Velazquez Framing, LLC v. Cascadia Homes, Inc. ( 2024 )


Menu:
  •             FILE                                                                    THIS OPINION WAS FILED
    FOR RECORD AT 8 A.M. ON
    JANUARY 11, 2024
    IN CLERK’S OFFICE
    SUPREME COURT, STATE OF WASHINGTON
    JANUARY 11, 2024
    ERIN L. LENNON
    SUPREME COURT CLERK
    IN THE SUPREME COURT OF THE STATE OF WASHINGTON
    )
    VELAZQUEZ FRAMING, LLC,        )               No. 101591-7
    )
    Petitioner,     )
    )               En Banc
    v.                        )
    )
    CASCADIA HOMES, INC.,          )               Filed: January 11, 2024
    )
    Respondent.     )
    _______________________________)
    GONZÁLEZ, C.J. — Legislatures have long sought to balance the need to
    ensure that those who provide labor, professional services, equipment, or materials
    are paid for their work and the need to ensure that property owners have notice and
    the ability to avoid paying duplicative liens. In so doing, there is often a
    distinction drawn between those who labor and those who provide other things.
    Chapter 60.04 RCW strikes this balance. Chapter 60.04 RCW gives contractors
    the right to lien property they improve through their labor, professional services,
    materials, or equipment. RCW 60.04.021. Chapter 60.04 RCW specifically
    requires prelien notice for professional services, materials, or equipment liens.
    RCW 60.04.031(1). It does not say prelien notice is required for a labor lien.
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    In this case, a second-tier subcontractor was not paid for the work it did. It
    filed a lien for labor and materials without giving prelien notice. We must decide
    whether, taken as a whole, chapter 60.04 RCW requires prelien notice for labor
    liens. We conclude it does not. Accordingly, we reverse the Court of Appeals and
    remand for the trial court to determine the value of labor performed.
    FACTS
    Cascadia Homes Inc., a general contracting company, purchased real
    property in Lakewood, Washington to build a home on. Cascadia had worked with
    High End Construction LLC before and asked it to submit a bid for framing the
    home. High End successfully bid and then orally contracted with Velazquez
    Framing LLC to finish the framing work. High End subcontracted the work to
    Velazquez Framing without informing Cascadia.
    After Velazquez Framing did that work, High End billed Cascadia.
    Cascadia paid High End. High End did not pay Velazquez Framing. Velazquez
    Framing contacted Cascadia directly in December 2019 about its unpaid work.
    Velazquez Framing was not paid, and the next month, it filed a lien on the
    Lakewood property. In its lien, Velazquez Framing asserted that it “furnished
    labor, professional services, materials and/or equipment to the subject property . . .
    at the request of Cascadia Homes, Inc.” Clerk’s Papers at 56. Velazquez Framing
    later explained that it provided labor, a generator, a compressor, and five boxes of
    2
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    nails for the project. Velazquez Framing mailed Cascadia a copy of the lien.
    Velazquez Framing acknowledges it did not give prelien notice. Appellant’s Reply
    Br. at 5-6 (Wash. Ct. App. No. 56513-7-II (2022)).
    After Cascadia did not pay, and after waiting several months, Velazquez
    Framing sought to foreclose on its lien. Concluding that prelien notice was
    required, the trial court dismissed the foreclosure action at summary judgment.
    The Court of Appeals affirmed. Velazquez Framing, LLC v. Cascadia Homes,
    Inc., 24 Wn. App. 2d 780, 
    521 P.3d 257
     (2022). We granted review.
    ANALYSIS
    We must first decide whether our lien statutes require prelien notice to lien
    for labor. This is a question of statutory interpretation we review de novo. Dep’t
    of Ecology v. Campbell & Gwinn, LLC, 
    146 Wn.2d 1
    , 9, 
    43 P.3d 4
     (2002). Our
    objective in statutory interpretation is to identify and implement the legislature’s
    intent. 
    Id.
     Our analysis begins with the statutory language and frequently ends
    there when its meaning is plain. State v. Gonzalez, 
    168 Wn.2d 256
    , 263, 
    226 P.3d 131
     (2010). “In discerning the plain meaning of a provision, we consider the entire
    statute in which the provision is found, as well as related statutes or other
    provisions in the same act that disclose legislative intent.” State v. Alvarado, 
    164 Wn.2d 556
    , 562, 
    192 P.3d 345
     (2008). Whenever possible, we interpret the
    statutory language such that “‘no clause, sentence or word shall be superfluous,
    3
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    void, or insignificant.’” City of Seattle v. Long, 
    198 Wn.2d 136
    , 148, 
    493 P.3d 94
    (2021) (internal quotation marks omitted) (quoting Kasper v. City of Edmonds, 
    69 Wn.2d 799
    , 804, 
