Nova Contracting, Inc. v. City Of Olympia ( 2017 )


Menu:
  •                                                                                                Filed
    Washington State
    Court of Appeals
    Division Two
    April 18, 2017
    IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    DIVISION II
    NOVA CONTRACTING, INC., a Washington                                No. 48644-0-II
    Corporation,
    Appellant,
    v.                                                    UNPUBLISHED OPINION
    CITY OF OLYMPIA, a Washington
    Municipal Corporation,
    Respondent.
    MAXA, A.C.J. – Nova Contracting, Inc. appeals the trial court’s summary judgment
    dismissal of its claim that the City of Olympia breached the implied duty of good faith and fair
    dealing in its administration and termination of a construction contract between the City and
    Nova. Nova also appeals the trial court’s award of liquidated damages to the City on the City’s
    counterclaim for breach of contract.
    We hold that the trial court erred in granting summary judgment in favor of the City on
    Nova’s duty of good faith and fair dealing claim because Nova presented sufficient evidence to
    create a genuine issue of material fact that the City prevented Nova from attaining its justified
    expectations under the contract. As a result, we also vacate the trial court’s award of liquidated
    damages and reasonable attorney fees to the City. However, because the liquidated damages
    issue may arise again on remand, we consider the enforceability of the liquidated damages
    No. 48644-0-II
    clause. We hold that the trial court did not err in ruling on summary judgment that the liquidated
    damages clause is enforceable if the City prevails on its breach of contract claim on remand.
    Accordingly, we reverse the trial court’s summary judgment dismissal of Nova’s claim
    for breach of the duty of good faith and fair dealing, vacate the trial court’s award of liquidated
    damages and reasonable attorney fees to the City, and remand for further proceedings consistent
    with this opinion.
    FACTS
    Project Award
    In early 2014, the City published an invitation for bids to replace a culvert that conveyed
    a creek underneath a paved bike trail. In May 2014, the City accepted Nova’s bid, although
    Nova alleges that some City staff wanted another contractor to get the bid and were looking for
    reasons to reject the bid. The parties executed a contract that incorporated the project’s plans
    and specifications, Nova’s bid proposal, and the Washington State Standard Specifications for
    Road, Bridge, and Municipal Construction.1
    The contract required that Nova send several submittals for the City’s engineer to
    approve before construction could begin, including a detailed description of the work, a bypass
    pumping plan, a work area excavation plan, and an access and haul route plan. The contract also
    required the City’s engineer to approve other submittals before the work outlined in those
    submittals could proceed. The contract provided that the City would review these submittals,
    1
    The record does not contain the entire contract, including many of the project-specific plans
    and specifications. In addition, on summary judgment the parties submitted only portions of the
    standard specifications.
    2
    No. 48644-0-II
    that the City’s decisions would be final, and that Nova would bear all risk and cost of work
    delays caused by non-approval of any submittals.
    Under the contract, Nova was required to complete the work within 45 working days
    after the City issued a notice to proceed. The contract stated that Nova would be liable for
    liquidated damages of $939.46 per day if it failed to complete the project on time.
    Problems with Submittal Process
    On August 11, 2014, the City issued a notice to proceed. Nova’s initial schedule
    indicated that Nova intended to mobilize to the construction site on August 12. But Nova could
    not mobilize as scheduled because of delays in the submission and approval of Nova’s
    submittals. On August 19, the City sent Nova an email stating that it was clear that Nova would
    be unable to meet the project schedule and requesting a revised schedule.
    The parties continued to have problems as the City rejected many submittals, in some
    cases rejecting re-submittals as well. Nova claimed that the City had been improperly rejecting
    submittals and that it could not meet the project schedule as a result. The City expressed
    concerns about the lack of sufficient information in several of Nova’s submittals. By September,
    key submittals remained unapproved. Nova provided several submittals on September 4 that the
    City rejected.
