Northwood Estates, Llc v. Lennar Northwest, Inc. ( 2020 )


Menu:
  •                                                                                            Filed
    Washington State
    Court of Appeals
    Division Two
    March 3, 2020
    IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    DIVISION II
    NORTHWOOD ESTATE, LLC, a Washington                             No. 52000-1-II
    State limited liability company,
    Respondent,
    v.
    LENNAR NORTHWEST, INC., a Delaware                         UNPUBLISHED OPINION
    corporation,
    Appellant.
    GLASGOW, J.—Northwood Estate LLC contracted to sell 33 residential lots to Lennar
    Northwest, Inc. In relevant part, an amendment to their agreement provided that if Northwood
    successfully recorded an approved plat modification by a specified deadline, the number of lots
    would increase by five and Lennar would pay Northwood an additional $765,000. When the
    deadline passed without successful approval and recording, Lennar assumed control of the
    modification application and refused to pay Northwood the additional $765,000. Northwood sued
    Lennar for breach of contract and included alternative claims of quantum meruit and unjust
    enrichment.
    Lennar argued the relevant provision was an unsatisfied condition precedent excusing
    Lennar from payment. The trial court ultimately agreed with Northwood that the plat modification
    provision was instead a contractual obligation, and so Lennar was not excused from payment, but
    it could seek damages for Northwood’s delay. The court granted summary judgment to Northwood
    No. 52000-1-II
    on its breach of contract claim and granted summary judgment to Lennar rejecting the quantum
    meruit and unjust enrichment claims.
    Lennar obtained discretionary review of the breach of contract decision. Northwood
    counters that the trial court was correct to rule in its favor because treating the provision as a
    condition precedent would result in forfeiture, and forfeitures are disfavored. In the alternative,
    Northwood argues that if the provision was a condition precedent, we should employ equitable
    remedies to prevent the forfeiture of $765,000 that would result from enforcement of the condition.
    In that event, Northwood asks that we reinstate its equitable claims.
    We reverse the trial court’s conclusion that the plat modification provision was a
    contractual promise and its grant of summary judgment to Northwood on this basis. We hold that
    the relevant provision created a condition precedent and recognize that conditions precedent
    should not be strictly enforced if they effectuate a harsh forfeiture. We remand to the trial court
    to determine whether any equitable relief is appropriate to prevent forfeiture in this case and, if so,
    what form that relief should take.
    FACTS
    In December 2015, Northwood entered into a purchase and sale agreement to sell 33
    residential lots in the city of Edgewood, Washington to Lennar for $153,000 per lot. Paragraph 2.3
    of the agreement provided that Northwood would obtain, at its expense, a plat modification to
    convert 8 of the lots into 13 separate lots, increasing the total number of lots by 5. If the plat
    modification was recorded within a year after closing, Lennar would pay Northwood an additional
    $765,000. If Northwood could not meet that deadline, it could extend the plat modification
    deadline once for up to three months.
    2
    No. 52000-1-II
    Paragraph 2.3 also provided that if Northwood could not obtain finished lots prior to
    closing, then it would be in default. Paragraph 7.1 defined “default” as the “failure of either party
    to perform any act to be performed by such party” if the failure continued for 10 days after written
    notice by the nondefaulting party. Clerk’s Papers (CP) at 29. Paragraph 10.14 also provided,
    “Time is of the essence with respect to the performance by Buyer and Seller of each and every
    obligation under each and every provision of this Agreement.” CP at 33.
    On December 6, 2016, the parties amended the agreement’s plat modification provision,
    changing the modification deadline to December 1, 2017, and removing Northwood’s right to
    extend the deadline any further. The second amendment reaffirmed, “If the Plat Modification has
    recorded not later than the Plat Modification Deadline, the number of Lots will increase by five
    (5) and Buyer shall pay Seller an additional Seven Hundred Sixty Five Thousand and No/100
    Dollars ($765,000).” CP at 38. It then continued, “If Seller does not obtain the Plat Modification
    by the Plat Modification Deadline, Seller shall assign and turn over to Buyer Seller’s applicant
    status to the Plat Modification and all other entitlements, development rights, and permits related
    thereto.” CP at 38.
    Closing occurred on December 8, 2016, and Northwood had almost a year to fulfill its
    remaining obligation to obtain approval for and record the plat modification by the new deadline
    of December 1, 2017.