    420 P.2d 346
     (1966)).
    Where the statutory language is plain on its face, we give effect to that plain
    language and our inquiry ends. Gonzalez, 
    168 Wn.2d at 263
    . Where the statutory
    language is ambiguous—allowing for more than one reasonable interpretation—we
    may turn to legislative history. Jametsky v. Olsen, 
    179 Wn.2d 756
    , 762, 
    317 P.3d 1003
     (2014); State v. Evans, 
    177 Wn.2d 186
    , 192-93, 
    298 P.3d 724
     (2013).
    Velazquez Framing argues that the plain language of RCW 60.04.031
    requires that prelien notice be provided for professional services, materials, and
    equipment, but not for labor. We agree.
    The legislature has given contractors a right to lien to secure payment for
    their services. Specifically,
    [e]xcept as provided in RCW 60.04.031, any person furnishing labor,
    professional services, materials, or equipment for the improvement of
    real property shall have a lien upon the improvement for the contract
    price of labor, professional services, materials, or equipment furnished
    at the instance of the owner, or the agent or construction agent of the
    owner.
    RCW 60.04.021 (emphasis added). The legislature has also required some
    claimants to provide prelien notice:
    Except as otherwise provided in this section, every person furnishing
    professional services, materials, or equipment for the improvement of
    real property shall give the owner or reputed owner notice in writing of
    4
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    the right to claim a lien. . . . The notice may be given at any time but
    only protects the right to claim a lien for professional services,
    materials, or equipment.
    RCW 60.04.031(1) (emphasis added). If a claimant required to provide prelien
    notice fails to do so, their lien will not be enforced. See RCW 60.04.031(6). But
    under the plain language of RCW 60.04.031(1), no prelien notice is required for
    labor.
    Other portions of the statute bolster this conclusion. The legislature has
    provided a sample prelien notice form that claimants must substantially follow in
    cases where prelien notice is required. RCW 60.04.031(4). The form is intended,
    in part, to tell the owner “who is providing professional services, materials, or
    equipment for the improvement of [their] property and to advise [the owner] of the
    rights of these persons.” 
    Id.
     The form gives owners notice that claimants “have or
    will be providing professional services, materials, or equipment” and may claim a
    lien for such, but the form does not include “labor.” 
    Id.
    Similarly, RCW 60.04.091 provides a sample claim of lien form. Unlike the
    sample prelien notice form, the lien claim form includes language concerning
    labor. RCW 60.04.091. Pertinently, this form includes the “first and last date on
    which the labor, professional services, materials, or equipment was furnished or
    employee benefit contributions were due.” RCW 60.04.091(1)(b) (emphasis
    added).
    5
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    Taken together, these provisions of chapter 60.04 RCW require prelien
    notice for professional services, materials, and equipment, but not for labor. The
    presence and absence of “labor” throughout chapter 60.04 RCW is consistent with
    no prelien notice for labor being required. Under RCW 60.04.021, a lien claimant
    is explicitly entitled to a lien for their labor. However, “labor” is noticeably absent
    in the prelien notice requirement statute. RCW 60.04.031(1). The plain language
    of RCW 60.04.031(1) instead suggests that the legislature intended to require
    prelien notice in a limited set of circumstances: for the provision of professional
    services, materials, or equipment. 
    Id.
    Cascadia urges us to adopt a different interpretation of the statute. Cascadia
    argues that unless an exception under RCW 60.04.031(2) applies, a subcontractor
    must provide prelien notice. We disagree. Under RCW 60.04.031(2) notice is not
    required by
    (a) Persons who contract directly with the owner or the owner’s
    common law agent;
    (b) Laborers whose claim of lien is based solely on performing
    labor; or
    (c) Subcontractors who contract for the improvement of real
    property directly with the prime contractor, except as provided in
    subsection (3)(b) of this section.
    None of these exceptions apply to the labor done by Velazquez Framing.
    Taken together, however, the statutes do not require prelien notice to lien for labor,
    either by a subcontractor that provides the labor or by the laborers themselves.
    6
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    RCW 60.04.021 entitles everyone, including Velazquez Framing, to lien for their
    labor. Cascadia is correct that the general right to lien under RCW 60.04.021 is
    subject to the requirements of RCW 60.04.031. However, Cascadia’s proposed
