John Babbitt, Res. / X-app. v. Kingsgate Ridge Manor Association, App. / X-res. ( 2018 )


Menu:
  •                                                                                        •
    moo..
    IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON                        -
    ••••
    ••
    ••••••
    JOHN BABBITT,
    No. 76555-8-1
    Respondent/Cross-Appellant,
    DIVISION ONE
    V.                                 1
    KINGSGATE RIDGE MANOR
    ASSOCIATION OF APARTMENT                     UNPUBLISHED OPINION
    OWNERS,a Washington Corporation,
    Appellant/Cross-Respondent.
    KINGSGATE RIDGE, a Washington
    Corporation,
    Appellant/Cross-Respondent,
    V.
    TT1 CONSTRUCTION, INC., a
    Washington Corporation,
    Respondent/Cross-Appellant.         FILED: October 29, 2018
    CHUN, J. — Over the course of several years, John Babbitt and his
    corporation, TTI Construction, Inc., performed construction work for Kingsgate
    Ridge Manor Association (KRM). When KRM encountered financial trouble, it
    requested a loan from Babbitt. KRM also needed replacement of a deteriorating
    retaining wall and asked TTI to bid on the project. The parties agreed to and
    executed both a promissory note memorializing the loan and a contract for TTI's
    construction of the wall.
    No. 76555-8-1/2
    KRM defaulted on repayment of the loan and Babbitt sued to enforce the
    note. KRM filed a counterclaim and third party suit against TTI, alleging breach
    of contract due to TTI's failure to obtain proper permits for the wall project. The
    trial court construed the promissory note and wall construction contract
    separately, entering judgment for Babbitt on the promissory note and for KRM on
    the breach of contract claim. All parties filed notices of appeal of a number of the
    trial court's decisions.
    We conclude the trial court properly construed the promissory note and
    wall contract as separate agreements but erred in the decisions to pierce the
    corporate veil and deny postjudgment interest on the entirety of the judgment for
    Babbitt. Therefore, we affirm in part and reverse as to only those two issues.
    I.
    BACKGROUND
    KRM is a condominium owners' association for the Kingsgate Ridge
    Manor Condominium complex in Kirkland, Washington. Babbitt is the sole officer
    and shareholder of TTI, a Washington corporation and licensed and bonded
    construction contractor. TTI specializes in logging, utility, and earthwork,
    including retaining wall construction.
    Beginning in 2009, Babbitt and his contractor corporation& successfully
    bid on and completed several maintenance projects for KRM. While working on
    these projects for KRM, Babbitt observed that the association experienced
    1 Babbitt was previously the sole officer and shareholder of AAA Tree Tech, Inc., which
    was administratively dissolved in 2011.
    2
    No. 76555-8-1/3
    chronic underfunding. To help KRM, Babbitt offered "value engineering" and
    term financing on some of the projects.
    In 2012, KRM encountered significant financial trouble. It was
    underfunded and had outstanding bills. In addition, rocks began falling out of
    one of the retaining walls in its condominium complex and KRM became
    concerned about possible injury to people and property. KRM had attempted to
    obtain a conventional bank loan but was rejected due to a lack of financial
    reserves.
    Having exhausted its options, KRM invited Babbitt to an association board
    meeting in August 2012 to discuss a loan. KRM gave Babbitt a written proposal
    requesting a $600,000 loan at 10 percent fixed interest with monthly payments of
    $11,000. The proposal included a condition that Babbitt's construction company
    submit an estimate for replacement of the complex's failing rock wall, which KRM
    would consider against three other competitive bids.2 Babbitt said he would try to
    help KRM, but indicated he needed time to think about the terms and secure
    funding for the loan. The parties did not execute a written agreement at that
    time.
    Babbitt obtained $150,000 in financial assistance from his uncle. Babbitt
    then issued a $150,000 cashier's check to KRM for immediate cash reserves.
    He paid $56,561.04 towards KRM's homeowners' insurance bill, water district
    bill, sewer bill, and Home Depot bill.
    2 The proposal erroneously identified Babbitt's corporation as AAA Tree Tech rather than
    TTI. AAA Tree Tech had already been administratively dissolved by the time of the proposal.
    3
    No. 76555-8-1/4
    TTI prepared an estimate for replacement of the retaining wall. It
    proposed construction of a Keystone wall for $299,847. The estimate specified
    exclusions for "permits and fees." Two officers of the KRM board approved and
    signed the bid on October 9,2012. Due to winter weather conditions, TTI did not
    begin construction until March 2013.