    On November 13, 2017, Northwood submitted the plat modification application to the city
    of Edgewood. The city then informed Northwood that the city council would not review the
    application until January 9, 2018 due to holiday schedules. On December 4, 2017 Lennar informed
    Northwood that it would not pay the $765,000 and that it would take over as the applicant with all
    3
    No. 52000-1-II
    related entitlements, development rights, and permits, as outlined in the second amendment.
    Northwood did not receive a 10-day notice of default and opportunity to cure, as is provided for
    in the agreement where one party is in default. On December 13, 2017, Lennar received a notice
    of incomplete application. The notice requested that Lennar correct and resubmit the final plat
    drawing by removing buffer setback lines. The notice also requested that Lennar submit a corrected
    application with the signatures of parties authorized to act on its behalf. On January 9, 2018,
    Lennar submitted a revised application. The city deemed the application complete on January 10,
    2018, granted the application, and recorded it on January 25, 2018.
    Lennar refused to pay Northwood for the additional five lots because Northwood had not
    complied with the deadline established in the second amendment. Northwood sued Lennar for
    breach of contract. It alternatively sought recovery under quantum meruit and unjust enrichment.
    In a declaration, Northwood’s managing member stated that Northwood had spent approximately
    $260,000 and 750 hours on modifying the plat and preparing the application. This included, for
    example, engineering, surveying, excavation, and the reworking of driveway approaches, curbing,
    and gutters. He further stated that he had not intended to assume the risk of the modification not
    being recorded in time, and that he was no longer in control of the application once it was submitted
    to city officials, who informed him after submission that recording may be delayed by its holiday
    schedule.
    Both parties moved for summary judgment. Lennar argued that the amended plat
    modification provision established a condition precedent—that Northwood would obtain the
    modification by the deadline—and so once Northwood failed to meet that condition, Lennar was
    excused from payment. Northwood countered that the provision should instead be read as a
    4
    No. 52000-1-II
    contractual promise in order to avoid a forfeiture, such that Northwood’s failure to meet the
    deadline constituted a minor breach but did not excuse Lennar from paying the $765,000. In the
    alternative, Northwood argued that if the provision was a condition precedent, Northwood was
    entitled to recovery under unjust enrichment or quantum meruit.
    The trial court initially concluded there was a condition precedent, but indicated that unjust
    enrichment or quantum meruit may be available to avoid enforcement because enforcement would
    result in a forfeiture. The court dismissed the breach of contract claim but concluded that issues
    of fact existed with respect to Northwood’s claims for unjust enrichment and quantum meruit. The
    parties would therefore proceed to trial on those claims.
    Both parties moved for reconsideration. Lennar argued that the trial court should have
    dismissed Northwood’s unjust enrichment and quantum meruit claims, while Northwood argued
    the court should have interpreted the plat modification provision as a contractual promise. On
    reconsideration, the trial court agreed with Northwood that the provision was not, in fact, a
    condition precedent. The court also granted Lennar’s motion to dismiss Northwood’s quantum
    meruit and unjust enrichment claims. The court determined that the only remaining issue for trial
    would be the amount of offset damages to Lennar caused by Northwood’s delay, even though
    Lennar had not filed a counterclaim for damages.
    Lennar sought discretionary review on the condition precedent issue, which we granted.
    5
    No. 52000-1-II
    ANALYSIS
    I. INTERPRETATION OF THE PLAT MODIFICATION PROVISION
    A.     Standard of Review
    In reviewing a grant of summary judgment, we apply the same standard as the trial court.
    Summary judgment is appropriate “‘if the pleadings, depositions, answers to interrogatories, and
    admissions on file, together with the affidavits, if any, show that there is no genuine issue as to
    any material fact and that the moving party is entitled to a judgment as a matter of law.’” DeVeny
    v. Hadaller, 
    139 Wn. App. 605
    , 616, 
    161 P.3d 1059
     (2007) (quoting CR 56(c)). We consider the
    evidence and the reasonable inferences therefrom in the light most favorable to the nonmoving
    party. Sutton v. Tacoma Sch. Dist. No. 10, 
    180 Wn. App. 859
    , 864, 
    324 P.3d 763
     (2014). “‘We
    review the trial court’s conclusions of law de novo.’” DeVeny, 139 Wn. App. at 616 (quoting
    Bingham v. Lechner, 
    111 Wn. App. 118
    , 127, 
    45 P.3d 562
     (2002)).
