted,"Unlike RCW 60.04.141, RCW
    60.04.161 makes no mention ofthe 'owner of the subject property' as an entity
    necessarily impacted by a suit." Inland 
    Empire, 197 Wash. App. at 516
    . The only
    reference in RCW 60.04.161 to the owner of the property subject to a lien is in the
    context of identifying the owner as one of several entities permitted to dispute a
    lien and record a bond. RCW 60.04.161 does, however, explicitly refer to the
    surety and the conditions that would discharge its obligations, which evinces a
    10
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    legislative choice to treat the surety's rights and obligations distinct from those of
    the other parties.
    To complete the statutory picture, RCW 60.04.171 provides that "[i]n any
    action brought to foreclose a lien, the owner shall be joined as a party." Western,
    as well as Judge Fearing in his dissent, relied on this language to construe the
    statutory framework and the legislative intent to require that the lien claimant in an
    action to recover on the bond is required to join the principal as the "owner" ofthe
    bond. Tellingly, RCW 60.04.171 also states that "[t]he court shall have the power
    to order the sale ofthe property," which renders any reliance on this provision to
    equate Fowler to the owner ofthe subject property unconvincing.
    The concept of an "owner" in a two party, owner-versus-lien-claimant
    relationship is not easily transposed to a situation where general suretyship law
    principles provide that a bond lien claimant, here Inland Empire,"has two sets of
    rights, one set against the principal," here Western,"and the other against the
    secondary obligor," here Fowler. RESTATEMENT(THIRD)OF SURETYSHIP AND
    Guaranty § 50 cmt.(Am.Law Inst. 1996). Further,"[a] suretyship relationship
    is a three-party relationship between surety, principal, and obligee [, and] the
    surety undertakes to answer for the debt or default of the principal," RICHARD E.
    Tasker et al..Practical Guide to Construction Contract Surety Claims 9
    (1997). The legislature does not impose the constraints of a rather straightforward,
    11
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    two party relationship between a real estate owner and lien claimant on parties
    •»
    whose relationship originates from and is generally undertaken under the law of
    suretyship.
    A similar situation was analyzed in CalPortland, 180 Wn. App.379. In that
    case, the Court of Appeals determined that a real property owner is not a necessary
    party to a suit against a lien release bond. In CalPortland, a general contractor
    recorded a lien release bond after a building materials provider recorded a claim of
    lien against the construction property but before the provider filed suit. When the
    provider, as a lien claimant, thereafter sued on the lien, it named the general
    contractor and the surety among various defendants but did not name the real
    property owner as parties. The Court of Appeals held that the trial court erred in
    granting summary judgment in favor of the general contractor and stated that
    including the bond principal and surety is "sufficient" in an action on a release
    bond. But the Court of Appeals in CalPortland did not hold that the bond
    purchaser was a necessary party that had to be joined.
    Western contends its position is supported by Division One's decision in
    DBM Consulting Engineers, Inc. v. United States Fidelity & Guaranty Co., 
    142 Wash. App. 35
    , 170 P.3d 592(2007). There, the lien claimant, DBM,recorded a
    mechanics' lien against a client's property to secure a debt owed. Subsequently,
    the client recorded a lien release bond. In the action alleging breach of contract,
    12
    Inland Empire Dry Wall Supply Co. v. Western Surety Co.,'S\o. 94118-1
    unjust enrichment, and foreclosure of the mechanics' lien, DBM failed to ask for
    judgment on the lien foreclosure claim and no judgment was entered as to that
    claim. When DBM demanded that the surety pay the entire bond amount as partial
    satisfaction ofthe judgment,the surety refused, citing DBM's failure to foreclose
    on the lien. Division One noted that ROW 60.04.161 was not a model of clarity. It
    interpreted ROW 60.04.161 to require judgment against the bond. The DBM court
    concluded that because DBM did not obtain a judgment foreclosing its lien, the
    surety was not obligated to pay on the lien bond.
    DBM does not establish a requirement that a lien claimant seeking to
    foreclose on the lien cannot proceed against the surety, here Western, to do so. The
    facts and procedure differ. In DBM,the lien claimant initially filed suit against the
    property owner before the property owner filed a lien release bond. DBM could
    have, and likely should have, amended its pleadings and sought to foreclose on the
    lien secured by the bond. It did not do so. Unlike in CalPortland and here, no
    claim was asserted against the bond or the surety at the time the lawsuit was
    commenced.DBM dots, not impact the statutory analysis here.
