Bnbuilders Inc. v. Wa State Department Of Labor & Industries ( 2014 )


Menu:
  •                                    fs ••-•
    Ui
    29IUUL-1 h,i
    IN THE COURT OF APPEALS FOR THE STATE OF WASHINGTON
    BN BUILDERS, INC., a Washington
    corporation,                                  No. 70142-8-
    Appellant,                    DIVISION ONE
    DEPARTMENT OF LABOR AND                           UNPUBLISHED OPINION
    INDUSTRIES AND BOARD OF
    INDUSTRIAL INSURANCE APPEALS,                     FILED: July 7, 2014
    Respondent
    Leach, J. — BN Builders Inc. (BNB) appeals a superior court judgment
    affirming the decision of the Board of Industrial Insurance Appeals (Board)
    involving Department of Labor & Industries (Department) citations for asbestos
    workplace violations. BNB contends that substantial evidence does not support
    the Board's findings and that the Board applied an inappropriate strict liability
    standard.   BNB also disputes the assessed penalties, which the Department
    increased because of a "poor" rating for good faith. Because substantial evidence
    in the record supports the Board's findings and those findings support the Board's
    conclusions of law, we affirm.
    No. 70142-8-1/2
    FACTS
    In late December 2009, BNB began work as the general contractor to
    convert a former hospital into a private school. The original building dates from
    the 1920s, with an additional wing added in 1945. Federal and state law required
    BNB to obtain a good faith survey to assess the presence of asbestos before
    beginning demolition work.1
    The property owner gave BNB a survey that Earth Consulting Inc. (ECI)
    conducted in 2007.     This survey analyzed 87 samples and found asbestos-
    containing material (ACM) in vinyl floor tiles, tile and carpet mastic, cement
    asbestos board, pipe lagging, tank and water heater insulation, and asphaltic
    roofing materials. The ECI survey report noted that it did not address ACM that
    might be located "behind walls and/or columns, beneath flooring, above non
    removable ceilings, underground, or in any other inaccessible areas," and stated,
    "Should suspected ACM be uncovered during demolition activities, it should be
    sampled, tested, and characterized at that time." The property owner also gave
    BNB a 2008 inspection report from Argus Pacific Inc. This inspection analyzed
    samples for other possible contaminants, including lead, mercury, metals,
    radiation, and mold.   The Argus Pacific inspection also identified but did not
    analyze "a large number of suspect asbestos-containing materials that were not
    sampled and analyzed during the previous asbestos inspection." Argus Pacific
    
    140 CFR § 763.86
    ; WAC 296-62-07721(1)(c)(ii).
    -2-
    No. 70142-8-1/3
    recommended that the property owner commission a "more thorough asbestos
    inspection" before demolition.
    Before beginning its work, BNB solicited bids for a new asbestos survey.
    After two consultants recommended that "a quality abatement contractor would be
    money better spent," BNB decided to rely on the 2007 ECI asbestos assessment
    and not commission another survey. BNB was not a certified asbestos contractor,
    and BNB's contract with the property owner expressly excluded abatement or
    removal of hazardous materials. When BNB started work on December 28, 2009,
    it had not yet hired an abatement contractor.
    BNB performed a "soft demolition": removal of nonstructural portions of the
    building. Demolition areas included some not shown as tested in the ECI survey.
    As BNB workers removed carpet, they sometimes also removed old vinyl tiles that
    stuck to the carpet. Some of these tiles broke during removal. BNB foreman
    Robert Voss instructed workers to throw carpet free of tiles directly into the
    dumpster. For carpet containing tile or mastic, Voss directed workers to wrap the
    materials in plastic bags, secure the bags with duct tape, and place them in a
    designated room for asbestos abatement contractors to pick up later. Workers did
    not wear protective clothing or use respirators for most or all of the work. In the
    course of the work, workers sometimes also disturbed thermal system insulation.
