City Of Issaquah, V. Westridge-issaquah Ii Lp ( 2021 )


Menu:
  • IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    WESTRIDGE-ISSAQUAH II LP and
    POLYGON WLH LLC, Washington                      DIVISION ONE
    companies,
    No. 82025-7-I
    Respondents,
    PUBLISHED OPINION
    v.
    CITY OF ISSAQUAH, a municipal
    corporation,
    Appellant.
    DWYER, J. — The City of Issaquah (the City) appeals from the superior
    court’s order granting the petition filed pursuant to the Land Use Petition Act
    (LUPA)1 by Westridge-Issaquah II LP and Polygon WLH LLC (collectively
    Polygon). In its petition, Polygon claimed that the City illegally imposed certain
    general facility charges (GFCs) on several of its properties. Polygon contends
    that it had a vested right to have lower GFCs imposed on its properties pursuant
    to an expired development agreement. Additionally, Polygon asserts that the
    City’s imposition of the higher GFCs violated RCW 35.92.025—a statute
    requiring utility connection charges to be reasonable such that they are based on
    property owners’ equitable shares in the cost of the city utility systems.
    Both because Washington’s vesting doctrine does not apply to fees and
    because Polygon did not adduce any evidence challenging the basis on which
    1   Ch. 36.70C RCW.
    No. 82025-7-I/2
    the City’s ordinances established the disputed GFCs, we reverse the trial court’s
    order insofar as it requires the City to refund the GFCs that were imposed on
    Polygon’s properties and to assess GFCs for future building permits submitted by
    Polygon according to the development agreement. In an order that is not the
    subject of an assignment of error, the trial court varied the amount that the City is
    authorized to charge Polygon for side-sewer fees and water-meter installation
    fees. We leave that order undisturbed, thereby affirming it.
    I
    Polygon owns land in an area of the City known as the Issaquah
    Highlands. Polygon intends to construct numerous single-family residential units
    and townhomes in the Issaquah Highlands. One of Polygon’s development
    projects is known as the Westridge Single-Family North development, which is a
    73-unit single-family subdivision located within the northern portion of Polygon’s
    property.
    In June 1996, the City entered into a development agreement with Grand
    Ridge LP and Glacier Ridge LP (the Partnership). Under this agreement, the
    Partnership designated Port Blakely Communities, Inc. as their “agent with
    authority to give notices, approvals and otherwise act pursuant to [the]
    Agreement.” The parties agree that Port Blakely was Polygon’s predecessor in
    interest.
    The development agreement contained various “development standards,”
    which controlled aspects of development in the Issaquah Highlands. Under the
    development agreement, the Partnership was to construct water and sewer
    2
    No. 82025-7-I/3
    facilities to serve development in the Issaquah Highlands.2 According to a
    memorandum dated December 16, 2013, and authored by a city official, Port
    Blakely constructed water, sewer, and stormwater systems in the Issaquah
    Highlands that were “designed to support the planned development needs in the
    project.”
    In exchange for Port Blakely’s construction of these facilities, the City
    agreed to consider to amend its ordinances imposing water and sewer GFCs on
    properties that fell within the scope of the agreement.3 The development
    agreement did not contain any such provisions with regard to stormwater GFCs.
    Notably, the development agreement provided that “[t]he parties agree to
    take further actions and execute further documents, either jointly or within their
    2   With regard to water facilities, section 3.12 of the development agreement stated, in
    part:
    The Partnership shall provide at its cost water facilities and incorporate
    water conservation measures to serve the [urban growth area] consistent with
    the “Grand Ridge Water Service” document, which is set forth in Appendix F.
    The City shall provide water to the [urban growth area] Portion of the Project
    sufficient for the Allowable Development.
    With regard to sewer facilities, section 3.13 of the development agreement stated, in part:
    The Partnership shall provide at its cost sewer facilities to serve the
    [urban growth area] consistent with the “Grand Ridge Sewer Service” document,
    which is set forth in Appendix G.
    3 Under Appendix F, the City agreed to consider to amend its ordinance imposing a water
    GFC on the Highlands:
    In recognition of the Partnership’s obligation to provide the Grand Ridge
    water system through a series of water main extensions, pump stations and
    water reservoirs, the City agrees to consider adoption of amendments no later
    than August 4, 1996, to its current ordinance(s) which would authorize the City’s
    normal connection (hook-up) fee to be adjusted so the Partnership pays its fair
    share of the portion of the water supply system attributable to Grand Ridge.
    Under Appendix G, the City also agreed to consider to amend its ordinance imposing a
    sewer GFC on the Highlands:
    The sewer system shall be designed and constructed to city standards
    and become part of the City’s system upon completion. In recognition that the
    Grand Ridge sewer system will be installed at the Partnership’s cost . . . and will
    connect directly to the existing METRO GILMAN Interceptor, the City agrees to
    consider adoption of amendments, no later than August 4, 1996, to its current
    ordinances to authorize the Partnership to not pay any connection (hook-up) fee
    to the City.
    3
    No. 82025-7-I/4
    respective powers and authority, to implement the intent of this Agreement.”
    During the term of the agreement, Port Blakely and the City executed several
    documents which waived or lowered the GFCs that applied to the developments
    in the Issaquah Highlands. Ultimately, the City agreed to (1) waive the GFCs
    imposed on single-family residences seeking to connect to the City’s water and
    stormwater systems, and (2) impose a GFC of $165.06 on single-family
    residences seeking to connect to the City’s sewer system.
    The development agreement also set forth a build-out period of 20 years,
    during which the development standards contained within the agreement
    governed all development:
    All development within the [urban growth area] shall be
    governed by the Development Standards and shall be implemented
    through plats, short plats, binding site plans, site development
    permits, building permits and other permits and approvals
    (“Implementing Approvals”) issued by the City. A “Buildout Period”
    of twenty (20) years following first final plat approval is established
    for the development and construction of uses for the Grand Ridge
    Project. During the Buildout Period, the City shall not modify or
    impose new or additional Development Standards beyond those set
    forth in this Agreement.