    In February 2013, Babbitt prepared a promissory note to memorialize the
    loan. Prior to the promissory note, Babbitt had advanced money and paid KRM's
    bills. The promissory note provided for a loan of $600,000, at 10 percent interest
    per annum, with monthly payments of $12,748.23, over a repayment term of five
    years. The terms also included late fees, attorney fees, and an acceleration of
    debt clause. These terms differed from those of KRM's initial loan proposal.
    Babbitt presented the promissory note to the full KRM board on
    February 12, 2013. The board agreed to the terms, and two of its officers signed
    the note. The Board members knew the promissory note contained terms
    differing from the original loan proposal. KRM made its required payments in
    February and March 2013. KRM then requested an indefinite deferral on the
    remaining payments. Babbitt agreed to defer the payments, with the
    understanding interest would continue to accrue during the deferral period.
    TTI began demolition and construction of the retaining wall in March 2013.
    TTI soon discovered site conditions requiring significant changes to the scope of
    work, including a larger wall made up of a different stonework system. After
    consulting with KRM's construction manager, TT1 provided a change order
    4
    No. 76555-8-1/5
    reflecting an increase in cost to $331,332.46, reduced by a $10,000 credit for
    deferred pipe upgrades.
    TTI completed a non-reinforced StoneTerra retaining wall ranging from
    two feet to ten feet tall. Despite the requirements of Kirkland's municipal code,
    neither TTI nor KRM obtained a permit for construction of the wall.
    In April 2014, KRM's new financial manager, Robert Brencic, discovered
    the promissory note while reviewing the association's bills and books to create a
    budget. KRM's board asked Brencic to investigate the promissory note to
    determine the association's obligations. Brencic determined KRM owed Babbitt
    a total of $538,194.40 less the two payments made in February and March 2013.
    Brencic prepared an amortization schedule for payments over five years.
    KRM approved Brencic's findings and asked him to approach Babbitt to
    request waiver of the interest on the loan. Babbitt consented to a five year
    repayment period and waiver of the late fees to date, but refused to waive
    interest. Babbitt also offered the balance of the $600,000, but KRM did not want
    the additional money. KRM agreed to Babbitt's terms but made only four
    payments. Babbitt filed suit for default on the promissory note in September
    2015.
    In March 2016, the trial court granted Babbitt's motion for partial summary
    judgment for $150,000 as recovery for the cash payment to KRM. The trial court,
    however, did not rule on the enforceability of the promissory note and reserved
    judgment on Babbitt's request for attorney fees and costs and prejudgment
    5
    No. 76555-8-1/6
    interest. KRM subsequently satisfied the partial summary judgment, resulting in
    total payments of $228,407.42 on the principal loan amount of $538,194.40.
    KRM asserted a counterclaim against Babbitt and a third party claim
    against III for breach of contract in June 2016. KRM claimed Babbitt and TTI
    failed to obtain the necessary permits to build the wall, failed to inform KRM no
    permits had been obtained, and failed to use or retain engineered drawings to
    prove proper construction of the wall.
    During a six-day bench trial, the parties argued about the enforceability of
    the promissory note, the duty to obtain permits for the wall, and the proper
    construction of the wall. KRM also claimed TTI failed to construct a properly
    engineered wall, which subsequently required remediation and rebuilding.
    According to KRM,the permitting process would have prevented the engineering
    deficiency and the need for reconstruction of the wall. TTI contended the
    approved estimate for the wall construction specifically excluded permits and
    fees, requiring KRM to obtain the proper permits for the project. TTI argued it
    had properly built the wall.
    The trial court enforced the promissory note and awarded judgment,
    prejudgment interest, and attorney fees to Babbitt amounting to $502,216.92.
    The trial court also found TTI had materially breached the construction contract
    by failing to obtain a permit and "building a wall that is in danger of falling." The
    trial court extended personal liability to Babbitt, finding Babbitt "ignored the
    corporate distinction with regard to collecting payment for the wall project. . .
    Mr. Babbitt used the corporate protection of TTI as a shield to avoid personal
    6
    No. 76555-8-1/7
    liability for failure to obtain a permit." Because Babbitt did not reimburse TTI for
    the wall project, the trial court inferred TTI was underfunded and unable to satisfy
    a judgment in the action. As a result of this underfunding, the trial court
    concluded "an injustice will result if the court observes the corporate formalities,
    favoring Mr. Babbitt in the transactions at issue. Therefore, the court will
    disregard the corporate formalities in this case." The court awarded KRM a
    judgment of $258,143(the cost to remediate the wall) without interest or attorney
    fees.
