Pacific Coast Shredding, Llc, Appellant/cross-res. v. Port Of Vancouver, Usa, Res/cross-app. ( 2020 )


Menu:
  •                                                                                               Filed
    Washington State
    Court of Appeals
    Division Two
    September 1, 2020
    IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    DIVISION II
    PACIFIC COAST SHREDDING, L.L.C., a                                 No. 52020-6-II
    Washington limited liability company,
    Appellant/Cross-Respondent,
    v.
    PORT OF VANCOUVER, USA, a                                      PUBLISHED OPINION
    Washington municipal corporation,
    Respondent/Cross-Appellant.
    GLASGOW, J.—The Port of Vancouver USA (Port) condemned a portion of land it leased
    to Pacific Coast Shredding LLC (PCS) and informed PCS of its right under federal and state law
    to receive financial compensation for any reasonable and necessary costs that PCS incurred as a
    result of the taking. PCS made a number of significant modifications to its operations and requested
    reimbursement for each of them. The Port largely rejected the request and paid PCS only for the
    cost of moving some of its personal property out of the condemned area.
    PCS appealed to an administrative panel, which upheld the Port’s decision. PCS then
    appealed to the superior court, which reversed. The court ruled that the panel erred in denying
    additional compensation because it failed to consider which of PCS’s actions were reasonable and
    necessary responses to the taking. The court held that the taking required PCS to do more than
    simply move personal property out of the condemned area in order to continue its operations. The
    Port did not further appeal this decision.
    No. 52020-6-II
    On remand, the administrative panel again denied additional compensation to PCS. The
    panel found that none of PCS’s actions were reasonable and necessary and that any increased
    operational costs incurred as a result of the taking were minimal. PCS again appealed to the
    superior court. The court ruled that the panel violated its remand instructions from the initial appeal
    and erred in denying any additional compensation. The court determined that PCS was entitled to
    the cost of reconfiguring one piece of heavy equipment and increased costs of moving shred
    material that PCS had incurred up until it reconfigured the equipment. But PCS was not entitled to
    reimbursement for any other operational changes.
    PCS appeals, seeking reimbursement for the cost of its full site reconfiguration. It argues
    that the panel’s decision violated the law of the case and was unsupported by substantial evidence,
    contrary to law, and arbitrary and capricious. The Port also filed a notice of appeal from the
    superior court’s decision but does not assign error to any aspect of the panel’s decision.
    We hold that although the panel’s challenged factual findings were supported by
    substantial evidence, the panel erred in denying additional compensation to PCS because it
    misapplied the law. First, the panel was bound by the superior court remand order, which the Port
    did not appeal, to award some level of compensation beyond only reimbursement for moving
    personal property out of the condemned area. Second, although the panel’s findings were
    supported by substantial evidence, it was a misapplication of the law and arbitrary and capricious
    for the panel to reject some additional compensation when the panel established that the taking
    required periodic relocation of shred material and, therefore, the taking impacted PCS’s operations
    beyond simply necessitating a move of personal property out of the condemned area.
    2
    No. 52020-6-II
    We reverse the panel’s decision in part and conclude that PCS is entitled to some additional
    compensation for reasonable and necessary relocation of shred material, as well as reasonable and
    necessary reconfiguration of one piece of equipment, the conveyor. The panel’s alternative
    findings establish that the amounts awarded by the superior court are appropriate. This matter is
    therefore remanded to the panel for entry of a final order awarding PCS $347,800 in expenses for
    reconfiguration of the conveyor and an additional $46,000 in tramming costs incurred to move
    shred material prior to reconfiguration, in addition to the $68,259 already paid. We otherwise
    affirm the panel’s decision rejecting all other claims. Consistent with the superior court’s order,
    the panel may consider any requests related to costs and fees.
    FACTS
    PCS operates a scrap metal recycling operation on land leased from the Port. Prior to the
    taking at issue in this case, PCS bought scrap metal and collected it at the north end of the property,
    where it fed the metal into a shredder. The machine broke the scrap metal into smaller pieces and
    separated ferrous and nonferrous material. Nonferrous shred was deposited into piles, while
    ferrous shred was conveyed through a “‘Z box,’” which filtered out impurities, to a picking station
    where employees checked for additional impurities. Clerk’s Papers (CP) at 6. At this point, a
    conveyor picked up the shred and deposited it into a large, partial annulus shaped “‘conveyor-
    stacked shred’” pile near the southern edge of the property. CP at 187. Depending on the size of
    this pile, PCS occasionally used front-end loaders to push some of the shred into another pile at
    the southwest corner of the property. Trucks entered the property from the east and then moved
    counterclockwise around the property, loading and unloading at various piles.
    3
    No. 52020-6-II
    The Port condemned a 47,598-square foot strip of the 13-acre leasehold, left of the orange
    dotted line in the image below, of which 7,332 square feet was used by PCS for its operations. The
    condemned area overlapped with the truck traffic path and some of the area PCS used to pile shred
    material. The following image is a demonstrative exhibit depicting a portion of PCS’s operations
    prior to the taking, with the dotted line depicting the boundary of the taking:
    Administrative Record (AR) at 1155. The condemnation required PCS to move its truck traffic
    path several feet to the north of where it was previously located, which then encroached into
    another area where PCS would pile shred material. Around 45 times a year, this shred pile grew
    big enough that it would block or partially block the new truck traffic path, creating a choke point.