    reading of RCW 60.04.031(2), requiring prelien notice in all but three
    circumstances, violates the plain language of RCW 60.04.031(1). We hold the
    statutes unambiguously did not require Velazquez Framing to give prelien notice
    before filing a labor lien.
    Even if the plain language of our lien statutes was ambiguous, legislative
    history leads to the same conclusion that prelien notice is not required to lien for
    labor. Our legislature began seriously considering changes to our lien laws in
    1991. See LAWS OF 1991, ch. 281 (codified in RCW 19.27.095 and scattered
    sections of Title 60 RCW). The legislative history suggests that consumer
    protection concerns motivated these changes. FINAL B. REP. ON SUBSTITUTE S.B.
    5497, at 1, 52d Leg., Reg. Sess. (Wash. 1991). The legislature and the attorney
    general received reports from homeowners about subcontractors making lien
    claims after the homeowners paid the general contractor. 
    Id.
     The legislation was
    proposed, in part, to address this concern.
    Although the legislature seemed primarily concerned with consumer
    protection, the legislature was responding to other concerns as well. FINAL B. REP.
    ON SUBSTITUTE S.B. 5497, at 1. Specifically, “construction lien laws ha[d] not
    7
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    been substantially amended or modernized during [the 20th] century” and
    “[v]irtually all industry segments ha[d] reported problems with the current [lien]
    law[s].” 
    Id.
     As a result, much of Substitute S.B. 5497 was also “concerned with
    simply modernizing the language of the existing law without making substantive
    changes” and with addressing industry concerns about the law. S.B. REP. ON
    SUBSTITUTE S.B. 5497, at 2, 52d Leg., Reg. Sess. (Wash. 1991).
    The enacted language does not require prelien notice for labor. Legislative
    history in the house is consistent. A house bill report explains that under current
    law, “[a] notice of the right to claim a lien is required to establish a lien for
    material and equipment supplied for the project (not labor liens)” and that under
    the new notice requirements, “notice of the right to claim a lien is not required for
    a person supplying labor.” H.B. REP. ON SUBSTITUTE S.B. 5497, at 2, 3, 52d Leg.,
    Reg. Sess. (Wash. 1991).
    A legislative memorandum concerning a public hearing on Substitute S.B.
    5497 mirrors this intent. The memo provides a comparison between the prelien
    notice requirement in then current lien laws and Substitute S.B. 5497. H. COM. &
    LAB. COMM., PUB. HR’G MEM. ON SUBSTITUTE S.B. 5497, at 2, 52d Leg., Reg. Sess.
    (Wash. 1991). The memo explains that under the lien laws at the time, “pre-lien
    notice [was] required for material and equipment liens only (not labor liens).” 
    Id.
    Under Substitute S.B. 5497, “pre-lien notice is not required for a person supplying
    8
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    labor, or for a person providing professional services, materials, or equipment who
    contracts directly with the property owner, or for a subcontractor who contracts
    directly with the prime contractor.” 
    Id.
    The robust legislative history concerning our lien laws illuminates the
    complexity of the legislature’s intent in enacting the lien granting and prelien
    notice requirement statutes. We conclude that this history is consistent with the
    plain language of the statutes. The legislature intended to require prelien notice
    unless the lien was based on labor.
    Because Velazquez Framing did not lien solely for labor, we must next
    decide whether a claimant who provides materials and equipment in addition to
    labor may lien for their labor despite not having provided prelien notice. We
    conclude they may. Although Velazquez Framing will not be able to lien for its
    materials and equipment, its labor lien is still enforceable.
    Pre-1990s case law1 establishes the practice of lien segregation. These cases
    suggest that where a claimant liens for both labor and material without providing
    prelien notice, the claimant may enforce that portion relating to labor so long as the
    court has an evidentiary basis to segregate the value of the labor from materials.
    1
    Cascadia argues, and the Court of Appeals agreed, that this body of case law is not relevant or
    helpful for determining legislative intent because it predates the legislative amendments
    discussed above. See Velazquez Framing, 24 Wn. App. 2d at 790 n.5. We conclude that this case
    law interprets earlier lien statutes that are substantially similar in substance and form to our
    current lien statutes. Accordingly, this case law is relevant and helpful to the issue of lien
    segregation.
    9
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    See Hallett v. Phillips, 
    73 Wash. 457
    , 464, 
    132 P. 51
     (1913); Culbert v. Lindvall,
    