    Both parties filed multiple postjudgment motions including motions for
    reconsideration pertaining to sanctions, attorney fees, and offsets.
    KRM appeals. Babbitt and TTI cross-appeal.
    ANALYSIS
    The trial court heard several days of testimony and issued findings of fact
    and conclusions of law on Babbitt's and KRM's claims. Where the trial court has
    weighed the evidence, the reviewing court's role is limited to determining whether
    substantial evidence supports the findings of fact, and whether those findings
    support the trial court's conclusions of law. Ford Motor Co. v. City of Seattle,
    Exec. Serv. Dep't., 
    160 Wash. 2d 32
    , 56, 
    156 P.3d 185
    (2007). "Substantial
    evidence to support a finding of fact exists where there is sufficient evidence in
    the record ``to persuade a rational, fair-minded person of the truth of the finding."
    Hegwine v. Longview Fibre Co., Inc., 
    162 Wash. 2d 340
    , 353, 172 P.3d 688(2007)
    (quoting In re Estate of Jones, 
    152 Wash. 2d 1
    , 8, 93 P.3d 147(2004)). An
    7
    No. 76555-8-1/8
    appellate court will not substitute its judgment for that of the trial court, reweigh
    the evidence, or gauge witness credibility. In re Marriage of Rockwell, 141 Wn.
    App. 235, 242, 170 P.3d 572(2007).
    In contrast, we review conclusions of law de novo. 
    Hegwine, 162 Wash. 2d at 353
    .
    A.     Separate Agreements or Same Transaction?
    KRM claims the trial court erroneously construed the promissory note and
    wall construction contract as two separate agreements. KRM contends the
    promissory note and construction contract comprised one transaction between
    the parties, which Babbitt/TTI breached by failing to obtain a permit to construct
    the wall. We agree with the trial court's interpretation of the promissory note and
    construction contract as two separately enforceable agreements.
    Whether separate agreements are part of one transaction depends upon
    the intent of the parties as shown by the agreements. Boyd v. Davis, 
    127 Wash. 2d 256
    , 261, 897 P.2d 1239(1995). The trial court must discern the intent of the
    parties. 
    Boyd, 127 Wash. 2d at 261
    . The parties' intent is a question of fact. Don
    L. Cooney, Inc. v. Star Iron & Steel Co., 
    12 Wash. App. 120
    , 122, 
    528 P.2d 487
    (1974). A trial court's findings of fact are reviewed for substantial evidence.
    
    Hegwine, 162 Wash. 2d at 352
    .
    Discerning the parties' intent in this case required the court to examine the
    loan proposal, wall contract, and promissory note. The initial loan proposal
    requested a $600,000 loan with fixed interest and the condition Babbitt's
    construction company submit a competitive bid for the wall project. The proposal
    8
    No. 76555-8-1/9
    made no guarantee Babbitt's company would win the project. The condition only
    required the company submit a competitive bid.
    Babbitt, as representative of TTI, bid on the wall construction project.
    KRM accepted this bid, resulting in the contract between TTI and KRM. This
    contract contained terms related to only the construction of the wall and did not
    reference the proposal or loan from Babbitt.
    Several months after the proposal and wall contract, Babbitt memorialized
    his loan to KRM in the promissory note. KRM board members reviewed and
    signed the promissory note, which became a valid contract between KRM and
    Babbitt. KRM argues the promissory note was a modification of the contract
    formed by its proposal. But in this case, the promissory note is a negotiable
    instrument separate from the wall contract or the proposal.
    A negotiable instrument is "an unconditional promise or order to pay a
    fixed amount of money." RCW 62A.3-104(a). A promise to pay is unconditional
    "unless it contains an express condition to payment and states that(1)the
    promise or order to pay is subject to or governed by another writing or(2) rights
    or obligations with respect to the promise or order to pay are stated in another
    writing." Alpacas of America, LLC v. Groome, 
    179 Wash. App. 391
    , 396-97, 317
    P.3d 1103(2014)(citing RCW 62A.3-106(a)).
    Here, the text of the promissory note demonstrates KRM's unconditional
    promise to pay Babbitt. The promissory note makes no reference to the wall
    construction project or any other agreement. As a result, the promissory note is
    a negotiable instrument establishing a "separate promise" independent of the
    9
    No. 76555-8-1/10
    wall contract, governing only the financial relationship between Babbitt and KRM.
    See Alpacas of 
    America, 179 Wash. App. at 399
    .