    The development agreement further stated that “[t]he term of this
    Agreement shall continue at a minimum through the Buildout Period, and shall
    continue after the Buildout Period unless and until either the City or the
    Partnership . . . gives notice of termination.”
    On November 1, 2016, Port Blakely sent a letter to the City’s mayor, land
    development manager, and economic development director in which it provided
    notice to terminate the development agreement.
    4
    No. 82025-7-I/5
    After receiving the notice of termination from Port Blakely, the City was
    required, under the development agreement, to adopt replacement zoning and
    related development standards that would govern development in the area that
    was subject to the agreement:
    No sooner than six (6) months after the notice of termination, the
    City shall hold public hearings and shall adopt zoning and related
    development standards for the [urban growth area] portion of the
    Property, or portions thereof as determined appropriate by the City.
    Upon such adoption, this Agreement shall terminate and thereafter
    the [urban growth area] portion of the Property shall be governed
    by the adopted City zoning and related development regulations.
    On March 19, 2018, the Issaquah city council passed ordinance 2830,
    which, among other things, terminated the development agreement and required
    single-family residences in the Issaquah Highlands to pay the $6,029 city-wide
    GFC to connect to the City’s water utility system. Issaquah Ordinance 2830
    (Mar. 19, 2018). Ordinance 2830 also provided that “all property formerly
    governed by [the] Development Agreement shall . . . be governed by the Urban
    Village Replacement Regulations adopted by this ordinance and other applicable
    City zoning and related development regulations.” Issaquah Ordinance 2830
    (Mar. 19, 2018).
    On July 14, 2017, before the City terminated the development agreement,
    Polygon submitted a preliminary plat application to subdivide the Westridge
    Single Family North development into 73 single-family lots. On May 4, 2018, the
    chair of the City’s Urban Village Development Commission sent a letter to the city
    5
    No. 82025-7-I/6
    council recommending that it approve the preliminary plat application. The city
    council subsequently approved the preliminary plat application.4
    After the development agreement was terminated, Polygon submitted
    building permit applications in which it sought to connect several single-family
    properties to the City’s utility systems.5 In September 2019, the City issued
    several invoices for development fees and charges associated with building
    permits for these properties. For each building permit, these invoices imposed
    various fees and charges, including a water GFC of $6,029, a sewer GFC of
    $2,024, and a stormwater GFC of $1,256.6 Polygon paid these fees and charges
    under protest.
    4 The record does not contain the city council’s approval of the preliminary plat
    application. However, in its opening brief, the City states that “[t]he Issaquah City Council
    approved Westridge’s preliminary plat on July 16, 2018.” Br. of Appellant at 17. Additionally, in
    its response brief, Polygon states that “[t]he City approved the Westridge North preliminary plat.”
    Br. of Resp’t at 13.
    5 The record does not contain Polygon’s building permit applications. However, the
    parties agree that Polygon submitted its building permit applications after the development
    agreement was terminated. In its opening brief, the City states that “Polygon applied for its utility
    connections (via building permits) after termination of the Development Agreement.” Br. of
    Appellant at 28. Likewise, in its response brief, Polygon states that “the building permits for plats
    approved under the Development Agreement were not all applied for prior to the Agreement’s
    termination.” Br. of Resp’t at 38.
    Moreover, the record indicates that Polygon sought to connect to the City’s utility systems
    in its building permit applications. The Issaquah Municipal Code requires utility system
    connection charges to be assessed when the City issues the permit to connect to the utility
    system. IMC 13.24.090E; IMC 13.70.020B; IMC 13.30.055A. Here, the City assessed the utility
    connection charges upon issuance of Polygon’s building permits.
    6 Approximately two years before the Issaquah city council terminated the development
    agreement, the city council passed two ordinances that established the sewer and stormwater
    GFCs that were ultimately imposed on Polygon’s properties. The first, ordinance 2748, required
    a GFC of $2,024 to connect to the City’s sewer system. Issaquah Ordinance 2748 (Nov. 2,
    2015). The second, ordinance 2749, required a GFC of $1,256 to connect to the City’s
    stormwater system. Issaquah Ordinance 2749 (Nov. 2, 2015). These ordinances specified that
    the effective date for these GFCs was January 1, 2016. Issaquah Ordinance 2748, 2749.
    Neither party cites to these ordinances, and they are not contained within the record on appeal.
    However, these ordinances may be found at
    https://issaquah.civicweb.net/filepro/documents/3338 [https://perma.cc/M978-5ZWA (2748);
    https://perma.cc/TAL3-W4TL (2749)].
    6
    No. 82025-7-I/7
    Polygon then appealed the City’s imposition of the fees and charges
    associated with three building permits to the Issaquah hearing examiner. The
    hearing examiner dismissed Polygon’s appeal, reasoning that the Issaquah
    Municipal Code did not provide a procedural mechanism to appeal the fees and
    charges that were imposed on Polygon’s properties.
    In October and November 2019, the City issued several additional
    invoices for development fees and charges associated with building permits for
    properties located within the Westridge Single-Family North development. As
    with the previous invoices, these invoices assessed the GFCs according to the
    City’s ordinances rather than the development agreement.
    On October 17, 2019, Polygon filed a LUPA petition in the King County
    Superior Court. Polygon asserted that the City lacked the authority to impose
    various fees and charges, including (1) the water, sewer, and stormwater GFCs,
    and (2) a water-meter installation fee and side-sewer fee. In response, the City
    conceded that it improperly assessed the water-meter installation fee and side-
    sewer fee. However, the City maintained that it properly assessed the water,
    sewer, and stormwater GFCs that were imposed on Polygon’s properties.
