Denise Brackett Woodley v. Style Corporation D/b/a ( 2019 )


Menu:
  •                                                  ~~E0FVA~0~                       ~
    p~j 9: 18
    IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    DIVISION ONE
    DENISE BRACKETT WOODLEY,                  )      No. 77352-6-I
    Respondent,
    v.
    STYLE CORPORATION doing                   )
    business as SERVPRO OF                    )
    SHORELINE/WOODINVILLE,                    )      PUBLISHED OPINION
    lien claimant,                            )
    )      FILED: February 11,2019
    Appellant.
    VERELLEN, J. —A materialmen’s lien must be released pursuant to
    RCW 60.04.08 1 if it is frivolous and made without reasonable cause. Because
    Style Corporation’s (Servpro) lien presents debatable issues of law and fact, it is
    not frivolous and should not have been released.
    A lien is clearly excessive under RCW 60.04.08 1 when the amount
    claimed on the face of the lien is unquestionably far greater than the usual or
    agreed amount. Because Servpro’s lien clouds the title to Denise Brackett
    Woodley’s condominium unit for the entire $183,945.09 listed on its face for
    services provided to Woodley worth, at most, $6,001.90, the trial court correctly
    concluded the lien was clearly excessive.
    No. 77352-6-112
    Therefore, we reverse in part, affirm in part, and remand for further
    proceedings consistent with this opinion.
    FACTS
    Denise Brackett Woodley owns unit 208 in building E of the Bellevue Park
    condominium complex. Because of ongoing roof construction and a rainstorm,
    water leaked into Woodley’s unit and 19 others on September 17, 2016.1 That
    day, Bellevue Park’s property management company, MacPherson’s Property
    Management, called Servpro and asked it to clean up the water and conduct
    restoration work. MacPherson’s signed a work authorization contract with
    Servpro on the behalf of “Bellevue Park Condos,” and Servpro began placing
    drying equipment in affected units.
    Woodley’s unit was occupied by a tenant who gave Servpro permission to
    enter and set up its equipment. Interior surfaces in the unit’s living room, dining
    room, bedrooms, and bathroom needed to be dried. Three days later, Servpro
    returned to monitor drying progress and to perform asbestos testing.
    Woodley did not speak with Servpro or her tenant prior to the work
    completed between September 17 and September 20. Servpro’s equipment
    remained in Woodley’s unit until mid-November.
    The Bellevue Park condominium owners association planned to pay
    Servpro for its services and recoup the money from unit owners via a special
    1 The entire condominium complex consists of 78 units across multiple
    buildings.
    2
    No. 77352-6-1/3
    assessment. But the association failed to pay because it was trying
    unsuccessfully to obtain the money from the roofing company.
    Servpro filed a single lien for the total value of its services on January 26,
    2017. The lien claimed a debt of $183,945.09. The lien named the association
    as the indebted person but recited that it applied to the 20 specific units and a
    common storage area where Servpro provided services. The lien also names
    each owner of the 20 units but does not allocate a specific portion of the total
    debt to each unit.
    Pursuant to RCW 60.04.081, Woodley filed a motion to release the lien.
    Finding it both frivolous and clearly excessive, the court released the lien. The
    court denied a motion for reconsideration.
    Servpro appeals.
    ANALYSIS
    When evaluating release or reduction of a lien under RCW 60.04.081, we
    review the court’s legal conclusions de novo and review factual findings for
    substantial evidence.2
    A materialmen’s lien is authorized for “any person furnishing labor,
    professional services, materials, or equipment for the improvement of real
    property.   .   .   for the contract price of labor, professional services, materials, or
    equipment furnished at the instance of the owner, or the agent or construction
    2 Intermountain Elec., Inc. v. G-A-T Bros. Const., Inc., ll5Wn. App. 384,
    390, 
    62 P.3d 548
     (2003) (citing W.R.P. Lake Union Ltd. P’ship v. Exterior Servs.,
    lnc~ 85Wn. App. 744, 749-50, 
    934 P.2d 722
     (1997)).