    Notice of Default and Termination
    On September 4, the City sent Nova a letter stating that the City considered Nova to be in
    default on the contract for several reasons, including: (1) Nova’s failure to mobilize to the site,
    (2) the lapse of 17 out of 45 total working days, (3) Nova’s failure to provide an updated project
    schedule, (4) Nova’s repeated failure to provide satisfactory versions of several submittals, and
    3
    No. 48644-0-II
    (5) the City’s concern that Nova would not complete the project within the time remaining. The
    letter concluded that the cumulative effect of these problems constituted a material default under
    the contract. The City stated that Nova had 15 days to cure the default by providing acceptable
    submittals, submitting an updated schedule, and showing that the project could be completed in
    the original time frame.
    Also on September 4, Nova mobilized to the work site. But on September 8, the City
    delivered a stop work order to the site. The City’s reasons for the stop work order included
    Nova’s failure to notify the City before beginning any work, as required by the contract; Nova’s
    attempts to gain access to the project site and its entry to the site without prior approval; and
    placement of equipment on the site without approval for use of that equipment.
    Nova expressed surprise at the City’s action. Nova pointed out that the City’s first
    ground for default was Nova’s failure to mobilize to the site, but that the City simultaneously
    demanded that Nova remove its equipment from the site. In multiple letters sent on September 9,
    Nova protested the default and responded in detail to the City’s grounds for default.
    On September 18, the City rejected Nova’s protest. The City stated that the contract
    would be terminated unless Nova met the requirements in the September 4 default letter by
    September 19. In another letter dated September 18, the City responded to Nova’s protest of the
    default. On September 19, Nova sent a lengthy letter contesting the City’s grounds for
    terminating the contract.
    On September 24, the City sent Nova a letter terminating the contract. The letter asserted
    that Nova had “chosen to assert protests and excuses rather than provide the requested
    documents and assurances.” Clerk’s Papers (CP) at 215.
    4
    No. 48644-0-II
    Nova’s Lawsuit
    Nova filed a lawsuit against the City, asserting that the City had breached the parties’
    contract. Among other allegations, Nova claimed that the City’s handling of Nova’s submittals
    both imposed requirements that were not part of the project’s specifications and delayed Nova’s
    performance so that the project could not be timely completed. The City counterclaimed that
    Nova had breached the contract by failing to complete the project and therefore was liable for
    liquidated damages.
    The City moved for summary judgment, arguing that it properly terminated the contract
    for default, that Nova was liable for liquidated damages for failing to complete the project on
    time, and that Nova was not entitled to recover damages. The City agreed to limit its claim for
    liquidated damages to the amount accumulated over the 45 days allowed for performance.
    Nova argued that questions of fact existed as to why the project was not completed and
    that the City breached its duty of good faith and fair dealing and engaged in other conduct that
    constituted a breach of contract. Nova also argued that the contract’s liquidated damages clause
    should not be enforced. The trial court granted the City’s motion, dismissed Nova’s claims, and
    awarded the City liquidated damages of $42,140.70. The trial court also awarded attorney fees
    to the City under RCW 39.04.240.
    Nova appeals the trial court’s summary judgment order.
    ANALYSIS
    A.     STANDARD OF REVIEW
    We review summary judgment orders de novo. Keck v. Collins, 
    184 Wn.2d 358
    , 370,
    
    357 P.3d 1080
     (2015). On summary judgment, we construe all evidence and reasonable
    5
    No. 48644-0-II
    inferences in favor of the nonmoving party.2 
    Id.
     Summary judgment is appropriate when the
    record shows “no genuine issue as to any material fact” and “the moving party is entitled to a
    judgment as a matter of law.” CR 56(c); Keck, 
    184 Wn.2d at 370
    . An issue of fact is genuine if
    the evidence would be sufficient for a reasonable jury to find in favor of the nonmoving party.
    Keck, 
    184 Wn.2d at 370
    . Summary judgment is appropriate if reasonable minds can reach only
    one conclusion on an issue of fact. Sutton v. Tacoma Sch. Dist. No. 10, 
    180 Wn. App. 859
    , 865,
    
    324 P.3d 763
     (2014). To avoid summary judgment, the nonmoving party must set forth specific
    facts that rebut the moving party’s contentions and show a genuine issue of material fact. Elcon
    Constr., Inc. v. E. Wash. Univ., 
    174 Wn.2d 157
    , 169, 
    273 P.3d 965
     (2012).