    “The moving party bears the burden of first showing that there is no genuine issue of
    material fact.” State v. Grocery Mfrs. Ass’n, 5 Wn. App. 2d 169, 185, 
    425 P.3d 927
     (2018), review
    granted, 
    193 Wn.2d 1001
     (2019). Where reasonable minds could reach only one conclusion from
    the admissible facts in evidence, that issue may be determined on summary judgment. Sutton, 180
    Wn. App. at 864-65.
    “When interpreting a contract, our primary objective is to discern the parties’ intent.” Wm.
    Dickson Co. v. Pierce County, 
    128 Wn. App. 488
    , 493, 
    116 P.3d 409
     (2005).                 Contract
    interpretation is a question of law reviewed de novo where, as here, the “‘interpretation does not
    depend on the use of extrinsic evidence.’” Kelley v. Tonda, 
    198 Wn. App. 303
    , 312-13, 
    393 P.3d 824
     (2017) (quoting Spectrum Glass Co. v. Pub. Util. Dist. No. 1 of Snohomish County, 
    129 Wn. 6
    No. 52000-1-II
    App. 303, 311, 
    119 P.3d 854
     (2005)). Summary judgment therefore is appropriate where the only
    dispute is over the interpretation of particular contract language, without reliance on extrinsic
    evidence. Id. at 313. The parties here do not dispute any material facts, but rather dispute the
    proper interpretation of the plat modification provision based on the contract language.
    B.     The Plat Modification Provision Is a Condition Precedent
    Lennar argues that the trial court erred in interpreting the plat modification provision as a
    contractual promise,1 rather than as a condition precedent. We agree that the provision creates a
    condition precedent.
    A condition precedent is an event that must occur before there is a right to immediate
    performance of a contract. Tacoma Northpark, LLC v. NW, LLC, 
    123 Wn. App. 73
    , 79, 
    96 P.3d 454
     (2004). If the condition does not occur, the parties are excused from performance. 
    Id.
     In
    contrast, the breach of a contractual promise subjects the promisor to liability for damages, but it
    does not necessarily discharge the other party’s duty of performance. 
    Id.
    Therefore, if the second amendment is a condition precedent, then Lennar was not
    obligated under the contract to pay Northwood the additional $765,000 for the five additional lots
    once Northwood failed to record the plat modification at the deadline. However, if the second
    amendment is a promise, then Lennar may be entitled to damages from Northwood, but still must
    pay Northwood for the additional lots.
    Whether a contract provision is a condition precedent or a contractual promise depends on
    the intent of the parties, to be determined from a fair and reasonable construction of the language
    1
    The parties use the term “covenant,” whereas the case law uses the term “contractual obligation”
    or “contractual promise.” There being no meaningful distinction, we adopt the language used in
    the case law.
    7
    No. 52000-1-II
    used in light of all the surrounding circumstances. Lokan & Assocs., Inc. v. Am. Beef Processing,
    LLC, 
    177 Wn. App. 490
    , 499, 
    311 P.3d 1285
     (2013). “[W]ords such as ‘provided that,’ ‘on
    condition,’ ‘when,’ ‘so that,’ ‘while,’ ‘as soon as,’ and ‘after’ suggest a conditional intent, not a
    promise.” Tacoma Northpark, 123 Wn. App. at 80 (quoting Jones Assocs., Inc. v. Eastside Props.,
    Inc., 
    41 Wn. App. 462
    , 467, 
    704 P.2d 681
     (1985)). The terms “subject to” and “contingent upon”
    likewise demonstrate an intent to form a condition precedent. 
    Id.
     And the Jones Associates court
    noted that a provision using the term “if” created an express condition precedent in that case. 
    41 Wn. App. at
    467-68 & n.4.
    Where it is doubtful whether words create a contractual promise or an express condition
    precedent, we will interpret them as creating a promise. Tacoma Northpark, 123 Wn. App. at 80.
