Lennar Multifamily Builders, Llc, V. Saxum Stone, Llc ( 2021 )


Menu:
  • IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    LENNAR MULTIFAMILY BUILDERS,
    LLC f/k/a LMC CONSTRUCTION, LLC,                  DIVISION ONE
    Respondent,                No. 81879-1-I
    v.                              OPINION PUBLISHED IN PART
    SAXUM STONE, LLC,
    Appellant.
    DWYER, J. — Saxum Stone, LLC appeals from the superior court’s order
    releasing its construction lien and awarding attorney fees to Lennar Multifamily
    Builders, LLC. The order was entered pursuant to a proceeding initiated by
    Lennar to release Saxum’s lien as being frivolous. Saxum asserts that the
    superior court erred by (1) failing to enter findings of fact demonstrating that the
    lien was frivolous, (2) releasing the lien as being frivolous, and (3) awarding
    attorney fees to Lennar. Because Saxum’s lien was not frivolous, we reverse the
    superior court’s orders releasing the lien and awarding attorney fees and costs to
    Lennar. Additionally, we hold that Saxum is entitled to an award of attorney fees
    No. 81879-1-I/2
    and costs for defending this action both in the superior court and on appeal
    pursuant to RCW 60.04.081(4).1
    I
    Lennar Multifamily Builders, LLC was the general contractor for the
    construction of Totem Lake Apartments, a construction project located in
    Kirkland, Washington. On February 7, 2019, Lennar subcontracted with Wall to
    Wall Tile & Stone, LLC to build and install quartz countertops for the project. The
    total amount that Lennar agreed to pay Wall to Wall under the subcontract was
    $480,494.
    On July 16, 2019, Wall to Wall filed for chapter 11 bankruptcy protection in
    the United States Bankruptcy Court for the District of Oregon. The record is not
    clear as to whether Wall to Wall commenced work on the Totem Lake
    Apartments project prior to filing for bankruptcy protection. According to a
    declaration filed by one of Lennar’s members, Wall to Wall “began its work on the
    Project on or about February 7, 2019.” However, according to a declaration filed
    by one of Saxum Stone, LLC’s members, Wall to Wall “started to perform labor
    on the Project on December 3, 2019 by fabricating, transferring, and installing
    quartz countertops on units on the 6th floor of the Project.”
    It is clear, however, that after Wall to Wall commenced the bankruptcy
    proceeding, Wall to Wall performed work on the Totem Lake Apartments project
    pursuant to the existing subcontract. It did so as a debtor in possession. Wall to
    1  In the unpublished portion of the opinion, we address an argument advanced by Lennar
    that was not adequately briefed on appeal. In that section, we also provide guidance to the
    superior court should this issue arise on remand.
    2
    No. 81879-1-I/3
    Wall continued to fabricate and install the quartz countertops until March 24,
    2020, at which point Wall to Wall ceased to engage in any further work on the
    project.
    On April 6, 2020, Wall to Wall’s chapter 11 bankruptcy proceeding was
    converted to a chapter 7 proceeding. At that point, according to a declaration
    filed by one of Lennar’s members, Lennar had paid Wall to Wall for all of the
    quartz material that was needed to complete the subcontract, even though Wall
    to Wall had not finished installing the countertops. The remaining uninstalled
    quartz material was stored in Wall to Wall’s warehouse in Kent.
    As of March 24, 2020, according to a declaration filed by one of Saxum’s
    members, Wall to Wall held an outstanding account receivable for Lennar in the
    amount of $73,102.83. This account receivable regarded labor performed and
    materials supplied under the subcontract. Lennar does not dispute the existence
    of this account receivable.
    On May 1, 2020, Saxum entered into an agreement with the trustee of
    Wall to Wall’s bankruptcy estate to purchase substantially all of the estate’s
    assets for a price of $4,364,519. That same day, Lennar received notice from
    the trustee of the trustee’s intent to sell substantially all of the assets possessed
    by Wall to Wall’s bankruptcy estate to Saxum.
    The agreement entered into by the trustee and Saxum, entitled
    “Agreement for Sale and Purchase of Business Assets” (asset purchase
    agreement), stated, in part:
    Seller hereby sells to Buyer and Buyer hereby purchases from
    Seller all of the Assets of the Estate useful in the Business,
    3
    No. 81879-1-I/4
    including, but not limited to accounts receivable, equipment,
    inventory, supplies, the real property leases listed in Schedule 1.2,
    software, licenses, Intellectual Property, books and records, tools,
    vehicles listed on Schedule 1.1, all claims, if any, against Buyer, its
    members, agents, attorneys, officers, and directors (“Buyer
    Claims”).
    (First emphasis added.)
    The agreement also excluded certain specified assets:
    [T]he purchased assets do not include: a) cash; b) vehicle leases
    with Enterprise Fleet Management, Inc. (“Enterprise”); c) claims
    and causes of action, if any, against present or former insiders or
    otherwise listed in paragraphs 4 and 8 of the Conversion
    Declaration filed on April 20, 2020 as Lead Case Docket No. 356
    (the “Conversion Declaration”)[2] (other than claims against Buyer
    and Buyer’s members) or arising under or pursuant to [various
    sections] of the Bankruptcy Code, other than the Buyer Claims; d)
    Benefit Plans of the Seller; e) any vehicles not listed on Schedule
    1.1 and any other items listed in paragraphs 3(i)-(j) of the
    Conversion Declaration; and f) claims pursuant to any insurance
    policy insuring the Debtors’ for general liability or for acts of officers
    and owners of Debtors, other than the Buyer Claim (the “Assets”),
    free and clear of all mortgages, pledges, liens, security interests,
    options, claims (including but not limited to any claim for successor
    liability), charges, other encumbrances, interests, or restrictions of
    any kind (collectively, “Liens”).