    On October 2, 2020, the superior court entered an order granting
    Polygon’s LUPA petition. The order required the City to “refund the water, and
    stormwater general facilities charges assessed against the Westridge North
    single family building permits” and “refund the sewer general facility charge
    except for $165.06.” Additionally, the order required the City to “assess fees for
    all future single-family home building permits in the Westridge North subdivision
    7
    No. 82025-7-I/8
    based on the Development Agreement GFCs.” Finally, the order required the
    City to refund the water-meter installation fee and the side-sewer fee, as agreed
    to by the parties.
    The City appeals.
    II
    A party seeking relief from a land use decision must file a petition in the
    superior court pursuant to LUPA. RCW 36.70C.040(1). “A petition for review by
    the superior court constitutes appellate review on the administrative record
    before the local jurisdiction’s body or officer with the highest level of authority to
    make the final determination.”7 HJS Dev., Inc. v. Pierce County, 
    148 Wn.2d 451
    ,
    467, 
    61 P.3d 1141
     (2003).
    “‘When reviewing a superior court’s decision on a land use petition, the
    appellate court stands in the shoes of the superior court.’” HJS Dev., 
    148 Wn.2d at 468
     (quoting Citizens to Pres. Pioneer Park, LLC v. City of Mercer Island, 
    106 Wn. App. 461
    , 470, 
    24 P.3d 1079
     (2001)). Moreover, “[o]n appeal, the party who
    filed the LUPA petition bears the burden of establishing one of the errors set forth
    in RCW 36.70C.130(1), even if that party prevailed on its LUPA claim at the
    superior court.” Quality Rock Prods., Inc. v. Thurston County, 
    139 Wn. App. 125
    ,
    134, 
    159 P.3d 1
     (2007).
    Under RCW 36.70C.130(1), a challenged decision violates LUPA if:
    7 Polygon contends that the City’s building official was the officer with the highest level of
    authority to make the final determination regarding the GFCs that were imposed on Polygon’s
    properties. The building official is “[t]he officer or other designated authority charged with the
    administration and enforcement of the Uniform Building Code and assigned provisions of this
    [Land Use] Code.” IMC 18.02.040. However, under the Issaquah Municipal Code, it is the city
    engineer, not the building official, who is authorized to administer the sections of the code
    regarding water, sewer, and stormwater GFCs. IMC 13.04.010A; IMC 13.32.010.
    8
    No. 82025-7-I/9
    (a) The body or officer that made the land use decision
    engaged in unlawful procedure or failed to follow a prescribed
    process, unless the error was harmless;
    (b) The land use decision is an erroneous interpretation of
    the law, after allowing for such deference as is due the construction
    of a law by a local jurisdiction with expertise;
    (c) The land use decision is not supported by evidence that
    is substantial when viewed in light of the whole record before the
    court;
    (d) The land use decision is a clearly erroneous application
    of the law to the facts;
    (e) The land use decision is outside the authority or
    jurisdiction of the body or officer making the decision; or
    (f) The land use decision violates the constitutional rights of
    the party seeking relief.
    Polygon asserts that the City violated RCW 36.70C.130(1)(b) and (d) by
    imposing the higher GFCs on its properties.8 We review de novo whether a
    decision is based on an erroneous interpretation of the law under subsection (b).
    Phoenix Dev., Inc. v. City of Woodinville, 
    171 Wn.2d 820
    , 828, 
    256 P.3d 1150
    (2011). Additionally, “[a] finding is clearly erroneous under subsection (d) when,
    although there is evidence to support it, the reviewing court on the record is left
    with the definite and firm conviction that a mistake has been committed.”
    Phoenix Dev., 
    171 Wn.2d at 829
    .
    III
    Polygon contends that it had a vested right to have the GFCs imposed on
    its properties assessed according to the development agreement. This is so,
    Polygon avers, because it submitted its preliminary plat application before the
    development agreement was terminated. We disagree.
    8 Polygon also states that RCW 36.70C.130(1)(c) is “applicable” to this case. Br. of
    Resp’t at 18. However, Polygon concedes that, because the City’s assessment of the disputed
    GFCs did not involve findings of fact, “there are no factual findings for this Court to review under
    the substantial evidence standard.” Br. of Resp’t at 19-20.
    9
    No. 82025-7-I/10
    A
    “In Washington, ‘vesting’ refers generally to the notion that a land use
    application, under the proper conditions, will be considered only under the land
    use statutes and ordinances in effect at the time of the application’s submission.”
    Noble Manor Co. v. Pierce County, 
    133 Wn.2d 269
    , 275, 
    943 P.2d 1378
     (1997).
    “At common law, this state’s doctrine of vested rights entitled developers to have
    a land development proposal processed under the regulations in effect at the
    time a complete building permit application was filed.” Noble Manor, 
    133 Wn.2d at 275
    . “In 1987, the Legislature (1) codified the traditional common law vested
    rights doctrine regarding vesting upon application of building permits [in RCW
    19.27.095], and (2) enlarged the vesting doctrine to also apply to subdivision and
    short subdivision applications [in RCW 58.17.033].” Noble Manor, 
    133 Wn.2d at
    275 (citing LAWS OF 1987, ch. 104; Friends of the Law v. King County, 
    123 Wn.2d 518
    , 522, 
    869 P.2d 1056
     (1994)).
    “The purpose of the vested rights doctrine is to provide a measure of
    certainty to developers and to protect their expectations against fluctuating land
    use policy.” Noble Manor, 
    133 Wn.2d at 278
    . However, “[i]f a vested right is too
    easily granted, the public interest is subverted.” Noble Manor, 
    133 Wn.2d at 280
    .
    This is because “development interests protected by the vested rights doctrine
    come at a cost to the public interest because the practical effect of recognizing a
    vested right is to sanction the creation of a new nonconforming use.” Noble
    Manor, 
    133 Wn.2d at 280
    .
    10
    No. 82025-7-I/11
    B
    A developer may also have a right to have certain standards imposed on
    its development pursuant to a development agreement. Under RCW
    36.70B.170(1), “[a] local government may enter into a development agreement
    with a person having ownership or control of real property within its jurisdiction.”