    This is because forfeitures are disfavored, so when resolving doubts as to whether a condition
    precedent exists, “‘an interpretation is preferred that will reduce the obligee’s risk of forfeiture,
    unless the event is within the obligee’s control or the circumstances indicate that he has assumed
    the risk.’” Jones Assocs., 
    41 Wn. App. at 469
     (quoting RESTATEMENT (SECOND) OF CONTRACTS
    § 227(1) (1981)). On the other hand, “if the term that requires the occurrence of the event as a
    condition is expressed in unmistakable language, the possibility of forfeiture will not affect the
    interpretation of that language.” RESTATEMENT, supra, § 229 cmt. a.
    We conclude that the second amendment created a clear condition precedent.                The
    amendment provided, “If the Plat Modification has recorded not later than the Plat Modification
    Deadline, the number of Lots will increase by five (5) and Buyer shall pay Seller an additional
    Seven Hundred Sixty Five Thousand and No/100 Dollars ($765,000).” CP at 38 (emphasis added).
    “If Seller does not obtain the Plat Modification by the Plat Modification Deadline, Seller shall
    8
    No. 52000-1-II
    assign and turn over to Buyer Seller’s applicant status to the Plat Modification and all other
    entitlements, development rights, and permits related thereto.” CP at 38.
    The use of the term “if” makes clear that Lennar’s payment to Northwood of $765,000 is
    conditioned on Northwood obtaining the plat modification by the specified deadline. Under the
    second amendment, Northwood assumed the risk of not getting the modification recorded before
    the deadline. The parties agreed to an extension of the modification deadline and removed
    Northwood’s ability to extend it any further. Although Northwood did not have any direct control
    over how long it would take for city officials to approve the application after submission, it had
    full control over the submission and yet did not submit the application until only two weeks before
    the deadline. Furthermore, the city required a change to the application that Northwood had
    submitted before the city could process it.
    Northwood argues that the parties’ agreement did not create a condition precedent because
    it would enable Lennar to “walk[] away with everything.” Br. of Resp’t at 11-12. Northwood
    cites to Thatcher v. Salvo, 
    128 Wn. App. 579
    , 585-87, 
    116 P.3d 1019
     (2005), where the court
    found an unfulfilled condition precedent, and as a result, the buyer kept their money while the
    seller kept their property. Northwood contends this case is different because Lennar received five
    additional lots, while Northwood had to forgo the promised $765,000, and it spent $260,000 on
    the plat modifications. Thus, Lennar received a windfall that was absent in Thatcher.
    But in Thatcher, there was no dispute that the contract contained a condition precedent.
    128 Wn. App. at 585-87. Both parties were returned to their original position, but that was a
    consequence of the unfulfilled condition precedent and not a prerequisite for finding a condition
    precedent in the first place, as Northwood appears to argue. Id. The fact that Lennar ended up
    9
    No. 52000-1-II
    with a windfall in this case may implicate equitable remedies, but it does not bear on whether the
    provision was a condition precedent in the first place where it is clear from the contract language
    that one party’s performance is conditioned on some other act occurring first.
    Northwood also argues that we should apply the principles articulated in Jones Associates
    that both conditions precedent and forfeitures are disfavored. 
    41 Wn. App. at 469-70
    . Forfeitures
    are disfavored, and where there is some doubt as to whether a condition exists, we prefer
    interpretations that do not result in a forfeiture. Id. at 469. But the Jones Associates court rested
    its decision on the fact that the express language of the provision did not contain any words clearly
    creating a condition precedent. Id. at 467. It was therefore “unclear whether the parties intended
    obtaining King County approval to be a condition precedent to payment under the contract.” Id.
    In contrast, in this case, it is clear that the express language of the plat modification proviso created
    a condition precedent: if the plat modification was recorded by the deadline, then the number of
    lots would increase and Lennar would pay Northwood an additional $765,000.
    Northwood next argues that the second amendment did not create a condition precedent
    because it must be read in context with the rest of the contract, which contained default provisions
    addressing remedies when a party failed to perform. Paragraph 2.3 of the original agreement
    separately provided that if Northwood could not obtain the required finished lots prior to closing,
    it would be in default. In addition, paragraph 7.1 defined “default” as the “failure of either party
    to perform any act to be performed by such party” if the failure continued for 10 days after written
    notice by the nondefaulting party. CP at 29. Northwood argues that in the context of these
    provisions, the plat modification provision in the second amendment should be read as a
    contractual promise because the plat modification was an act to be performed by Northwood.
    10
    No. 52000-1-II
    According to Northwood, its failure to meet the December 1, 2017 deadline should have been
    interpreted as a failure to perform under paragraph 7.1 of the agreement, and Lennar should have
    notified Northwood and given it 10 days to cure the failure before nonperformance could be
    deemed a default.