    Western also cites to Olson Engineering, Inc. v. KeyBank National Ass'n,
    
    171 Wash. App. 57
    , 286 P.3d 390(2012), for the proposition that "Washington's
    construction lien foreclosure statutes control suits on lien release bonds because the
    bond claimant must still prove the validity and correctness of its lien." Suppl. Br.
    13
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    of Pet'r at 12. The primary issue before the court in           was whether RCW
    60.04.161 prevents a trial court from adjudicating the parties' lien priorities when
    one party files a release-of-lien bond. 
    Olson, 171 Wash. App. at 63
    . In reaching the
    conclusion that RCW 60.04.161 does allow a trial court to adjudicate the parties'
    lien priorities after the filing of such a bond, the Court of Appeals concluded that
    "[t]he plain language of the statute ... implies that to be entitled to the proceeds of
    the lien release bond, the lien claimant must obtain a favorable judgment on the
    lien." 
    Olson, 171 Wash. App. at 66
    . Relying on this interpretation, the court also
    went on to review the trial court's grant of summary judgment as to the validity of
    the lien at issue. This reading of the statutory language by the court in Olson is
    consistent with our conclusion here that the statutory language allows this
    determination of validity to be made in an action brought against the surety without
    naming and joining the principal in the action.
    Here, Inland Empire filed its lawsuit in the trial court after Fowler, the
    general contractor, had already posted the release bond, and in its complaint sought
    "judgment in the principle sum of $124,653.05" as well as "an order foreclosing
    Plaintiffs claim against Defendant Western Surety's Bond No. 58717161 and an
    Order directing the penal sum be paid to Plaintiff to satisfy the principal, interest
    and costs incurred in prosecuting this claim." CP at 5, 6. Inland Empire and
    Western appear to agree that Inland Empire cannot obtain a judgment on the lien
    14
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    and foreclose against the bond without first litigating the validity of the lien and
    correctness of the amount due and owed. The disagreement lies, rather, in that
    Western believes that determination requires Inland Empire to name and join
    Fowler, the general contractor who purchased the lien release bond from Western,
    as a necessary party. Inland Empire, on the other hand, argues that litigating the
    validity and correctness ofthe lien, although prerequisite to obtaining a judgment
    and foreclosing against the bond, can occur in the same action brought by the lien
    claimant obligee against the surety.
    Western appears to conflate two unrelated statutory requirements by arguing
    that because the validity of the lien must be determined first, the lien claimant
    obligee has to do so in an action against the principal before it can bind the surety
    and trigger its obligations, yet the remedy that it seeks before this court is
    compulsory joinder of the principal in what is essentially the same action. The
    analysis of the statutory language and the case law 
    discussed supra
    does not
    support Western's proposition.
    First, as previously stated, nothing in the statute or the case law discussed
    above suggests that the surety is precluded from challenging and litigating the
    validity or amount of the lien. RCW 60.04.161 functions to allow a substitution of
    the bond for the real estate, replacing the res to which the lien attaches. But aside
    from the requirements ofthe timing ofthe action ofRCW 60.04.141, it does not
    15
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    impose any requirements on the lien claimant such that it would have to litigate
    against both the principal and the surety. Nothing in the statute or our case law
    prevents the surety from asserting the same claims or defenses as the principal on
    the bond, and nothing prevents the surety from impleading the principal or from
    seeking its assistance.^ Counsel for the petitioner appears to have recognized as
    much at oral argument, agreeing that substantively, nobody's rights or obligations
    differ depending on who is named. Wash. Supreme Court oral argument.Inland
    Empire Dry Wall Supply Co. v. W. Sur. Co., No. 94118-1 (Sept. 28, 2017), at 8
    min., 11 sec., audio recording by TVW,Washington State's Public Affairs
    Network, http://www.tvw.org.
    Importantly, RCW 60.04.161 authorizes not only property owners but also
    contractors, subcontractors, lenders, or other lien claimants to obtain and record a
    lien release bond. Inland Empire points out that lien claimants, such as itself, may
    have no contractual or other basis for obtaining a judgment against these potential
    principals. In this instance. Inland Empire recorded a lien against the real property
    project in question on the basis ofEWD&P's alleged nonpayment, not Fowler's.
    The statutory lien claim against the property(and now the bond)is the only claim
    that can be successfully pursued, and in cases of unavailability or insolvency ofthe
    ^ Sureties, as well as bond purchasers, can likewise seek indemnification.