    The Port informed PCS of its right under federal and state law to receive financial
    assistance to relocate or reconfigure its operations in light of the taking. A relocation specialist for
    4
    No. 52020-6-II
    the Port, Martyn Daniel, determined that PCS was eligible for reimbursement only for the cost of
    moving the shred and other materials out of the condemned area. The Port accordingly paid PCS
    $68,259.
    PCS disputed the Port’s conclusion that it was entitled only to payment for moving personal
    property from the condemned area. PCS contended that the taking required more substantial
    changes to its operations to maintain the traffic path necessary for trucks to travel along the south
    side of the property, as well as the space necessary for piling shred. To make room for the
    relocation of the truck traffic path, PCS reconfigured the conveyor by turning it 90 degrees to the
    west and extending it 77 feet, and PCS built a new shred pad in the new conveyor-stacked shred
    location. The following is a demonstrative exhibit depicting a portion of PCS’s operations after
    the taking:
    5
    No. 52020-6-II
    AR at 1160. In addition, PCS relocated a rail spur to the west, upgraded some storm water facilities,
    expanded and improved employee parking, added a new picking conveyor, and made substantial
    changes to its office space and the property entrance. Together these changes cost over $6.1
    million.
    PCS sought full reimbursement for all of these changes, arguing that they were all
    reasonable and necessary consequences of the taking. The Port rejected the claim. PCS appealed,
    and the Port convened a three-person panel to consider the evidence, hear testimony, and resolve
    the appeal.
    Neil Fitzpatrick, an operations manager at PCS, authorized the site reconfigurations. He
    testified about PCS’s reasons for the reconfiguration, although he admitted that he did not
    understand the full scope of the taking until the hearing. Three engineers—Dr. Adam Aleksander,
    Neil Alongi, and Valerie Uskoski—testified to the safety and efficiency concerns facing PCS in
    terms of maintaining the truck path. In particular, Aleksander and Alongi both testified that prior
    to the taking, PCS maintained a truck path width of at least 20 feet. The panel received conflicting
    testimony and photographic evidence, however, that PCS had maintained the truck path at a
    minimum width of 14.9 feet. Moreover, PCS’s initial construction plans for the reconfiguration
    that were submitted to the city provided for a 15-foot wide truck path.
    The panel upheld the Port’s decision not to reimburse PCS for moving shred out of the new
    truck traffic path or the reconfigurations it made to adjust its operations after the taking. The panel
    determined that the issue presented was an “all or nothing proposition”—whether PCS’s full site
    reconfiguration was a reasonable and necessary response to the taking. CP at 17. The panel did not
    enter formal findings of fact, but it did note that the site remained “virtually unchanged” after the
    6
    No. 52020-6-II
    taking except that the taking infringed on the area containing the shred pile. CP at 6. The panel
    recognized that, after the taking, the shred pile could occasionally spill onto the truck path and
    create a potential “‘choke point’” in the circulation of truck traffic. CP at 6. However, the panel
    noted that there was evidence that the truck path was at times as narrow as 14.9 feet wide before
    the taking, so the choke point issue could be avoided by reducing the width of the truck path after
    the taking. Thus, the panel concluded that PCS’s full reconfiguration was not a reasonable and
    necessary response to the “purported ‘choke point’” resulting from the taking. CP at 20-21. The
    panel accordingly denied any reimbursement beyond the $68,259 already paid for relocating the
    shred material from the condemned area.
    PCS appealed to Clark County Superior Court. The superior court ruled that the panel erred
    by concluding that the taking resulted only in a “potential ‘choke point,’” when the parties had
    agreed that the choke point was an actual consequence of the taking. CP at 193. Rather than
    consider “‘all or nothing’” whether the entire reconfiguration of PCS’s operations was reasonable
    and necessary, the panel should have conducted a more detailed analysis of which aspects of the
    reconfiguration were reasonable and necessary consequences of the taking. CP at 193. The superior
    court explained: “In order to continue to operate its business, PCS was required to address the
    issue created by the Port’s action, either by relocating portions of its facilities or by increasing its
    operational expenses through the movement of excess shred.” CP at 193.
    The superior court also noted in its summary of the underlying facts that PCS had
    previously maintained a minimum 20-foot traffic corridor around the shred piles. But the court did
    not expressly conclude that substantial evidence in the record failed to support the panel’s finding
    that PCS had historically narrowed the truck path to 14.9 feet occasionally.
    7
    No. 52020-6-II
    The superior court remanded for the panel to reconsider “the issue of the amount of PCS’s
    reconfiguration expenses that were necessary and reasonably related to addressing the ‘choke
    point’ caused by the Port’s condemnation of the southern portion of the leasehold property.” CP
    at 194. Neither party appealed the superior court’s decision.
    On remand, the panel denied additional compensation to PCS. The panel again concluded
    that the full site reconfiguration was not reasonable and necessary. The panel found that the truck
    path before the taking was sometimes as narrow as 14.9 feet wide, specifically noting that the
    evidence provided by the Port was more reliable than PCS’s evidence that the minimum width of
    the truck path had been 20 feet. The panel found that the taking required moving the truck path 8.5
    feet to the north in order to maintain a 14.9-foot wide truck path, and this encroached only on the
    shred stack and did not impact any buildings, structures, or equipment. Even so, the panel also
    found that the shred stack became large enough to encroach on the new truck traffic path several
    times a year, and the cost of moving the excess shred out of the way would be approximately
    $46,000 a year. The panel noted that there was “no credible evidence that PCS ever evaluated the
    actual impacts of the Port’s project or any [less expensive] alternatives that mitigated the alleged
    impact.” CP at 203.
