Puget Sound Energy, Inc. v. Pilchuck Contractors, Inc. ( 2020 )


Menu:
  •         IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    PUGET SOUND ENERGY, INC., a                        )           No. 80162-7-I
    Washington corporation,                            )
    )           DIVISION ONE
    Appellant,                 )
    )           UNPUBLISHED OPINION
    v.                                 )
    )
    PILCHUCK CONTRACTORS, INC., a                      )
    Washington corporation,                            )
    )
    Respondent.                )
    )
    HAZELRIGG, J. — Puget Sound Energy, Inc. (PSE) seeks reversal of
    summary judgment for Pilchuck Contractors, Inc. PSE contends that the court
    erred in determining that its claims against Pilchuck were barred by Washington’s
    construction statute of repose. Because PSE’s claims arise from the type of
    activity that the statute was intended to cover and did not accrue within the
    allowable period, they are barred by the statute of repose. Although PSE urges
    this court to recognize a fraud exception to the statute, the broad language of the
    statute indicates the legislature’s intent to restrict the application of the discovery
    rule and establish a firm endpoint of liability for those who engage in construction
    activities. We affirm.
    Citations and pinpoint citations are based on the Westlaw online version of the cited material.
    No. 80162-7-I/2
    FACTS
    Puget Sound Energy, Inc. (PSE) is a public utility company that provides
    electricity and natural gas service to customers in the Puget Sound region. In
    2001, PSE and Pilchuck Contractors, Inc. entered into a Master Services
    Agreement (MSA) in which Pilchuck agreed to perform construction, operations,
    and maintenance projects for PSE from time to time. The MSA required Pilchuck
    to “defend, indemnify and hold harmless PSE from and against any and all Claims
    or Losses” arising from Pilchuck’s conduct as PSE’s contractor.
    In 2004, PSE contracted with Pilchuck to perform work on the 8400 block
    of Greenwood Avenue North in Seattle. PSE obtained a permit from the City of
    Seattle Department of Transportation to install new gas lines “to serve the property
    lines in the 8400 [block] of Greenwood Avenue North also, to cut and cap existing
    serves in Greenwood Avenue North.” All of the Greenwood gas relocation work in
    2004 fell under one “superior work order number,” while “specific sub order
    numbers” described discrete work to be done, and “specific work notification
    numbers” were assigned to each address to be serviced under a sub order.
    The deactivation of the gas service line at 8409 Greenwood Avenue North
    was assigned work notification number 10552392.           The version of the Gas
    Operating Standards in effect in 2004 required that the following be performed to
    properly deactivate a gas service line: (1) disconnect the service line from all
    sources and supplies of gas, (2) purge the line of existing natural gas, (3) seal the
    line at each end with expansive foam, (4) cut and cap the line, and (5) remove any
    above-ground portion of the retired or deactivated service line. Compliance with
    -2-
    No. 80162-7-I/3
    the Gas Operating Standards is mandatory for PSE employees, service providers,
    and contractors.
    Pilchuck submitted to PSE the required Gas Service Card, commonly
    referred to as a “D-4 Card,” for work notification number 10552392. The D-4 Card,
    dated September 1, 2004, indicated that the gas service line at 8409 Greenwood
    Avenue North had been retired. The information on the D-4 Card was entered in
    PSE’s mapping system, and PSE’s master map of gas service lines was updated
    to indicate that the service line no longer existed. Pilchuck finished work on the
    area of 8400 Greenwood Avenue North in September 2004 and was paid in full.
    By that time, PSE’s customers on the block were receiving gas service through the
    newly installed service lines.
    In the early hours of March 9, 2016, gas leaked from the line and ignited,
    causing an explosion that destroyed several businesses. The Washington Utilities
    and Transportation Commission (WUTC) issued an investigation report finding that
    the gas leak was directly caused by external physical damage to the gas service
    line. The WUTC determined that “the service line had not been ‘cut and capped’
    as documented by PSE’s contractor” and found that “the leak and explosion would
    not have occurred but for PSE’s improper abandonment of the service line in
    September 2004.”
    In 2018, PSE filed a lawsuit against Pilchuck for breach of contract, breach
    of warranties under the MSA, and fraud. PSE argued that Pilchuck was required
    under the MSA to indemnify PSE for its costs stemming from the emergency
    response to the explosion, WUTC enforcement proceeding, and third-party claims.
    -3-
    No. 80162-7-I/4
    Pilchuck moved for summary judgment, arguing that all of PSE’s claims were
    barred by Washington’s construction statute of repose.           The court granted
    summary judgment for Pilchuck. PSE appealed.