    On January 11, 2010, worker Jeff Pennington completed a "near miss" incident
    report describing insulation that fell on him from a wall he was demolishing. He
    wrote, "I had seen it befor[e] but didn't know if it contained asbestos or not. I
    No. 70142-8-1/4
    asked Bob Voss he said it has been tested but the results weren't in yet. WORK
    IN THAT AREA WAS HALTED!"                  At least two BNB workers expressed their
    concerns about asbestos exposure to managers. These managers were on site
    during several days of demolition.
    On January 12, 2010, worker Stewart Weston contacted the Department,
    which conducted an inspection the next day.          Based on her observations and
    belief that previous surveys had "serious flaws," inspector Janine Rees directed
    BNB to obtain another asbestos survey. Subsequent testing by NVL Laboratories
    Inc. revealed asbestos in a number of materials, including pipe insulation and vinyl
    floor tiles of varying sizes and colors.
    The Department issued a citation to BNB for ten serious and three general
    violations, with a total penalty of $19,300.2       Twelve of the violations involved
    2 Specifically, the citation alleged that BNB did not use critical barriers to
    isolate the class II removal of presumed asbestos containing vinyl flooring and
    mastic or have a negative exposure assessment for the work, in violation of WAC
    296-62-07712(9)(b)(i); did not conduct asbestos air monitoring during removal or
    air clearance monitoring after removal of vinyl flooring and mastic, in violation of
    WAC 296-62-07709(3)(a)(ii) and -07709(3)(h); did not ensure the use of full body
    protective clothing during asbestos removal, which is required in the absence of a
    negative exposure assessment, in violation of WAC 296-62-07717(1); removed
    asbestos in a dry state without the use of supplied air respirators rather than in a
    wet, saturated state, in violation of WAC 296-62-07712(2)(c) and -07715(4)(a)(ii);
    did not use certified asbestos workers or obtain certification as a certified asbestos
    contractor before conducting a class II asbestos abatement project, in violation of
    WAC 296-62-07722(3)(b)(i)(A) and 296-65-030(1); did not obtain an asbestos
    survey identifying all asbestos containing materials on the site before starting
    work, in violation of WAC 296-62-07721 (2)(e); did not promptly encapsulate or
    clean up presumed asbestos thermal system insulation damaged by employees
    during interior wall demolition, in violation of WAC 296-62-07712(2)(d), -07723(8),
    or -07723(2); did not conduct preabatement asbestos air monitoring before
    removing presumed asbestos containing vinyl floor tile and mastic, in violation of
    No. 70142-8-1/5
    asbestos removal procedures, and one cited an inadequate respirator program.
    The Department gave BNB a "poor" rating for good faith, which increased the
    penalties for ten of the violations. BNB appealed the citations, and an industrial
    appeals judge affirmed.    BNB then petitioned the Board of Industrial Appeals,
    which affirmed nine of the serious violations and all three general violations,
    imposing a judgment against BNB of $16,800.3 BNB appealed to King County
    Superior Court, which affirmed the Board's decision.
    BNB appeals.
    STANDARD OF REVIEW
    The Washington Industrial Safety and Health Act of 1973 (WISHA), chapter
    49.17 RCW, governs judicial review of a decision issued by the Board.4 This court
    directly reviews the Board's decision based on the record before the agency.5 The
    Board's findings of fact are conclusive if they are supported by substantial
    evidence when viewed in light of the record as a whole.6 Substantial evidence is
    evidence sufficient to persuade a fair-minded person of the truth of the matter
    WAC 296-62-07709(3)(g); did not file with the Department a notice of intent to
    remove asbestos abatement project before conducting a class II asbestos
    abatement project, in violation of WAC 296-65-020(1 )(e); and did not maintain an
    adequate respirator protection program, in violation of WAC 296-842-12005(1).
    3 The Board reversed violation 1-8, in which the Department found that
    "Before starting work on site, the employer did not obtain an asbestos survey to
    determine if all materials to be worked on, or removed, contain asbestos."
    4 RCW 49.17.140.150(1).
    5 Mowat Constr. Co. v. Dep't of Labor & Indus., 
    148 Wn. App. 920
    , 925, 
    201 P.3d 407
     (2009).