    The panel concluded that none of PCS’s reconfiguration costs, taken individually, were
    reasonable or necessary because the reasonable solution was to periodically move any excess shred
    to another area and do nothing else. The panel also concluded that the increased costs PCS would
    have incurred of about $46,000 a year by following this “‘do nothing’” approach were de minimis
    and not reimbursable. CP at 205. The panel reasoned that it would have been far cheaper to move
    the shred and that the Port presented several other cheaper alternatives to a full reconfiguration,
    8
    No. 52020-6-II
    costing from $25,000 to about $775,000. One of these alternatives was turning the conveyor 90
    degrees at a cost of $347,800.
    The panel emphasized that PCS apparently never engaged in a cost-benefit analysis of its
    reconfiguration, and so it was unreasonable to proceed with the full $6.1 million reconfiguration
    without exploring cheaper alternatives. The panel also rejected PCS’s contention that the Port’s
    suggested alternatives were unsafe because PCS presented no evidence regarding the safety of
    those alternatives.
    The panel then entered a series of secondary findings specific to each action taken by PCS
    in case the superior court reversed the panel’s conclusion that PCS was not entitled to any further
    reimbursement. First, it found that turning the conveyor 90 degrees was not reasonable and
    necessary and, even if it were, only $347,800 of the $3,129,528 claimed by PCS for accomplishing
    the conveyor turn was actually attributable to the taking and reimbursable.
    Second, the panel found that relocating the rail spur was not reasonable and necessary
    because there was evidence that PCS had often used the existing rail spur to store scrap metal
    before the taking, so there was nothing to suggest that PCS could not continue that practice with
    excess shred after the taking. Again, the panel emphasized that PCS did not analyze any
    alternatives. The panel explained that the only plausible explanation for moving the rail spur was
    PCS’s decision to extend the conveyor 77 feet to the west, but that extension was not related to the
    taking and instead was an improvement that was not eligible for reimbursement. And even if the
    extension and moving the spur were reasonable and necessary, the panel found that a minor (and
    cheaper) alternative adjustment to the spur was available to PCS.
    9
    No. 52020-6-II
    Third, the panel concluded that PCS’s remaining expenditures for the full site
    reconfiguration were not necessary and reasonably related to addressing the choke point. Cheaper
    alternative options were available, and the panel did not find PCS’s expert on this matter to be
    credible. The panel specifically concluded that tramming costs, or costs of moving shred out of
    the new truck traffic path, were only $46,000 a year, and PCS’s claimed increased annual operation
    costs of $5,426,850 were “significantly overstated.” CP at 214. The panel also reasoned that
    reimbursement for tramming costs for the shred creating the choke point was not appropriate
    because PCS was only eligible for reimbursement to move personal property from the condemned
    area.
    PCS appealed once more to the superior court, which ruled that the panel erred in denying
    PCS any additional compensation for its reconfiguration expenses. The superior court reasoned
    that the panel failed to follow the court’s remand instructions because the panel continued to focus
    on the entire reconfiguration, rather than consider piecemeal each of PCS’s actions.
    The superior court emphasized it had already ruled in an order that was not appealed that
    PCS was entitled to some additional costs associated with the choke point problem, so the panel
    erred in denying PCS any additional compensation. The superior court explained that its prior
    “order noted that the taking required PCS ‘to either (a) use machinery to “tram” materials away
    from the area and store these materials in additional “loader-stacked shred” piles or (b) reconfigure
    the conveyor . . . to deposit the “conveyor-stacked shred” pile on another portion of the leasehold
    property,’” rather than so near the truck path that it would regularly block the road. CP at 369
    (alterations in original).
    10
    No. 52020-6-II
    The superior court therefore ruled that in addition to the reimbursement already paid, PCS
    was entitled to the costs of turning the conveyor and tramming materials before the conveyor was
    turned, which the panel had calculated at $347,800 and $46,000, respectively. The superior court
    adopted those figures in its order.
    PCS appeals and the Port cross-appeals, but the Port asks only that we affirm the panel’s
    decision.
    ANALYSIS
    PCS argues that the panel’s decision denying additional compensation contradicted the law
    of the case, was not supported by substantial evidence, was contrary to law, and was internally
    inconsistent and arbitrary and capricious. PCS assigns error to the panel’s finding that PCS
    previously operated with a 14.9-foot wide truck path, its rejection of PCS’s arguments pertaining
    to safety, and its determination that PCS was entitled to compensation only for a one-time move
    of personal property from the condemned area.
    With regard to the panel’s finding on the 14.9-foot truck path, the law of the case doctrine
    did not apply to this factual finding and it was supported by substantial evidence. The panel’s
    findings related to PCS’s safety concerns were also supported by substantial evidence. However,
    we hold that the panel erred in denying any additional compensation to PCS. The superior court’s
    order bound the panel to compensate PCS for additional reasonable and necessary costs caused by
    the taking. Having recognized that the taking forced PCS to do more than just the one-time move
    of personal property out of the condemnation area, the panel was required under the law to award
    some amount of additional compensation. The panel’s refusal to order any additional
    11
    No. 52020-6-II
    compensation violated the law of the case, was a misapplication of the law, and was arbitrary and
    capricious.