    ANALYSIS
    PSE contends that the trial court erred in granting summary judgment for
    Pilchuck on the grounds that PSE’s claims were barred by the construction statute
    of repose. We review a summary judgment order de novo, engaging in the same
    inquiry as the trial court. Folsom v. Burger King, 
    135 Wash. 2d 658
    , 663, 
    958 P.2d 301
    (1998). Summary judgment is proper when, viewing all facts and inferences
    in the light most favorable to the non-moving party, there is no genuine dispute as
    to any material fact and the moving party is entitled to judgment as a matter of law.
    Id. The meaning of
    a statute is a question of law that we also review de novo.
    Porter v. Kirkendoll, 
    194 Wash. 2d 194
    , 200, 
    449 P.3d 627
    (2019); Smith v. Showalter,
    
    47 Wash. App. 245
    , 248, 
    734 P.2d 928
    (1987). Our purpose in interpreting a statute
    is to ascertain and carry out the intent of the legislature. Columbia Riverkeeper v.
    Port of Vancouver USA, 
    188 Wash. 2d 421
    , 435, 
    395 P.3d 1031
    (2017). If the plain
    meaning of the statute is clear on its face, we must give effect to that plain meaning
    as an expression of the legislature’s intent.
    Id. Appellate courts will
    avoid adding
    to or taking away from the language of a statute; statutes are construed to avoid
    rendering any language superfluous, void, or insignificant, and the court cannot
    insert words that the legislature has chosen not to include. 
    Porter, 194 Wash. 2d at 211
    –12.
    -4-
    No. 80162-7-I/5
    To ascertain a statute’s plain meaning, courts “consider the text of the
    provision, the context of the statute in which the provision is found, related
    provisions, amendments to the provision, and the statutory scheme as a whole.”
    Columbia 
    Riverkeeper, 188 Wash. 2d at 435
    . If the meaning of the statute remains
    unclear or ambiguous after this inquiry, “it is appropriate to resort to canons of
    construction and legislative history” to determine the legislature’s intent.
    Id. Washington’s construction statute
    of repose is set out in two parts:
    RCW 4.16.300 defines the scope of the statute and describes those
    entitled to claim its protection. RCW 4.16.310 defines when this
    statute of repose bars a claim. Together, they bar certain claims
    arising from construction of any improvement on real property that
    have not accrued within six years after substantial completion of
    construction.
    Cameron v. Atl. Richfield Co., 
    8 Wash. App. 2d
    795, 800, 
    442 P.3d 31
    (2019).
    Washington courts use a three-step analysis in cases involving the statute. Pfeifer
    v. City of Bellingham, 
    112 Wash. 2d 562
    , 567, 
    772 P.2d 1018
    (1989). First, we decide
    whether the claims fall within the scope of the statute.
    Id. If the statute
    applies,
    we determine whether the cause of action accrued within the time period allowed
    by the statute.
    Id. Finally, the plaintiff
    must have filed suit within the appropriate
    statute of limitation for the cause of action.1
    Id. 1
    Although the statute of limitation is relevant to the statute of repose analysis, the two are
    significantly different. Wash. State Major League Baseball Stadium Pub. Facilities Dist. v. Huber,
    Hunt & Nichols-Kiewit Constr. Co., 
    176 Wash. 2d 502
    , 511, 
    296 P.3d 821
    (2013). “A statute of
    limitation bars a plaintiff from bringing an accrued claim after a specific period of time. A statute of
    repose terminates the right to file a claim after a specified time even if the injury has not yet
    occurred.”
    Id. -5-
    No. 80162-7-I/6
    I.     Scope of the Statute of Repose
    PSE first argues that the statute of repose does not bar its claims against
    Pilchuck because the claims do not fall within the scope of the statute. As noted
    above, RCW 4.16.300 sets out the scope of the statute of repose:
    RCW 4.16.300 through 4.16.320 shall apply to all claims or causes
    of action of any kind against any person, arising from such person
    having constructed, altered or repaired any improvement upon real
    property, or having performed or furnished any design, planning,
    surveying, architectural or construction or engineering services, or
    supervision or observation of construction, or administration of
    construction contracts for any construction, alteration or repair of any
    improvement upon real property. This section is specifically intended
    to benefit persons having performed work for which the persons must
    be registered or licensed under RCW 18.08.310, 18.27.020,
    18.43.040, 18.96.020, or 19.28.041, and shall not apply to claims or
    causes of action against persons not required to be so registered or
    licensed.
    A. Construction Activities
    PSE contends that “there is, at minimum, an issue of material fact
    precluding summary judgment on whether Pilchuck ‘constructed, altered or
    repaired’ an ‘improvement,’ or ‘performed work’ to deactivate the subject gas
    service line.” Pilchuck argues that there is no factual dispute and PSE’s argument
    concerns the legal definition of an “improvement” under the statute of repose.