    Additionally, the construction contract and the promissory note were
    prepared months apart and without contingencies or conditions. Again, the two
    agreements make no reference to, or mention of, the other. KRM needed the
    loan from Babbitt regardless of whether TTI or another corporation built the wall.
    Thus, the facts point toward the parties' intention to establish separate
    agreements on the two distinct issues—the loan and the wall construction.
    Based on the documents and the evidence presented, substantial
    evidence supports the trial court's separate construction of the agreements. The
    trial court properly interpreted the promissory note and accepted construction
    estimate as two distinct, valid contracts governing the relationships between the
    various parties.
    B.     Affirmative Defenses
    At trial, in response to Babbitt's claim on the promissory note, KRM
    pursued the affirmative defenses of mistake, misrepresentation, and fraud,
    claiming it would never have entered the transaction knowing the contractor
    would not obtain permits. Because these defenses are inapplicable to the
    promissory note claim, the trial court properly rejected them.
    KRM's affirmative defenses depend in large part on its one-contract
    theory. That is, if the promissory note and wall are part of one agreement, then
    success on the affirmative defenses would theoretically allow KRM to avoid
    liability on the note. But, under the proper interpretation of the promissory note
    10
    No. 76555-8-1/11
    and construction contracts as two separate agreements, these affirmative
    defenses are inapposite.
    On appeal, KRM argues that the affirmative defenses apply solely to the
    promissory note, alleging Babbitt committed fraud or misrepresentation by writing
    the loan for an amount greater than KRM actually borrowed and included terms
    beyond those in the initial proposal. But the KRM Board reviewed the promissory
    note and approved the terms, despite the differences. KRM voluntarily signed
    the agreement and cannot now claim ignorance of its terms. See Michak v.
    Transnation Title Ins. Co., 
    148 Wash. 2d 788
    , 799,64 P.3d 22(2003). As a result,
    the trial court properly dismissed the affirmative defenses of mistake,
    misrepresentation, and fraud.
    C.     Attorney Fees
    1.     Fee Award to Babbitt But Not KRM
    KRM contends the trial court erroneously awarded attorney fees to Babbitt
    under the terms of the promissory note or should have awarded fees to both
    sides. Based on the terms of the two separate contracts, the trial court properly
    awarded fees only to Babbitt.
    Attorney fees and costs may be recovered only when authorized by
    private agreement of the parties, statute, or a recognized ground in equity. Pa.
    Life Ins. Co. v. Dep't of Emp't Sec., 
    97 Wash. 2d 412
    , 413, 645 P.2d 693(1982).
    RCW 4.84.330 provides for award of attorney fees to the prevailing party in a
    contract dispute. The prevailing party "is one that receives an affirmative
    judgment in its favor." Newport Yacht Basin Ass'n of Condo. Owners v. Supreme
    11
    No. 76555-8-1/12
    NW Inc., 
    168 Wash. App. 86
    , 98, 285 P.3d 70(2012). For a court to award
    attorney fees, the prevailing party must substantially prevail but does not need to
    have succeeded on its entire claim. Newport Yacht 
    Basin, 168 Wash. App. at 98
    .
    A defendant can recover as a prevailing party by successfully defending against
    a plaintiffs claims. Newport Yacht 
    Basin, 168 Wash. App. at 99
    .
    A trial court's determination of whether a party is entitled to attorney fees
    is an issue of law reviewed de novo. Bopuch v. Landover Corp., 
    153 Wash. App. 595
    , 615, 224 P.3d 795(2009).
    Here, the promissory note contained a provision for KRM to pay
    "reasonable attorney fees... for collection of this Note upon default." According
    to the trial court, Babbitt prevailed on the enforcement of the promissory note. As
    a result, this term in the note authorized the award of attorney fees to Babbitt for
    the expenses required to obtain repayment. Thus, the trial court properly
    awarded attorney fees and costs to Babbitt.
    In contrast, the wall contract does not include a provision for attorney fees.
    Therefore, KRM had no contractually established means for recovering fees in its
    successful claim for breach of the construction contract.3 The trial court properly
    declined to awarded attorney fees and costs to KRM.
    3 In its reply brief, KRM argues that it should recover attorney fees under the two-contract
    theory because it prevailed when Babbitt recovered only one-third of his requested recovery
    under the promissory note. KRM raises this argument for the first time in the reply brief. We will
    not consider issues raised for the first time in a reply brief. RAP 10.3(c); Ainsworth v. Progressive
    Cas. Ins. Co., 
    180 Wash. App. 52
    , 78 n.20, 322 P.3d 6(2014).