    A.     Background on Relocation Law
    PCS’s claim for compensation arose under Washington’s real property acquisition policy
    act (chapter 8.26 RCW) and its corresponding administrative regulations (chapter 468-100 WAC),
    as well as the federal Uniform Relocation Assistance and Real Property Policies Act of 1970 (
    42 U.S.C. §§ 4601-4655
    ) and its corresponding regulations (
    49 C.F.R. § 24.1
    -.306).1 The Washington
    State Department of Transportation Right of Way Manual (Aug. 2012) (M 26-01.08) (WSDOT
    Manual)2 also provides guidance to agencies implementing these laws, including the Port. The
    Port acknowledges that it relies on the WSDOT Manual. Both the federal and state statutes indicate
    that their primary purpose is to minimize the hardship of displacement for individuals and
    businesses affected by public projects by providing uniform procedures for providing relocation
    assistance. 
    42 U.S.C. § 4621
    (b); RCW 8.26.010(1)(a).
    RCW 8.26.035(1) provides in relevant part that when an agency project will result in the
    displacement of a business, the agency shall pay the displaced business the (a) actual reasonable
    expenses in moving the business or other personal property; (b) actual losses of tangible personal
    property as a result of moving the business, not to exceed an amount equal to the reasonable
    expenses that would have been required to relocate the property; (c) actual reasonable expenses in
    searching for a replacement business; and (d) “[a]ctual reasonable expenses necessary to
    1
    The federal statutes and regulations contain substantially the same language as the state statutes
    and regulations.
    2
    https://www.wsdot.wa.gov/publications/manuals/fulltext/M26-01/M26-01.08Complete.pdf
    [https://perma.cc/5NDY-8VK5].
    12
    No. 52020-6-II
    reestablish a displaced farm, nonprofit organization, or small business at its new site.” WAC 468-
    100-301(1)(a) explains that a displaced business is entitled to all “actual moving and related
    expenses” that the displacing agency determines to be “reasonable and necessary.”
    A displacement may be characterized as “[p]ersonal property only,” where the agency
    action forces the business to relocate personal property but does not necessitate the relocation of
    the entire business. WAC 468-100-301(5) (bold type omitted); WSDOT Manual § 12-9.1, at 12-
    110. The version of the WSDOT Manual in effect at the time of this condemnation explained that
    the movement of personal property that is located within the condemned or acquired area is
    reimbursable. Id. But a business can also receive reimbursement for expenses where personal
    property must be moved because the agency’s acquisition requires the business to otherwise move
    personal property from real property that is located outside the condemned or acquired area. See
    id. (“Business . . . operations that must incur reestablishment expenses to facilitate the continuous
    operation of their business on the subject property should be relocated under the provisions of
    Section 12-7.”); WSDOT Manual § 12-7.1, at 12-73 (“Moving of personal property when the
    acquisition of real property used for nonresidential use causes the displaced occupant to vacate . .
    . other real property not acquired.”).
    Moreover, WAC 468-100-301 does not limit moving expenses for personal property to
    instances where the personal property is moved from the condemned or acquired area. WAC 468-
    100-301(5). The regulations provide:
    Eligible expenses for a person who is required to move personal property from real
    property but is not required to move from a . . . business . . . include . . .
    ....
    [t]ransportation of the displaced . . . personal property . . . [and]
    ....
    13
    No. 52020-6-II
    [d]isconnecting, dismantling, removing, reassembling, and reinstalling relocated . .
    . personal property. For businesses, . . . this includes machinery [and] equipment[,]
    . . . it also includes modifications to the personal property, including those mandated
    by federal, state or local law, code or ordinance, necessary to adapt it to the
    replacement structure, the replacement site, or the utilities at the replacement site,
    and modifications necessary to adapt the utilities at the replacement site to the
    personal property.
    WAC 468-100-301(5), (7)(a), (c).
    Storage expenses not to exceed 12 months and “[o]ther moving-related expenses that are
    not . . . ineligible under subsection (8) . . . as the agency determines to be reasonable and necessary”
    are also eligible for reimbursement. WAC 468-100-301(7)(d), (g). Certain increased operating
    expenses incurred as a result of the acquisition, such as personal or real property taxes or insurance
    premiums, are recoverable up to $50,000 for the first two years, but otherwise increased operating
    expenses are not eligible. WAC 468-100-301(7), (8); WAC 468-100-306(1)(f).
    In sum, eligible expenses include the costs of moving personal property, reassembling and
    reinstalling machinery and equipment, and making modifications necessary for adapting
    machinery and equipment as a result of the agency’s acquisition. Eligible expenses in this category
    also include storage expenses up to 12 months and can include some increased operating expenses
    up to 2 years and up to $50,000.
    Neither the statute nor any relevant regulation defines “reasonable and necessary.” The
    WSDOT Manual explained that “reasonable means the costs are typical in the geographic area in
    which the displacement occurred for the type of goods or services being purchased. Necessary
    means that such goods or services are needed to carry out the reestablishment of [the] business.”
    § 12-7.2.3, at 12-85. “[T]he test is one of necessity, i.e., is the expense necessary to reestablish the
    displaced business[?]” Id.
    14
    No. 52020-6-II
    The WSDOT Manual also provided:
    It is important to remember that [relocation] expenses should be necessary to
    reestablish the present operation, not to improve it . . . . Displacement provides an
    excellent opportunity for an operation to do all those things itself, but they should
    not be accomplished with public funds. In the situation where a displaced business
    selects a larger replacement site or a betterment, these tests allow the specialist to
    set a reasonable threshold for reimbursement based on the size or quality of the
    displacement site.
    Id.