    B.     DUTY OF GOOD FAITH AND FAIR DEALING
    Nova argues that questions of fact exist concerning whether the City breached the duty of
    good faith and fair dealing when considering Nova’s submittals. Nova specifically argues that
    the City prevented Nova from attaining its justified expectations under the contract.3 We agree.
    1.    Legal Principles
    Under Washington law, every contract is subject to an implied duty of good faith and fair
    dealing. Rekhter v. Dep’t of Soc. & Health Servs., 
    180 Wn.2d 102
    , 112, 
    323 P.3d 1036
     (2014).
    This duty obligates the parties to a contract to cooperate with each other so that each party may
    2
    Nova argues that the trial court applied incorrect standards for evaluating the evidence on
    summary judgment, weighing the evidence instead of viewing it in the light most favorable to
    Nova. But because our review is de novo, how the trial court evaluated the evidence is
    immaterial to our analysis.
    3
    Initially, the City argues that Nova waived all claims relating to the rejection of its submittals
    because Nova failed to submit a timely protest under section 1-04.5 of the contract. We
    disagree. Although Nova may have waived claims for the cost of work performed under the
    contract, section 1-04.5 does not apply to expectancy and consequential damages.
    6
    No. 48644-0-II
    benefit from full performance. 
    Id.
     The duty of good faith and fair dealing applies to public
    agencies. Id. at 114.
    The duty of good faith and fair dealing “exists only in relation to performance of a
    specific contract term.” Badgett v. Sec. State Bank, 
    116 Wn.2d 563
    , 570, 
    807 P.2d 356
     (1991).
    As a result, the duty “cannot add or contradict express contract terms and does not impose a free-
    floating obligation of good faith on the parties.” Rekhter, 180 Wn.2d at 113. And a party is
    entitled to require performance of a contract according to its terms. Badgett, 
    116 Wn.2d at 570
    .
    The duty “requires only that the parties perform in good faith the obligations imposed by their
    agreement.” 
    Id. at 569
    .4
    To identify whether a breach of the duty of good faith and fair dealing has occurred,
    Washington courts have looked to a party’s justified expectations under their contract. The
    Supreme Court has stated that “[t]he duty of good faith requires ‘faithfulness to an agreed
    common purpose and consistency with the justified expectations of the other party.’ ” Edmonson
    v. Popchoi, 
    172 Wn.2d 272
    , 280, 
    256 P.3d 1223
     (2011) (quoting RESTATEMENT (SECOND) OF
    CONTRACTS § 205 cmt. a (AM. LAW INST. 1981)). Similarly, the court in Rekhter approved a jury
    instruction stating that a plaintiff asserting a duty of good faith claim must prove that the
    defendant “acted in a manner that prevented the [plaintiff] from attaining his or her reasonable
    expectations under the contract.” 180 Wn.2d at 119.5
    4
    However, a violation of a contractual term is not required in order to find a violation of the duty
    of good faith and fair dealing. Rekhter, 180 Wn.2d at 111-12.
    5
    Nova argues that a party breaches the duty of good faith and fair dealing by exercising its
    discretion unreasonably. The City argues that its actions should be reviewed under an arbitrary
    and capricious standard. But Washington law does not support either standard of liability.
    7
    No. 48644-0-II
    But because a party’s justified expectations depend on the contractual terms at issue, the
    particular requirements of the duty of good faith and fair dealing change with the context. See
    RESTATEMENT § 205 cmt. a (“The phrase ‘good faith’ is used in a variety of contexts, and its
    meaning varies somewhat with the context.”). It therefore is difficult to define the duty of good
    faith in terms that are both precise and generally applicable. See Best v. U.S. Nat’l Bank of Or.,
    
    303 Or. 557
    , 
    739 P.2d 554
    , 557 (1987).