    6 RCW 49.17.150(1); Mowat, 148 Wn. App. at 925.
    No. 70142-8-1/6
    asserted.7 If this court determines that substantial evidence supports the Board's
    findings, it then decides if those findings support the Board's conclusions of law.8
    This court reviews the Board's interpretation of a statute or regulation de
    novo, under an error of law standard.9 This court gives "substantial weight" to the
    agency's interpretation of regulations within its area of expertise and will uphold
    that interpretation if "'it reflects a plausible construction of the language of the
    statute and is not contrary to the legislative intent.'"10 This court reviews WISHA
    penalty amounts for abuse of discretion.11 A court abuses its discretion where its
    decision is arbitrary or rests on untenable grounds or reasons.12
    ANALYSIS
    WISHA and Asbestos
    The legislature enacted WISHA "to assure, insofar as may reasonably be
    possible, safe and healthful working conditions for every man and woman working
    in the state of Washington."13 In RCW 49.26.010, the legislature recognized the
    dangers of exposure to asbestos, which is "known to produce irreversible lung
    damage and bronchogenic carcinoma. . . . The nature of this problem is such as to
    7 Mowat, 148 Wn. App. at 925.
    8 J.E. Dunn Nw. Inc. v. Dep't of Labor & Indus., 
    139 Wn. App. 35
    , 42, 
    156 P.3d 250
     (2007).
    9 Roller v. Dep't of Labor & Indus., 
    128 Wn. App. 922
    , 926, 
    117 P.3d 385
    (2005).
    10 Cobra Roofing Serv.. Inc. v. Dep't of Labor & Indus., 
    122 Wn. App. 402
    ,
    409, 
    97 P.3d 17
     (2004) (quoting Seatoma Convalescent Ctr. v. Dep't of Soc. &
    Health Serv., 
    82 Wn. App. 495
    , 518, 
    919 P.2d 602
     (1996)).
    " Panzer v. Dep't of Labor & Indus., 
    104 Wn. App. 307
    , 326, 
    16 P.3d 35
    (2000).
    12 Panzer, 104 Wn. App. at 326.
    13 RCW 49.17.010.
    -6-
    No. 70142-8-1/7
    constitute a hazard to the public health and safety, and should be brought under
    appropriate regulation."   The legislature established a comprehensive statutory
    regime to regulate asbestos, and the Department promulgates and enforces rules
    for all occupational exposure to asbestos in workplaces that WISHA covers.14
    The regulations define "ACM" as any material containing more than one
    percent asbestos.15 When friable thermal system insulation crumbles or flooring
    materials break during demolition, asbestos fibers may be released into the air.
    In buildings constructed before 1980, vinyl and asphalt flooring materials are
    presumed to contain asbestos.16        Friable thermal system insulation is also
    presumed to contain asbestos.17 To ensure proper identification and abatement of
    ACM, an owner or agent must perform a good faith inspection for ACM before any
    construction, renovation, remodeling, or demolition that may disturb and expose
    workers to asbestos.18 An employer may rebut the presumption of asbestos by
    producing a report by an industrial hygienist who has used "recognized analytical
    techniques" showing that the material is asbestos-free.19        Removal of broken
    asbestos-containing vinyl floor tile is a class II asbestos project, requiring the use
    of certified asbestos workers.20
    14 RCW 49.26; WAC 296-62-077 to -0755; WAC 296-65-001 to -050.
    15 WAC 296-62-07703.
    16 WAC 296-62-07712(10)(a)(ix); WAC 296-62-07721 (1)(b).
    17 WAC 296-62-07712(12)(b).
    18 RCW 49.26.013(1); WAC 296-62-07721 (2)(b)(ii); Prezant Assocs.. Inc. v.
    Dep't of Labor & Indus., 
    141 Wn. App. 1
    , 8, 
    165 P.3d 12
     (2007).