    16
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    original debtor, chapter 60.04 RCW operates to establish the only feasible legal
    basis for recovery for lien claimants like Inland Empire. While including Fowler as
    the principal on the bond it obtained to free up the apartment complex project
    would have been feasible,joinder is not a statutory prerequisite.
    Western cites to case law from Virginia in support ofthe proposition that a
    surety should be considered a necessary and indispensable party in Washington,
    focusing on Synchronized Construction Services, Inc. v. Prav Lodging, LLC,288
    Va. 356, 
    764 S.E.2d 61
    (2014), and Johnson Controls, Inc. v. Norair Engineering
    Corp., 86 Va. Cir. 138 (2013). While those cases do suggest that in Virginia, both
    the principal and the surety are necessary parties in a lien foreclosure action, they
    rely on and stem from the statutory language of the Virginia mechanics' lien
    statute. Va. Code Ann. § 43-71 explicitly states that "[t]he sureties on any [lien
    release] bond, which may be involved in any suit or action brought under the
    provisions ofthis section, shall be made parties to such suit or action." The
    Virginia statutory provision differs from RCW 60.04.161 and is not helpful here.^
    ^ It is noteworthy that in Oregon, where the lien release statute directs lien claimants to
    proceed against the principal on the bond, sureties have also argued a surety is an indispensable
    party in an action to foreclose the underlying lien. See, e.g., Valencich v. TMT Homes ofOr.,
    Inc., 
    193 Or. App. 47
    , 88 P.3d 300(2004)(rejecting a surety's argument that had it been made a
    party, it would have been able to contest the validity ofthe underlying liens).
    17
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    Western also cites to statutory provisions out of Arizona(Ariz. Rev. Stat. §
    33-1004(C),(D)), New York(N.Y. Lien Law § 37(7)), Oklahoma(Okla. Stat.
    tit. 42, § 147.1) and Nevada(Nev.Rev. Stat. § 108.242l(2)(b)) for the
    proposition that "general suretyship law principles can be superseded and rendered
    inapplicable by contrary statutory requirements or other authority." Suppl. Br. of
    Pet'r at 14. Western is correct that lien statutes are viewed by most courts to be in
    derogation of common law. See, e.g., THE Law OF MISCELLANEOUS AND
    Commercial Surety Bonds,supra, at 158. In applying this principle, we analyze
    our statute in accordance with the general guiding principles of statutory
    construction. We cannot ignore or add to the language of RCW 60.04.161. The
    statute defines a "payment bond"^ to mean "a surety bond issued by a surety
    licensed to issue surety bonds in the state of Washington that confers upon
    potential claimants the rights of third party beneficiaries," RCW 60.04.011(10),
    and further provides that the terms be liberally construed. RCW 60.04.900."^
    Although the type of bond at issue is a lien release bond, the rule of liberal
    ^ A "payment bond" is an agreement in which the surety assures the obligee that the
    suppliers of labor, material, and rental equipment to the project will be paid by the principal.
    Tasker,supra, at 44.
    4 RCW 60.04.900 provides that"RCW 19.27.095, 60.04.230, and 60.04.011 through
    60.04.226 and 60.04.261 are to be liberally construed to provide security for all parties intended
    to be protected by their provisions."
    18
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    construction applies^ and is a directive to construe the language of RCW
    60.04.011(10) and RCW 60.04.161 in favor ofthe claimant in the event any
    question of statutory meaning existed.
    In following this directive, the Court of Appeals has relied on a California
    Supreme Court decision in Hutnick v. United States Fidelity & Guaranty Co., 
    47 Cal. 3d 456
    , 
    763 P.2d 1326
    (1988). In Hutnick, the California State Supreme Court
    concluded that "[i]f only the surety is joined, the resulting judgment will be
    binding on the principal, provided only that the surety has given notice to the
    principal 'and an opportunity at the surety's request to join in the 
    defense.'" 47 Cal. 3d at 469
    (quoting Cal. Civ.Proc. § 1912). The court noted that "[a]
    principal notified of the action by the surety will have the same motivation to
    defend the action as if formally named as a party, because the judgment will be
    equally conclusive as a determination of the principal's liability" and that "the
    surety has the means to call upon the principal to defend the lien foreclosure
    action." 
    Hutnick, 47 Cal. 3d at 469
    .