    The parties agree that, pursuant to the asset purchase agreement, Saxum
    was not assigned the subcontract concerning the Totem Lake Apartments
    project.3
    On May 14, 2020, the bankruptcy court entered an order approving the
    asset purchase agreement. This order stated that “[o]nly one response was filed
    – a limited objection by Baffco Enterprises, LLC.” This order also provided that
    2 The referenced Conversion Declaration is not in the record on appeal.
    3 In its opening brief, Saxum states that “[t]his case does not involve an assignment or
    assumption of future contractual performance.” Br. of Appellant at 17. Likewise, in its response
    brief, Lennar states that the asset purchase agreement “did not assign the . . . Subcontract to
    Saxum.” Br. of Resp’t at 4.
    4
    No. 81879-1-I/5
    “[t]he Trustee may sell the assets free and clear of all liens, claims, and
    encumbrances . . . because, in each case, one or more of the standards set forth
    in 11 U.S.C. § 363(f)(1)-(5) has been established.” Additionally, the order stated
    that “[t]he terms and conditions of the [asset purchase agreement] are approved.”
    That same day, the trustee executed a bill of sale, which assigned the
    assets referenced in the asset purchase agreement to Saxum.
    On June 12, 2020, an attorney representing Saxum sent an attorney
    representing Lennar a letter demanding payment of the outstanding account
    receivable. On June 15, Lennar’s attorney responded by informing Saxum’s
    attorney that Lennar would not pay any amount due on the account receivable.
    On June 22, 2020, Saxum recorded a lien on the Totem Lake Apartments
    property in the amount of $73,149.90. Consistent with the language for claim of
    lien forms recommended by RCW 60.04.091(2), the claim of lien filed declared:
    “If the claimant is the assignee of this claim state so here: Claimant is the
    assignee of Wall to Wall Tile & Stone.”
    On July 28, 2020, Lennar filed a motion in the King County Superior Court
    pursuant to RCW 60.04.081, a statute providing a mechanism for a party to
    challenge a frivolous construction lien. In the motion, Lennar asserted that
    Saxum’s lien was frivolous and requested that the trial court release the lien and
    award attorney fees and costs to Lennar. Lennar claimed that Saxum’s lien was
    frivolous because (1) Saxum did not perform any lienable work on the Totem
    Lake Apartments project, (2) Saxum was not assigned the subcontract, and (3)
    5
    No. 81879-1-I/6
    Wall to Wall did not record a lien. Also in this motion, Lennar requested that the
    superior court order Saxum to show cause.
    On August 5, 2020, a commissioner of the King County Superior Court
    granted the motion to show cause. On August 20, the superior court held a show
    cause hearing. During the hearing on Lennar’s motion to release Saxum’s lien,
    the superior court opined that Saxum was not assigned the lien because (1)
    Saxum was not assigned the subcontract, and (2) Wall to Wall did not record the
    lien:
    [SAXUM’S COUNSEL]: . . . And it’s -- the key point for this
    Materialmen’s Lien statute is that it’s the debt and the cause of
    action that was clearly assigned; there’s a Bill of Sale from the
    Chapter 7 trustee.
    Wall To Wall, it’s undisputable that they fall under the
    statute. There’s no --
    THE COURT: Oh, they definitely fall under it. I mean they
    did the work. They would fall under it.
    The question is, because you didn’t buy the sub -- because
    you didn’t get the subcontract, I mean the question is, and they
    didn’t file a lien, whether you fall under it.
    On August 21, 2020, the superior court entered an order releasing the lien
    and awarding attorney fees and costs to Lennar. The order did not contain
    written findings of fact demonstrating that Saxum’s claim of lien was frivolous.
    Saxum appeals.
    II
    As an initial matter, Saxum contends that the superior court erred by not
    entering findings of fact demonstrating that Saxum’s lien was frivolous. We
    disagree.
    6
    No. 81879-1-I/7
    RCW 60.04.0814 “creates a summary proceeding in which a property
    owner may quickly obtain the release of a lien that is frivolous and made without
    reasonable cause.” W.R.P. Lake Union Ltd. P’ship v. Exterior Servs., Inc., 
    85 Wn. App. 744
    , 749, 
    934 P.2d 722
     (1997). This “statutory procedure is . . . in the
    nature of a trial by affidavit.” W.R.P. Lake Union Ltd. P’ship, 85 Wn. App. at 750.
    We have previously noted that motions filed pursuant to RCW 60.04.081
    initiate a “special proceeding.” Andries v. Covey, 
    128 Wn. App. 546
    , 550, 
    113 P.3d 483
     (2005). In such a special proceeding, strict compliance with the CR 52
    mandate concerning the entry and content of findings of fact is not required. CR
    81(a). Indeed, we have previously explained that RCW 60.04.081 “contains no
    4 RCW 60.04.081 provides:
    (1) Any owner of real property subject to a recorded claim of lien under this
    chapter, or contractor, subcontractor, lender, or lien claimant who believes the
    claim of lien to be frivolous and made without reasonable cause, or clearly
    excessive may apply by motion to the superior court for the county where the
    property, or some part thereof is located, for an order directing the lien claimant
    to appear before the court at a time no earlier than six nor later than fifteen days
    following the date of service of the application and order on the lien claimant, and
    show cause, if any he or she has, why the relief requested should not be granted.
    The motion shall state the grounds upon which relief is asked, and shall be
    supported by the affidavit of the applicant or his or her attorney setting forth a
    concise statement of the facts upon which the motion is based.
    (2) The order shall clearly state that if the lien claimant fails to appear at
    the time and place noted the lien shall be released, with prejudice, and that the
    lien claimant shall be ordered to pay the costs requested by the applicant
    including reasonable attorneys’ fees.
    (3) If no action to foreclose the lien claim has been filed, the clerk of the
    court shall assign a cause number to the application and obtain from the
    applicant a filing fee pursuant to RCW 36.18.016. If an action has been filed to
    foreclose the lien claim, the application shall be made a part of that action.