    12
    No. 76555-8-1/13
    2.      Specific Attorney Fees
    KRM assigns error to the trial court's award of specific attorney fees.
    When authorized by contract, the determination of a reasonable attorney fee
    award is a matter within the trial court's discretion. Noble v. Safe Harbor Family
    Pres. Trust, 
    167 Wash. 2d 11
    , 15, 216 P.3d 1007(2009). "In order to reverse an
    attorney fee award made pursuant to a statute or contract, an appellate court
    must find the trial court manifestly abused its discretion." 
    Noble, 167 Wash. 2d at 17
    . The party challenging the fee award bears the burden of demonstrating the
    award was clearly untenable or manifestly unreasonable. Washington State
    Communication Access Project v. Regal Cinemas, Inc., 
    173 Wash. App. 174
    , 219,
    293 P.3d 413(2013).
    KRM contends the trial court erred by awarding fees for duplicative,
    unreasonable, and unproductive work. Babbitt requested compensation for
    380.10 hours of attorney work. The trial court found 264 hours were reasonably
    expended by counsel and awarded attorney fees based on that number. The
    trial court provided a list of all the reductions due to duplicative, inaccurate,
    excessive, unsuccessful, or unproductive work. KRM disagrees with the
    substantial reduction in hours, claiming further reduction was required. But
    nothing in the record demonstrates manifest abuse of discretion. Therefore, we
    will not disturb the attorney fees award on appeal.
    13
    No. 76555-8-1/14
    D.     Chapter 64.50 RCW Notice Requirements
    On cross-appeal, TT1 claims the trial court should have dismissed KRM's
    construction defect claim for failure to comply with the required notice set forth in
    RCW 64.050.030 and 64.050.040(2)(a). KRM counters its failure to notify was
    not fatal to the claim. We agree with KRM.
    Chapter 64.50 RCW sets forth notice requirements for construction defect
    claims. Construction professionals must "provide notice to each homeowner
    upon entering into a contract for sale, construction, or substantial remodel of a
    residence, of the construction professional's right to offer to cure construction
    defects before a homeowner may commence litigation against the construction
    professional." RCW 64.50.050(1). The statute provides, if the contractor does
    not give this notice, the chapter shall not bar a homeowner's lawsuit. RCW
    64.50.050(3).
    Chapter 64.50 RCW establishes additional responsibilities for plaintiff
    homeowners' construction defect cases. Homeowners must provide at least
    45 days' notice to a construction professional prior to filing an action.
    RCW 64.50.020(1). For condominium construction defect claims, the board of
    directors for the homeowners' association must mail or deliver written notice of
    the commencement of a construction defect action to each homeowner prior to
    service of the summons or complaint on a defendant. RCW 64.50.040(1)(2)(a).
    Additionally, the plaintiff in a construction defect action must file with the court,
    and serve the defendant with, a list of known construction defects within thirty
    14
    No. 76555-8-1/15
    days after commencement of the action. RCW 64.50.030(1),(2). This list must
    contain a description of the allegedly defective construction. RCW 64.50.030(2).
    Only one case has interpreted the notice requirements in chapter 64.50
    RCW. In Lakemont Ridge Homeowners Assoc. v. Lakemont Ridge Limited
    P'ship, 
    156 Wash. 2d 696
    , 131 P.3d 905(2006), the Washington Supreme Court
    considered the interplay between RCW 64.50.020 and RCW 64.50.050. In
    Lakemont, the condominiums at issue were constructed prior to the enactment of
    chapter 64.50 RCW,and the construction professional did not provide the
    homeowners with notice of the prelitigation requirement of notice and opportunity
    to 
    cure. 156 Wash. 2d at 697-98
    . The homeowners' association brought a
    construction defect claim after enactment of chapter 64.50 RCW, but failed to
    comply with notice to the construction professional as required by RCW
    64.50.020(1). 
    Lakemont, 156 Wash. 2d at 697-98
    .
    The court concluded the homeowners' association's failure to give notice
    was not fatal to the construction defect claim, because the prelitigation notice
    requirement "became operative only where the construction professionals have
    given prior notice to the homeowner of the requirement." 
    Lakemont, 156 Wash. 2d at 698
    . If the construction professional provides notice of the prelitigation notice
    requirement, then the homeowner must give notice of the alleged defects and
    comply with the requirements of chapter 64.50 RCW. 