    The comments to Restatement § 205 provide some guidance by listing examples of
    improper conduct. Comment a notes that types of conduct can be characterized as bad faith if
    they “violate community standards of decency, fairness or reasonableness.” RESTATEMENT
    § 205 cmt. a. Further, comment d states:
    Subterfuges and evasions violate the obligation of good faith in performance even
    though the actor believes his conduct to be justified. But the obligation goes
    further: bad faith may be overt or may consist of inaction, and fair dealing may
    require more than honesty. A complete catalogue of types of bad faith is
    impossible, but the following types are among those which have been recognized
    in judicial decisions: evasion of the spirit of the bargain, lack of diligence and
    slacking off, willful rendering of imperfect performance, abuse of a power to
    specify terms, and interference with or failure to cooperate in the other party’s
    performance.
    Id. cmt. d. The Restatement reaffirms that whether a defendant has violated the duty of good
    faith and fair dealing requires courts to identify whether the defendant has violated a plaintiff’s
    justified expectations under the contract.
    Significantly, the Supreme Court cases and the Restatement commentary do not suggest
    that the defendant must intend to harm the plaintiff. The Ninth Circuit reached the same
    conclusion when applying Washington law in Scribner v. Worldcom, Inc., 
    249 F.3d 902
     (9th Cir.
    2001), a case cited in Rekhter, 180 Wn.2d at 113. The court in Scribner stated that a breach of
    8
    No. 48644-0-II
    the duty of good faith and fair dealing does not require that the defendant acted with “affirmative
    malice” toward the plaintiff “or even that [the defendant] knew its decisions were inappropriate
    when it made them.” 
    249 F.3d at 909
    . The court rejected the idea that “dishonesty or an
    unlawful purpose is a necessary predicate to proving bad faith.” 
    Id. at 910
    .
    2.    Application of Good Faith Duty
    The City argues that the duty of good faith does not apply to its consideration of Nova’s
    submittals. We disagree.
    The duty of good faith and fair dealing applies when a party has discretionary authority to
    determine a contract term. Rekhter, 180 Wn.2d at 113. The party must act in good faith in
    setting and performing that term. Id. at 115. On the other hand, “if a contract gives a party
    unconditional authority to determine a term, there is no duty of good faith and fair dealing.” Id.
    at 119-20 (emphasis added).
    The City argues that under Rekhter, it had no duty of good faith because it had
    unconditional authority to determine whether to accept or reject Nova’s submittals. The City
    points to section 1-05.1 of the contract, which stated that the City engineer’s “decisions will be
    final on all questions,” including the project’s rate of progress, interpretation of project plans and
    specifications, and termination of the contract for default. CP at 92. The City asserts that this
    provision gave it total authority regarding Nova’s submittals and therefore the duty of good faith
    did not apply to its decisions to reject them.
    But this was not a situation where the City had an absolute right to reject all submittals
    for any reason. Cf. Johnson v. Yousoofian, 
    84 Wn. App. 755
    , 759-63, 
    930 P.2d 921
     (1996)
    (noting that the duty of good faith did not apply where a lease included an unqualified statement
    9
    No. 48644-0-II
    that a tenant could not assign the lease without the landlord’s consent). The contract stated that
    the City “shall be satisfied that all the Work is being done in accordance with the requirements of
    the Contract.” CP at 92. The City was therefore required to exercise its discretion in a manner
    that was consistent with those requirements. Further, although the contract provided that the
    City’s “decisions will be final on . . . Interpretation of Plans and Specifications,” CP at 92, that
    clause indicated that the City had complete authority, not that it could exercise that authority on
    any basis.
    The contract provisions clearly provided the City with discretion over accepting or
    denying submittals. But that discretion was not absolute. And the only way both parties could
    obtain the benefits of the contact was if the City accepted submittals that complied with the
    contract’s requirements. Rekhter requires that the duty of good faith and fair dealing apply under
    these circumstances. 180 Wn.2d at 113
    We hold that the contract gave the City discretionary authority, not unconditional
    authority, to accept or reject submittals. As a result, the duty of good faith and fair dealing
    applied to the City’s consideration of Nova’s submittals.