    (4) If, following a hearing on the matter, the court determines that the lien
    is frivolous and made without reasonable cause, or clearly excessive, the court
    shall issue an order releasing the lien if frivolous and made without reasonable
    cause, or reducing the lien if clearly excessive, and awarding costs and
    reasonable attorneys’ fees to the applicant to be paid by the lien claimant. If the
    court determines that the lien is not frivolous and was made with reasonable
    cause, and is not clearly excessive, the court shall issue an order so stating and
    awarding costs and reasonable attorneys’ fees to the lien claimant to be paid by
    the applicant.
    (5) Proceedings under this section shall not affect other rights and
    remedies available to the parties under this chapter or otherwise.
    7
    No. 81879-1-I/8
    requirement for entry of findings of fact and conclusions of law.” W.R.P. Lake
    Union Ltd. P’ship, 85 Wn. App. at 750. However, “[a]t a minimum, the trial court’s
    reasoning for entering the order should be clearly set out in the order itself.”
    W.R.P. Lake Union Ltd. P’ship, 85 Wn. App. at 750.
    Nevertheless, Saxum contends that our opinion in S.D. Deacon Corp. of
    Washington v. Gaston Bros. Excavating, Inc., 
    150 Wn. App. 87
    , 
    206 P.3d 689
    (2009), required the superior court to enter findings of fact demonstrating that
    Saxum’s lien was frivolous in order to release the lien. Not so. In that case, the
    parties disputed facts that were material to the superior court’s determination of
    whether a construction lien was frivolous. S.D. Deacon Corp., 150 Wn. App. at
    95. Because there was a material factual dispute as to the validity of the lien, we
    explained that “the court must make specific findings establishing that the lien is
    so meritless as to justify depriving the claimant of the opportunity to present live
    testimony and cross-examine witnesses.” S.D. Deacon Corp., 150 Wn. App. at
    96.
    Here, however, the material facts were not in dispute. Moreover, the
    superior court’s reasoning for releasing the lien is apparent from the record and
    the order. During the hearing on Lennar’s motion to release Saxum’s lien, the
    following exchange occurred between Saxum’s counsel and the superior court:
    [SAXUM’S COUNSEL]: . . . And it’s -- the key point for this
    Materialmen’s Lien statute is that it’s the debt and the cause of
    action that was clearly assigned; there’s a Bill of Sale from the
    Chapter 7 trustee.
    Wall To Wall, it’s undisputable that they fall under the
    statute. There’s no --
    THE COURT: Oh, they definitely fall under it. I mean they
    did the work. They would fall under it.
    8
    No. 81879-1-I/9
    The question is, because you didn’t buy the sub -- because
    you didn’t get the subcontract, I mean the question is, and they
    didn’t file a lien, whether you fall under it.
    The day after the hearing, the superior court entered its order granting
    Lennar’s motion. This order was entitled, “ORDER TO RELEASE FRIVOLOUS
    LIEN AND FOR AWARD OF ATTORNEY FEES PURSUANT TO RCW
    60.04.081.” Based on this record, the superior court’s reasoning for releasing
    Saxum’s lien is apparent.
    Accordingly, Saxum’s assignment of error fails.
    III
    Saxum next contends that the superior court erred by releasing Saxum’s
    lien as being frivolous. Because the lien was assigned to Saxum pursuant to the
    asset purchase agreement, which was approved by a bankruptcy court order, we
    agree.
    A
    We review a superior court’s interpretation of chapter 60.04 RCW de
    novo. Intermountain Elec., Inc. v. G-A-T Bros. Constr., Inc., 
    115 Wn. App. 384
    ,
    390, 
    62 P.3d 548
     (2003). “Mechanics’ and materialmen’s liens are creatures of
    statute, in derogation of common law, and therefore must be strictly construed to
    determine whether a lien attaches.” Estate of Haselwood v. Bremerton Ice
    Arena, Inc., 
    166 Wn.2d 489
    , 498, 
    210 P.3d 308
     (2009). “But if it is determined a
    party’s lien is covered by chapter 60.04 RCW, the statute is to be liberally
    construed to provide security for all parties intended to be protected by its
    provisions.” Estate of Haselwood, 166 Wn.2d at 498 (citing RCW 60.04.900).
    9
    No. 81879-1-I/10
    A court’s fundamental objective when determining the meaning of a
    statute “is to ascertain and carry out the Legislature’s intent.” Dep’t of Ecology
    v. Campbell & Gwinn, LLC, 
    146 Wn.2d 1
    , 9, 
    43 P.3d 4
     (2002). “Where a
    ‘statute’s meaning is plain on its face, then the court must give effect to that plain
    meaning as an expression of legislative intent.’” Inland Empire Dry Wall Supply
    Co. v. W. Sur. Co., 
    189 Wn.2d 840
    , 843, 
    408 P.3d 691
     (2018) (quoting Campbell
    & Gwinn, LLC, 146 Wn.2d at 9-10). A statute’s plain meaning “is discerned from
    all that the Legislature has said in the statute and related statutes which disclose
    legislative intent about the provision in question.” Campbell & Gwinn, LLC, 146
    Wn.2d at 11.
    “To be frivolous, a lien must be improperly filed beyond legitimate dispute.”
    Pac. Indus., Inc. v. Singh, 
    120 Wn. App. 1
    , 5, 
    86 P.3d 778
     (2003) (citing W.R.P.
    Lake Union Ltd. P’ship, 85 Wn. App. at 752). A lien “is frivolous ‘only if it
    presents no debatable issues and is so devoid of merit that it had no possibility of
    succeeding.’” Pac. Indus., Inc., 120 Wn. App. at 6 (quoting Intermountain Elec.,
    Inc., 115 Wn. App at 394). “Every frivolous lien is invalid, but not every invalid
    lien is frivolous.” Pac. Indus., Inc., 120 Wn. App. at 6.