    19 WAC 296-62-07712(10)(a)(ix).
    20 WAC 296-62-07703, -07722(3)(b)(i)(B). Class II asbestos work involving
    intact materials or less than one square foot of ACM is not considered an asbestos
    No. 70142-8-1/8
    RCW 49.17.180 divides civil violations of WISHA into three categories:
    willful or repeat, serious, and not serious.   The Department cited BNB for 10
    serious violations, which exist where
    a substantial probability that death or serious physical harm could result
    from a condition which exists, or from one or more practices, means,
    methods, operations, or processes which have been adopted or are in use
    in such workplace, unless the employer did not, and could not with the
    exercise of reasonable diligence, know of the presence of the violation.[21]
    To prove a violation of a specific health and safety standard, the
    Department must prove (1) the cited standard applies, (2) the employer did not
    meet the requirements of the standard, (3) employees were exposed to the
    violative condition, (4) "'the employer knew or, through the exercise of reasonable
    diligence, could have known of the violative condition,'" and (5) there is a
    substantial probability that death or serious injury could result from the violative
    condition.22   "[Cjonstructive knowledge is sufficient to prove knowledge of the
    violative condition."23 The Department may establish constructive knowledge of a
    WISHA violation in a number of ways, including with evidence showing that the
    violation was readily observable or in a conspicuous location in the area where the
    employees were working.24       "'Reasonable diligence involves several factors,
    project and does not require asbestos worker certification.        WAC 296-62-
    07722(3)(b)(ii)(A)-(B).
    21 RCW 49.17.180(6).
    22 Wash. Cedar & Supply Co. v. Dep't of Labor & Indus., 
    119 Wn. App. 906
    ,
    914, 
    83 P.3d 1012
     (2003) (quoting D.A. Collins Constr. Co. v. Sec'v of Labor, 117
    F.3d691,694(2dCir. 1997)).
    23 BD Roofing, Inc. v. Dep't of Labor & Indus.. 
    139 Wn. App. 98
    , 109, 
    161 P.3d 387
     (2007).
    24 BD Roofing, 139 Wn. App. at 109-10.
    -8-
    No. 70142-8-1/9
    including an employer's obligation to inspect the work area, to anticipate hazards
    to which employees may be exposed, and to take measures to prevent the
    occurrence.'"25
    BNB's Knowledge of the Violative Condition
    BNB challenges the Department's proof of the fourth element, arguing that
    BNB exercised reasonable diligence by obtaining and relying on ECl's survey and
    could not have known of the presence of asbestos at the site. BNB contends that
    the Board's decision to reverse violation 1-8, "the employer did not obtain an
    asbestos survey to determine if all materials to be worked on, or removed, contain
    asbestos," supports its argument that it exercised reasonable diligence. As BNB
    frames the issue, the Board improperly penalized it for reasonably relying on a
    good faith survey and "inappropriately applied a strict liability standard" to reach a
    decision that "defies common sense and construction industry practice."26
    BNB mischaracterizes the issue. The Board did not sanction BNB for its
    initial reliance upon its good faith survey. Instead, the Board sanctioned BNB
    because, as a result of its work, it later "knew or, through the exercise of
    reasonable diligence, could have known" of the hazardous conditions that the
    survey did not reveal. In its findings of fact, the Board found that "[t]he employer
    did not take measures to protect employees as soon as it had reason to suspect
    25 Erection Co. v. Dep't of Labor & Indus.. 
    160 Wn. App. 194
    , 206-07, 
    248 P.3d 1085
     (2011) (internal quotation marks omitted) (quoting Kokosing Constr. Co.
    v. Occupational Safety & Hazard Review Comm'n, 
    232 Fed. Appx. 510
    , 512 (6th
    Cir. 2007)).
    26 In an amicus brief, the Associated General Contractors of Washington
    makes a similar argument.
    No. 70142-8-1/10
    employees were working with asbestos-containing material." Substantial evidence
    supports these findings.   Voss appeared to treat the vinyl tiles pulled up with
    carpet as ACM when he ordered that they be double-bagged, sealed, and
    segregated from other waste. Rees testified that when she interviewed Voss, "He
    told me that he suspected there might be asbestos in the mastic; and that it was
    only two percent, and he wasn't concerned about it because it was nonfriable."