    B.     Standard of Review and Burden to Show Invalidity of Agency Action
    The Administrative Procedure Act, chapter 34.05 RCW, governs appellate review of state
    and local agency decisions. Utter v. Dep’t of Soc. & Health Servs., 
    140 Wn. App. 293
    , 299, 
    165 P.3d 399
     (2007). “On appeal from the superior court, we sit in the same position as the superior
    court and review the agency’s order based on the administrative record rather than the superior
    court’s decision.” B&R Sales, Inc. v. Dep’t of Labor & Indus., 
    186 Wn. App. 367
    , 374, 
    344 P.3d 741
     (2015). Upon review, we generally “treat any findings of fact or conclusions of law the
    superior court made as surplusage.” Morawek v. City of Bonney Lake, 
    184 Wn. App. 487
    , 491, 
    337 P.3d 1097
     (2014).
    The party asserting the invalidity of an agency’s decision has the burden of demonstrating
    invalidity. RCW 34.05.570(1)(a); PacifiCorp v. Wash. Utils. & Transp. Comm’n, 
    194 Wn. App. 571
    , 586, 
    376 P.3d 389
     (2016). RCW 34.05.570(3) sets out nine grounds for invalidating an agency
    action. PCS’s challenge implicates three of those grounds. PCS argues that the panel misapplied
    the law, the panel’s factual findings were not supported by substantial evidence, and the panel’s
    decision was arbitrary and capricious. RCW 34.05.570(3)(d), (e), (i).
    15
    No. 52020-6-II
    We review the panel’s factual findings for substantial evidence, asking whether the record
    contains evidence sufficient to convince a rational, fair-minded person that the finding is true. B&R
    Sales, 186 Wn. App. at 375. An agency’s determination of actual costs under RCW 8.26.035 is
    one of fact that we review for substantial evidence. Cedar River Water & Sewer Dist. v. King
    County, 
    178 Wn.2d 763
    , 797, 
    315 P.3d 1065
     (2013). “We do not reweigh evidence or judge witness
    credibility” but instead defer to the agency’s broad discretion in weighing expert testimony.
    PacifiCorp, 194 Wn. App. at 588-89.
    We review an agency’s legal conclusions de novo, but give substantial weight to its
    interpretation of the law when subjects fall within its area of expertise. B&R Sales, 186 Wn. App.
    at 375. In addition, a mixed question of law and fact requires the application of legal precepts to
    factual circumstances. Tapper v. Emp’t Sec. Dep’t, 
    122 Wn.2d 397
    , 402, 
    858 P.2d 494
     (1993). For
    example, determining whether particular facts meet a legal definition of a term like “misconduct”
    is a mixed question of law and fact. 
    Id.
     “Analytically, resolving a mixed question of law and fact
    requires establishing the relevant facts, determining the applicable law, and then applying that law
    to the facts.” 
    Id. at 403
    . We are not free to substitute our judgment for that of the agency as to the
    facts. 
    Id.
     “[T]he factual findings of the agency are entitled to the same level of deference which
    would be accorded under any other circumstance.” 
    Id.
     “The process of applying the law to the
    facts, however, is a question of law and is subject to de novo review.” 
    Id.
    “An agency’s action is arbitrary and capricious only if it ‘is willful and unreasoning and
    taken without regard to the attending facts or circumstances.’” PacifiCorp, 194 Wn. App. at 587
    (internal quotation marks omitted) (quoting Att’y Gen.’s Office v. Wash. Utils. & Transp.
    Comm’n, 
    128 Wn. App. 818
    , 824, 
    116 P.3d 1064
     (2005)). “‘Where there is room for two opinions,
    16
    No. 52020-6-II
    an action taken after due consideration is not arbitrary and capricious even though a reviewing
    court may believe it to be erroneous.’” 
    Id.
     (internal quotation marks omitted) (quoting Att’y Gen.’s
    Office, 128 Wn. App. at 824). “‘Neither the existence of contradictory evidence nor the possibility
    of deriving conflicting conclusions from the evidence renders an agency decision arbitrary and
    capricious.’” Id. (quoting Att’y Gen.’s Office, 128 Wn. App. at 824).
    C.     Historical Width of the Truck Path
    PCS argues that the panel’s determination that PCS maintained only a minimum 14.9-foot
    wide traffic path before the taking was not supported by substantial evidence. PCS also contends
    that we are bound by the superior court’s determination in its first decision that PCS instead
    required a 20-foot wide traffic path because that decision was not appealed. We disagree.
    The superior court’s reference to a 20-foot wide path was a factual statement that did not
    bind the panel on remand under the law of the case. The law of the case doctrine most commonly
    “‘stands for the proposition that once there is an appellate holding enunciating a principle of law,
    that holding will be followed in subsequent stages of the same litigation.’” State v. Johnson, 
    188 Wn.2d 742
    , 755, 
    399 P.3d 507
     (2017) (emphasis added) (quoting Roberson v. Perez, 
    156 Wn.2d 33
    , 41, 
    123 P.3d 844
     (2005)). The doctrine does not apply to factual findings. Karanjah v. Dep’t
    of Soc. & Health Servs., 
    199 Wn. App. 903
    , 916, 
    401 P.3d 381
     (2017).
    Moreover, a superior court acting in its limited appellate capacity may review whether
    substantial evidence supports a finding of fact, but it generally may not decide disputed factual
    issues. See RCW 34.05.570(3); Herman v. Shorelines Hr’gs Bd., 
    149 Wn. App. 444
    , 455, 
    204 P.3d 928
     (2009). Findings of fact made by a superior court acting in its appellate capacity are
    surplusage. Morawek, 184 Wn. App. at 491. The aspects of the superior court’s order that were
    17
    No. 52020-6-II
    statements of fact were not binding on the panel, nor are they binding on this court even though
    the superior court’s first decision was not appealed.