    Significantly, the development standards contained within a development
    agreement govern only during the term or build-out period specified in the
    agreement:
    Unless amended or terminated, a development agreement is
    enforceable during its term by a party to the agreement. A
    development agreement and the development standards in the
    agreement govern during the term of the agreement, or for all or
    that part of the build-out period specified in the agreement, and
    may not be subject to an amendment to a zoning ordinance or
    development standard or regulation or a new zoning ordinance or
    development standard or regulation adopted after the effective date
    of the agreement. A permit or approval issued by the county or city
    after the execution of the development agreement must be
    consistent with the development agreement.
    RCW 36.70B.180 (emphasis added).
    The development agreement herein, which was entered into in June 1996,
    established a build-out period of 20 years:
    A “Buildout Period” of twenty (20) years following first final plat
    approval is established for the development and construction of
    uses for the Grand Ridge Project. During the Buildout Period, the
    City shall not modify or impose new or additional Development
    Standards beyond those set forth in this Agreement.
    This agreement specified that, upon expiration of the build-out period,
    either party could give notice to terminate the agreement. On November 1, 2016,
    11
    No. 82025-7-I/12
    Port Blakely sent a letter to City officials in which it provided notice to terminate
    the development agreement.
    Upon receiving the notice of termination from Port Blakely, the City was
    required, under the development agreement, to adopt zoning and related
    development standards that would govern development in the area that was
    subject to the agreement:
    No sooner than six (6) months after the notice of termination, the
    City shall hold public hearings and shall adopt zoning and related
    development standards for the [urban growth area] portion of the
    Property, or portions thereof as determined appropriate by the City.
    Upon such adoption, this Agreement shall terminate and thereafter
    the [urban growth area] portion of the Property shall be governed
    by the adopted City zoning and related development regulations.
    On March 19, 2018, the City passed ordinance 2830, which, among other
    things, terminated the development agreement and required properties that were
    subject to the agreement to be “governed by the Urban Village Replacement
    Regulations adopted by this ordinance and other applicable City zoning and
    related development regulations.” Issaquah Ordinance 2830 (Mar. 19, 2018).
    C
    Polygon asserts that, because it submitted a preliminary plat application
    before the development agreement was terminated, it had a vested right to have
    the GFCs provided in the agreement imposed on its development until approval
    of its preliminary plat expires.9 This is so, Polygon avers, because the
    preliminary plat application specified that the development was for single-family
    9 Under the Issaquah Municipal Code, “[a]pproval of any preliminary plat shall expire and
    the preliminary plat shall be considered withdrawn seven (7) years from the date of such
    preliminary plat approval.” IMC 18.13.170A.
    12
    No. 82025-7-I/13
    use. Therefore, according to Polygon, the GFCs agreed to under the
    development agreement—which applied to properties for single-family use—
    governed the processing of its building permit applications, which were submitted
    after the development agreement was terminated. Polygon’s argument fails for
    three reasons.
    1
    First, the vesting statute for preliminary plat applications, RCW 58.17.033,
    does not apply to fees. This statute provides:
    A proposed division of land, as defined in RCW 58.17.020, shall be
    considered under the subdivision or short subdivision ordinance,
    and zoning or other land use control ordinances, in effect on the
    land at the time a fully completed application for preliminary plat
    approval of the subdivision, or short plat approval of the short
    subdivision, has been submitted to the appropriate county, city, or
    town official.
    RCW 58.17.033(1).
    In New Castle Investments v. City of LaCenter, 
    98 Wn. App. 224
    , 226, 
    989 P.2d 569
     (1999), the court held that RCW 58.17.033 “does not apply to
    transportation impact fees (TIFs) because they do not fall within the definition of
    ‘land use control ordinances.’” The court therein reasoned that a transportation
    impact fee did not qualify as a “land use control ordinance” because it neither
    limited the use of land nor resembled a zoning law:
    The right that vests, according to Noble Manor, is “the right
    to have the uses disclosed in [the applicant’s] application
    considered by the county or local government under the laws in
    existence at the time of the application.” 
    133 Wn.2d at 283
    .
    According to legal commentators, “[t]he vested rights rule is
    generally limited to those laws which can loosely be considered
    ‘zoning’ laws.” W ASH. STATE BAR ASS’N, WASHINGTON REAL
    PROPERTY DESK BOOK, § 97.8(2)(d) (3rd ed. 1996). A TIF does not
    13
    No. 82025-7-I/14
    limit the use of land, nor does it resemble a zoning law. Instead, a
    TIF merely affects the ultimate cost of the development. Thus, it
    is not the type of right that vests under the vested rights doctrine.
    New Castle Invs., 98 Wn. App. at 232.
    Similarly, in Lincoln Shiloh Associates, Ltd. v. Mukilteo Water District, 
    45 Wn. App. 123
    , 128, 
    724 P.2d 1083
    , 
    742 P.2d 177
     (1986), we explained that “it is
    inappropriate to apply the vesting doctrine to fees.” A property owner therein
    “submitted to the [Mukilteo Water] District an application for permission to extend
    [a] water main.” Lincoln Shiloh Assocs., 45 Wn. App. at 126. After the district
    approved the application, it adopted a resolution that imposed a GFC for
    connecting to the district’s water facility and increased the property owner’s cost
    to connect from $6,400 to $95,680. Lincoln Shiloh Assocs., 45 Wn. App. at 126.
    After the connection charge was increased, the property owner applied to
    connect to the district’s water facility and paid the increased connection charge
    under protest. Lincoln Shiloh Assocs., 45 Wn. App. at 126. We rejected the
    property owner’s argument that it had a vested right to the connection charge in
    effect when its application to extend the water main was approved:
    [The property owner] is not being forced to use its land or build
    differently from that which [the property owner] was able to do at
    the time its plans were approved by the District. Instead, the cost is
    increased. [The property owner] had no more than an expectation
    that the connecting charges would remain $6,400. There is no
    vested right here to the connection fee remaining $6,400.