    B
    It is well established in Washington that “[a] lien, like a mortgage, is a
    chose in action.” Mueller v. Rupp, 
    52 Wn. App. 445
    , 450, 
    761 P.2d 62
     (1988)
    (citing In re Estate of Adler, 
    116 Wash. 484
    , 489, 
    199 P. 762
     (1921);
    Congregational Church Bldg. Soc’y v. Scandinavian Free Church of Tacoma, 
    24 Wash. 433
    , 436-37, 
    64 P. 750
     (1901)). “A chose in action is personal property.”
    10
    No. 81879-1-I/11
    Mueller, 
    52 Wn. App. at 450-51
     (citing In re Estate of Plasterer, 
    49 Wn.2d 339
    ,
    341, 
    301 P.2d 539
     (1956); Ennis v. Ring, 
    49 Wn.2d 284
    , 289, 
    300 P.2d 773
    (1956)).
    The relevant statute provides that, subject to certain notice requirements,
    any person furnishing labor, professional services, materials, or
    equipment for the improvement of real property shall have a lien
    upon the improvement for the contract price of labor, professional
    services, materials, or equipment furnished at the instance of the
    owner, or the agent or construction agent of the owner.
    RCW 60.04.021.
    Under this statute, a construction lien5 “arises and attaches upon the
    performing of labor or furnishing of materials.” A.A.R. Testing Lab., Inc. v. New
    Hope Baptist Church, 
    112 Wn. App. 442
    , 448, 
    50 P.3d 650
     (2002) (citing RCW
    60.04.021). This interpretation of RCW 60.04.021 is consistent with the statutory
    language of RCW 60.04.061, which addresses the priority of liens:
    The claim of lien created by this chapter upon any lot or parcel of land
    shall be prior to any lien, mortgage, deed of trust, or other encumbrance
    which attached to the land after or was unrecorded at the time of
    commencement of labor or professional services or first delivery of
    materials or equipment by the lien claimant.
    (Emphasis added.)
    Construction liens “are a class of ‘off-the-record’ interests that may be
    senior to interests actually recorded prior to the recording of the . . . lien but after
    5 “In 1991, Washington’s comprehensive mechanics’ and materialmen’s lien statute was
    repealed and replaced with a revised and recodified law.” Diversified Wood Recycling, Inc.
    v. Johnson, 
    161 Wn. App. 891
    , 902 n.14, 
    251 P.3d 908
     (2011) (citing LAWS OF 1991, ch. 281; ch.
    60.04 RCW). “‘The title “mechanics’ and materialmen’s lien” is still used in the RCW, but the liens
    are called by the more inclusive title, “construction liens,” in this subchapter.’” Diversified Wood
    Recycling, Inc., 161 Wn. App. at 902 n.14 (quoting 27 MARJORIE DICK RAMBAUER, W ASHINGTON
    PRACTICE: CREDITORS’ REMEDIES—DEBTORS’ RELIEF § 4.51, at 347 (1998)).
    11
    No. 81879-1-I/12
    commencement of work on the project.” A.A.R. Testing Lab., Inc., 112 Wn. App.
    at 448. “During the period of time between commencement of work and actual
    recording of the claim of lien, a [construction] lien has an ‘off-record’ priority.”
    A.A.R. Testing Lab., Inc., 112 Wn. App. at 448-49. Construction liens attach to
    the “lot, tract, or parcel of land which is improved.” RCW 60.04.051.
    Notably, under chapter 60.04 RCW, construction liens are assignable.
    RCW 60.04.121 provides: “Any lien or right of lien created by this chapter and the
    right of action to recover therefor, shall be assignable so as to vest in the
    assignee all rights and remedies of the assignor.” The statutory scheme of
    chapter 60.04 RCW demonstrates that a construction lien is assignable
    regardless of whether that lien has been recorded. Indeed, the language that is
    recommended, by statute, to be used on forms for recording construction liens,
    provides, in pertinent part: “IF THE CLAIMANT IS THE ASSIGNEE OF THIS
    CLAIM SO STATE HERE.” RCW 60.04.091(2).
    C
    Wall to Wall’s bankruptcy estate possessed a construction lien right on the
    land on which the Totem Lakes Apartments project was situated. On July 16,
    2019, Wall to Wall filed for chapter 11 bankruptcy. Although the record is not
    clear as to whether Wall to Wall had commenced work prior to commencing the
    bankruptcy proceeding, Wall to Wall continued to fabricate and install quartz
    countertops on the Totem Lake Apartments project through March 2020.
    Once Wall to Wall provided and installed quartz material on the Totem
    Lake Apartments project, a construction lien arose and attached to the land on
    12
    No. 81879-1-I/13
    which the Totem Lake Apartments project was located.6 See RCW 60.04.021;
    A.A.R. Testing Lab., Inc., 112 Wn. App. at 448.
    The construction lien that arose and attached when Wall to Wall
    commenced lienable work on the Totem Lake Apartments project was assigned
    to Saxum pursuant to the bill of sale and asset purchase agreement, which was
    approved by a bankruptcy court order. The asset purchase agreement stated, in
    part:
    Seller hereby sells to Buyer and Buyer hereby purchases from
    Seller all of the Assets of the Estate useful in the Business,
    including, but not limited to accounts receivable, equipment,
    inventory, supplies, the real property leases listed in Schedule 1.2,
    software, licenses, Intellectual Property, books and records, tools,
    vehicles listed on Schedule 1.1, all claims, if any, against Buyer, its
    members, agents, attorneys, officers, and directors (“Buyer
    Claims”).
    (First emphasis added.)
