Lsf Structures Ltd & Lightweight Steel Framing 2007 Ltd, Apps v. Brix Condos, Resps ( 2016 )


Menu:
  •        IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    LSF STRUCTURES LTD, a foreign,
    corporation; LIGHTWEIGHT STEEL                   No. 73427-0-1
    FRAMING 2007 LTD, a Washington
    corporation,                                     DIVISION ONE
    Appellants,
    v.
    BRIX CONDOMINIUM, LLC, a                         UNPUBLISHED OPINION
    Washington limited liability company;
    W.G. CLARK CM, INC., a Washington                FILED: November 7, 2016
    corporation;
    Respondents,
    SAFECO INSURANCE COMPANY OF
    AMERICAAS SURETY FOR
    CONTRACTOR'S REGISTRATION
    BOND NO. 6079369, a Washington
    corporation,
    Defendant.
    Becker, J. — Respondents Brix Condominium LLC and W.G. Clark CM
    Inc. were entitled to summary judgment because Appellants LSF Structures LTD
    and Lightweight Steel Framing 2007 Ltd. failed to satisfy the contractual condition
    precedent to bringing the lawsuit and failed to show that its lawsuit should be
    interpreted as a complaint to compel arbitration. We affirm.
    No. 73427-0-1/2
    FACTS
    This is the second time these parties have been before this court on the
    same facts and mostly the same legal issues. Brix Condominium LLC (Brix) was
    the developer of the Brix Condominiums project. W.G. Clark CM Inc. (WGC) was
    the general contractor for the Brix Condominiums project and a member of Brix.
    In 2007, subcontractor Lightweight Steel Framing 2007 Ltd. and LSF Structures
    Ltd. (together LSF)1 and WGC executed a subcontract for work on the Brix
    Condominiums project. Section U2 and U3 of the subcontract required the
    parties to submit their disputes to nonbinding mediation followed by binding
    arbitration. Section U3 also provided:
    Subcontractor agrees not to file any claim in mediation, arbitration,
    or litigation, until thirty (30) days after having submitted its full claim
    in writing to Mike Ducey, president of [WGC], along with detailed
    cost documentation and all points of argument in Subcontractor's
    favor. Subcontractor acknowledges its responsibility to cooperate
    with [WGC] in avoiding unnecessary arbitration or litigation by
    providing [it] with all information available upon which a decision
    can be made.
    (Emphasis added.) Effective July 1, 2008, WGC assigned its interest in the
    subcontract to Brix and notified LSF that all references in the subcontract to
    WGC would be deemed to mean Brix. The notice informed LSF that Brix had
    retained H.A. Andersen Company (Andersen) as the new representative and all
    "applications, lien releases and notices should be delivered" to Brix with a copy to
    Andersen.
    1 The subcontract states that it is with LSF Structures Ltd., but it is signed
    by Lightweight Steel Framing 2007 Ltd.
    -2-
    No. 73427-0-1/3
    Later in July 2008, Brix terminated LSF. A dispute arose over unpaid
    invoices. By letter dated February 4, 2009, Brix invoked the arbitration and
    mediation provisions of the subcontract and made a formal demand for
    arbitration.2 The parties subsequently agreed on a mediator and arbitrator but
    did not reach agreement on dates for holding the mediation and arbitration.
    In August 2009, LSF filed a complaint in superior court for, among other
    claims, breach of contract, quantum meruit, and recovery of its contractor
    registration bond. LSF does not mention the 2009 complaint in its brief. While
    the 2009 complaint was pending, the parties continued to discuss arbitration.
    However, LSF failed to produce the files or documentation requested by Brix
    despite a series of e-mail exchanges between February 2010 and August 2010.
    In August 2010, Brix moved for summary judgment. Brix argued that LSF
    had failed to satisfy the condition precedent set forth in section U3 prior to filing
    the complaint. In response, LSF argued that there were issues of fact regarding
    its compliance with section U3. In support of its response, LSF attached the
    declaration of Al Malcolm, president of LSF, stating that he had been submitting
    monthly billing statements and had met with Brix personnel regarding the
    amounts due. Malcolm attached a one-page exhibit that was a summary of the
    amounts LSF claimed were owed.
    2 Some of this background factual information is gleaned from this court's
    2012 opinion, which was entered into the record as an attachment to Brix's
    motion for summary judgement.
    -3-
    No. 73427-0-1/4
    On September 10, 2010, the superior court granted summary judgment,
    dismissing the 2009 complaint without prejudice and finding that LSF had failed
    to satisfy the condition precedent to filing the lawsuit. LSF appealed. On April
    30, 2012, this court dismissed the appeal, holding that a dismissal without
    prejudice is not appealable and concluding that discretionary review was not
    warranted.