    This reasoning is persuasive both from a practical standpoint and from the
    standpoint of general suretyship principles that confer third party beneficiary rights
    on lien claimants in Washington. As previously noted, nothing in the language of
    See 
    Williams, 172 Wash. 2d at 696-97
    .
    19
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    RCW 60.04.161 or our case law interpreting it prevents the surety from impleading
    the principal or from seeking its assistance or bringing a third party claim.
    Western next argues that the general principles of suretyship law should be
    inapplicable here because attempting to foreclose on a lien release bond against
    only the surety is illogical or impractical. Western insists that we should look only
    to the statute in resolving the dispute. While Western's observation that statutory
    language should control is correct, nothing in our interpretation ofthe statute runs
    afoul ofthe statute's language or renders the foreclosure process illogical or
    impractical.
    RCW 60.04.161 operates similarly to a situation where, for example,
    someone guarantees a debt. In such a situation a lawsuit can properly be pursued
    against the guarantor; the debtor need not be made a party. Surety bonds are
    underwritten based on the principal's creditworthiness and ability to perform, and
    the principal may be obligated to repay the surety for any losses incurred. 
    Tasker, supra, at 9
    . The "contract of suretyship is one to answer for the debt, default, or
    miscarriage of another." Meyer v. Bldg. & Realty Serv. Co., 
    209 Ind. 125
    , 
    196 N.E. 250
    , 254(1935). "[D]espite a surety's contract being collateral to a valid principal
    obligation contracted by another, a contract of a surety involves a direct promise to
    perform the obligations of another person. In other words, the surety is primarily
    20
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    and jointly bound with the principal." 74 Am.Jur. 2d Suretyship § 1 (2017 Supp.)
    (footnote omitted).
    While not interpreting chapter 60.04 RCW,we have held that an obligee
    named in a surety bond containing joint and several promises has a right to sue the
    surety alone without joining the principals in the action, where a breach has
    occurred. Kampendonkv. Am. Bonding Co. ofBaltimore,6 Wn.2d 312, 318, 
    107 P.2d 588
    (1940); see also Kanters v. Kotick, 
    102 Wash. 523
    , 526, 
    173 P. 329
    (1918). This is consistent with the general suretyship law principle that the obligee
    has two sets of rights: one against the principal obligor and the other against the
    secondary obligor. RESTATEMENT(Therd)OF SURETYSHIP AND Guaranty § 50
    cmt.(1996); see also LAURENCE P. SIMPSON, SIMPSON ON SURETYSHIP 9(1950)(a
    surety's obligation to pay for another's debt not conditioned on another's default).
    The record does not reveal whether the bond in question contemplated that the
    parties would be jointly and severally liable, and neither does the bond's
    boilerplate language, but that does not change the statutory language.
    In similar cases, a payment bond claimant may bring suit solely against the
    surety and not against the principal on the bond, often "because the principal is
    bankrupt, insolvent, defunct, beyond the reach ofjudicial process, or not otherwise
    capable of satisfying the debt owed to the claimant." The Law OF Payment Bonds
    894(Kevin L. Lybeck et al. eds., 2d ed. 2011). "[Sjureties have sometimes argued
    21
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    that the claimant is obligated to bring suit against both the surety and the principal
    in the same action," and the majority of the courts relying on general suretyship
    law principles have rejected this argument. The Law of Payment Bonds,supra,
    at 895. In the present case, although the bond in question is not a payment bond but
    a lien release bond, similar considerations inform lien claimants' decisions to bring
    suit solely against the surety. We interpret the statutory language while mindful of
    the practical considerations of the parties whose interests the statute protects.
    Attorney Fees
    Both parties request an award of attorney fees and costs pursuant to RCW
    60.04.181(3) and RAP 18.1. Pursuant to RAP 18.1(1) and RCW 60.04.181(3), if on
    remand the trial court determines Inland Empire to be the prevailing party in the
    lien foreclosure action and upon submission of satisfactory proof of the claimed
    amount due,judgment against the bond should be entered. Reasonable attorney
    fees and expenses, including statutory fees and costs on appeal, are also
    recoverable.
    22
    Inland Empire Dry Wall Supply Co. v. Western Surety Co., No. 94118-1
    Conclusion
    We affirm the Court of Appeals and remand the case to the trial court for
    further proceedings.
    WE CONCUR:
    kAAAJ^Jr.
    fTlqcId^, Q.                                                          ^
    23