    In other words, the assets that were encompassed by the asset purchase
    agreement were not limited to those assets that were specifically listed in the
    writing. Although the asset purchase agreement excluded certain assets, the
    construction lien in dispute was not listed as an excluded asset. Accordingly, the
    6   11 U.S.C. § 541 explains what assets are part of the bankruptcy estate after a party
    files for bankruptcy:
    (a) The commencement of a case under section 301, 302, or 303 of this title
    creates an estate. Such estate is comprised of all the following property,
    wherever located and by whomever held:
    (1) Except as provided in subsections (b) and (c)(2) of this section, all legal or
    equitable interests of the debtor in property as of the commencement of the
    case.
    ....
    (7) Any interest in property that the estate acquires after the commencement
    of the case.
    The exceptions provided in 11 U.S.C. § 541(b) and (c)(2) do not apply to the construction
    lien in dispute. Accordingly, regardless of whether Wall to Wall commenced work on the Totem
    Lake Apartments project prior to filing for bankruptcy, the bankruptcy estate clearly possessed the
    construction lien at the time the sale was approved by the bankruptcy court.
    13
    No. 81879-1-I/14
    construction lien was assigned to Saxum pursuant to the asset purchase
    agreement, as approved by the bankruptcy court.
    Lennar asserts that Saxum was not assigned the construction lien. This is
    so, according to Lennar, because “the cause of action did not exist at any time
    during the pendency of the [Wall to Wall] bankruptcy or at the time of the
    bankruptcy sale.”7 We disagree. As previously explained, a construction lien
    “arises and attaches upon the performing of labor or furnishing of materials.”
    A.A.R. Testing Lab., Inc., 112 Wn. App. at 448. As such, the cause of action
    arose when Wall to Wall fabricated and installed the quartz material in the Totem
    Lake Apartments project.
    Lennar also contends that Saxum does not fall within the class of persons
    contemplated by chapter 60.04 RCW as entitled to claim a construction lien.
    According to Lennar, “RCW 60.04.021 is explicit regarding those who come
    under the statute’s terms and quantifies this group as ‘any person furnishing
    labor, professional services, materials, or equipment for the improvement of real
    property.’”8 But this argument is off the mark. To be clear, RCW 60.04.121
    provides: “Any lien or right of lien created by this chapter and the right of action to
    recover therefor, shall be assignable so as to vest in the assignee all rights and
    remedies of the assignor.” (Emphasis added.) Therefore, Saxum—as assignee
    of the construction lien possessed by Wall to Wall’s bankruptcy estate—is
    entitled to enforce the construction lien.
    7   Br. of Resp’t at 23.
    8   Br. of Resp’t at 9-10.
    14
    No. 81879-1-I/15
    Lennar next asserts that chapter 60.04 RCW requires that only the entity
    who performed lienable work can record a construction lien even if the right of
    lien is assigned. We disagree. In Lennar’s view of the law, that entity must
    record the lien prior to assignment and, if it does not, the assignee engages in a
    frivolous frolic by attempting enforcement. The basis for Lennar’s assertion lies
    in RCW 60.04.091, which states:
    Every person claiming a lien under RCW 60.04.021 shall file for
    recording . . . a notice of claim of lien not later than ninety days
    after the person has ceased to furnish labor, professional services,
    materials, or equipment or the last date on which employee benefit
    contributions were due.
    Lennar claims that this language requires that only the entity who
    performed lienable work can record the lien—to the exclusion of assignees. The
    folly of this contention, however, is made plain by a provision of the
    recommended claim of lien form in this same section. This form states: “IF THE
    CLAIMANT IS THE ASSIGNEE OF THIS CLAIM SO STATE HERE.” RCW
    60.04.091(2).
    Lennar asserts that the quoted language in RCW 60.04.091(2) must be
    interpreted to apply only to notice of claim forms that are filed to amend an
    already-filed notice of claim of lien.9 To the contrary, RCW 60.04.121 provides:
    “Any lien or right of lien created by this chapter and the right of action to recover
    therefor, shall be assignable so as to vest in the assignee all rights and remedies
    of the assignor.” (Emphasis added.) This broad and inclusive language clearly
    9 RCW 60.04.091(2) authorizes parties to amend a notice of claim of lien under certain
    circumstances: “Where an action to foreclose the lien has been commenced such notice of claim
    of lien may be amended as pleadings may be by order of the court insofar as the interests of third
    parties are not adversely affected by such amendment.”
    15
    No. 81879-1-I/16
    authorizes the assignment of a construction lien regardless of whether that lien
    has already been recorded. Additionally, because an assignee is vested with all
    of the rights of the assignor, an assignee is plainly entitled to file a notice of claim
    of lien under RCW 60.04.091.
    Finally, Lennar avers that RCW 60.04.191 prevented the construction lien
    that was possessed by Wall to Wall’s bankruptcy estate from being assigned to
    Saxum by means of the asset purchase agreement. The cited statute provides:
    Nothing in this chapter shall be construed to impair or affect
    the right of any person to whom any debt may be due for the
    furnishing of labor, professional services, material, or equipment to
    maintain a personal action to recover the debt against any person
    liable therefor.
    RCW 60.04.191.
    According to Lennar, “it is impossible to reconcile that [Wall to Wall]’s
    rights could be transferred free and clear through bankruptcy when RCW 60.04
    itself prevents [Wall to Wall]’s rights from being impaired.”10 But again, RCW
    60.04.121 expressly authorizes the assignment of construction liens. And, in any
    event, Wall to Wall forfeited any right that it may have otherwise had in the lien to
    the bankruptcy estate when it filed for bankruptcy. See 11 U.S.C. § 541. We
    decline to hold that RCW 60.04.191 prevented the construction lien from being
    assigned to Saxum pursuant to the bill of sale, asset purchase agreement, and
    bankruptcy court order.
    In sum, chapter 60.04 RCW authorizes the assignment of a construction
    lien regardless of whether that lien has already been recorded. Saxum was
    10   Br. of Resp’t at 18.
    16
    No. 81879-1-I/17
    assigned the construction lien pursuant to the bill of sale and asset purchase
    agreement, which was approved by the bankruptcy court.