    Washington courts have interpreted the phrase “improvement to real
    property” as used in the construction statute of repose. The first in the line of cases
    concerning this definition found that the replacement and reinstallation of pipe,
    coils, hangers, and rods in a cold storage warehouse constituted an improvement
    to real property rather than installation of a removable trade fixture. Yakima Fruit
    & Cold Storage Co. v. Cent. Heating & Plumbing Co., 
    81 Wash. 2d 528
    , 530–31, 503
    -6-
    No. 80162-7-I/7
    P.2d 108 (1972). This court then applied Yakima Fruit & Cold Storage Co. v.
    Central Heating & Plumbing Co. to determine that a ski lift was an improvement to
    real property rather than a fixture because it “adds to the value of the property, is
    an amelioration of its condition, and enhances its use.” Pinneo v. Stevens Pass,
    Inc., 
    14 Wash. App. 848
    , 852, 
    545 P.2d 1207
    (1976). We in turn applied Pinneo v.
    Stevens Pass, Inc. to find that installation of underground power lines was “an
    improvement upon real property even though potentially subject to removal under
    some circumstances” because “[t]he power lines add to the value of the property
    and enhance its use, and Tyee, being a contractor, is clearly within the class to be
    protected by the statute.” Wash. Nat. Gas Co. v. Tyee Const. Co., 
    26 Wash. App. 235
    , 239, 
    611 P.2d 1378
    (1980).
    PSE does not appear to be arguing that the work, if completed, would not
    have constituted an improvement. Rather, PSE argues that actions not taken
    cannot constitute an improvement. However, this argument does not quite square
    with the definition of “improvement on real property” developed in the case law.
    Under Washington National Gas Co. v. Tyee Construction Co., gas service lines,
    like power lines, are an improvement on real property because they add to the
    value of the property and enhance its use.
    Id. at 239.
    Pilchuck was hired to alter
    these existing improvements. The fact that Pilchuck did not complete that work
    does not change the status of gas service lines as an “improvement upon real
    property” for purposes of the statute of repose.
    Although Pilchuck contracted with PSE to perform construction work on the
    gas service line, PSE contends that the question of whether Pilchuck actually
    -7-
    No. 80162-7-I/8
    “constructed, altered or repaired” the gas service line affects the applicability of the
    statute of repose. The parties disagree on the scope of the project relevant to this
    analysis. Pilchuck contends that the entirety of the work around 8400 Greenwood
    Avenue North constituted one construction project, as it fell under one superior
    work order number. In contrast, PSE argues that the court should consider the
    specific work notification number covering the deactivation of this specific service
    line as its own project.
    This disagreement, however, does not affect the applicability of the statute
    of repose because the statute evidences a legislative intent to apply broadly to
    protect contractors such as Pilchuck. This court has noted that the language of
    RCW 4.16.300 covering “all claims or causes of actions of any kind” is “broad and
    sweeping.” Parkridge Assocs., Ltd. v. Ledcor Indus., Inc., 
    113 Wash. App. 592
    , 602,
    
    54 P.3d 225
    (2002) (emphasis omitted). As this court recognized in Pinneo, the
    legislature adopted the statute of repose “to protect architects, contractors,
    engineers, and others from extended potential tort and contract liability.” 14 Wn.
    App. at 852.
    PSE contracted with Pilchuck to retire the gas service line, that is, to alter
    an improvement on real property, and Pilchuck represented to PSE that it had done
    so. Had Pilchuck properly retired the gas service line, its conduct would certainly
    fall within the scope of the statute of repose. The fact that the work was not done
    as represented may give rise to a claim but does not remove the situation from the
    purview of the statute of repose. To except this situation from the statute of repose
    -8-
    No. 80162-7-I/9
    would not serve the legislature’s intent to protect contractors from extended
    liability. PSE’s claims fall within the scope of the statute of repose.
    B. Reporting Activities
    PSE briefly argues that Pilchuck’s submission of a false report on the D-4
    Card is not within the scope of the statute of repose because it is not a protected
    construction activity under the statute. The statute of repose applies to “all claims
    or causes of action of any kind against any person, arising from such person having
    constructed, altered or repaired any improvement upon real property, or . . .
    administration of construction contracts for any construction, alteration or repair of
    any improvement upon real property.” RCW 4.16.300. In this context, “[t]he
    phrase ‘arising out of’ means ‘originating from,’ ‘having its origin in,’ ‘growing out
    of,’ or ‘flowing from.’” Parkridge 
    Assocs., 113 Wash. App. at 603
    .