    On July 28, 2014, LSF3 filed the present lawsuit in superior court for
    breach of contract, promissory estoppel/unjust enrichment, quantum meruit, and
    recovery of its contractor registration bond. It was based upon the same
    underlying facts as the 2009 complaint. The complaint requested a stay pending
    resolution of the claims by mediation/arbitration, pursuant to the subcontract.
    On February 20, 2015, Brix again moved for summary judgment based on
    LSF's failure to satisfy the condition precedent prior to filing the lawsuit. In
    response, LSF again claimed that there were issues of material fact as to
    whether it complied with the condition precedent. LSF presented the same
    August 30, 2010, declaration of Al Malcolm that had been presented in the prior
    lawsuit. Attached to Malcom's declaration was the same one-page summary
    listing the amounts allegedly due from Brix pursuant to the subcontract.
    3 Lightweight Steel Framing 2007 Ltd. was the plaintiff in the 2009
    complaint. In 2014, LSF Structures Ltd. was added as a second plaintiff, but LSF
    has not argued that there is anything significant about adding a second named
    plaintiff.
    -4-
    No. 73427-0-1/5
    In reply, Brix noted that LSF was presenting the same arguments and
    declaration that were previously unsuccessful but expecting a different result.
    Brix asked the court to dismiss this case with prejudice because the complaint
    was filed on the day the statute of limitations was set to expire, precluding LSF
    from filing another complaint. The superior court granted summary judgment and
    dismissed the complaint with prejudice. LSF appeals.
    ANALYSIS
    "We review summary judgment orders de novo . . ., viewing all facts and
    reasonable inferences in the light most favorable to the nonmoving party. . . .
    [S]ummary judgment is appropriate where there is 'no genuine issue as to any
    material fact and ... the moving party is entitled to a judgment as a matter of
    law.'" Eicon Const.. Inc. v. E. Wash. Univ., 
    174 Wash. 2d 157
    , 164-65, 
    273 P.3d 965
    (2012) (some alteration in original) (citations omitted) (quoting CR 56(c)).
    Although the evidence is viewed in the light most favorable to the nonmoving
    party, ifthat party is the plaintiff and it fails to make a factual showing sufficient to
    establish an element essential to its case, summary judgment is warranted.
    Young v. Key Pharms., Inc., 
    112 Wash. 2d 216
    , 225, 770 P.2d 182(1989).
    "Conclusory statements and speculation will not preclude a grant of summary
    judgment." Eicon Const., 
    Inc., 174 Wash. 2d at 169
    .
    -5
    No. 73427-0-1/6
    The complaint does not ask the trial court to compel arbitration
    LSF contends that it filed this lawsuit "for the purpose of compelling
    arbitration," and the trial court erred because the arbitrator should decide
    "'whether a condition precedent to aribitrability has been fulfilled.'"
    LSF filed a complaint alleging breach of contract and seeking over one
    million dollars "in an amount to be proven at trial (or arbitration)." It is not a
    complaint to compel arbitration, it contains no allegations that Brix refused to
    arbitrate, and it does not ask the trial court to compel arbitration. Accordingly, the
    trial court rightfully considered whether LSF satisfied that condition precedent to
    filing a lawsuit. Although LSF contends that it filed the lawsuit so that it would
    have "a mechanism to compel [Brix] to arbitrate" the issue of enforcing the
    arbitration provision was never before the trial court.
    LSF failed to comply with section U3 of the subcontract
    LSF filed the lawsuit. As the party seeking enforcement of the contract,
    LSF had "the burden of proving performance of an express condition precedent."
    Walter Implement, Inc. v. Focht, 
    107 Wash. 2d 553
    , 557, 
    730 P.2d 1340
    (1987);
    Ross v. Harding, 
    64 Wash. 2d 231
    , 240, 
    391 P.2d 526
    (1964). LSF did not raise a
    genuine issue of material fact with respect to performance.
    Brix submitted declarations from Mike Ducey, president of WGC, Matt
    Adamson, counsel for Brix, and Barbara Cowan, controller of a Brix affiliate
    charged with overseeing disputes involving Brix. With these declarations, Brix,
    as the moving party, met its initial burden by showing there was an absence of
    No. 73427-0-1/7
    evidence supporting LSF's case. See 
    Young, 112 Wash. 2d at 224
    n.1. At that
    point, the burden shifted to LSF to show an issue of material fact as to whether it
    satisfied the condition precedent. Eicon Const., 
    Inc., 174 Wash. 2d at 169
    .