    3.    Evidence of Breach
    Nova’s duty of good faith and fair dealing claim relates to a specific contract term: the
    City’s review of Nova’s submittals. Nova argues that it presented sufficient evidence to create a
    genuine issue of fact that the City breached its duty of good faith in the handling of those
    submittals. We agree.
    The question here is whether the City’s actions interfered with Nova’s justified
    expectations under the contract. See Rekhter, 180 Wn.2d at 119; Edmonson, 
    172 Wn.2d at 280
    .
    10
    No. 48644-0-II
    To support its claim, Nova presented the declarations of Nova’s president Jordan Opdahl, Nova’s
    project manager Dana Madsen, and a construction management expert, Frank Pita. These
    declarations allege that there were certain irregularities regarding the City’s review of its
    submittals.
    First, Madsen stated that the City’s requirement that all submittals be approved before
    Nova could start any work was “very unusual and inefficient.” CP at 316. Opdahl claimed that
    this requirement was contrary to industry practice, which only required approval of submittals
    before starting the work to which the submittals applied.
    Section 7-28.1(4) did list nine specific submittals that were required to be submitted
    before construction. However, Madsen alleged that the City required the approval of all
    submittals before any work could start. For instance, Madsen alleged that the City refused to
    allow Nova to begin work because it had not approved a submittal for work that would occur in
    the last three days of the project. The contract did not expressly require that all submittals be
    approved before any work could begin. Other than the specific submittals for which pre-
    approval was required, section 1-05.3 stated that the City must approve any drawings before
    proceeding with the work that those drawings represent.
    Second, Madsen stated that “the City failed to impose reasonable and proper
    requirements on Nova when rejecting our submittals” and that some of the City’s requirements
    were “nonsensical or impossible.” CP at 316. For example, Madsen claimed that the City
    repeatedly rejected submittal 9 because mill reports for the new pipe had not been provided, even
    though mill reports could not be prepared until the pipe was available for delivery and the City
    11
    No. 48644-0-II
    prohibited delivery until all submittals were approved. The City does not argue that the contract
    required Nova to produce these mill reports before the pipe was available for delivery.
    Third, Madsen stated that the City repeatedly rejected submittal 13 because the submittal
    did not provide that flaggers must accompany all vehicles coming onto the work site. But
    Madsen claimed that the project specifications did not require flaggers (as opposed to Nova’s
    proposal for either a pilot car or flaggers), and therefore argued that imposing such a requirement
    would require a formal change order. Nevertheless, the City rejected the submittals even though
    Nova complied with the contract requirements. Opdahl also noted that the City requested that
    Nova perform other work in a more cumbersome and expensive manner than required by the
    contract.
    Fourth, Madsen alleged that the City appeared to be reviewing submittals with the goal of
    rejecting them, looking for any excuse to do so. He referred to this as “gotcha” review. CP at
    318. Madsen claimed that “the City was using the submittal process to prevent Nova from
    performing the contract rather than to assure itself that Nova’s performance would match the
    contract.” CP at 318. For example, Madsen claimed that the City rejected submittal 7C because
    a work layout plan was not attached even though it had been attached to submittals 7, 7B, and 8.
    Madsen also referred to submittals 10 and 12, which the City ultimately did approve but initially
    intended to reject for improper reasons.
    Fifth, Madsen stated that the City rejected submittals for particular reasons and then
    rejected re-submittals for new and different reasons. For example, Madsen claimed that
    submittal 7 was rejected four times, each time for new and different reasons. Pita also noted this
    situation, pointing out that the City’s conduct caused a serious problem for Nova because Nova
    12
    No. 48644-0-II
    was faced with moving targets as it attempted to obtain approval of its submittals. Madsen
    alleged, “This creation of new excuses to reject resubmitted submittals that addressed the
    previous reasons given for rejection strongly indicates that the City did not intend to approve
    Nova’s submittals and allow Nova to perform the work.” CP at 319.