    3
    No. 77352-6-1/4
    agent of the owner.”3 After a claimant files a lien, ROW 60.04.081 authorizes a
    “narrow and limited”4 ‘summary proceeding” to determine whether the lien “is
    frivolous and made without reasonable cause or clearly excessive.”5 A court
    must release the lien “if frivolous and made without reasonable cause” or reduce
    the lien if “clearly excessive.”6 This ‘trial by affidavit” should not be a substitute
    for trial on the merits where the facts “do not clearly indicate” the lien is frivolous
    or clearly excessive.7
    Servpro’s Lien Is Not Frivolous
    A lien is frivolous if “improperly filed beyond legitimate dispute” and “so
    devoid of merit that it has no possibility of succeeding.”8 Even if a lien is invalid,
    it may not be frivolous.9 This high standard exists to ensure contractors and
    laborers are not deprived of their right to trial on a legitimate lien claim.10 Thus, a
    lien is not frivolous if it presents debatable issues of law and fact.11
    ~ ROW 60.04.021.
    ~ Andries v. Covey, 
    128 Wn. App. 546
    , 551, 
    113 P.3d 483
     (2005).
    ~ Williams v. Athletic Field, Inc., 
    172 Wn.2d 683
    , 699, 
    261 P.3d 109
     (2011)
    (quoting W.R.P., 85 Wn. App. at 749); ROW 60.04.081.
    6 ROW 60.04.081 (4).
    ~ W.R.P., 85 Wn. App. at 750, 753.
    8Williams, 
    172 Wn.2d at 699
     (internal quotation marks omitted) (quoting
    Intermountain Elec., 115 Wn. App. at 394).
    ~ S.D. Deacon Cow. of Wash. v. Gaston Bros. Excavating, Inc., 
    150 Wn. App. 87
    , 91, 
    206 P.3d 689
     (2009).
    10 Id. at 89.
    11See W.R.P., 85 Wn. App. at 752 (“Because this lien presents debatable
    issues of law and fact, it does not satisfy the requirements of frivolous and
    without reasonable cause justifying its release in this summary procedure.”).
    4
    No. 77352-6-115
    Woodley makes several arguments to explain why Servpro’s lien is
    frivolous, but none meet this high standard.
    First, Woodley argues Servpro’s lien is frivolous because she never
    directly authorized any of Servpro’s work after September 26, 2016. Servpro
    agrees that Woodley herself never directly authorized its services. But
    Wood ley’s brief does not contest, and she confirmed at oral argument that she
    views the association as having actual authority under the condominium
    declaration for three days following the roof leak to arrange for Servpro’s
    emergency repairs to her unit. Woodley’s admission creates debatable issues of
    law and fact around the scope of agency authorized by the condominium
    declaration.12
    Second, Woodley contends the lien is frivolous because it was filed after
    the 90-day statutory limitations period lapsed. The court found Servpro stopped
    providing beneficial services to Woodley on September 21, 2016, and filed its lien
    more than 90 days later on January 26, 2017. Servpro argues the limitations
    period did not lapse before filing because it continued to provide beneficial
    services to Woodley through November 17, 2016, when it removed its equipment
    from her unit. But even though an untimely lien is presumptively invalid, that
    does not mean the lien is frivolous.
    12 See RCW 60.04.021. However, Servpro’s lien would have been
    frivolous had there been no agency relationship at all between Woodley and the
    association because none of Servpro’s work would have been furnished “at the
    instance of the owner.” RCW 60.04.021.
    5
    No. 77352-6-1/6
    A materialmen’s lien must be filed ‘not later than [90] days” after the lien
    claimant stops providing services.13 This “strict time limit”14 is “a period of
    limitation,” so “no action to foreclose a lien shall be maintained” if the claimant
    failed to file within the limitations period.15 A lien filed after the 90-day limit is
    presumptively invalid.16 Any provision of supplies or services at the owner’s
    request extends the limitation period for another 90 days.17
    In Intermountain Electric, Inc. v. G-A-T Brothers Construction, Inc., a lien
    was invalid because it was filed 94 days after the lien claimant, an electrician,
    stopped providing beneficial services to a general contractor.18 On June 6, 2000,
    the electrician performed its last active work for the contractor and left its
    construction trailer at the construction site in anticipation of future work.19 The
    electrician filed a lien 94 days later but argued its lien was valid because it was
    still furnishing equipment to the general contractor at the time it filed.2° Because
    13   RCW 60.04.091.
    14Inland Empire Dry Wall Supply Co. v. W. Sur. Co., 
    189 Wn.2d 840
    , 844,
    
    408 P.3d 691
     (2018).
