Robert A. Lerner v. Cascade Designs, Inc. ( 2019 )


Menu:
  •   IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    DIVISION ONE
    ROBERT A. LERNER,                        )       No. 78570-2-1
    )
    Appellant,          )
    )
    v.                               )
    )       UNPUBLISHED OPINION
    CASCADE DESIGNS, INC., a                 )
    Washington corporation,                  )       FILED: August 26, 2019
    )
    Respondent.         )
    )
    VERELLEN, J. — A stay of litigation pending arbitration may expire if the
    party seeking relief does not take the steps required to commence the arbitration
    within a reasonable time. Once the stay has expired and the requirements of
    CR 41(b)(1) are satisfied, the court has the authority to involuntarily dismiss the
    litigation for want of prosecution.
    Here, the issues were joined when defendant Cascade Designs Inc. filed its
    motion to compel arbitration, necessarily asserting disputed issues of law and fact
    required arbitration. The court order staying litigation pending arbitration expired
    when Lerner failed to take the steps required to commence arbitration within a
    reasonable time. Because more than 12 months of inaction passed after the
    issues were joined and the stay expired, the trial court had the authority to dismiss
    for want of prosecution under CR 41(b)(1). We affirm.
    No. 78570-2-1/2
    BACKGROUND
    In 1996, Robert Lerner and Cascade Designs, Inc. entered into an asset
    purchase agreement. The agreement required the parties to arbitrate "any
    controversy arising from this [a]greement or its breach" under the rules of the
    American Arbitration Association (AAA).1
    On July 16, 2016, Lerner sued Cascade alleging a breach of the record
    1
    inspection provisions of the agreement.2 Cascade did not file an answer to the
    complaint but, on July 26, 2016, Cascade filed a motion to compel arbitration and
    dismiss or stay the proceeding pending the arbitration.3 On August 18, 2016, the
    court granted Cascade's motion to stay the proceedings "as the parties proceed to
    address their differences in arbitration per the terms of their [agreement]."
    The arbitration provision of the agreement included a process to select a
    three-person panel. On September 12, 2017, Lerner selected his arbitrator. And
    on October 24, 2017, Cascade selected its arbitrator. The two arbitrators arrived
    at a list of four candidates to serve as the third arbitrator and, on February 7, 2018,
    the third arbitrator was determined. Lerner never filed a demand for arbitration,
    and no one paid the AAA fee.
    1   Clerk's Papers(CP)at 37.
    2 CP   at 1-8.
    3 CP at 100-08.
    4 CP at 247-48.
    2
    No. 78570-2-1/3
    On April 26, 2018, Cascade moved to dismiss the lawsuit for lack of
    prosecution under CR 41(b)(1). On May 14, 2018, the trial court granted the
    motion and awarded Cascade attorney fees and costs.5
    Lerner appeals the dismissal and the award of attorney fees and costs.
    ANALYSIS
    I. CR 41(b)(1)
    We review a trial court's order dismissing an action under CR 41 for abuse
    of discretion."6
    CR 41(b)(1) governs involuntary dismissal for want of prosecution.
    Dismissal is mandatory when the plaintiff "neglects to note the action for trial or
    hearing within 1 year after any issue of law or fact has been joined."7 But the case
    will not be dismissed if noted for trial before the dismissal hearing.5
    First, Lerner argues the 12-month requirement of CR 41(b)(1) cannot be
    satisfied because no issue of law or fact was ever "joined." Normally, issues of
    law or fact are joined when the defendant files an answer to the complaint. But in
    State ex rel Goodnow v. O'Phelan, our Supreme Court recognized, in the context
    of the joinder requirement for a dismissal for lack of prosecution, it "is plainly a
    5   CP at 349.
    6 Woodhead       v. Discount Waterbeds, Inc., 
    78 Wn. App. 125
    , 130-31, 
    896 P.2d 66
     (1995).
    7 CR41(b)(1); Snohomish County v. Thom Meats, 
    110 Wn.2d 163
    , 167,
    
    750 P.2d 1251
     (1988); Polello v. Knapp, 
    68 Wn. App. 809
    , 815, 
    847 P.2d 20
    (1993).
    8 CR 41(b)(1); Thorp Meats, 
    110 Wn.2d at 168-69
    .
    3
    No. 78570-2-1/4
    legal truth .. . that an issue of law or an issue of fact arises whenever in the
    progress of a legal action or proceeding it becomes necessary and proper to
    decide a question of law or a question of fact."9
    Here, although Cascade never filed an answer to the complaint, Cascade's
    motion to compel arbitration and dismiss or stay proceedings pending arbitration
    necessarily acknowledged that there were disputed issues of law and fact that
    s
    required arbitration rather than litigation.
    Lerner cites only two cases in his opening brief for the proposition that filing
    an answer to a complaint is the way issues of law or fact may be joined. He cites
    no legal authority supporting the premise that there were no disputed issues of law
    or fact to be resolved in the course of the litigation or arbitration proceeding. On
    this limited briefing, we conclude that issues of law or fact were joined, for
    purposes of dismissal for lack of prosecution under CR 41(b)(1), on July 26, 2016,
    when Cascade filed its motion to compel arbitration and dismiss or stay the
    proceeding pending arbitration.
    Second, Lerner argues the court had no authority to grant Cascade's
    CR 41(b)(1) motion to dismiss because the court never lifted the stay pending
    arbitration. As a result, Lerner contends the 12-month inactivity requirement was
    tolled. But "[am n order staying the proceedings pending the arbitration is a
    temporary suspension of the proceedings in court. . . . When the arbitration
    9 
    6 Wn.2d 146
    , 150, 
    106 P.2d 1073
    (1940).
    4
    No. 78570-2-1/5
    [compelled by the court] did not go forward, the stay was no longer in effect."1°
    Here, when Lerner did not take the steps required to commence the arbitration
    within a reasonable time, the stay expired.
    Specifically, the arbitration provision provides "the arbitration shall be
    governed by the rules of the American Arbitration Association."11 At oral
    argument, Lerner suggested this provision does not require arbitration under the
    auspices of AAA, but he cites no authority to support his argument. An agreement
    that an arbitration will be "governed by" the rules of AAA clearly requires
    compliance with those rules.
    Under R-4 of the AAA commercial arbitration rules, a demand for arbitration
    must be filed with the AAA, and the AAA fee must be paid to commence an
    arbitration.12
    Lerner contends that Cascade's reliance upon the R-4 requirements is
    inconsistent with its participation in selecting the three arbitrator panel as provided
    in the arbitration provision. But the AAA commercial dispute rules expressly defer
    to any selection process agreed to by the parties.13 The commencement of
    10 Everett Shipyard v. Puget Sound Env't Corp., 
    155 Wn. App. 761
    , 769-70,
    