    Lakemont, 156 Wash. 2d at 703
    . If the construction professional fails to give notice of the prelitigation notice
    requirement, then RCW 64.50.050(3) explicitly states this failure does not bar a
    claim. 
    Lakemont, 156 Wash. 2d at 703
    . This interpretation serves the express
    15
    No. 76555-8-1/16
    purpose of "preserving adequate rights and remedies for property owners."
    
    Lakemont, 156 Wash. 2d at 704
    .
    TTI correctly points out that Lakemont examined different notice
    provisions. TTI relies on RCW 64.50.030 and 64.50.040 mandating prelitigation
    notice to condominium owners and postfiling notice of defects rather than
    RCW 64.50.020 and 64.50.050. But the language of RCW 64.50.050(3) places
    the burden on the construction professional to give notice of the prelitigation
    requirements to trigger homeowner duties under the statute. The statute
    provides, "[t]his chapter shall not preclude or bar any action if notice is not given
    to the homeowners as required by this section." RCW 64.50.050(3)(emphasis
    added). Thus, a homeowner's failure to comply with any of the requirements of
    chapter 64.50 RCW will not preclude an action if the construction professional did
    not give notice at the time of contracting.
    TTI does not claim to have fulfilled the notice obligation of
    RCW 64.50.050. Because TTI did not give notice as required, KRM's failure to
    comply with RCW 64.50.030 and 64.50.040 was not fatal to the breach of
    contract claim.
    Even if KRM was required to comply with the statutory obligations, we do
    not believe dismissal would be a proper remedy for failure to fulfill the notice
    16
    No. 76555-8-1/17
    requirements of RCW 64.50.030.4 The language of RCW 64.50.030 indicates
    the court has discretion over the filing period for the defect list.5 RCW 64.50.
    030(2) requires filing and service of a description of the construction defects
    "within thirty days after the commencement of the action or within such longer
    period as the court in its discretion may allow." This discretion with regard to the
    allowable time frame of RCW 64.50.030 suggests the legislature did not intend
    strict compliance.6 Further, remedies for noncompliance may include
    enforcement at the trial court level, akin to an order to compel discovery. As
    such, mandatory dismissal of the claims would not be the appropriate remedy for
    failure to provide notice under these provisions.
    Whether RCW 64.50.00(3) or the discretion permitted under
    RCW 64.50.030 applies, the trial court's decision to deny dismissal for failure to
    comply with the statute was not error.
    4 We note TTI/Babbitt's standing is questionable on the issue of KRM's failure to provide
    notice to the individual homeowners under RCW 64.50.040. A party has standing if it is arguably
    within the zone of interest to be protected by the statute and has suffered an injury in fact.
    Branson v. Port of Seattle, 
    152 Wash. 2d 862
    , 875-876, 101 P.3d 67(2004). RCW 64.50.040
    governs the board of directors' responsibility to individual homeowners. Thus, TTI/Babbitt is
    arguably not within the zone of interest protected by that section of chapter 64.50 RCW. Neither
    party raised this issue on appeal.
    5 Courts do not construe unambiguous statutes. Davis v. State ex rel. Dep't of Licensing,
    
    137 Wash. 2d 957
    , 963, 977 P.3d 554(1999). "If the statute's meaning is plain on its face, then
    courts must give effect to its plain meaning as an expression of what the Legislature intended."
    State v. J.M., 
    144 Wash. 2d 472
    , 480, 28 P.3d 720(2001). In the case of ambiguity, however, the
    court's fundamental objective is to ascertain and carry out the legislative intent. 
    J.M., 144 Wash. 2d at 480
    .
    6 The legislature included mandatory dismissal as the remedy elsewhere in chaptef 64.50
    RCW. RCW 64.50.020(6) provides that "[a]ny action commenced by a claimant prior to
    compliance with the requirements of this section shall be subject to dismissal without prejudice,
    and may not be recommenced until the claimant has complied with the requirements of this
    section." This section pertains to the required 45 days' notice and opportunity to cure provided by
    the homeowner to the construction professional. "This section" refers only to RCW 64.50.020,
    rather than the entirety of chapter 64.50 RCW. The legislature clearly included mandatory
    dismissal to ensure strict compliance.
    17
    No. 76555-8-1/18
    E. Disregard of the Corporate Form
    The trial court pierced the corporate veil after concluding injustice would
    otherwise result due to its belief Babbitt intentionally underfunded TTI and
    manipulated the corporate form to his benefit. Babbitt contends the trial court
    improperly disregarded the corporate entity without evidence of the requisite
    abuse of the corporate form. We agree.