    Sixth, as Pita emphasized, the City gave Nova mixed messages about mobilization to the
    project site. The City notified Nova that it was in default for not mobilizing to the site. But
    when Nova attempted to mobilize to the site, the City would not provide access and then claimed
    that Nova’s entry onto the site was an additional basis for default.
    Seventh, Opdahl stated that at the beginning of the project some City staff wanted
    another contractor to get the bid and were looking for reasons to reject the bid. Later, the City’s
    engineer stated that “[t]his is not going to be another Martin Way project,” a reference to a prior
    project that had resulted in Nova receiving extra compensation because of the City’s design
    errors. CP at 278. Opdahl claimed that the engineer continued to hold a grudge against Nova
    because of that project.
    Madsen summarized the City’s conduct as follows:
    In my forty-six years in the construction industry, I have never seen a submittal
    process such as this one. Olympia acted in a manner calculated to prevent project
    performance by using changing standards and a “gotcha” review process on the
    submittals. Rather than working with Nova to get the job done, while assuring itself
    the work would be in accordance with the plans and specifications, Olympia
    actually undermined and delayed the work, refusing to allow it to proceed despite
    Nova’s proven willingness and ability to perform the work in accordance with the
    plans and specifications. . . . Olympia misused the submittal process to prevent,
    rather than advance, proper contract performance – and that is objectionable and
    irritating.
    CP at 320.
    13
    No. 48644-0-II
    Pita stated an opinion based on this conduct that the City used the submittal process to
    “frustrate Nova’s performance and put Nova into a position where it could not perform.” CP at
    253. He believed that the City “prevent[ed] contract performance by failing to approve
    submittals in a proper and orderly fashion.” CP at 253. Pita further stated that “[t]he City’s
    failure to approve the submittals and allow Nova to work was unreasonable, and may have been
    an attempt to prevent Nova’s contract performance.” CP at 254. Pita concluded that “the City’s
    failure to reasonably approve submittals in a manner that allowed both parties to reach a
    reasonable conclusion is itself a breach of the contract.” CP at 254.
    The City argues that it was justified in rejecting Nova’s submittals under certain contract
    terms, and those arguments may be legitimate. Further, each one of Nova’s complaints, standing
    alone, may not support liability. But we hold that under the broad standard of liability adopted
    by the Supreme Court and viewing the evidence in a light most favorable to Nova, Nova’s
    assertions and allegations taken together raise a question of fact of whether the City acted in a
    manner that prevented Nova from attaining its justified expectations under the contract. See
    Rekhter, 180 Wn.2d at 119. Accordingly, we hold that the trial court erred in granting summary
    judgment in favor of the City on Nova’s implied duty of good faith and fair dealing claim.
    C.     AWARD OF LIQUIDATED DAMAGES
    The trial court granted summary judgment in favor of the City on its breach of contract
    counterclaim and awarded liquidated damages and reasonable attorney fees to the City. Because
    we reverse on Nova’s duty of good faith and fair dealing claim, we vacate the trial court’s award
    of liquidated damages and reasonable attorney fees to the City.
    14
    No. 48644-0-II
    D.     ENFORCEABILITY OF LIQUIDATED DAMAGES CLAUSE
    Even though we vacate the trial court’s award of liquidated damages to the City, we
    address the enforceability of the liquidated damages clause because the issue may arise again on
    remand. Nova argues that the trial court erred in enforcing the contract’s liquidated damages
    clause because (1) questions of fact exist regarding whether the clause represented a reasonable
    estimate of fair compensation and (2) the clause is unconscionable. We disagree.