    15 RCW6O.04.091.
    16  RCW 60.04.091; see Intermountain Elec., 115 Wn. App. at 391
    (“Intermountain’s last day of work was June 6, 2000. The lien was filed 94 days
    later on September 8. The lien is, then, invalid on its face.”)
    17 See Intermountain Elec., 115 Wn. App. at 393 (“Even small quantities of
    additional supplies, if furnished at the request of the owner to complete the
    contract will serve to keep the 90-day lien limitation period from starting.”).
    18 
    115 Wn. App. 384
    , 391-92, 
    62 P.3d 548
     (2003).
    19k1.at389.
    Id. at 390.
    6
    No. 77352-6-117
    the general contractor neither requested nor required the electrician’s
    construction trailer, the electrician stopped providing beneficial services on June
    6 and did not have a valid lien.21 But the court declined to hold the lien frivolous,
    despite it being invalid because it presented debatable issues of law and fact.22
    Like the electrician in Intermountain Electric, Servpro stopped providing
    beneficial services to Wood ley well before it retrieved its equipment.23 But
    without more, the lien is not frivolous even accepting it was invalidly filed more
    than 90 days after Servpro concluded beneficial work.
    Third, Wood ley contends the lien was frivolous because the contract
    between MacPherson’s and Servpro did not state the actual amount charged.
    Authorized liens are only for ‘the contract price” of what the claimant provided.24
    2Hd.at 393.
    22k1.at394.
    23 Servpro explains that its services were still necessary from September
    into November based on its own moisture readings and its contract with
    MacPherson’s. But this argument presumes a party to a Servpro contract has no
    power to refuse ongoing services, even if unwanted. Servpro’s employees knew
    someone repeatedly unplugged their equipment. And within one week of the
    leak, Woodley told MacPherson’s to tell Servpro to remove their equipment from
    her unit. Wood ley’s demand revoked the authority for MacPherson’s or the
    Association to authorize additional work. See CKP, Inc. v. GRS Const. Co., 
    63 Wn. App. 601
    , 608, 
    821 P.2d 63
     (1991) (“Whether one is the agent of another for
    a specific purpose depends in part upon whether that person has power to act
    with reference to that purpose.”); see also RESTATEMENT (THIRD) OF AGENCY §
    1.01 cmt. c (AM. LAW. INST. 2006) (“As defined by the common law, the concept
    of agency posits a consensual relationship in which one person, to one degree or
    another or respect or another, acts as a representative of or otherwise acts on
    behalf of another person with power to affect the legal rights and duties of the
    other person.”). Servpro provides no authority that it was entitled to insist on
    unwanted services
    24 RCW 60.04.021.
    7
    No. 77352-6-118
    But RCW 60.04.011(2) defines “contract price” as “the amount agreed upon by
    the contracting parties, or if no amount is agreed upon, then the customary and
    reasonable charge therefor.” An authorized lien does not require a specific
    agreed-upon contract price before a claimant begins work.
    Finally, Wood ley contends the lien is frivolous because it contains factual
    inaccuracies, one inaccuracy being that Servpro’s work was “ongoing” when it
    filed the lien.25 The other is that the association owned the properties listed on
    the lien. These inaccuracies may be material to the ultimate validity of the lien,
    but they do not automatically make it frivolous.26
    Because Servpro’s lien presents debatable issues of law and fact, it is not
    frivolous.
    Servpro’s Lien Is Clearly Excessive
    Servpro argues that its lien was not clearly excessive because it did not
    file it in bad faith or with an intent to defraud. Servpro cites to Pacific Industries,
    Inc. v. Sinqh for the proposition that “[a] materialman’s lien will be declared
    invalid because it is excessive only if the amount is claimed with an intent to
    defraud or in bad faith.”27 But this standard relies on cases that predate
    RCW 60.04.081 and consequently, fail to account for the statute.