    The doctrine of disregard of the corporate entity, or piercing the veil, is an
    equitable remedy imposed in exceptional circumstances where recognition of the
    corporate form would aid in perpetrating a fraud or result in a manifest injustice.
    Truckweld Equip. Co., Inc. v. Olson, 
    26 Wash. App. 638
    , 643-44, 
    618 P.2d 1017
    (1980). To pierce the veil,(1) the corporate form must have been intentionally
    used to violate or evade a duty, and (2) disregard must be necessary to prevent
    unjustified loss to the injured party. Meisel v. M&N Modern Hydraulic Press Co.,
    97 Wn.2d 403,410,645 P.2d 689(1982). Regarding the first element, abuse of
    the corporate form typically involves fraud, misrepresentation, or some form of
    manipulation to the entity's benefit and the creditor's detriment. 
    Meisel, 97 Wash. 2d at 410
    . Regarding the second element, the "wrongful corporate activities
    must actually harm the party seeking relief so that disregard is necessary."
    
    Meisel, 97 Wash. 2d at 410
    . "Intentional misconduct must be the cause of the harm
    that is avoided by the disregard." 
    Meisel, 97 Wash. 2d at 410
    . The corporation
    should not be disregarded solely because its assets are not sufficient to meet its
    obligations. 
    Meisel, 97 Wash. 2d at 411
    ; Norhawk Invest., Inc. v. Subway Sandwich
    Shops, Inc., 
    61 Wash. App. 395
    , 399-400, 
    811 P.2d 221
    (1991).
    18
    No. 76555-8-1/19
    The alter ego doctrine provides,"where one entity ``so dominates and
    controls a corporation that such corporation is [the entity's] alter ego, a court is
    justified in piercing the veil of corporate entity and holding that the corporation
    and private person are one and the same." In re Rapid Settlements, Ltd. v.
    Symetra Life Ins. Co, 
    166 Wash. App. 683
    , 692, 271 P.3d 925(2012)(quoting
    Standard Fire Ins. Co. v. Blakeslee, 
    54 Wash. App. 1
    , 5, 
    771 P.2d 1172
    (1989)).
    The doctrine is most commonly invoked "to impose personal liability upon
    corporate officers for fraud committed by a corporation." Standard Fire, 54 Wn.
    App. at 5-6. The trial court will find a corporate entity is one and the same with
    another entity "when the corporate form has been intentionally used to violate or
    evade a duty." In re Rapid 
    Settlements, 166 Wash. App. at 692
    .
    The issue of whether the corporate form should be disregarded is a
    question of fact. Norhawk Invest., 
    Inc., 61 Wash. App. at 398
    . A trial court's
    findings of fact are reviewed for substantial evidence. 
    Heciwine, 162 Wash. 2d at 352
    .
    Even where the entities are alter egos, piercing the corporate veil requires
    misconduct. See In re Rapid 
    Settlements, 166 Wash. App. at 692
    . Here, the trial
    court made no findings related to fraud, misrepresentation, or corporate
    misconduct.7 Without evidence of such behavior, Babbitt's conduct did not rise
    to the level of misconduct generally required to pierce the corporate veil.
    7 In its findings of fact about the breach of promissory note, the trial court stated, "[t]here
    was no evidence that Mr. Babbitt, on behalf of his corporation, made any misrepresentations or
    fraudulent inducements to persuade KRM to accept his bid."
    19
    No. 76555-8-1/20
    Instead of fraud or misrepresentation, the trial court grounded its rationale
    for corporate disregard on TTI's presumed undercapitalization. But based on
    Meisel and Norhawk Investments, undercapitalization alone does not amount to
    misconduct requiring disregard of the corporate form. "The absence of an
    adequate remedy alone does not establish corporate misconduct." 
    Meisel, 97 Wash. 2d at 411
    . Norhawk Investments specifically states, "the separate existence
    of a corporation should not be disregarded solely because its assets are not
    sufficient to discharge its 
    obligations." 61 Wash. App. at 399-400
    . Therefore, the
    trial court's reliance on TTI's presumed undercapitalization does not support
    corporate disregard.
    The trial court pierced the corporate veil based only on the lack of
    corporate distinction and presumed undercapitalization of TTI, without evidence
    TTI attempted to violate or evade a duty to KRM. Because TTI's conduct did not
    rise to the level of fraud, misconduct, or manipulation to benefit TTI, the trial court
    erred by disregarding the corporate entity and holding Babbitt personally liable.
    Therefore, we reverse on this issue.