    231 P.3d 200
    (2010)(citing In re Matter of Koome, 
    82 Wn.2d 816
    , 819, 
    514 P.2d 520
     (1973)).
    11 CP at 37. Here, the most suitable AAA rules are the commercial dispute
    rules. For example, this is not a construction, employment, or consumer dispute.
    12 AAA    Commercial Dispute Rule 4.
    Brown v. MHN Gov't Servs., 
    178 Wn.2d 258
    , 273, 
    306 P.3d 948
    13 See
    (2013)("Under both the commercial and employment rules, if the arbitration
    agreement provides its own method for arbitrator selection, that method is used
    and the AAA does not provide a list of neutral arbitrators.").
    5
    No. 78570-2-1/6
    arbitration remains subject to the R-4 requirement of a demand for arbitration filed
    with AAA and payment of the AAA fee. And here, the R-4 requirements were
    never met.
    We do not need to set a bright line for what is a "reasonable time" to
    commence arbitration, following an order compelling arbitration. By the end of
    April 2017, eight months had passed and Lerner had not complied with R-4. We
    conclude the stay was no longer in effect by the end of April 2017. As a
    consequence, in May 2018, the superior court had the authority to apply CR 41
    and involuntarily dismiss for lack of prosecution.
    As acknowledged by Cascade in its motion to dismiss, if Lerner had
    commenced the arbitration or otherwise noted the matter prior to the May 14, 2018
    hearing, the court could not have dismissed for want of prosecution. But he did
    not take advantage of that opportunity. When the court entered its May 14, 2018
    order of dismissal, issues of fact and law had been joined for 21 months, and there
    were at least 12 months of inactivity after the stay expired. The requirements of
    CR 41(b)(1) were satisfied.
    II. Attorney Fees and Costs
    Lerner argues the court erred in awarding attorney fees and costs under the
    agreement. The agreement provides:
    In the event of litigation or arbitration relating to this [a]greement, the
    prevailing party shall be entitled to recover interest as may be
    provided by law, court costs and reasonable attorneys' fees. The
    6
    No. 78570-2-1/7
    court or arbitrator, as the case may be, shall determine which party
    has, under all the circumstances, "prevailed."[14]
    Here, the trial court found that as "a result of the May 14, 2018 [o]rder and
    other facts, documents, and exhibits of record,[Cascade] is the 'prevailing party'
    per the [agreement].15
    Because there was no completed arbitration on the ultimate issues, Lerner
    argues neither party prevailed at arbitration. But the agreement also allows fees to
    the prevailing party in the lawsuit. Lerner provides no authority that Cascade
    failed to prevail when it obtained the dismissal of the lawsuit for lack of
    prosecution.
    III. Fees on Appeal
    Cascade requests attorney fees on appeal. Because Cascade is the
    prevailing party on appeal, it is entitled to an award of attorney fees under the
    agreement attorney fee provision, upon compliance with RAP 18.1.
    CONCLUSION
    On the limited briefing provided,16 Lerner does not establish that the stay
    remained in effect or that issues of law and fact were not joined. Because more
    14   CP at 38.
    15   CP at 517 (Finding of Fact 10).
    16The appellant has the burden of citing to specific authority supporting the
    appellant's assignments of error. See Norcon Builders, LLC v. GMP Homes VG,
    LLC 
    161 Wn. App. 474
    , 486, 
    254 P.3d 835
    (2011)("We will not consider an
    inadequately briefed argument"); DeHeer v. Seattle Post-Intelliqencer, 
    60 Wn.2d 122
    , 126, 
    372 P.2d 193
    (1962)("Where no authorities are cited in support of a
    proposition, the court is not required to search out authorities, but may assume
    that counsel, after diligent search, has found none.").
    7
    No. 78570-2-1/8
    than 12 months of inactivity passed after joinder and expiration of the stay, the trial
    court did not abuse its discretion in dismissing the lawsuit under CR 41(b)(1).
    Additionally, the trial court did not err in awarding fees to Cascade.
    We affirm.
    WE CONCUR:
    l       iottelj   A -,7-
    8