    25    Resp’t’s Br. at 21.
    26 See S.D. Deacon, 150 Wn. App. at 91 (stating that a lien must have
    been “improperly filed” “beyond legitimate dispute” for it to be held frivolous).
    Inaccuracies and misrepresentations on the face of the lien may be sufficient in
    circumstances not present here to show that the lien has been improperly filed
    beyond legitimate dispute.
    27 
    120 Wn. App. 1
    , 10, 
    86 P.3d 778
     (2003).
    8
    No. 77352-6-119
    In Knibb v. Mortensen, our Supreme Court noted that liens “must be
    claimed in good faith” and that “willful excess would vitiate the whole lien”
    regardless of evidence of bad intent.28 The court released the lien because the
    claimant “burdened a little dwelling with twice as much [debt] as he had a right to
    claim by lien, and, in our opinion, he did it willfully, out of an ill humor which is
    exhibited in sundry features of the record.”29
    In Radley v. Raymond, the court considered whether a mechanic lost his
    lien by overcharging a customer for a rebuilt engine.30 An overcharge could lead
    to release of the lien if “the court finds that such mistake or error [on the face of
    the lien] was made with intent to defraud or in bad faith.”31 Bad faith could be
    demonstrated by a claimant “claiming a lien for items to which he knew he was
    not entitled.”32 Because the mechanic filed a lien for an amount almost 40
    percent more than the contract price and failed to provide a good faith
    explanation for doing so, the court released the lien.33
    More recently in CHG International, Inc. v. Platt Electric Supply, Inc., this
    court relied on Knibb and Radley to determine whether an electrical supply
    company lost its right to a materialmen’s lien “by claiming an excessive
    
    2889 Wash. 595
    , 596, 
    154 P. 1109
     (1916).
    29   
    Id.
    30   
    34 Wn.2d 475
    , 477-79, 
    209 P.2d 305
     (1949).
    31   
    Id. at 481
    .
    32   
    Id.
    ki. at 482-83.
    9
    No. 77352-6-1110
    amount.”34 In CHG, the trial court authorized foreclosure of a lien and entered a
    judgment for $25,000 of the $77,000 claimed on the face of the lien.35 The
    debtor appealed and argued that the reduced judgment showed the lien should
    be released because the claimant overcharged for the services provided.36 This
    court declined to release the lien because the evidence explained the
    overcharges without showing bad faith or fraudulent intent by the claimant.37
    But these cases were decided before the legislature created the
    procedural mechanism in RCW 60.04.081 to release or reduce a lien. In 1991,
    the legislature repealed and replaced most of the materialmen’s lien statute, and
    created the mechanism in RCW 60.04.081 to manage liens prior to foreclosure.38
    The prior version of the statute had no equivalent procedure.39
    When interpreting a statute, we rely on the plain meaning of its terms to
    give effect to the intent of the legislature.4° We determine legislative intent from
    the context of the statute and statutes related to it.41 We do not engage in
    ~ 
    23 Wn. App. 425
    , 426, 
    597 P.2d 412
     (1979).
    ~ 
    Id.
    36   
    Id.
    ~ ki. at 426-27.
    38   See generally LAWS OF 1991, ch. 281,   § 8.
    ~ Compare LAWS OF 1991, ch. 281, § 8, wfth former ch. 60.04
    RCW (1989).
    40 Inland Empire, 189 Wn.2d at 843 (quoting Dept of Ecology v. Campbell
    & Gwin, LLC, 
    146 Wn.2d 1
    , 9-10, 
    43 P.3d 4
    (2002)); W.R.P., 85 Wn. App. at 749.
    41 Inland Empire, 189 Wn.2d at 843 (quoting Campbell & Gwinn, 146
    Wn.2d at 11, 12)).