    Accordingly, the trial court erred by releasing Saxum’s lien.11
    IV
    Saxum asserts that, because its lien was not frivolous, the superior court
    erred by awarding attorney fees and costs to Lennar. We agree.
    In a summary frivolous lien proceeding, the prevailing party is statutorily
    entitled to an award of attorney fees:
    If, following a hearing on the matter, the court determines that the
    lien is frivolous and made without reasonable cause, or clearly
    excessive, the court shall issue an order releasing the lien if
    frivolous and made without reasonable cause, or reducing the lien if
    clearly excessive, and awarding costs and reasonable attorneys’
    fees to the applicant to be paid by the lien claimant. If the court
    determines that the lien is not frivolous and was made with
    reasonable cause, and is not clearly excessive, the court shall
    issue an order so stating and awarding costs and reasonable
    attorneys’ fees to the lien claimant to be paid by the applicant.
    RCW 60.04.081(4) (emphasis added); accord W.R.P. Lake Union Ltd. P’ship, 85
    Wn. App. at 753 (“Attorney fees are mandatory for the prevailing party under
    RCW 60.04.081(4).”).
    Additionally, we have interpreted RCW 60.04.081(4) to encompass
    attorney fees incurred by the prevailing party on appeal. See, e.g., W.R.P. Lake
    Union Ltd. P’ship, 85 Wn. App. at 753; Intermountain Elec., Inc., 115 Wn. App. at
    395-96.
    11 Saxum also asserts that it was assigned the construction lien merely by purchasing the
    account receivable from the bankruptcy trustee. According to Saxum, “it is the assignment of the
    debt alone that confers Saxum’s rights as a lien claimant under RCW 60.04.” Br. of Appellant at
    17. Because Saxum was assigned the construction lien under the plain terms of the asset
    purchase agreement, we need not address this argument.
    17
    No. 81879-1-I/18
    Because Saxum’s lien is not frivolous, the award of attorney fees to
    Lennar is reversed. On remand, Saxum is entitled to an award of attorney fees
    and costs for defending this action in both the superior court and on appeal.
    The remainder of this opinion has no precedential value. Therefore, it will
    be filed for public record in accordance with the rules governing unpublished
    opinions. See RCW 2.06.040.
    V
    We next address an argument that Lennar raised, but did not adequately
    brief, on appeal. Additionally, we will attempt to provide guidance to the superior
    court in the event that Lennar, on remand, advances the defenses of setoff or
    recoupment against Saxum’s lien.
    A
    Lennar claims that, in order for Saxum to have been assigned Wall to
    Wall’s lien, it must have also been assigned the subcontract that was executed
    between Wall to Wall and Lennar. Lennar asserts that “[t]his is embodied in
    statute in RCW 60.04.121, which notes, a lien or right of lien ‘shall be assignable
    so as to vest in the assignee all rights and remedies of the assignor, subject to all
    defenses thereto that might be made.’”12 According to Lennar, “[w]ithout the
    assignment of the underlying contract, [Lennar] is precluded from raising all
    defenses this assignment statute contemplates.”13 This argument was not
    contained within the statement of the issues in Lennar’s brief as is required by
    12   Br. of Resp’t at 19.
    13   Br. of Resp’t at 19.
    18
    No. 81879-1-I/19
    RAP 10.3(b).14 Instead, the issue was raised in a perfunctory manner within a
    section of the brief devoted to a different claim of error.
    Contrary to Lennar’s apparent belief, RCW 60.04.121 does not guarantee
    a party against whom a construction lien is filed the right to assert any defense
    whatsoever against the lien. Instead, the statute permits a party to advance
    defenses that it is entitled to advance. Indeed, the statute provides that an
    assigned construction lien is “subject to all defenses thereto that might be made.”
    RCW 60.04.121 (emphasis added). To the extent that the bankruptcy court order
    approving the asset purchase agreement extinguished any defenses or claims
    that Lennar may have otherwise been able to advance, Lennar is not entitled to
    advance such defenses or claims against Saxum’s lien.
    B
    The bankruptcy court order approving the asset purchase agreement
    provided that the assets encompassed by the agreement were sold free and
    clear of all claims. The basis for this was the bankruptcy court’s ruling: “The
    Trustee may sell the assets free and clear of all liens, claims, and encumbrances
    . . . because, in each case, one or more of the standards set forth in 11 U.S.C. §
    363(f)(1)-(5) has been established.”
    14The statement of the issues in Lennar’s brief are:
    1. Whether the trial court was required to make findings of fact to determine
    Saxum’s lien was frivolous as a matter of law based on an undisputed
    record?
    2. Whether Saxum did not fall under the class of people contemplated by RCW
    60.04 to bring a claim of lien, rendering the claim of lien frivolous?
    3. Whether Saxum had no valid right of lien when no lien was filed by Wall to
    Wall Tile & Stone, LLC, upon conclusion of its work on the Project, rendering
    the claim of lien frivolous?
    Br. of Resp’t at 2.
    19
    No. 81879-1-I/20
    The cited authority provides:
    The trustee may sell property under subsection (b) or (c) of this
    section free and clear of any interest in such property of an entity
    other than the estate, only if—
    (1) applicable nonbankruptcy law permits sale of such
    property free and clear of such interest;
    (2) such entity consents;
    (3) such interest is a lien and the price at which such
    property is to be sold is greater than the aggregate value of all liens
    on such property;
    (4) such interest is in bona fide dispute; or
    (5) such entity could be compelled, in a legal or equitable
    proceeding, to accept a money satisfaction of such interest.
    11 U.S.C. § 363(f).
    In an opinion not cited to us by either party, a federal circuit court
    observed that, in the context of 11 U.S.C. § 363(f), “[c]ourts faced with the task of
    defining the scope of the term ‘any interest’ have been unable to provide a
    precise definition.” Folger Adam Sec., Inc. v. DeMatteis/MacGregor JV, 
    209 F.3d 252
    , 258 (3d Cir. 2000) (citing 3 COLLIER ON BANKRUPTCY ¶ 363.06[1]).