    Both parties cite to Pfeifer in support of their arguments. In Pfeifer, the court
    engaged in an “activity analysis” to determine whether the claim of concealment
    during a sale arose from the enumerated activities in the 
    statute. 112 Wash. 2d at 567
    –69. The court reasoned that “[s]elling and building involve different activities”
    and noted that a seller who was not the builder would not be shielded by the statute
    of repose for the same conduct.
    Id. at 568.
    PSE contends that the distinction between building and reporting parallels
    the distinction between building and selling. However, unlike selling a building,
    “record keeping, certifying records, and reporting a gas service change on a D-4
    Card” are activities arising from the construction activities specified in the statute.
    The MSA between PSE and Pilchuck required Pilchuck to submit such
    -9-
    No. 80162-7-I/10
    documentation when performing construction on its gas utilities. The activities are
    not separable like the activities in Pfeifer. There would be no need to submit a D-
    4 Card to PSE if Pilchuck had not been engaged in construction activities. The
    reporting activities arose from the construction activities and the statute of repose
    applies.
    II.    Accrual of Cause of Action
    We next consider whether the cause of action accrued within the period
    allowed by the statute. 
    Pfeifer, 112 Wash. 2d at 567
    . The construction statute of
    repose bars claims that do not accrue within the allowable period:
    All claims or causes of action as set forth in RCW 4.16.300 shall
    accrue, and the applicable statute of limitation shall begin to run only
    during the period within six years after substantial completion of
    construction, or during the period within six years after the
    termination of the services enumerated in RCW 4.16.300, whichever
    is later. The phrase “substantial completion of construction” shall
    mean the state of completion reached when an improvement upon
    real property may be used or occupied for its intended use. Any
    cause of action which has not accrued within six years after such
    substantial completion of construction, or within six years after such
    termination of services, whichever is later, shall be barred:
    PROVIDED, That this limitation shall not be asserted as a defense
    by any owner, tenant or other person in possession and control of
    the improvement at the time such cause of action accrues.
    RCW 4.16.310. “The fact that additional contract work remains, including punch
    list work, does not affect the conclusion that a project is substantially complete if it
    is otherwise fit for occupancy.” Dania, Inc. v. Skanska USA Bldg. Inc., 185 Wn.
    App. 359, 371, 
    340 P.3d 984
    (2014).
    Although there does not appear to be any dispute that Pilchuck terminated
    its work in September 2004, PSE contends that Pilchuck never substantially
    - 10 -
    No. 80162-7-I/11
    completed the construction work on the subject gas service line. The parties again
    disagree on the scope of the construction.          Pilchuck argues that the 8400
    Greenwood Avenue North project as a whole was substantially complete because
    PSE began serving its customers using the new gas lines and PSE treated the
    subject gas service line as abandoned. PSE contends that Pilchuck did not
    substantially complete the work of the specific work notification and that “a
    reasonable jury could find that the businesses in the area could not be used or
    occupied for their intended purpose when there was a hidden, active, and
    unmonitored gas line that could break and cause an explosion.”
    PSE argues that the scope of the project and whether it was substantially
    complete are disputed issues of fact precluding summary judgment. It submitted
    as additional authority a recent California case in which the Court of Appeals
    determined that the contractual standard of substantial completion did not
    conclusively establish the date of substantial completion for purposes of the statute
    of repose. Hensel Phelps Constr. Co. v. Super. Ct. of San Diego County, 44 Cal.
    App. 5th 595, 616, 
    257 Cal. Rptr. 3d 746
    (2020). The California court remarked:
    The date of substantial completion is an objective fact about the state
    of construction of the improvement, to be determined by the trier of
    fact. It is a statutory standard, not a contractual one. The parties to a
    construction contract may not arrogate to themselves the ability to
    conclusively determine when the statutory limitations period begins
    to run.
    Id. at 613.
    Here, no party is arguing for any standard of substantial completion other
    than that defined in RCW 4.16.310. Again, the scope of the project does not affect
    the conclusion on this issue. The broader project was substantially complete
    - 11 -
    No. 80162-7-I/12
    because PSE’s customers were receiving service via the new gas lines and PSE
    treated the subject gas service line as retired. PSE does not point to anything in
    the record to suggest that the businesses in the area were not being used or
    occupied normally despite the hidden danger of the gas line. The specific project
    of retiring the subject gas service line was substantially complete because the line
    was being “used . . . for its intended use,” which, in this instance, was disuse. As
    intended, the subject gas service line was no longer being used to provide gas
    service to PSE’s customers. Because substantial completion and termination of
    the construction both occurred in 2004 and PSE’s claims did not accrue until 2016,
    the claims accrued outside of the allowable period and are barred by the statute of
    repose.