    10
    No. 77352-6-I/il
    statutory construction if its plain terms are unambiguous and will not produce an
    absurd result.42 “We presume the [Ijegislature is familiar with past judicial
    interpretations of its enactments.”43
    When the legislature enacted RCW 60.04.081, it created a distinct
    procedural mechanism to adjudicate a lien prior to foreclosure.44
    RCW 60.04.081(4) provides the remedies available to a property owner
    contesting a lien:
    If, following a hearing on the matter, the court determines that the
    lien is frivolous and made without reasonable cause, or clearly
    excessive, the court shall issue an order releasing the lien if
    frivolous and made without reasonable cause, or reducing the lien if
    clearly excessive, and awarding costs and reasonable attorneys’
    fees to the applicant to be paid by the lien claimant.[45J
    The statute delineates between a “frivolous” lien and a “clearly excessive” lien by
    consistently separating the two with commas and the disjunctive “or.”46 In the
    limited summary proceeding authorized by RCW 60.04.081, the only remedy for
    a clearly excessive lien is reduction of the lien. Release is available only where a
    42   In re Dep. of D.L.B., 
    186 Wn.2d 103
    , 116, 
    376 P.3d 1099
     (2016).
    ~ Hangman Ridge Training Stables, Inc. v. Safeco Title Ins. Co., 
    105 Wn.2d 778
    , 789, 
    719 P.2d 531
     (1986) (quoting Glass v. Stahl Specialty Co., 
    97 Wn.2d 880
    , 887, 
    652 P.2d 948
     (1982)).
    ~ See RCW 60.04.081 (3) (allowing adjudication of a lien prior to an action
    to foreclose the lien).
    ~ RCW 60.04.081(4) (emphasis added).
    46 See RCW 60.04.081(4); see also RCW 60.08.081(1) (“Any owner of
    real property subject to a recorded claim of lien who believes the claim of lien
    .   .   .
    to be frivolous and made without reasonable cause, or clearly excessive may
    apply by motion. .“) (emphasis added).
    .   .
    ii
    No. 77352-6-1112
    lien is “frivolous and made without reasonable cause.”47 Moreover, “shall”
    indicates that these remedies are mandatory, and courts do not have discretion
    in deciding which remedy is appropriate.48
    We presume the legislature knew that “claiming an excessive amount”
    with bad faith or an intent to defraud could result in release of the lien.49 But
    RCW 60.04.08 1 limits the remedy for a “clearly excessive” lien to reduction of the
    lien’s face value and allows release only where a lien is frivolous.50 Thus, the
    proscriptive language in RCW 60.04.081(4) eliminates the possibility of release
    of a lien where it is “clearly excessive” but not frivolous.51
    We also cannot read RCW 60.04.081(4) to allow release of a
    non-frivolous, excessive lien even if made in bad faith or with intent to defraud
    because it would read additional terms into the statute and undermine the
    ~ RCW 60.04.081(4).
    48Erection Co. v. Dept of Labor & Indus. of State of Wash., 
    121 Wn.2d 513
    , 518, 
    852 P.2d 288
     (1993).
    ~ CHG Int’l, 
    23 Wn. App. at 426
    ; see Hangman Ridge, 
    105 Wn.2d at 789
    .
    50   ROW 60.04.081(4).
    51 We note that our Supreme Court in Williams described the proceeding
    created by RCW 60.04.08 1 as “a summary proceeding in which a property owner
    may quickly obtain the release of a lien that is frivolous and made without
    reasonable cause or is clearly excessive.” 
    172 Wn.2d at 699
     (emphasis added)
    (quoting W.R.P., 85 Wn. App. at 749). Because ROW 60.04.081(4) distinguishes
    the remedies for frivolous liens from clearly excessive liens, we do not believe
    either the Williams or W.R.P. courts were attempting to redraft the statute
    through a casual description. ~ In re Marriage of Ruff and Worthley, 
    198 Wn. App. 419
    , 425, 
    393 P.3d 859
     (2017) (“Courts cannot amend statutes by judicial
    construction.”).
    12
    No. 77352-6-1/13
    statute’s mandatory language limiting each remedy to a particular problem.52 We
    note that in Sinqh, this court cited pre-1991 cases to describe a “clearly
    excessive” lien as one “claimed with an intent to defraud or in bad faith.”53 But
    this reading would undercut the purpose of the clearly excessive provision of
    RCW 60.04.081. For example, if a lien claimant accidentally filed a lien for
    $100,000 on $1,000 worth of work without any bad faith or an intent to defraud,
    then the property owner would not be entitled to a reduction. The language of
    RCW 60.04.081 does not include such a bad faith or intent to defraud
    requirement.