    Lincoln Shiloh Assocs., 45 Wn. App. at 128-29.
    The water, sewer, and stormwater GFCs imposed on Polygon’s properties
    did not limit Polygon’s use of the properties or the development thereon. In other
    words, the water, sewer, and stormwater GFCs were not “land use control
    14
    No. 82025-7-I/15
    ordinances” under RCW 58.17.033(1). Accordingly, Polygon did not have a
    vested right to have the GFCs that were imposed on its properties assessed
    pursuant to the development agreement.
    2
    Polygon’s argument fails for another reason, as well. Despite its claim to
    the contrary, Polygon did not have a right to have its building permit applications
    vest to the land use laws in effect when it submitted its preliminary plat
    application. Our Supreme Court has clarified which rights vest upon the
    submission of a complete preliminary plat application:
    Not all conceivable uses allowed by the laws in effect at the time of
    a short plat application are vested development rights of the
    applicant. However, when a developer makes an application for a
    specific use, then the applicant has a right to have that application
    considered under the zoning and land use laws existing at the time
    the completed plat application is submitted.
    Noble Manor, 
    133 Wn.2d at 285
     (emphasis added).
    Stated differently, upon submission of a preliminary plat application, an
    applicant has a right to have the specific uses sought in the application
    considered under the land use laws in effect when the application was submitted.
    Additionally, an applicant has the right to have only the preliminary plat
    application—not a subsequently filed building permit application—considered
    under the land use laws in effect when the preliminary plat application was
    submitted.
    Polygon did not seek to connect to the City’s water, sewer, or stormwater
    systems in its preliminary plat application. Rather, Polygon sought to connect to
    these utility systems in its building permit applications, which were filed after the
    15
    No. 82025-7-I/16
    development agreement was terminated. It is of no significance that Polygon
    specified in its preliminary plat application that it sought to develop single-family
    residences—Polygon had a vested right to have only its preliminary plat
    application considered under the land use laws in effect when that application
    was submitted.
    Polygon cites to Association of Rural Residents v. Kitsap County, 
    141 Wn.2d 185
    , 
    4 P.3d 115
     (2000), and Schneider Homes, Inc. v. City of Kent, 
    87 Wn. App. 774
    , 
    942 P.2d 1096
    , 
    971 P.2d 56
     (1997), in support of its argument
    that, because its preliminary plat application specified that the development was
    for single-family use, its subsequently-filed building permit applications vested to
    the development standards contained within the development agreement.
    However, these cases do not support Polygon’s argument.
    In Schneider Homes, we held that a developer had a right to have both its
    preliminary plat application and a “companion” planned unit development permit
    application vest to the ordinances in effect when those applications were
    submitted. 87 Wn. App. at 779. We reasoned that the preliminary plat
    application was “inextricably linked” to the planned unit development application
    such that the preliminary plat application could not “go forward without” the
    planned unit development application. Schneider Homes, 87 Wn. App. at 778.
    In Association of Rural Residents, our Supreme Court relied on our reasoning in
    Schneider Homes and held that, “when a preliminary plat application is coupled
    with a [planned unit development] proposal, the [planned unit development]
    16
    No. 82025-7-I/17
    ordinance is one of the laws in effect at the time of application to which the
    vested rights doctrine applies.” 141 Wn.2d at 195.
    Polygon’s building permit applications were not “inextricably linked” to its
    preliminary plat application such that the preliminary plat application could not be
    approved unless the building permit application was also approved. Indeed, the
    Issaquah Municipal Code generally requires preliminary plat applications to be
    approved before a party may submit a building permit application: “All
    development proposals . . . are subject to Project Permit[10] approval prior to
    Building Permit application unless otherwise allowed by the Building Official.”
    IMC 18.04.090. Thus, Polygon did not have a right to have its building permit
    applications vest to the land use laws in effect when it submitted its preliminary
    plat application.11
    10  The term “Project Permit” is defined to include “subdivisions.” IMC 18.02.180.
    11  Polygon also asserts that various assurances made by the City demonstrate that it had
    a vested right to the GFCs agreed to under the development agreement. However, mere
    assurances from city officials do not grant a party vested rights. Deer Creek Developers, LLC v.
    Spokane County, 
    157 Wn. App. 1
    , 12-13, 
    236 P.3d 906
     (2010). In any event, none of the
    documents cited by Polygon indicate that the City assured Polygon that it had a vested right to
    the GFCs agreed to under the development agreement.
    First, Polygon cites to an e-mail message from a City official explaining that the GFCs
    imposed on single-family residences seeking to connect to the City’s (1) water and stormwater
    systems would amount to $0, and (2) sewer system would amount to $165.06. However, this e-
    mail message was sent to Polygon on March 10, 2017—approximately one year before the city
    council terminated the development agreement. Additionally, this e-mail message was a
    response to an e-mail message sent by an employee of Polygon that requested the City to
    “confirm what we will pay . . . under the Developer Agreement.” Plainly, in this message, the City
    did not assure Polygon that these GFCs would apply after the development agreement was
    terminated.
    Second, Polygon cites to a March 2017 letter from the City’s director of the Department of
    Development Services which merely explained that, when a complete “application” is submitted,
    that application vests to the zoning and development regulations in effect at that time:
    Requirements for a complete application necessary to vest are set forth by
    municipal code. IMC 18.01.050(C)(1) sets forth the requirements for a complete
    application. When an application is submitted meeting those requirements, the
    application is vested and would be unaffected by any future changes in zoning or
    development regulations so long at the application remains active
    (IMC.18.04.220.D.2). This would, [sic] include any changes as a result of
    termination of the Issaquah Highlands Development Agreement.