    Nevertheless, the circuit court sought to give meaning to the term.
    The bankruptcy court order at issue therein was one approving the sale of
    assets. It provided:
    “The sale of the Acquired Assets and the assignment of the
    Assigned Contracts to Purchaser is made free and clear of all liens,
    mortgages, security interests, encumbrances, liabilities, claims,
    or any other interests, other than the Assumed Liabilities, whether
    arising before or after the Petition Date.”
    Folger Adam Sec., Inc., 
    209 F.3d at 257
    . In addition, the notice of auction that
    preceded the sale “indicated that the sale was to be ‘free and clear’ of all claims
    and other ‘interests’ that could be asserted against the Debtors.” Folger Adam
    Sec., Inc., 
    209 F.3d at 255
    .
    20
    No. 81879-1-I/21
    The circuit court opined that “the phrase ‘any other interests’” in the
    bankruptcy court’s order “would not include [the defenses of] setoff and
    recoupment[15] since those interests are not similar to those enumerated in the
    Notice of Auction.” Folger Adam Sec., Inc., 
    209 F.3d at 260
    . Although the notice
    of auction in that case provided that the sale was to be free and clear of all
    claims, the circuit court reasoned that the Bankruptcy Code’s definition of claim
    “requires an enforceable obligation of the debtor to pay the claimant.” Folger
    Adam Sec., Inc., 
    209 F.3d at 260
    . Conversely, “a defense seeks to diminish a
    claim or to defeat recovery rather than to share in it.” Folger Adam Sec., Inc.,
    
    209 F.3d at 260
     (citing BLACK’S LAW DICTIONARY 419 (6th ed. 1990)).
    However, and significantly, the circuit court suggests that a creditor may
    advance the defenses of recoupment and setoff only with regard to debts that
    arose prior to the commencement of the bankruptcy case.16
    15   “Recoupment and set-off rights are usually determined by state law.” In re Lawrence
    United Corp., 
    221 B.R. 661
    , 669 (Bankr. N.D.N.Y. 1998). In Washington, the defense of
    recoupment is “‘the keeping back or stopping something which is otherwise due, because the
    other party to the contract has violated some duty devolving upon him in the same transaction.’”
    J.A. Campbell Co. v. Holsum Baking Co., 
    15 Wn.2d 239
    , 253, 
    130 P.2d 333
     (1942) (quoting
    Nelson Co. v. Goodrich, 
    159 Wash. 189
    , 194, 
    292 P. 406
     (1930)). Additionally, “when setoff is
    asserted against an assignee [of a contract], it diminishes or defeats the assignee’s claim,
    although the assignee has no liability in excess of the amount sued on.” Nancy’s Prod., Inc.
    v. Fred Meyer, Inc., 
    61 Wn. App. 645
    , 650-61, 
    811 P.2d 250
     (1991). Although Saxum was not
    assigned the subcontract executed between Lennar and Wall to Wall, RCW 60.04.121 states that
    an assigned construction lien is “subject to all defenses thereto that might be made.” A breach of
    contract may form the basis of such a defense. See 33 DAVID K. DEWOLF & MATTHEW C.
    ALBRECHT, W ASHINGTON PRACTICE: CONSTRUCTION LAW MANUAL § 14.38, at 315 (2d ed. 2018)
    (listing breach of contract as a viable defense in a construction lien foreclosure proceeding); Pilch
    v. Hendrix, 
    22 Wn. App. 531
    , 533, 
    591 P.2d 824
     (1979) (holding that a breach of contract
    counterclaim brought in a mechanics’ lien foreclosure proceeding was supported by substantial
    evidence).
    16 With regard to the defense of recoupment, the Third Circuit stated that “we agree with
    the Bankruptcy Court in In re Lawrence United Corp. and hold that a right of recoupment is a
    defense and not an interest and therefore is not extinguished by a § 363(f) sale.” Folger Adam
    Sec., Inc., 
    209 F.3d at 261
    . In the cited case, In re Lawrence United Corp., 
    221 B.R. at 671,
     the
    bankruptcy court found that the creditor therein “does not have a right of recoupment against the
    commissions earned postpetition.” The bankruptcy court determined that “[s]uch a result would
    21
    No. 81879-1-I/22
    Similarly, in Marley v. United States, 
    381 F.2d 738
    , 743 (Ct. Cl. 1967),17
    the Court of Claims held that a bankruptcy sale of certain causes of action
    against the United States “free and clear of liens” did not mean that the causes of
    action “were sold free and clear of the Government’s already asserted right to
    setoff.” (Emphasis added.) In that case, the government had asserted a right to
    setoff in a contract dispute with the debtor in the Court of Claims prior to the
    commencement of the bankruptcy proceeding. Marley, 
    381 F.2d at 741
    .
    We note that there is a dearth of published authority in the Ninth Circuit
    regarding the issue of whether a defense is an “interest” within the context of 11
    U.S.C. § 363(f). See, e.g., In re Fraser’s Boiler Serv., Inc., No. 3:18-CV-05637-
    RBL, 
    2019 WL 1099713
     (W.D. Wash. 2019) (unpublished)18 (“[A]n ‘interest in
    such property’ includes ‘obligations that may flow from ownership of property’ or
    ‘obligations that are connected to, or arise from, the property being sold.’”
    (quoting Folger Adam Sec., Inc., 
    209 F.3d at 258
    )). Accordingly, on this record
    and briefing, it is unclear whether, or to what extent, the Third Circuit’s reasoning
    in Folger Adam Sec., Inc., 
    209 F.3d 252
    , is applicable to the order entered by the
    United States Bankruptcy Court for the District of Oregon with regard to Saxum’s
    construction lien.
    enable [the creditor] to receive better treatment than other general, unsecured creditors, a result
    inconsistent with one of the [Bankruptcy] Code’s canons: equal treatment for similarly-situated
    creditors.” In re Lawrence United Corp., 
    221 B.R. at 671
    .