    The superior court’s reference to the 20-foot wide path appeared in its statement of the
    case, and the court did not make any legal rulings with respect to this issue or state that the panel’s
    finding of a 14.9-foot wide path was unsupported by substantial evidence. Absent an appellate
    decision based on a lack of substantial evidence, the panel was not constrained on remand from
    determining, as a factual matter, that the historical minimum width of the truck path was only 14.9
    feet.
    PCS submitted an aerial photograph from before the taking that showed the truck path was
    14.9 feet wide at its narrowest point. Daniel, the Port’s expert, testified that by using photographic
    evidence and consulting with the project surveyor he was able to determine that the narrowest
    point along the truck path before the taking occurred was 14.9 feet wide. Daniel also pointed out
    that standard highway lanes are 10 to 12 feet wide. Another expert similarly testified that the
    narrowest point along the path after the taking was about 15 feet wide, and this was consistent with
    the width of that part of the path before the taking. In addition, PCS’s initial construction plans for
    the reconfiguration submitted to the city provided for a 15-foot wide truck path, which suggested
    that PCS did not think that a path of that width was unworkable.
    PCS contends that this evidence was not reliable because Daniel’s testimony was based on
    an informal survey that was intended only for illustrative purposes and Daniel was not an engineer
    or safety expert. PCS also contends that because some of its trucks are 14.3 feet wide, a 14.9-foot
    wide path would be untenable. PCS argues that its construction plans submitted to the city were
    18
    No. 52020-6-II
    only preliminary, not final, and that Uskoski testified that the 15-foot wide path denoted in the
    plans did not necessarily define the actual truck path.
    PCS argues instead that the truck path was at least 20 feet wide before the taking, pointing
    to Aleksander’s and Alongi’s testimonies. Aleksander testified that 20 feet was the minimum
    historical width and Alongi testified that the width of the traffic path typically fluctuated between
    28 and 34 feet. Aleksander also opined that 28 feet was the minimum width for a safe path.
    But the panel specifically found that Alongi’s testimony was not credible, and that the
    Port’s evidence establishing a 14.9-foot wide path was more reliable than PCS’s evidence of a 20-
    foot wide path. Although Daniel admitted that some of PCS’s loaders are too wide for a 14.9-foot
    wide path, he explained that those loaders could simply take a different path to reach their
    maintenance building. And even if Daniel himself is not a surveyor or engineer, he confirmed his
    measurements and conclusions regarding the 14.9-foot wide path with the project surveyor.
    Multiple witnesses testified that the minimum width of the truck path was 14.9 feet and
    this testimony was supported by the evidence, even though there was also conflicting testimony in
    the record. The panel had considerable discretion to weigh the competing testimony and evidence,
    and we are not permitted on appeal to reweigh the evidence and come to a different conclusion
    where there is substantial evidence supporting the panel’s findings. PacifiCorp, 194 Wn. App. at
    588-89. We accordingly hold that, based on testimony from Daniel and other witnesses, the aerial
    photograph, and PCS’s construction plans submitted to the city, there was substantial evidence to
    support a finding that 14.9 feet was the minimum width of the truck path before the taking
    occurred.
    19
    No. 52020-6-II
    D.        Safety as a Basis for Reconfiguring the Conveyor
    PCS also argues the panel erred by not considering safety in its determination that the full
    site reconfiguration was not reasonable and necessary. We disagree.
    To support its argument that the panel did not factor safety into its decision, PCS points to
    testimony on the need to change the Z box and dual picking station to accommodate safe access to
    the shredder, to move the conveyor and rail spur for safe access across the site, and to reconfigure
    the entire operation to maintain a safe operating corridor through the site. PCS also argues that the
    panel’s finding of a 14.9-foot wide traffic path ignored safety considerations because Aleksander
    testified that such a path would negatively impact safety and visibility.
    Although Fitzpatrick mentioned safety as a concern for the reconfiguration, the panel
    specifically noted that Fitzpatrick did not understand the scope or impact of the Port’s taking when
    he decided that the reconfiguration was necessary. The testimony PCS cites suggests that the
    necessity for making changes to the Z box and dual picking station was more related to
    considerations of cost and efficiency rather than safety, these changes resulted from the decision
    to rotate the conveyor, and they were not directly linked to safety concerns related to the underlying
    taking.
    Most of the other testimony PCS cites did not specifically mention safety as a concern and,
    although Alongi stated that a safe operating corridor was an important concern for the
    reconfiguration, the panel specifically found that Alongi’s testimony was not credible. Although
    Aleksander also testified about the safety concerns regarding a 14.9-foot wide traffic path, as
    discussed above, there was substantial evidence that such a path was viable and had been used by
    20
    No. 52020-6-II
    PCS in the past, and Daniel testified that he did not see any safety issues with a 14.9-foot wide
    path.
    The record does not support PCS’s claim that the panel completely ignored safety. Rather,
    the panel did not find credible PCS’s conclusory claim that the Port’s suggested alternatives were
    unsafe because PCS did not present evidence regarding the safety of those alternatives. Although
    PCS presented some testimony regarding the safety concerns it claims motivated the site
    reconfiguration, we do not reweigh evidence that the panel found unpersuasive, and the panel had
    considerable discretion to judge the credibility of that testimony. PacifiCorp, 194 Wn. App. at
    588-89.