    17
    No. 82025-7-I/18
    3
    Finally, Polygon’s argument fails for a third reason. Polygon did not have
    a vested right to have the GFCs assessed at any particular amount until it both
    applied to connect to the City’s utility systems and paid the applicable fees. In
    Irvin Water Dist. No. 6 v. Jackson Partnership, 
    109 Wn. App. 113
    , 122, 
    34 P.3d 840
     (2001), the court concluded that the developers therein “did not have a
    vested right in any particular fee schedule, at least before application and
    payment of the applicable connection fees.” This was so because application to
    connect to the district’s utility system and payment of the applicable connection
    fees were both “required by District regulations and bylaws to secure service.”
    Irvin Water Dist., 109 Wn. App. at 118. Likewise, the Issaquah Municipal Code
    requires property owners to both apply to connect to the City’s utility systems and
    pay the applicable connection charges in order to secure service.12 And here,
    (Emphasis added.)
    This letter did not provide that Polygon had a vested right to have the GFCs agreed to
    under the development agreement imposed on its properties.
    Finally, Polygon cites to a November 2017 memorandum which regarded a proposal to
    extend vesting rights to administrative site development permits and site development permits
    following the termination of the development agreement. However, the memorandum did not
    state that building permit applications submitted after the development agreement was terminated
    would be processed according to the development agreement.
    12 With regard to applications for water service, the Issaquah Municipal Code provides:
    “The owner of any property who desires to connect to the City Water System shall make
    application for the connection on the standard form for water service and at that time, he shall pay
    all connection charges, fees, or assessments required by the Water System Code.” IMC
    13.04.020. Additionally, the code provides that “there is imposed upon the owners of property
    seeking to provide water service to their property by connecting to the City’s water system a
    general facility charge.” IMC 13.24.090. Next, with regard to the City’s sewer system, the code
    provides: “The general facility charge shall be paid and collected at the time of permit issuance
    for a sewer connection and prior to actual connection.” IMC 13.70.020B. Finally, with regard to
    City’s stormwater system, the code provides: “[T]here is imposed upon the owner of property
    seeking to connect to the City’s stormwater system a general facility charge,” and that “[t]he
    general facility charge shall be paid and collected at the time of permit issuance for development
    and prior to actual development.” IMC 13.30.055A-B.
    18
    No. 82025-7-I/19
    Polygon applied to connect to the City’s utility systems and paid the connection
    charges after the development agreement was terminated.
    Accordingly, Polygon did not have a vested right to have the GFCs
    imposed on its properties assessed pursuant to the development agreement.
    IV
    Polygon next contends that the City’s imposition of the higher water,
    sewer, and stormwater GFCs violated RCW 35.92.025.13 Specifically, Polygon
    asserts that these charges were not reasonable because the impacts of the
    Westridge Single-Family North development on the City’s utility systems were
    already “fully mitigated” under the development agreement. Because RCW
    35.92.025 does not permit the sort of individualized challenge advanced by
    Polygon, this claim also fails.
    RCW 35.92.025 authorizes cities to assess charges to property owners
    seeking to connect to city utility systems. This statute provides, in pertinent part:
    Cities and towns are authorized to charge property owners seeking
    to connect to the water or sewerage[14] system of the city or town as
    a condition to granting the right to so connect, in addition to the cost
    of such connection, such reasonable connection charge as the
    legislative body of the city or town shall determine proper in order
    13  Under the Issaquah Municipal Code, the City of Issaquah elected to be classified as a
    noncharter code city: “The classification of ‘non-charter code city’ is adopted for the City of
    Issaquah in lieu of its present classification as a municipal corporation of the third class.” IMC
    1.08.010. Cities that elect to be classified as noncharter code cities are “governed according to
    the provisions of [Title 35A] under one of the optional forms of government provided for
    noncharter code cities.” RCW 35A.01.020. Under Title 35A, “[a] code city may protect and
    operate utility services as authorized by chapters 35.88, 35.91, 35.92, and 35.94 RCW.” RCW
    35A.80.010. “The term ‘code city’ means any noncharter code city or charter code city.” RCW
    35A.01.035. Accordingly, as a noncharter code city, the City was authorized to impose GFCs
    pursuant to RCW 35.92.025.
    14 Under chapter 35.92 RCW, “[a] city or town may . . . operate systems, plants, sites, or
    other facilities of sewerage as defined in RCW 35.67.010.” RCW 35.92.020(1). The cited statute
    defines “system of sewerage” to include, among other things, “[c]ombined sanitary sewage
    disposal and storm or surface water sewers,” “[s]torm or surface water sewers,” and “[o]utfalls for
    storm drainage . . . and facilities for storm drainage.” RCW 35.67.010(2)-(4).
    19
    No. 82025-7-I/20
    that such property owners shall bear their equitable share of the
    cost of such system.
    RCW 35.92.025.
    The connection charges imposed on Polygon’s properties were
    established pursuant to three city ordinances. First, ordinance 2748, which was
    passed in November 2015, stated with regard to the city-wide sewer GFC that
    “the general facility charge currently of $2,039 has not been evaluated since
    2006 and it is determined the rate should decrease to $2,024.” Issaquah
    Ordinance 2748 (Nov. 2, 2015). Next, ordinance 2749, which was also passed in
    November 2015, stated with regard to the city-wide stormwater GFC that “the
    current general facilities charge of $789.00 per equivalent service units (ESU) is
    increased to $1,256 to reflect the cost of service.” Issaquah Ordinance 2749
    (Nov. 2, 2015). Lastly, in March 2018, the city council passed ordinance 2830,
    which terminated the development agreement and required single-family
    residences in the Issaquah Highlands to be charged the city-wide water GFC of
    $6,029. Issaquah Ordinance 2830 (Mar. 18, 2018).
    “We presume the validity of ordinances, but this presumption no longer
    exists when evidence discloses that the basis on which the ordinance establishes
    the fee is not the proper basis the statute authorized.” Palermo at Lakeland, LLC
    v. City of Bonney Lake, 
    147 Wn. App. 64
    , 76, 
    193 P.3d 168
     (2008) (citing Boe v.