    BNB worker Stewart Weston also testified that Voss told him some of the tile
    mastic contained asbestos.     He testified that he and several other employees
    brought their concerns about asbestos to Voss "right away."
    On December 31, 2009, Casey Blake, BNB general superintendent for the
    jobsite, told Voss that "we needed to stop carpet removal until an abatement crew
    is on site." BNB safety director Bruce Campbell testified in a deposition, "As soon
    as the tile started coming up with the carpet they should have stopped work."
    Blake's notes about January 11 also describe a conversation with Weston about
    Weston's concerns and reference "a lot of concerned people . . . [we] decided to
    have a quick meeting with the guys and tell them by no way do we want people
    exposed to hazards." On that day, Blake also asked Voss "to have the abatement
    crew look at the [presumed] ACM we found as well and I learned we did not have
    one signed up yet." A BNB "Weekly Safety Review" dated January 9, 2010, noted
    that at the site, "[a]sbestos floor tiles that come up when carpet is removed need to
    be replaced or set aside in a sealed bag for the abatement contractor. Took
    -10-
    No. 70142-8-1/11
    additional samples to lab for possible asbestos. Samples were not listed on the
    Good Faith Survey."
    BNB challenges the Board's finding that BNB "did not take measures to
    protect employees as soon as it had reason to suspect employees were working
    with asbestos-containing material," asserting, "The correct legal standard is
    'knowledge,' not 'suspicion.'" But the fact that the Board's finding did not use the
    precise statutory language does not prevent us from affirming the Board's
    decision.    Substantial evidence supports the Board's finding that BNB had
    constructive knowledge of the violative condition under RCW 49.17.180(6).
    The Board found that BNB "obtained an asbestos survey adequate to
    determine if the materials to be demolished contained asbestos." BNB infers from
    this that "the Board concluded that an adequate [survey] had been obtained," and
    "the Board found BNB had been reasonably diligent and reasonably believed it
    was following the [survey] and the promulgated standard." However, BNB was not
    entitled to rely only on this survey for the duration of its work, ignoring readily
    observable conditions discovered at the jobsite demonstrating workers' exposure
    to asbestos.   Despite evidence that contradicted the ECI survey, BNB did not
    "'anticipate hazards to which employees may be exposed,'" or "'take measures to
    prevent the occurrence.'"27 Substantial evidence shows that BNB could have
    protected its workers from asbestos exposure through the exercise of reasonable
    diligence.
    27 Erection Co., 160 Wn. App. at 206-07 (quoting Kokosing, 232 Fed. Appx.
    At 512).
    -11-
    No. 70142-8-1/12
    Failure to Dispose of Wastes
    BNB also challenges violation 1-9, which sanctioned BNB for its failure to
    ensure "[p]rompt cleanup and disposal of wastes and debris contaminated with
    asbestos in leak-tight containers." BNB argues that (1) there was no evidence that
    BNB created or was aware of the debris and (2) because BNB is not a certified
    asbestos contractor, such cleanup was beyond the scope of its work.               BNB
    contends, "It is inconsistent for the Department to cite BNB for failing to engage in
    the clean up operations for asbestos, when BNB was never certified to engage in
    such activities."   However, BNB's lack of certification and the limitations of its
    contract do not excuse workers' exposure to "chunks of fluffy, dry friable asbestos
    pipe insulation," which Rees found "dropped on the floor" during her inspection.
    Moreover, BNB did not dispute that for nearly two weeks, workers demolished
    carpet and broken floor tiles without air monitoring, protective clothing, respirators,
    critical barriers, or wet saturation removal. At the end of that time, BNB had still
    not engaged an abatement contractor. The record contains substantial evidence
    showing that BNB failed to clean up debris contaminated with asbestos.
    Written Respirator Program
    BNB argues next that substantial evidence does not support the
    Department's citation for violation 2-3, in which the Department found that BNB's
    written respirator program was deficient.        The Department cited BNB for "not
    listfing] specific respirators to be used for each type of hazard, such as lead, silica,
    -12-
    No. 70142-8-1/13
    asbestos or dusts. The program is generic in nature and must be tailored to the
    employer's workplace and hazards found on the work site."