    In its response opposing summary judgment, LSF again relied on the
    declaration of Malcolm and the one-page summary attached thereto. The
    summary does not satisfy section U3 of the subcontract because it is not a "full
    claim in writing" nor a "detailed cost documentation," much less "all points of
    argument in Subcontractor's favor," or "all information available upon which a
    decision can be made."
    Malcolm's declaration states that (1) throughout its work on the project,
    LSF sent monthly invoices to WGC requesting progress payments; (2) from July
    through September 2008, he attended meetings with personnel from Brix and
    Andersen to discuss the project and LSF's outstanding invoices; (3) he
    exchanged numerous phone calls, e-mails, and written correspondence with
    management personnel from Brix and Andersen regarding outstanding invoices;
    and (4) he provided Brix and Andersen's management personnel with "other
    written cost documentation detailing the amounts of LSF's claim."
    These statements are not the detailed breakdown required by section U3
    of the subcontract. They are too conclusory to withstand summary judgment.
    See Eicon Const., 
    Inc., 174 Wash. 2d at 169
    ; Little v. Countrvwood Homes, Inc.,
    
    132 Wash. App. 777
    , 780, 
    133 P.3d 944
    , review denied, 158Wn.2d 1017(2006).
    LSF should have presented, or at least described in greater detail, the
    No. 73427-0-1/8
    documents it claims to have provided to Brix. See CR 56(e). Absent such
    documents or details, LSF failed to carry its burden. Sch. Dist. No. U,
    Multnomah County v. ACandS, Inc., 
    5 F.3d 1255
    , 1262 (9th Cir. 1993) (When
    documentary evidence is cited as a source of a factual contention, the affidavit
    should attach the documents.), cert, denied, 
    512 U.S. 1236
    (1994).
    LSF relies on Staples v. Allstate Ins. Co., 
    176 Wash. 2d 404
    , 
    295 P.3d 201
    (2013), to contend that "substantial compliance" with the condition precedent is
    sufficient to withstand summary judgment. This reliance is misplaced.
    Substantial compliance was sufficient in Staples due to the quasi-fiduciary nature
    of the insurer/insured relationship. 
    Staples, 176 Wash. 2d at 414
    . Brix did not owe
    a fiduciary duty to LSF.
    Waiver
    LSF also argues that Brix waived the condition precedent by filing a
    demand for arbitration and agreeing to arbitrate. LSF is incorrect for two
    reasons. First, section U3 applies to "any claim in" mediation, arbitration, or
    litigation. Thus, Brix's demand for arbitration did not waive the condition
    precedent as to any claim or counterclaim LSF might assert. And even if a
    demand for arbitration could waive the condition for purposes of arbitration, LSF
    filed a lawsuit; the condition would still apply to claims brought in litigation.
    Dismissal was warranted for failure to comply with the condition precedent
    In general, when a party fails to satisfy a condition precedent prior to filing
    a lawsuit, dismissal is appropriate. See 
    Ross, 64 Wash. 2d at 241
    ("breach by a
    8
    No. 73427-0-1/9
    plaintiff of a material condition precedent relieves a defendant of liability under a
    contract"). LSF claims that failure to comply with a condition precedent warrants
    dismissal only if the contract explicitly states that dismissal is the remedy for non
    compliance, citing Shepler Construction v. Leonard, 
    175 Wash. App. 239
    , 246, 
    306 P.3d 988
    (2013).
    Shepler Construction is not on point because there the parties waived
    arbitration. The court did not address the consequence of a failure to satisfy a
    condition precedent to either arbitration or litigation.
    Finally, we reject LSF's contention that dismissal was improper absent a
    showing of prejudice. The cases cited by LSF concern the unique relationship
    between an insurer and an insured. See, e.g., 
    Staples. 176 Wash. 2d at 418
    ; Pub.
    Util. Dist. No. 1 of Klickitat County v. Int'l Ins. Co., 
    124 Wash. 2d 789
    , 803-04, 
    881 P.2d 1020
    (1994); see generally Mendoza v. Rivera-Chavez, 140Wn.2d659,
    662-65, 
    999 P.2d 29
    (2000). The public policy governing conditions precedent in
    insurance contracts is not applicable in this case.
    We conclude that the trial court properly granted Brix's motion for
    summary judgment and dismissal with prejudice.                                    ^
    CD
    !
    Affirmed.
    WE CONCUR:
    Vw^