    This argument ignores the fact that closing had already occurred, and the provision
    addressing failure to obtain finished lots before closing specifically invoked the default paragraph
    7.1. In contrast, the provision at issue here regarding plat modification postclosing does not refer
    to the default provision. If the parties had intended for the plat modification to be encompassed
    by paragraph 7.1, they could have explicitly stated as much, as they did with respect to the
    requirement that Northwood obtain finished lots before closing. Instead, they used language that
    signaled that obtaining a plat modification was a condition precedent to Lennar paying Northwood
    the additional $765,000, as well as language that described what would happen in the event that
    Northwood could not obtain the modification.
    In sum, we hold that, based on the plain language of the second amendment, the parties
    intended for the plat modification provision to create a condition precedent. We next consider
    whether Northwood’s failure to meet the condition should nevertheless be excused to avoid
    forfeiture.
    C.      Northwood May Be Entitled to Equitable Remedies to Prevent a Forfeiture
    Northwood argues in the alternative that, even if the plat modification provision is a
    condition precedent, it should nevertheless not be strictly enforced in order to avoid a forfeiture.
    We agree that equitable remedies may be appropriate and remand for the trial court to make this
    determination.
    11
    No. 52000-1-II
    1. Equitable grace period to avoid forfeiture
    “‘[E]quity has a right to step in and prevent the enforcement of a legal right whenever such
    an enforcement would be inequitable.’” Proctor v. Huntington, 
    169 Wn.2d 491
    , 500, 
    238 P.3d 1117
     (2010) (alteration in original) (quoting Arnold v. Melani, 
    75 Wn.2d 143
    , 152, 
    437 P.2d 908
    ,
    
    449 P.2d 800
    , 
    450 P.2d 815
     (1968)). Forfeitures are not favored in law and to avoid their
    harshness, courts have granted equitable remedies to avoid the hardship that often results from
    strict enforcement. Pardee v. Jolly, 
    163 Wn.2d 558
    , 574, 
    182 P.3d 967
     (2008). Conditions
    precedent “will be excused if enforcement would involve extreme forfeiture or penalty and if the
    condition does not form an essential part of the bargain.” Ashburn v. Safeco Ins. Co. of Am., 
    42 Wn. App. 692
    , 698, 
    713 P.2d 742
     (1986); see also Kilcullen v. Calbom & Schwab, PSC, 
    177 Wn. App. 195
    , 204-05, 
    312 P.3d 60
     (2013) (“A trial court has the authority to excuse a condition to
    performance . . . where enforcing the condition would cause disproportionate forfeiture.”);
    RESTATEMENT, supra, § 229. “‘To justify a forfeiture for the violation of the condition, the
    violation must be wilful and substantial.’” Port of Walla Walla v. Sun-Glo Producers, Inc., 
    8 Wn. App. 51
    , 59, 
    504 P.2d 324
     (1972) (quoting In re Estate of Murphy, 
    191 Wash. 180
    , 188, 
    71 P.2d 6
     (1937), rev’d on other grounds, 
    193 Wash. 400
    , 
    75 P.2d 916
     (1938)).
    For example, where strict enforcement of a forfeiture would result in hardship and “‘do
    violence to the principle of substantial justice between the parties’” under the facts of a case, courts
    may excuse performance of a condition by extending a grace period for the party violating the
    condition to complete their performance. Ryker v. Stidham, 
    17 Wn. App. 83
    , 89, 
    561 P.2d 1103
    (1977) (quoting Dill v. Zielke, 
    26 Wn.2d 246
    , 252, 
    173 P.2d 977
     (1946)); see Rains v. Lewis, 
    20 Wn. App. 117
    , 122, 
    579 P.2d 980
     (1978). In other words, the court may “‘rewrite’” the contract
    12
    No. 52000-1-II
    to provide a reasonable amount of time for the offending party to complete performance before
    allowing forfeiture and to set terms whereby the contract can be reinstated. Vacova Co. v. Farrell,
    
    62 Wn. App. 386
    , 405, 
    814 P.2d 255
     (1991). Whether a grace period is warranted depends on the
    equities in each particular case. Pardee, 
    163 Wn.2d at 574
    . In determining whether an equitable
    grace period is appropriate, courts have considered nonexclusive factors such as the amount that
    would be forfeited without the equitable relief sought, whether the failure to meet the deadline was
    inadvertent, and whether the other party was prejudiced by the delay. Cornish Coll. of the Arts v.