    To the extent that p re-i 991 cases discussing release of excessive liens
    may still have vitality, they are not controlling where a court considers a motion
    made under RCW 60.04.081. In a summary lien proceeding, a court must
    reduce rather than release a “clearly excessive” lien.
    In absence of any statutory definition for “clearly excessive,”54 we must
    read those words to give them their ordinary meaning.55 Because they are
    52 See Ruff and Worth 1ev, 198 Wn. App. at 425 (“We cannot read into a
    statute that which we may believe ‘the legislature has omitted, be it an intentional
    or inadvertent omission.”) (internal quotation marks omitted) (quoting In re
    Custody of Smith, 
    137 Wn.2d 1
    , 12, 
    969 P.2d 21
    (1998), aff’d sub nom Troxel v.
    Granville, 
    530 U.S. 57
    , 
    120 S. Ct. 2054
    , 
    147 L. Ed. 2d 49
     (2000)).
    ~~120 Wn. App. at 10.
    545ee RCW6O.04.011.
    ~ Univ. of Washington v. City of Seattle, 
    188 Wn.2d 823
    , 837, 
    399 P.3d 519
     (2017).
    13
    No. 77352-6-1/14
    undefined by statute, we may look to standard English dictionaries.56 In standard
    English, something “excessive” is “characterized by or present in excess.”57
    Something is present in “excess” when there is “[m]ore than or above the usual
    or specified amount.”58 “Clearly” means “without doubt or question.”59 Thus, for
    a lien to be “clearly excessive,” it must be unquestionably characterized by being
    far above the usual or agreed amount.
    This accords with the requirement in RCW 60.04.021 that a lien is
    authorized only “for the contract price” of what the claimant provided. The statute
    defines “contract price” as “the amount agreed upon by the contracting parties, or
    if no amount is agreed upon, then the customary and reasonable charge
    therefor.”6° In providing a remedy for a clearly excessive lien, the legislature
    created a mechanism by which a court could efficiently reduce a lien where the
    amount claimed on the face of the lien is unquestionably far greater than the
    value of the goods or services provided.
    But this remedy is not intended to be used to harm lien claimants, who are
    the very persons the legislature enacted chapter 60.04 RCW to protect.6’ Nor
    56Quinault Indian Nation v. Imperium Terminal Servs., LLC, 
    187 Wn.2d 460
    , 477, 
    387 P.3d 670
     (2017).
    ~ WEBSTER’S THIRD NEW INTERNATIONAL DICTIONARY 792 (2002).
    58   
    Id.
    59kLat420.
    60 RCW6O.04.011(2).
    61See Williams, 
    172 Wn.2d at 697
     (“The claimants are therefore parties
    ‘intended to be protected’ by the statute, RCW 60.04.900, and we will liberally
    construe the statute to protect them.”).
    14
    No. 77352-6-1/15
    should the availability of this summary proceeding to reduce the value of a clearly
    excessive lien be used “as a substitute for trial where there is a legitimate dispute
    about the amount of work done and money paid.”62 And we must read the
    statute in context. Congruent with the requirement that a party challenging a lien
    in this summary proceeding must show that it is frivolous “beyond legitimate
    dispute,”63 a party challenging a lien as clearly excessive must show that the face
    value of the lien is unquestionably far greater than the value of the goods or
    services provided.
    Here, the lien purports to encumber 20 specific units and a common
    storage area in building E of the condominium complex. This approach failed to
    properly account for how lien statutes and condominium statutes interact.64
    A condominium is comprised of two legally distinct physical parts: units
    and common elements.65 The unit “is the subject of individual ownership” and “is
    legally a separate parcel of realty, separately owned, taxed, and financed.”66 A
    62S.D. Deacon, 150 Wn. App. at 90; see Gray v. Bourgette Const., LLC,
    l6OWn. App. 334, 341, 
    249 P.3d 644
     (2011) (“[A]s we cautioned recently, ‘[t]rial
    courts should take care not to let the frivolous lien statute be misused to deprive
    contractors of their right to trial on a lien claim.”) (second alteration in original)
    (quoting S.D. Deacon, 150 Wn. App. at 89).