    III.   Fraud Exception to Statute of Repose
    PSE argues that we should recognize a fraud or equitable estoppel
    exception to the statute of repose. Although PSE cites to cases from multiple other
    jurisdictions recognizing an exception to the statute of repose when there is
    evidence of fraud, Washington courts have not yet decided whether a fraudulent
    concealment exception to the statute of repose exists. In Pfeifer, the Washington
    Supreme Court declined to address an argument urging the court “to create an
    exception to the statute for a cause of action based on intentional or fraudulent
    concealment” and instead resolved the case on the basis of statutory 
    construction. 112 Wash. 2d at 569
    –71. This court has also declined to reach the issue. See 1519-
    1525 Lakeview Blvd. Condo. Ass’n v. Apartment Sales Corp., 
    101 Wash. App. 923
    ,
    932–33, 
    6 P.3d 74
    (2000). We noted that “[w]hether fraudulent concealment has
    - 12 -
    No. 80162-7-I/13
    the effect of tolling the statute is an unsettled question” but found that we need not
    resolve the question because there was no evidence of concealment in that case.
    Id. In other contexts,
    Washington courts have generally interpreted the
    language of the statute of repose broadly in favor of the parties that it is “specifically
    intended to benefit.” RCW 4.16.300. In Parkridge, this court considered “whether
    the Legislature intended to include equitable indemnity claims within the broad
    sweep of RCW 
    4.16.310.” 113 Wash. App. at 602
    . The court noted that “[t]he
    Legislature’s choice of the words ‘all claims or causes of actions of any kind . . .
    arising from . . . construction’ is broad and sweeping,” and it did not read that
    language “to imply an exception for equitable indemnity claims.”
    Id. (emphasis omitted) (quoting
    RCW 4.16.300). Even if a contractor committed an unlawful act
    by performing work for which it was not licensed, the broad language providing
    protection for “[a]ny person” allowed the contractor to “fit into the statute regardless
    of its allegedly having furnished design services in violation of another statute.”
    Yakima 
    Fruit, 81 Wash. 2d at 531
    –32.
    PSE argues that, “without a mechanism akin to the discovery rule (like
    equitable estoppel), businesses can escape penalties by failing to make accurate
    reports as otherwise required.”        This court has noted that “RCW 4.16.310
    legislatively restricts the application of the discovery rule,” under which a cause of
    action accrues when “‘the plaintiff learns of or in the exercise of reasonable
    diligence should have learned of the facts which give rise to the cause of action.’”
    Hudesman v. Meriwether Leachman Assocs., Inc., 
    35 Wash. App. 318
    , 321, 
    666 P.2d -
    13 -
    No. 80162-7-I/14
    937 (1983) (quoting Metro. Servs., Inc. v. City of Spokane, 
    32 Wash. App. 714
    , 720,
    
    649 P.2d 642
    (1982)). In doing so, the statute “sets an outer limit for discovery” of
    contractor conduct giving rise to a claim.
    Id. at 322.
    Division Three of this court
    also remarked on the statute’s interaction with the discovery rule in Rodriguez v.
    Niemeyer:
    While important policy reasons support the accrual at discovery rule,
    we also recognize it may be desirable to place some outer limit upon
    the delayed accrual of actions in order to avoid an undue burden on
    potential defendants. . . . The creation of limitation periods is primarily
    a legislative function, and the legislature has the constitutional power
    to enact a clear line of demarcation to fix a precise time beyond which
    no remedy will be available. . . . [RCW 4.16.310] has a broad scope
    barring [a]ll causes of action that do not accrue within 6 years after
    substantial completion or termination of any of the specified services,
    whether the damage was or could have been discovered within that
    period. This court cannot constitutionally ignore such a clear
    mandate from the legislature.
    
    23 Wash. App. 398
    , 400–01, 
    595 P.2d 952
    (1979) (citations omitted) (citing Gazija v.
    Nicholas Jerns Co., 
    86 Wash. 2d 215
    , 222 n.2, 
    543 P.2d 338
    (1975)).
    Considering the broad language of the statute and Washington courts’
    repeated deferral to the legislature’s authority to limit periods of liability, we decline
    to adopt an exception to the statute of repose. The plain language of the statute
    evidences the legislature’s intent for the statute to apply broadly to “all claims . . .
    of any kind” and to restrict the application of the discovery rule, even for latent
    defects. The trial court did not err in granting summary judgment for Pilchuck.
    Affirmed.
    WE CONCUR:
    - 14 -