    City of Seattle, 
    66 Wn.2d 152
    , 155, 
    401 P.2d 648
     (1965)); accord Prisk v. City of
    Poulsbo, 
    46 Wn. App. 793
    , 804, 
    732 P.2d 1013
     (1987) (“Connection fees
    established by ordinance are presumptively valid, and one who challenges them
    has the burden of proving that the charges are unreasonable.” (citing Boe, 66
    20
    No. 82025-7-I/21
    Wn.2d at 155)). Additionally, “[w]e will sustain a legislative determination if we
    can conceive of any state of facts that justify the determination.” Palermo, 147
    Wn. App. at 76.
    Under RCW 35.92.025, “the only requirements placed on [cities] are that
    the charge is reasonable and that [cities] base[] these charges on the equitable
    cost of their [utility] system.” Palermo, 147 Wn. App. at 79. Additionally, “‘the
    fundamental basis on which the fee is to be calculated . . . is not that of the
    benefit received but merely an equitable sharing of the cost of the system.’” Boe,
    
    66 Wn.2d at 156
    .
    Polygon contends that the water, sewer, and stormwater GFCs imposed
    on its properties located within the Westridge Single-Family North development
    were not reasonable under RCW 35.92.025. This is so, Polygon argues,
    because the impacts of the Westridge Single-Family North development were
    “fully mitigated” under the development agreement.15 However, Polygon does
    15 In support of its argument that the impacts of the Westridge Single-Family North
    development on the City’s utility systems were “fully mitigated,” Polygon cites to various
    documents. However, none of these documents demonstrate that Polygon had paid an equitable
    share in the cost of the city-wide utility systems. Rather, these documents provide merely that (1)
    the infrastructure in the Issaquah Highlands was adequate to support the needs of the
    development, and (2) the City utility systems had the capacity to support the needs of the
    development.
    First, Polygon quotes the development agreement, which provides that “[t]he
    Partnership’s compliance with the Development Standards and performance of its obligations
    contained in this Agreement . . . shall constitute the adequacy and sufficiency of public facilities
    and services for the Project.” This language indicates only that Port Blakely’s performance under
    the development agreement would allow the Issaquah Highlands to be adequately supported by
    public facilities. It does not indicate that Port Blakely had paid an equitable share of the cost of
    the city-wide utility systems.
    Second, Polygon cites to two City memoranda, dated December 16, 2013, and February
    26, 2015, which provided that adequate capacity existed in the City’s water, sewer, and
    stormwater systems to support further development in the Issaquah Highlands. These
    memoranda did not provide that the Westridge Single-Family North development’s impacts on the
    water, sewer, and stormwater systems were “fully mitigated” such that Polygon had paid an
    equitable share of the cost of these city-wide utility systems.
    21
    No. 82025-7-I/22
    not attempt to demonstrate that the GFCs enacted pursuant to ordinances 2748,
    2749, and 2830 were established on an improper basis.
    Yet to successfully challenge GFCs enacted pursuant to RCW 35.92.025,
    a party must adduce “‘evidence disclos[ing] that the basis on which the ordinance
    establishes the fee is not the proper basis authorized by the statue.’” Boe, 
    66 Wn.2d at 155
     (emphasis added). The statute requires connection charges
    established by ordinance to be “reasonable” such that “property owners shall
    bear their equitable share of the cost of” the city’s utility system. RCW 35.92.025
    (emphasis added). This language contemplates the equitable share of property
    owners as a class, not what is equitable to charge an individual property owner
    based on that particular owner’s impact on the city utility system.
    This reading of the statute is supported by the fact that “adopting a fee
    ordinance for [connection charges] is a purely legislative function under RCW
    35.92.025.” Palermo, 147 Wn. App. at 84-85. Indeed, “area-wide actions, such
    as the adoption of comprehensive plans and zoning ordinances, involving the
    Third, Polygon cites to a letter from the chair of the City’s Urban Village Development
    Commission recommending approval of Polygon’s preliminary plat application. This letter
    provided that “[t]he development standards for storm water management and groundwater
    protection as set forth in Appendix D of the Development Agreement were used to evaluate the
    proposal. Appropriate measures for storm water management and groundwater will be provided.”
    This letter also stated that “[t]he development standards for utilities as set forth in City standards
    were used to evaluate the proposal. The proposal, with the recommended conditions of approval,
    complies with the applicable standards.” This letter does not provide that Polygon had already
    paid an equitable share of the cost of the city-wide utility systems.
    Finally, Polygon cites to a letter from a City official commemorating Polygon’s purchase
    of “storm water capacity” from the City for a fee of $181,095. According to a staff report from the
    City’s Development Services Department, Polygon’s payment of this fee “allow[ed] [Polygon] to
    contribute additional stormwater to the City’s facilities.” In its response brief, Polygon states that,
    “[w]ith respect to stormwater, the City assessed the adequacy of the facilities built by Port Blakely
    specifically for the Westridge North subdivision and found those sufficient once Polygon paid a
    supplemental $181,095 fee.” Br. of Resp’t at 26-27. Thus, Polygon’s payment of this fee
    ensured that the facilities constructed by Port Blakely adequately served Polygon’s development.
    It did not ensure that Polygon paid an equitable share of the cost of the city-wide stormwater
    system.
    22
    No. 82025-7-I/23
    exercise of the legislative body’s policy-making role, are generally considered
    legislative.” Holbrook, Inc. v. Clark County, 
    112 Wn. App. 354
    , 365, 
    49 P.3d 142
    (2002). Notably, “such actions are not made quasijudicial simply because they
    affect specific individuals.” Holbrook, 112 Wn. App. at 365. “Although legislative
    decisions may appear adjudicatory when groups focus on how the particular
    decisions will affect their individual rights, all policy decisions begin with the
    consideration and balancing of individual rights.” Raynes v. City of Leavenworth,
    
    118 Wn.2d 237
    , 249, 
    821 P.2d 1204
     (1992).