    WAC 296-842-12005(1) requires that employers "[d]evelop a complete
    worksite-specific written respiratory protection program" that includes a list of
    required elements related to respirator selection and use, medical evaluation, fit
    test procedures, and training. BNB did not present a worksite-specific respirator
    program. "Pre-activity hazard analysis" forms in the record identify hazards such
    as lead and note the need for personal protective equipment.        But neither the
    respirator program nor the hazard analysis forms specify "the appropriate
    respirator for each respiratory hazard in your workplace,"28 as required by the
    applicable regulation.   Substantial evidence supports the Board's finding that
    BNB's written respirator program was deficient.
    Penalties
    Finally, BNB argues the Board erred by affirming penalties that the
    Department increased because of a "poor" rating for good faith. The Department
    may adjust a base penalty using several factors, including "good faith effort."29 A
    "poor" rating for good faith results in a 20 percent increase in the base penalty.30
    To determine good faith, the Board considers if the employer "(1) took prompt
    action to understand and comply with the regulation, (2) cooperated with the
    investigation, (3) worked with the Department to resolve the problem, and (4)
    28 WAC 296-842-12005 (Table 3).
    29 WAC 296-900-14015 (Table 5).
    30 WAC 296-900-14015 (Table 5).
    -13-
    No. 70142-8-1/14
    appeared committed to assuring a safe and healthful workplace."31 Conscious
    disregard of risks, delay in correcting the violation, deceptive behavior, and willful
    resistance to compliance indicate a lack of good faith.32
    Rees testified that "a variety of factors" contributed to her good faith rating,
    including "incorrect or evasive information" from management:
    Mr. Voss told me the workers were wearing respirators during the removal
    of the floor tile.   Later on when I interviewed him in BNBuilders office, he
    admitted that the respirators weren't provided until the very end. Mr. Voss
    stated that Pete Campbell took the—some of the supplemental asbestos
    samples during the course of the work, and that he was an accredited
    inspector. Later on Mr. Voss admitted that he was the one who took the
    samples, not Mr. Campbell, and Mr. Campbell was not accredited at the
    time. Mr. Voss completely misrepresented the amount of tile that was
    removed by workers from BNBuilders, which he corrected much later. So
    information was not candid and forthright at the outset of the inspection.
    When I contained [sic] information that contradicted what I had been told by
    management from multiple sources, I confronted them, and then they did
    admit the truth. But BNBuilders, you know, was not particularly cooperative
    in this inspection in providing truthful information.1331
    The substantial evidence standard "necessarily entails acceptance of the
    factfinder's views regarding the credibility of witnesses and the weight to be given
    reasonable but competing inferences."34 Testimony in the record supports the
    Board's finding that BNB "failed to fully and completely disclose pertinent
    information during the inspection." Because the Department based its penalty
    calculation on the factors in RCW 49.17.180(7) and substantial evidence supports
    31 Panzer. 104 Wn. App. at 324.
    32 Panzer, 104 Wn. App. at 324.
    33 Voss denied at hearing that he told Rees he had taken any samples.
    34 State v. ex rel. Lige & Wm. B. Pickson Co. v. Pierce County, 
    65 Wn. App. 614
    , 618, 
    829 P.2d 217
     (1992).
    -14-
    No. 70142-8-1/15
    the calculations, the penalties are not arbitrary or based on untenable grounds.35
    The Pepartment did not abuse its discretion.
    CONCLUSION
    Because substantial evidence in the record supports the Board's findings
    that BNB knew or could have known through reasonable diligence that its
    employees were exposed to asbestos, that BNB failed to properly clean up
    asbestos debris or maintain a written respirator program, and that the Pepartment
    did not abuse its discretion by assessing a "poor" good faith rating, we affirm.
    MjA^JC^
    WE CONCUR:
    "^U^A^n^
    35 Panzer at 104 Wn. App. at 327.
    -15-