    Additionally, the Third Circuit explained that, with regard to the defense of setoff, a
    creditor “must prove that it actually took a setoff, the amounts and against which contracts, before
    the bankruptcy filing. This does not mean it actually must have received funds, but that its
    accounts receivable were reduced or offset.” Folger Adam Sec., Inc., 
    209 F.3d at 263
    .
    17 This case was also not cited to us by either party.
    18 This case was also not cited to us by either party.
    22
    No. 81879-1-I/23
    C
    Given the inadequacy of the record and briefing on appeal, we decline to
    decide whether Lennar is entitled to assert the defenses of setoff and
    recoupment against Saxum’s lien. However, on remand, the superior court
    should be aware of several things.
    First, the bankruptcy court order approving the asset purchase agreement
    provides: “This Court shall retain jurisdiction to resolve any controversy or claim
    arising out of or related to the implementation of this Order or the transactions
    contemplated thereby.” Thus, the bankruptcy court retains jurisdiction to
    determine whether the defenses of setoff and recoupment are “claims” within the
    meaning of its order. Therefore, the question of whether Lennar is entitled to
    assert the defenses of setoff and recoupment—either in this proceeding or in a
    judicial foreclosure proceeding initiated pursuant to RCW 60.04.17119—appears
    to be reserved to the bankruptcy court (not the superior court) by virtue of the
    wording in the order itself.
    Second, even if the bankruptcy court’s ruling—namely, that the trustee
    was authorized to sell all of the assets encompassed by the asset purchase
    agreement free and clear of all claims—was erroneous, Lennar is not entitled to
    dispute the validity of that ruling in state court. Indeed, when a “factual finding
    19RCW 60.04.171 provides, in part:
    The lien provided by this chapter, for which claims of lien have been recorded, may be
    foreclosed and enforced by a civil action in the court having jurisdiction in the manner
    prescribed for the judicial foreclosure of a mortgage. The court shall have the power to
    order the sale of the property. In any action brought to foreclose a lien, the owner shall
    be joined as a party. The interest in the real property of any person who, prior to the
    commencement of the action, has a recorded interest in the property, or any part thereof,
    shall not be foreclosed or affected unless they are joined as a party.
    23
    No. 81879-1-I/24
    [under 11 U.S.C. § 363(f)] is made but is erroneous, or the interested party
    simply does not like the outcome of the sale, his only remedy is to collaterally
    attack the order to sell free and clear.” In re DeCelis, 
    349 B.R. 465
    , 470 (Bankr.
    E.D. Va. 2006) (emphasis added). “[T]he order approving a bankruptcy sale is a
    judicial order and can be attacked collaterally only within the tight limits that Fed.
    R. Civ. P. 60(b)[20] imposes on collateral attacks on civil judgments.”
    FutureSource LLC v. Reuters Ltd., 
    312 F.3d 281
    , 286 (7th Cir. 2002).
    Accordingly, should Lennar dispute whether the construction lien was assigned
    to Saxum free and clear of all claims, Lennar must turn to the bankruptcy court
    for resolution of the question.
    Third, in Lennar’s reply in support of its motion to release Saxum’s lien,21
    Lennar stated that it “is not asking for setoff or recoupment damages.” Because
    Lennar both affirmatively disclaimed the defenses of setoff and recoupment in
    the superior court and failed to adequately brief on appeal whether it was entitled
    to advance such defenses, the superior court may be called upon to determine
    whether Lennar has forfeited any defense of setoff or recoupment. This
    20 Federal Rule of Bankruptcy Procedure 9024 states that “Rule 60 F. R. Civ. P. applies
    in cases under the Code.” Federal Rule of Civil Procedure 60(b) provides, in part:
    (b) Grounds for Relief from a Final Judgment, Order, or Proceeding. On motion
    and just terms, the court may relieve a party or its legal representative from a
    final judgment, order, or proceeding for the following reasons:
    (1) mistake, inadvertence, surprise, or excusable neglect;
    (2) newly discovered evidence that, with reasonable diligence, could not
    have been discovered in time to move for a new trial under Rule 59(b);
    (3) fraud (whether previously called intrinsic or extrinsic),
    misrepresentation, or misconduct by an opposing party;
    (4) the judgment is void;
    (5) the judgment has been satisfied, released, or discharged; it is based
    on an earlier judgment that has been reversed or vacated; or applying it
    prospectively is no longer equitable; or
    (6) any other reason that justifies relief.
    21 A pleading filed in the superior court.
    24
    No. 81879-1-I/25
    determination will influence any further review we may conduct, given that “‘[i]t is
    . . . the rule that questions determined on appeal, or which might have been
    determined had they been presented, will not again be considered on a
    subsequent appeal if there is no substantial change in the evidence at a second
    determination of the cause.’” Folsom v. County of Spokane, 
    111 Wn.2d 256
    ,
    263, 
    759 P.2d 1196
     (1988) (emphasis added) (quoting Adamson v. Traylor, 
    66 Wn.2d 338
    , 339, 
    402 P.2d 499
     (1965)); see also RAP 2.5(c). We do not, at this
    time, make any determination on the question.
    Fourth, in the event that Lennar is determined to be entitled to assert the
    defenses of setoff or recoupment, Lennar must then establish that the right in
    question arose before Wall to Wall filed for bankruptcy. See Folger Adam Sec.,
    Inc., 
    209 F.3d at 261, 263
    ; In re Lawrence United Corp., 
    221 B.R. 661
    , 669, 671
    (Bankr. N.D.N.Y. 1998). This is a factual question that we cannot determine on
    the present record.
    Reversed and remanded.
    WE CONCUR:
    25