    PCS argues that it was the Port’s burden to show that its proposed alternatives were safe,
    not PCS’s burden to show they were unsafe, but PCS does not cite to any authority to support this
    contention and it is PCS’s burden on appeal to show the panel’s decision was improper. RCW
    34.05.570(1)(a). The panel determined there was not enough evidence to suggest legitimate safety
    concerns that would necessitate a complete reconfiguration of the site, and PCS has not met its
    burden on appeal to show that this finding was unsupported by substantial evidence or otherwise
    legally unsound.
    E.      The Panel’s Denial of Additional Compensation
    1.     Law of the case
    PCS argues that the superior court’s order bound the panel to award PCS additional
    compensation because the superior court determined that the taking forced PCS to either
    reconfigure its operations or incur greater expenses to tram excess shred to another area of the
    property, either of which would elevate the required compensation above a mere one-time payment
    21
    No. 52020-6-II
    for moving personal property out of the condemned area. We agree that the superior court
    determined that PCS was entitled to some amount of compensation beyond the one-time payment
    to move personal property out of the condemned area, and this portion of the ruling was binding
    on the panel on remand.
    A legal decision of an appellate court establishes the law of the case and must be followed
    on remand. Lodis v. Corbis Holdings, Inc., 
    192 Wn. App. 30
    , 58, 
    366 P.3d 1246
     (2015). This rule
    “‘forbids, among other things, a lower court from relitigating issues that were decided by a higher
    court, whether explicitly or by reasonable implication, at an earlier stage of the same case.’” 
    Id. at 56
     (internal quotation marks omitted) (quoting Mun. of San Juan v. Rullan, 
    318 F.3d 26
    , 29 (1st
    Cir. 2003)). The trial court “may exercise discretion where an appellate court directs it to ‘consider’
    an issue,” provided it adheres to the appellate court’s instructions. Marriage of McCausland, 
    129 Wn. App. 390
    , 399, 
    118 P.3d 944
     (2005) (quoting State ex. rel. Smith v. Superior Court, 
    71 Wash. 354
    , 357, 
    128 P. 648
     (1912)), rev’d on other grounds, 
    159 Wn.2d 607
    , 
    152 P.3d 1013
     (2007). But
    the trial court must adhere to the appellate court’s instructions and cannot ignore specific holdings
    and directions on remand. Bank of Am., N.A. v. Owens, 
    177 Wn. App. 181
    , 189, 
    311 P.3d 594
    (2013).
    Because the superior court here was acting in its appellate capacity, its legal rulings were
    binding on the panel. The superior court ruled that the panel erred in taking an “‘all or nothing’”
    approach rather than considering whether PCS’s individual actions were reasonable and necessary.
    CP at 193. Applying the law to the facts, the superior court concluded that PCS was entitled to
    more than compensation for just the one-time move of personal property. It was entitled to
    whatever costs were reasonable and necessary to address the ongoing choke point problem that
    22
    No. 52020-6-II
    would occur about 45 times a year when the shred pile reached capacity. This ruling was binding
    on the panel. The panel was bound to recognize some ongoing impact of the taking beyond the
    one-time move of personal property out of the condemned area.
    The panel’s ruling on remand improperly ignored the superior court’s command, and
    instead determined that none of PCS’s costs were reasonable and necessary costs expended as a
    result of the taking. This was error.
    2.       Determination of reasonable and necessary costs
    PCS argues that the panel’s denial of any further compensation was a misapplication of the
    law and arbitrary and capricious. We agree that the panel erred in denying PCS some additional
    compensation, but reject PCS’s claim that it is entitled to the cost of the entire site reconfiguration.
    PCS points to the panel’s conclusion that “do nothing” was the reasonable alternative,
    where it was undisputed that PCS would have to do something about the taking’s displacement of
    excess shred storage. CP at 204. The panel understood that PCS would have to do something about
    the excess shred, but it concluded that PCS could simply move the shred to other areas on the site
    whenever the shred pile reached a volume that would block the truck path. By “do nothing,” the
    panel appears to have meant that no permanent reconfiguration was necessary, not that PCS could
    literally do nothing whenever the shred pile overflowed. See CP at 204.
    The panel concluded that the need to move the excess shred “equates to approximately
    $46,000 per year in increased operating costs for PCS if they had done nothing except move the
    shred more often with front-end loaders.” CP at 204-05 (emphasis added). Daniel testified that the
    loss of shred pile capacity resulting from the taking would result in an increased annual operating
    cost to PCS of $46,000 if PCS made no other changes to its operation. The Port and its expert
    23
    No. 52020-6-II
    therefore agreed with PCS that at least this annual cost would result from the taking if PCS did
    nothing to reconfigure its machinery.
    But having recognized that PCS would at least have to incur this additional expense as a
    result of the taking if it did not reconfigure its machinery, the panel did not conclude that some
    action to avoid this ongoing expense was reasonable and necessary. This approach ignored the
    regulations and the WSDOT Manual, which both explain that PCS was entitled to additional
    reimbursement in these circumstances. See WAC 468-100-301(5), (7).
    The relevant regulations allow reimbursement for the costs of moving personal property,
    reassembling and reinstalling machinery and equipment, and making modifications necessary for
    adapting machinery and equipment as a result of the agency’s acquisition. WAC 468-100-
    301(7)(a), (c). Eligible expenses in this category also include storage expenses up to 12 months
    and can include some increased operating expenses up to 2 years and up to $50,000. Id.; WAC
    468-100-306(1)(f). Thus, even where a business does not need to entirely relocate, it is entitled to
    reimbursement for moving personal property that is displaced by the taking (i.e., the excess shred
    and the reconfiguration of equipment that must be adjusted as a result of the taking). WAC 468-
    100-301(5). This is true even if the business must move personal property only and not the entire
    business.