    Because the City’s adoption of the GFCs at issue was legislative, rather
    than adjudicatory, in nature, Polygon cannot challenge these GFCs under RCW
    35.92.025 solely as they apply to its particular properties. After all, “‘the
    fundamental basis on which the fee is to be calculated . . . is not that of the
    benefit received but merely an equitable sharing of the cost of the system.’” Boe,
    
    66 Wn.2d at 156
    . Furthermore, the remedy when a party has established that
    connection charges enacted pursuant to RCW 35.92.025 are not reasonable is to
    invalidate the ordinance that enacted the connection charges, not to simply
    invalidate the charges as they apply to an individual property. See Boe, 
    66 Wn.2d at 156
     (“‘Under the evidence in this case, Ordinance No. 90233 Seattle
    Code No. 7.20.025 is unreasonable and therefore void.’”); Palermo, 147 Wn.
    App. at 68-69 (“We hold that the City arbitrarily adopted ordinance 1192 under
    which it assessed Palermo for connecting to the City’s water system; thus, the
    ordinance was void, leaving the prior ordinance in effect.”).
    23
    No. 82025-7-I/24
    Polygon cites to RCW 82.02.020 in support of its argument that cities are
    limited in “charg[ing] a project only to the extent reasonably related to the impacts
    a project will have on the larger system.”16 Under that statute, utility charges
    imposed by cities must generally be proportionate to a property’s share of the
    utility system’s cost:
    Nothing in this section prohibits counties, cities, or towns
    from imposing or permits counties, cities, or towns to impose water,
    sewer, natural gas, drainage utility, and drainage system charges.
    However, no such charge shall exceed the proportionate share of
    such utility or system’s capital costs which the county, city, or town
    can demonstrate are attributable to the property being charged.
    Furthermore, these provisions may not be interpreted to expand or
    contract any existing authority of counties, cities, or towns to
    impose such charges.
    RCW 82.02.020.
    However, RCW 82.02.020 does not apply to connection charges
    established pursuant to RCW 35.92.025. We say this because RCW 35.92.025
    was enacted in 1965 and the language quoted above was amended to RCW
    82.02.020 in 1982. See LAWS OF 1965, ch. 7; LAWS OF 1982, 1st Ex. Sess., ch.
    49, § 5. In Prisk, for instance, two property owners asserted that connection
    charges enacted by the Poulsbo city council pursuant to RCW 35.92.025 violated
    the requirement set forth in RCW 82.02.020 that utility charges must be
    proportionate to a property’s share of the utility system’s cost. 
    46 Wn. App. at 803
    . Division Two disagreed:
    [W]e hold that RCW 82.02.020 does not limit the City’s authority to
    impose these connection charges. That statute would require that
    utility charges be proportionate to the share of the utility’s costs
    “attributable to the property being charged.” However, the statute
    has no application here as it specifically states that the existing
    16   Br. of Resp’t at 23.
    24
    No. 82025-7-I/25
    authority of cities to impose such charges remains unaffected by
    the statute. The City’s existing authority is derived from RCW
    35.92.025, which was enacted prior to RCW 82.02.020.
    Prisk, 
    46 Wn. App. at 803
    .
    Therefore, the City’s water, sewer, and stormwater GFCs were not
    required, under RCW 82.02.020, to be proportionate to the share of the utility
    systems’ costs attributable to Polygon’s properties.
    Polygon asserts that the City bore the burden to prove that the GFCs
    imposed on its properties were reasonable. In support of this argument, Polygon
    cites to Palermo, 
    147 Wn. App. 64
    . However, that opinion provides that the
    burden of proof shifts to a city only when a property owner adduces evidence
    demonstrating that the ordinance in dispute established a connection charge on
    an improper basis. See Palermo, 147 Wn. App. at 75, 84.
    Indeed, a property owner in the Palermo dispute demonstrated that “the
    City adopted the ordinances based on outdated and incorrect numbers.” 147
    Wn. App. at 81. The city therein did not adduce any evidence based on data that
    was actually considered by the city when it adopted the charges at issue.
    Palermo, 147 Wn. App. at 83. Because the evidence that was adduced by the
    city was not based on data that was before the city when it adopted the
    ordinances at issue, the court held that the evidence that was presented by the
    city was “not relevant to [the] court’s consideration.” Palermo, 147 Wn. App. at
    84. In light of the evidence that was adduced at trial, the court clarified that “the
    City still bears the burden of satisfying RCW 35.92.025 by providing reasonable
    25
    No. 82025-7-I/26
    [charges] based on equitable shares of the cost of the system.” Palermo, 147
    Wn. App. at 84.
    Polygon did not adduce any evidence challenging the method by which
    the City’s ordinances established the GFCs at issue. For example, Polygon did
    not demonstrate that, in adopting these GFCs, the City excluded from its
    calculations properties that fell within the scope of the development agreement
    and that such exclusion unreasonably impacted the rate at which the GFCs were
    assessed against property owners city-wide. Because Polygon failed to satisfy
    its initial burden of proof, the burden never shifted to the City to prove that the
    GFCs were calculated on a proper basis.
    Accordingly, Polygon fails to meet its burden to prove that the GFCs
    imposed by the City violate RCW 35.92.025. Additionally, under LUPA, the City’s
    imposition of the disputed GFCs do not constitute an erroneous interpretation of
    law or a clearly erroneous application of law to the facts.
    V
    The superior court’s order is reversed insofar as it requires the City to (1)
    refund the water, sewer, and stormwater GFCs that were imposed on Polygon’s
    properties located within the Westridge Single-Family North development, and
    (2) assess GFCs for future building permits submitted by Polygon according to
    the development agreement. The order is affirmed insofar as it varies the
    amount that the City is authorized to charge Polygon for the side-sewer fees and
    water-meter installations fees that were imposed on its properties.
    26
    No. 82025-7-I/27
    Affirmed in part, reversed in part.
    WE CONCUR:
    27