    1.   Legal Principles
    A liquidated damages clause in a contract generally provides that a party in breach of the
    contract will be liable for an agreed amount. See Minnick v. Clearwire US LLC, 
    174 Wn.2d 443
    ,
    449, 
    275 P.3d 1127
     (2012). Washington courts hesitate to interfere with the parties’ right to
    contract as they please, even if application of a liquidated damages clause appears inequitable to
    the breaching party. See Watson v. Ingram, 
    124 Wn.2d 845
    , 852, 
    881 P.2d 247
     (1994); Salewski
    v. Pilchuck Veterinary Hosp., Inc., 
    189 Wn. App. 898
    , 908, 
    359 P.3d 884
     (2015), review denied,
    
    185 Wn.2d 1006
     (2016). As a result, liquidated damages clauses are favored and “courts will
    uphold them if the sums involved do not amount to a penalty or are not otherwise unlawful.”
    Watson, 
    124 Wn.2d at 850
    .
    A liquidated damages clause is not a penalty and must be enforced if the agreed amount
    constitutes a reasonable prediction of fair compensation for the probable harm that a breach
    would cause. 
    Id. at 850-51
    . The reasonableness of the estimate is evaluated at the time the
    contract was formed, not at the time of trial. 
    Id. at 851
    . Courts can consider a party’s actual
    damages only in evaluating the reasonableness of the estimate. Wallace Real Estate Inv. Inc. v.
    Groves, 
    124 Wn.2d 881
    , 893, 
    881 P.2d 1010
     (1994).
    15
    No. 48644-0-II
    Courts also have stated that a liquidated damages clause is enforceable only if probable
    damages are difficult to estimate, but this issue is more accurately treated as a factor in the
    reasonableness analysis. Watson, 
    124 Wn.2d at 853
    . The greater the difficulty in estimating the
    amount of harm, the easier it is to show that the estimate of harm is reasonable. 
    Id.
    Proof of actual damages is not required to uphold a liquidated damages clause. Wallace
    Real Estate, 
    124 Wn.2d at 892
    . However, “actual damages may be considered where they are so
    disproportionate to the estimate that to enforce the estimate would be unconscionable.” 
    Id. at 894
    .
    2.    Reasonableness of Estimate
    Nova argues that questions of fact exist regarding the reasonableness of the liquidated
    damages clause because it is uncertain whether the City has suffered any damages as a result of
    the project not being performed. More specifically, Nova claims that the city could not suffer
    any actual damages from the delay of a contract of “convenience” as opposed to a contract of
    “urgency.”
    But as stated above, a liquidated damages clause can be reasonable even if the non-
    breaching party does not incur actual damages. See Wallace Real Estate, 
    124 Wn.2d at 892
    .
    And Nova has presented no evidence or even argument that the agreed liquidated amount was
    not a reasonable estimate of probable damages at the time the contract was formed. Nova also
    cites no authority for the proposition that a non-breaching party cannot suffer damages unless the
    contract involves a “necessary” or “urgent” project.
    Further, in support of its summary judgment motion the City presented evidence of actual
    damages. The City submitted a declaration stating that it had spent much more than the
    16
    No. 48644-0-II
    liquidated amount on the project, which would need to be duplicated on a future project. Nova
    did not produce any evidence contesting this statement. As the nonmoving party, Nova had the
    burden of coming forward with specific facts that show unreasonableness to avoid summary
    judgment. See Elcon, 
    174 Wn.2d at 169
    . We therefore hold that Nova presented no evidence
    that the liquidated damages clause was an unreasonable estimate of the City’s probable damages.
    3.   Unconscionability
    Nova argues that the liquidated damages provisions is unenforceable because it is
    unconscionable. We disagree.
    a.   Substantive Unconscionability
    Whether an agreement is unconscionable is a question of law. McKee v. AT&T Corp.,
    
    164 Wn.2d 372
    , 396, 
    191 P.3d 845
     (2008). An unconscionable contract clause is voidable.
    Romney v. Franciscan Med. Grp., 
    186 Wn. App. 728
    , 735, 
    349 P.3d 32
    , review denied, 
    184 Wn.2d 1004
     (2015). An agreement may be either substantively or procedurally unconscionable.
    McKee, 
    164 Wn.2d at 396
    . A contract is substantively unconscionable when it is one-sided or
    overly harsh. 
    Id.
     Substantively unconscionable clauses have been described as clauses that are
    “[s]hocking to the conscience,” “monstrously harsh,” or “exceedingly calloused.” Nelson v.