    73 Wash. 643
    , 646, 
    132 P. 729
     (1913); Northlake Concrete Prods., Inc. v. Wylie,
    
    34 Wn. App. 810
    , 818-19, 
    663 P.2d 1380
     (1983). Where a contractor liens for
    both labor and equipment without prelien notice, remand to determine the value of
    labor is usually appropriate. See Northlake, 
    34 Wn. App. at 815, 818-19
    .
    A claimant may not maintain a lien for labor where the record does not
    allow the value of the labor to be determined. See Hallett, 
    73 Wash. at 464
    . In
    Hallett, subcontractors liened for their labor and materials without providing
    notice. 
    Id. at 459-60, 464
    . This court determined that the subcontractors could not
    maintain a lien for their materials without providing notice. 
    Id. at 464
    . We
    explained that because there was no evidence “showing what proportion of [the]
    claims was for material and what proportion was for labor . . . it [was] impossible
    to fix or award any amount for which [the subcontractors could] maintain labor
    liens.” 
    Id.
    Conversely, a claimant may maintain its lien for labor where there is
    evidence to segregate the value of the labor from that of the materials and
    equipment. In Culbert, we concluded that a subcontractor who provided a furnace
    and labor could not lien for the furnace without providing notice but could lien for
    its labor. 73 Wash. at 645-46. We explained that the evidence “segregates the
    10
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    value of the labor that went into the construction of the furnace, and for [that the
    subcontractor] is entitled to the foreclosure of its lien.” Id. at 646.
    We conclude that Velazquez Framing can lien for its labor so long as it can
    establish an evidentiary basis for segregation.
    CONCLUSION
    The plain language of our lien statutes does not require prelien notice to lien
    for labor. Legislative history supports this interpretation. Accordingly, we reverse
    the Court of Appeals and remand to the trial court for further proceedings
    consistent with this opinion. Velazquez Framing’s RAP 18.1 request for attorney
    fees is granted.
    11
    Velazquez Framing, LLC v. Cascadia Homes, Inc., No. 101591-7
    ____________________________
    WE CONCUR:
    _____________________________             ____________________________
    _____________________________             ____________________________
    _____________________________             ____________________________
    _____________________________             ____________________________
    12
    

Document Info

Docket Number: 101,591-7

Filed Date: 1/11/2024

Precedential Status: Precedential

Modified Date: 1/11/2024