    1000 Va. Ltd. P’ship, 
    158 Wn. App. 203
    , 218-20, 
    242 P.3d 1
     (2010).
    In Pardee, our Supreme Court remanded to the trial court to consider, in light of the
    “significant forfeiture” at issue, whether the facts and circumstances of that case demanded that an
    equitable grace period be extended. 
    163 Wn.2d at 576
    . That case involved the termination of an
    option to purchase after Pardee failed to timely notify the property owner that he was exercising
    the option. 
    Id. at 572
    . But because Pardee had expended over $20,000 and 2,500 hours of work
    improving the property, the court concluded that he may have been entitled to a grace period to
    avoid the forfeiture. 
    Id. at 576
    .
    Pardee followed the reasoning of two Court of Appeals cases, Wharf Restaurant, Inc. v.
    Port of Seattle, 
    24 Wn. App. 601
    , 
    605 P.2d 334
     (1979), and Heckman Motors, Inc. v. Gunn, 
    73 Wn. App. 84
    , 
    867 P.2d 683
     (1994). In Wharf Restaurant, a long term lessee failed to timely
    exercise an option to renew its lease, although it had made substantial improvements to the
    property and intended to renew. 
    24 Wn. App. at 603
    . The court considered the equities of the
    case, noting equity’s abhorrence of forfeitures, and concluded that a grace period should be
    extended to enable the lessee to renew the option. Id. at 611-12. In doing so, the court considered
    13
    No. 52000-1-II
    the following factors: (1) whether the failure to exercise the option was inadvertent rather than
    intentional, culpable, or grossly negligent; (2) whether the lessee made valuable permanent
    improvements; (3) whether the lessor was prejudiced by the untimely notice; (4) the length of the
    lease; and (5) whether the lessor contributed to the delay. Id. at 612-13.
    In Heckman Motors, in contrast, we held that the lessee failing to renew an option was not
    entitled to a grace period because it had not made substantial improvements to the property, there
    was a substantial delay in exercising the option, and the lessor had done nothing to contribute to
    the delay. 
    73 Wn. App. at 88-89
    . We noted that whether an equitable grace period is appropriate
    is largely within the trial court’s discretion, and the trial court there determined that equity did not
    demand an exception to excuse the untimely exercise of the option. Id. at 88.
    Here, the plat modification deadline arguably may have been essential to the contract
    because the plat modification was the only remaining task under the contract and the parties’ time-
    is-of-the-essence provision suggests that a condition involving the modification deadline was
    important. However, apart from the boilerplate time-is-of-the-essence provision, Lennar does not
    point to anything in the record showing that timeliness was an essential part of the bargain or that
    Lennar suffered substantial harm or prejudice as a result of the delay. Nor is there any evidence
    that Northwood’s failure to record the modification in time was willful, intentional, or even grossly
    negligent. Finally, without a grace period or other equitable relief, the forfeiture would be extreme:
    the inability to recover the $260,000 expended, the additional 750 hours of work expended, other
    forgone opportunities, and the lost anticipated profits that Northwood would have received as a
    result of the $765,000 payment. In contrast, Lennar essentially received five extra lots at no
    apparent significant additional expense.
    14
    No. 52000-1-II
    In part because it incorrectly concluded that the second amendment did not contain a
    condition precedent, the trial court did not expressly consider an equitable grace period or other
    equitable relief in the face of Northwood’s failure to satisfy a condition precedent. Because
    providing an equitable remedy is within the trial court’s discretion and because the trial court in
    this case has not yet made this determination, we remand for the trial court to determine whether
    equitable relief is appropriate and, if so, what form it should take. See Pardee, 
    163 Wn.2d at 576
    .
    Such relief may include extension of an equitable grace period to Northwood to complete its
    performance of the condition, reduction of the $765,000 contract price based on the costs or other
    harm incurred by Lennar as a result of the delay, payment of costs to Northwood for its time and
    effort spent preparing the plat modification application, or some combination of these or other
    possible remedies.2 See Emerick v. Cardiac Study Ctr., Inc., 
    189 Wn. App. 711
    , 730, 
    357 P.3d 696
     (2015) (“[A] trial court has broad discretionary authority to fashion equitable remedies.”). A
    party does not need to plead damages for the trial court to consider all types of remedies in equity,
    including, for example, reducing the $765,000 by an amount that Lennar was harmed by
    Northwood’s delay. The trial court may hear additional evidence to inform its determination.