    It was a misapplication of these regulations for the panel to deny PCS any additional
    compensation beyond moving personal property out of the condemnation area. The panel
    recognized that the taking created an occasional choke point that PCS would have to address
    whenever the shred pile reached capacity, and yet it did not award any compensation for the
    24
    No. 52020-6-II
    reasonable and necessary cost of doing so. This decision misapplied the law and was arbitrary and
    capricious in that it ignored the ongoing cost to PCS that resulted from the taking.
    Eligible expenses for a move of personal property include the reasonable and necessary
    costs of reassembling and reinstalling machinery and equipment and making modifications
    necessary for adapting machinery and equipment as a result of the agency’s acquisition. WAC
    468-100-301(7)(c). In PCS’s case, such expenses included the cost of making necessary
    modifications to adapt its operations to address the choke point issue. And as discussed above, the
    superior court concluded, as a matter of law, that an award only for the cost of moving personal
    property out of the condemned area was insufficient because it did not adequately address the
    choke point issue that both parties agreed existed, and the Port did not appeal that ruling.
    Thus, PCS was entitled to compensation for the cost of moving excess shred for so long as
    it was necessary and for the reasonable cost of reconfiguration of PCS’s equipment to avoid that
    ongoing cost. This does not mean that PCS was entitled to all of its expenses associated with a full
    site reconfiguration, but the panel did not point to anything in the statute, the regulations, or the
    WSDOT Manual that authorized it to reject reasonable and necessary expenses simply because it
    considered them to be de minimis. As the superior court noted in the initial appeal, it was wrong
    for the panel to consider PCS’s compensation as an all-or-nothing proposition. The statutory and
    regulatory framework clearly provides that there is an obligation to compensate for reasonable and
    necessary expenses to move personal property and reconfigure equipment, even where the business
    also must absorb the cost of additional, noncompensable improvements or modifications that are
    not necessitated by the government action. WSDOT Manual § 12-7.2.3, at 12-85.
    25
    No. 52020-6-II
    PCS made numerous improvements and alterations to its site operations, but the fact that
    most of those actions were not necessitated by the taking does not preclude PCS from being entitled
    to compensation for the portion that would have been a reasonable and necessary response. In other
    words, just because PCS did not take the route determined by the panel to be reasonable and
    necessary does not mean that it is not entitled to any compensation. The law does not require PCS
    to do only the bare minimum in response to the taking; it simply provides that public funding is
    only available up to the amount that was both reasonable and necessary. See id.
    The panel determined that the taking caused increased operating costs of moving the excess
    shred whenever the pile reached capacity, which it calculated as $46,000 a year based on the
    testimony of Daniel, the Port’s expert. Daniel and another Port expert identified turning the
    conveyor as one reasonable and necessary option to eliminate the $46,000 a year expense. The
    panel also determined that turning the conveyor was one of the options available, and the cost of
    this option was $347,800. Daniel testified that PCS would be entitled to reimbursement for
    modifying the conveyor.
    Although the Port, in its briefing, challenges the adequacy of PCS’s evidence supporting
    its claims for reimbursement, the Port did not appeal or assign error to any portion of the panel’s
    second decision, and it did not assign error to any of the panel’s secondary findings, including the
    finding as to the cost of turning the conveyor. PCS was entitled to these moving and machinery
    reconfiguration expenses necessary to avoid the ongoing cost and to cover the cost of moving the
    shred until the alterations were complete. We adopt the panel’s calculation of the cost to turn the
    conveyor and the cost of tramming excess shred before the conveyor could be turned: $347,800
    and $46,000.
    26
    No. 52020-6-II
    Otherwise, we find no other error in the panel’s decision rejecting the remainder of PCS’s
    claimed expenses. There is substantial evidence in the record supporting the panel’s conclusion
    that the costs incurred by PCS in relocating the rail spur, upgrading storm water facilities,
    expanding and improving employee parking, adding a new picking conveyor, and making
    substantial changes to its office space and the property entrance were not reasonable and necessary
    responses to the taking. These changes were too attenuated from the underlying choke point issue
    created by the taking to be reimbursable. The panel’s decision not to reimburse PCS for these costs
    was neither arbitrary and capricious nor contrary to law.
    CONCLUSION
    The panel’s decision denying any additional compensation violated the law of the case by
    ignoring the superior court’s remand order, misapplied the applicable regulations, and was
    arbitrary and capricious because the panel recognized that the taking created a choke point that
    would result in increased operating expenses for PCS. The statutory and regulatory framework
    entitles PCS to some level of additional compensation.
    We therefore affirm the panel’s decision in part and reverse in part. We conclude that some
    additional compensation is due to PCS for reasonable and necessary relocation of shred material,
    as well as the reasonable and necessary reconfiguration of the conveyor. The panel’s alternative
    findings establish that the amounts awarded by the superior court are appropriate. Thus, this matter
    is remanded to the panel for entry of a final order awarding PCS $347,800 in expenses for
    reconfiguration of the conveyor and an additional $46,000 in tramming costs incurred prior to
    reconfiguration, in addition to the $68,259 already paid. And consistent with the superior court’s
    order, the panel may consider any requests related to costs and fees.
    27
    No. 52020-6-II
    Glasgow, J.
    We concur:
    Lee, C.J.
    Cruser, J.
    28