    63SD Deacon, 150 Wn. App. at 91.
    64 Chapter 60.04 RCW is the germane lien statute. Because Woodley’s
    condominium complex was created before July 1, 1990, portions of both the
    Horizontal Property Regimes Act, ch. 64.32 RCW, and the Condominium Act, ch.
    64.34 RCW, apply. RCW64.34.010.
    65 18 WILLIAM B. STOEBUCK & JOHN W. WEAVER, WASHINGTON PRACTICE:
    REAL ESTATE: TRANSACTIONS § 12.2, at 21-22 (2nd ed. 2004); RCW 64.32.010(1).
    6618 STOEBUCK&WEAVER, supra, at 22; RCW64.32.040.
    15
    No. 77352-6-1/16
    unit’s boundaries are “the interior surfaces of the perimeter walls, floors, ceilings,
    windows and doors thereof.”67 Common elements are, generally, “all parts of a
    condominium other than the units.”68 Common elements include the building’s
    roof.69 Unit owners collectively own the condominium’s common elements as
    tenants in common.7° Generally, an owners’ association does not own any of the
    condominium’s real property.71
    An owners’ association “is a statutorily required unit owners’ profit or
    nonprofit corporation, which has powers to manage common elements and to
    perform other functions” as required by statute or by private agreement.72 Those
    private agreements include the “declaration,” the legal document creating the
    condominium and defining the association’s powers.73 By statute, an association
    has the power to make contracts and incur liabilities, hire managing agents, and
    regulate “maintenance, repair, [and] replacement” of common elements in a
    condominium.74 Accordingly, an association has a statutory right of access
    related to its duties to repair and maintain:
    67   RCW 64.32.010(1).
    68   18 STOEBUCK & WEAVER, supra, at 22.
    69   RCW 64.32.010(6)(a)-(b).
    7018 STOEBUCK&WEAVER, supra, at 22; RCW64.32.050(1).
    7118 ST0EBUCK & WEAVER, supra, at 23.
    72   Id.
    ki. at 22.
    ~ RCW 64.34.304(1).
    16
    No. 77352-6-1/17
    The association  .   shall have the irrevocable right. to have
    .   .                            .
    access to each [unit] from time to time during reasonable hours as
    may be necessary for the maintenance, repair, or replacement of
    any of the common [elements] therein or accessible therefrom, or
    for making emergency repairs therein necessary to prevent
    damage to the common [elements] or to another apartment or
    apartments.[751
    Typically, an association pays its liabilities and then levies assessments
    on unit owners who, in turn, pay the association.76 An association may file a lien
    against the unit of an owner who fails to pay assessments.77
    A contractor may file a mechanics’ or materialmen’s lien against an entire
    condominium complex in the same way it would file a lien against an individual
    property, such as a single-family house, by naming an owner’s association as the
    indebted person and listing the whole condominium as the property against
    which a lien is claimed.78 When a contractor files a lien naming an owner’s
    association as the indebted person and describing the whole condominium as
    the property against which a lien is claimed, then a judgment enforcing the lien
    extends to all units in the condominium and each owner’s interest in the common
    ~ RCW 64.32.050(6). We note that in this case, Servpro’s services to
    Woodley were for only the interior walls and ceiling of her unit, which are not
    common elements.
    7618 STOEBUCK&WEAVER, supra, at 23; RCW64.34.360(3), .364.
    ~ RCW 64.34.364.
    78 RCW 64.32.070; see RCW 64.34.368(1) (‘[A] judgment for money
    against the association perfected under RCW 4.64.020 is a lien in favor of the
    judgment lienholder against all the units in the condominium and their interest in
    the common elements at the time the judgment was entered. No other property
    of a unit owner is subject to the claims of the creditors of the association.”).