    2
    In equity to avoid forfeiture, Washington courts have crafted remedies specific to the
    circumstances of a particular case. For example, courts have also allowed conditional
    reinstatement of a real estate contract, Falaschi v. Yowell, 
    24 Wn. App. 506
    , 510, 
    601 P.2d 989
    (1979), a right of prepayment in full, Terry v. Born, 
    24 Wn. App. 652
    , 656, 
    604 P.2d 504
     (1979),
    and substitution of a reasonable time for completing payment, Kilcullen, 177 Wn. App. at 205-
    06.
    15
    No. 52000-1-II
    2. Unjust enrichment and quantum meruit
    Northwood also argues that if the modification provision is a condition precedent, we
    should remand for the trial court to reinstate its equitable claims for unjust enrichment and quantum
    meruit. We disagree.
    “‘A party to a valid express contract is bound by the provisions of that contract, and may
    not disregard the same and bring an action on an implied contract relating to the same matter, in
    contravention of the express contract.’” Boyd v. Sunflower Props., LLC, 
    197 Wn. App. 137
    , 149,
    
    389 P.3d 626
     (2016) (quoting Chandler v. Wash. Toll Bridge Auth., 
    17 Wn.2d 591
    , 604, 
    137 P.2d 97
     (1943)). Unjust enrichment and quantum meruit are used to fill in gaps in a contract related to
    an unforeseen event or in situations where there is no contract governing the parties’ relationship.
    Young v. Young, 
    164 Wn.2d 477
    , 484-86, 
    191 P.3d 1258
     (2008); Hensel Phelps Constr. Co. v.
    King County, 
    57 Wn. App. 170
    , 174, 
    787 P.2d 58
     (1990). Neither remedy is available if the claim
    is covered by the terms of a contract. Boyd, 197 Wn. App. at 149; Douglas Nw., Inc. v. Bill O’Brien
    & Sons Constr., Inc., 
    64 Wn. App. 661
    , 683, 
    828 P.2d 565
     (1992).
    Here, the parties have a detailed contract that explicitly provided for what would happen
    in the event the plat modification provision was not recorded by the agreed upon deadline. As
    discussed above, the relevant question is whether equity demands that the contractual plat
    modification provision not be strictly enforced in order to avoid an extreme forfeiture. We
    accordingly decline to reinstate the unjust enrichment and quantum meruit claims.
    16
    No. 52000-1-II
    II. ATTORNEY FEES
    Northwood asks for attorney fees on appeal.       In its reply brief, Lennar suggests that it
    would be entitled to attorney fees as the prevailing party, but does not explicitly request attorney
    fees on appeal. Under RAP 18.1(a), a party must request fees to be entitled to them on appeal.
    Where a contract provides that attorney fees and costs shall be awarded to one of the
    parties, we shall award reasonable attorney fees and costs to the prevailing party. RCW 4.84.330;
    Connell Oil Inc. v. Johnson, 5 Wn. App. 2d 856, 865, 
    429 P.3d 1
     (2018). Paragraph 10.19 of the
    parties’ agreement entitles the prevailing party in any legal proceeding to attorney fees and costs.
    Nevertheless, because we remand to the trial court for further proceedings, neither party is yet a
    prevailing party. We decline to award either party attorney fees at this stage.
    CONCLUSION
    We reverse the trial court’s conclusion that the plat modification provision was a
    contractual promise and its grant of summary judgment to Northwood on this basis. We hold that
    the provision was instead a condition precedent. Because conditions precedent should not be
    strictly enforced if they effectuate a harsh forfeiture, we remand to the trial court to determine
    whether equitable relief is appropriate to prevent forfeiture and, if so, what form that relief should
    take.
    17
    No. 52000-1-II
    A majority of the panel having determined that this opinion will not be printed in the
    Washington Appellate Reports, but will be filed for public record in accordance with RCW 2.06.040,
    it is so ordered.
    Glasgow, J.
    We concur:
    Worswick, P.J.
    Cruser, J.
    18