    F. Postjudgment Interest
    Babbitt argues the trial court erred by failing to award postjudgment
    interest on the prejudgment interest awarded on the principal judgment. KRM
    contends RCW 4.56.110 authorizes but does not require postjudgment interest
    on a judgment with both principal and interest. Due to the statutory requirement
    of postjudgment interest on the entirety of the judgment, the trial court should
    have awarded postjudgment interest on the prejudgment interest.
    20
    No. 76555-8-1/21
    RCW 4.56.110(1) allows for postjudgment interest for judgments based on
    written contracts at the rate specified in the contract. Sharbano v. Universal
    Underwriters, Ins. Co., 
    158 Wash. App. 963
    , 971, 247 P.3d 430(2010). "When
    prejudgment interest is awarded, it is added to the judgment and becomes part of
    the judgment principal." State v. Trask, 
    98 Wash. App. 690
    , 695-96, 
    990 P.2d 976
    (2000). Postjudgment interest is calculated based on this new judgment
    principal. 
    Sharbano, 158 Wash. App. at 971
    . The judgment then accrues interest at
    the stipulated rate until paid in full. 
    Trask, 98 Wash. App. at 696
    ; RCW 4.56.110(1).
    Postjudgment interest is mandatory under RCW 4.56.110. TJ Landco
    LLC. v. Harley C. Douglass, Inc., 
    186 Wash. App. 249
    , 256, 346 P.3d 777(2015).
    "Consequently, awards of postjudgment interest are matters of law that are
    reviewed de novo." TJ 
    Landco, 186 Wash. App. at 256
    .
    Here, the trial court awarded Babbitt a principal judgment of $309,786.98
    and prejudgment interest of $187,149.94. The judgment provided an interest
    rate of 10 percent for both the principal judgment and attorney fees and costs,
    but did not establish an interest rate for the prejudgment interest.
    Based on Sharbano and Trask, the prejudgment interest merges with the
    principal judgment to become the new total judgment. This new total judgment
    serves as the basis for calculating postjudgment interest.
    KRM contends RCW 4.56.110 does not require postjudgment interest on
    prejudgment interest awards based on additional language in Sharbano that the
    statute, "authorizes a trial court to calculate postjudgment interest on a judgment
    that already contains within it both principal and interest, especially where a
    21
    No. 76555-8-1/22
    written underlying contract so 
    provides." 158 Wash. App. at 971
    . But this ignores
    the language of RCW 4.56.110, which states "interest on judgments shall
    accrue." The use of "shall" imposes a mandatory requirement unless a contrary
    legislative intent is apparent. Erection Co. v. Dep't of Labor and Indus., 
    121 Wash. 2d 513
    , 518, 852 P.2d 288(1993). Thus, the award of postjudgment interest
    is not discretionary.
    Postjudgment interest accrues on the principal judgment. An award of
    prejudgment interest combines with the original principal amount to become the
    total principal for the purposes of postjudgment interest. As a result, Babbitt was
    entitled to postjudgment interest on the prejudgment interest award. The trial
    court's failure to award interest on this prejudgment interest was error requiring
    reversal and recalculation.
    G. Attorney Fees on Appeal
    Babbitt and KRM both request fees on appeal.
    Babbitt requests fees on appeal based on the attorney fees provision of
    the promissory note. As noted above, the promissory note included a term for
    "reasonable attorney fees...for collection of this Note upon default." This term
    applies to appellate proceedings as well. "A provision in a contract providing for
    the payment of attorneys' fees in an action to collect any payment due under the
    contract includes both fees necessary for trial and those incurred on appeal as
    well." Granite Equip. Leasing Corp. v. Hutton, 
    84 Wash. 2d 320
    , 327, 
    525 P.2d 223
    (1974). As the prevailing party in this appeal pertaining to the collection of the
    Note on default, Babbitt is entitled to attorney fees and costs on appeal.
    22
    No. 76555-8-1/23
    Under RAP 18.1(b), the party must devote a section of its opening brief to
    a request for attorney fees and expenses. KRM failed to request attorney fees
    on appeal in its opening brief, waiting until the reply brief to raise the issue. As a
    result, the request does not comply with RAP 18.1(b). Furthermore, KRM lacks a
    contractual basis to recover attorney fees and does not prevail on appeal.
    Therefore, we decline to award fees on appeal to KRM.
    We affirm in part, reverse in part, and remand for further proceedings
    consistent with this opinion.
    Cl......,.., 1.
    WE CONCUR:
    vctiv6292-1 cY
    23