    McGoldrick, 
    127 Wn.2d 124
    , 131, 
    896 P.2d 1258
     (1995).
    A liquidated damages clause is unlawful if the estimated probable damages are too
    disproportionate to actual damages. Wallace Real Estate, 
    124 Wn.2d at 894
    . Nova argues that
    the liquidated damages provision here is one-sided and unduly harsh and that it provides the City
    with a windfall benefit. Nova references the fact that the City did not need to have the project
    17
    No. 48644-0-II
    performed. Nova apparently relies on its claim that the City could not have incurred any actual
    damages from Nova’s breach.
    But once again, Nova has not provided any evidence that the City did not incur any actual
    damages. And Nova did not refute the City’s evidence that it had spent more than the liquidated
    amount in work that would have to be duplicated when it again attempts to complete the project.
    We hold that Nova has presented no evidence that the liquidated amount is too
    disproportionate to the City’s actual damages, and therefore hold that the clause is not
    substantively unconscionable.
    b.   Procedural Unconscionability
    Nova also argues that the liquidated damages clause was procedurally unconscionable. A
    contract is procedurally unconscionable when one party lacked meaningful choice in the
    agreement. Zuver v. Airtouch Commc’ns, Inc., 
    153 Wn.2d 293
    , 305, 
    103 P.3d 753
     (2004).
    Relevant considerations include the manner in which the contract was entered, whether the
    plaintiff had a reasonable opportunity to understand the contract’s terms, and whether important
    terms were hidden. Id. at 304.
    Nova further argues that the contract was an adhesion contract and that all adhesion
    contracts are procedurally unconscionable as a matter of law. But the case Nova cites, Blakely v.
    Hous. Auth. of King County, 
    8 Wn. App. 204
    , 
    505 P.2d 151
     (1973), does not support this
    argument. In fact, in Blakely the court assumed the contract at issue was an adhesion contract,
    but held that the contested provision was not unconscionable. 
    Id. at 213
    . Whether a contract is
    an adhesion contract is relevant but not determinative of procedural unconscionability. Zuver,
    18
    No. 48644-0-II
    153 Wn.2d at 304-05. As the City points out, all standard public works contracts would be
    deemed unconscionable if Nova’s position was correct.
    Apart from claiming that the contract was an adhesion contract, Nova does not explain
    why this contract was procedurally unconscionable. No evidence suggests it was. Nova was a
    sophisticated project bidder, it had a full opportunity to review the contract provisions, and the
    liquidated damages clause was not hidden. Further, Nova previously had contracted with the
    City, and as a company engaged in work of this type it was in a position to understand the
    contract’s terms.
    We hold that Nova has presented no evidence that the contract was procedurally
    unconscionable.
    4.   Summary
    There is no genuine issue of material fact that the liquidated damages clause constituted a
    reasonable estimate of probable breach of contract damages. Further, the clause was not
    unconscionable. Accordingly, we hold that the trial court did not err in ruling on summary
    judgment that the liquidated damages clause is enforceable and that the City is entitled to
    liquidated damages if it prevails on its breach of contract claim.
    E.     ATTORNEY FEES ON APPEAL
    The City argues that it should be awarded appellate attorney fees under RCW 39.04.240,
    which states that a party to an action arising out of a public works contract may be entitled to
    attorney fees. Because we remand this matter to the trial court for further proceedings, we do not
    award attorney fees to either party at this time.
    19
    No. 48644-0-II
    CONCLUSION
    We reverse the trial court’s summary judgment dismissal of Nova’s claim for breach of
    the duty of good faith and fair dealing, vacate the trial court’s award of liquidated damages and
    reasonable attorney fees to the City, and remand for further proceedings consistent with this
    opinion.
    A majority of the panel having determined that this opinion will not be printed in the
    Washington Appellate Reports, but will be filed for public record in accordance with RCW
    2.06.040, it is so ordered.
    MAXA, A.C.J.
    We concur:
    LEE, J.
    MELNICK, J.
    20