    17
    No. 77352-6-1/18
    elements.79 The collective lien is released if the association pays the total
    balance due or, in the alternative, an individual unit is released if the unit owner
    pays the lien holder her proportional share of the total amount owed by the
    association.80 Notably, this proportional share is not based on the value of the
    benefit to a unit but on the “fractional and proportionate amounts attributable to
    each of the [units] affected,” which must be computed by reference to the unit
    owner’s ownership percentage of the entire condominium ‘appearing on the
    declaration.”81
    A contractor can also file a lien against an individual unit improved by the
    contractor’s services where the unit owner or the owner’s agent “expressly
    consented” to the services.82
    Servpro erred by blending these two distinct methods of filing liens for
    work performed in a condominium. Servpro filed a lien listing individual units
    where it worked, naming the individual owners of those 20 units, naming the
    association as the indebted person, and providing a face value that includes the
    value of work benefiting those 20 units individually as well as work benefiting the
    condominium’s common elements. The face value of Servpro’s lien is
    ~ RCW 64.32.070; RCW 64.34.368.
    8018 STOEBUcK&WEAVER,        § 12.6, at42 (citing RCW64.34.368(3)); see
    also ROW 64.32.070(2).
    81 ROW 64.32.070(2). We note the Condominium Act, ROW 64.34.368(3),
    expresses this same concept as the “ratio which that unit owner’s allocated
    common expense liability bears to the allocated common expense liabilities of all
    unit owners whose units are subject to the lien.”
    82 ROW 64.32.070(1).
    18
    No. 77352-6-1/19
    $183,945.09, but Servpro agrees the maximum value of the services provided to
    Woodley’s unit was $6,001    gQ83   And the lien provides no information on its face
    to let another party know the amount owed by each owner or by the association.
    Servpro argues that no reasonable person could look at the lien and
    believe it is intended to encumber Woodley’s individual unit for its face value, but
    it provides no authority for this proposition. And this argument misunderstands
    the legal effect of a lien on real property. A lien encumbers property to secure
    payment of a debt, and encumbrances diminish the value of the property.84
    Unquestionably, then, Servpro’s lien clouds the title to Woodley’s unit for an
    amount far above the usual or specified value of its services benefiting Woodley.
    The lien is clearly excessive for purposes of RCW 60.04.081.
    Attorney Fees
    Both parties request fees. RAP 18.1(a) authorizes an award of attorney
    fees if authorized by law. RCW 60.04.081(4) requires that a court award attorney
    fees to the movant if she shows the lien is frivolous or clearly excessive.
    Because Wood ley demonstrated that Servpro’s lien is clearly excessive, we
    award her attorney fees upon her compliance with RAP 18.1.
    83  See Report of Proceedings (July 14, 2017) at 21 (stating the portion of
    the lien associated with Woodley’s unit is “like $6,000”); Appellant’s Br. at 8 (“In
    total, Servpro billed $6,001 .90 associated with services at Unit 208.”); Appellant’s
    Br. at 13 (“Respondent’s unit total was $6,001 .“); Clerk’s Papers at 195-96
    (itemized invoice showing a total of $6,001.90 in services and taxes for
    Woodley’s unit).
    84 S.D. Deacon, 150 Wn. App. at 89; Robinson v. Khan, 
    89 Wn. App. 418
    ,
    421, 
    948 P.2d 1347
     (1998) (quoting Merlin v. Rodine, 
    32 Wn.2d 757
    , 760, 
    203 P.2d 683
     (1949)).
    19
    No. 77352-6-1/20
    CONCLUSION
    The trial court erred by determining that Servpro’s lien was frivolous and
    releasing it. Although Servpro’s lien may ultimately be invalid and unenforceable,
    the narrow hearing authorized by RCW 60.04.081 does not allow for release of a
    lien based on invalidity alone.85 Accordingly, we reverse the trial court’s ruling
    releasing the lien.
    The court correctly concluded that Servpro’s lien was clearly excessive,
    but the court made no findings of fact about the amount by which the lien was
    excessive.
    Therefore, we reverse the trial court ruling in part, affirm in part, and
    remand for proceedings consistent with this decision.
    WE CONCUR:
    _____       ____     A   /                       __________________________
    —~           /
    85The parties vigorously debate the validity of Servpro’s charges for
    asbestos testing. But on the existing record and briefing, neither party
    establishes that the validity or invalidity of the asbestos charges affects our
    determination that the lien is not frivolous but is clearly excessive for purposes of
    RCW 60.04.081.
    20