Gary G. Gregg v. JRCC Inc. ( 2022 )


Menu:
  •                                                                            FILED
    April 7, 2022
    In the Office of the Clerk of Court
    WA State Court of Appeals Division III
    IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    DIVISION THREE
    GARY G. GREGG, an individual,                )
    )        No. 37855-1-III
    Appellant,               )
    )
    v.                                     )
    )
    JRCC, INC., a Washington corporation;        )        UNPUBLISHED OPINION
    and JUST RIGHT CLEANING &                    )
    CONSTRUCTION, INC., a Washington             )
    corporation; and,                            )
    )
    Respondents,             )
    )
    WESTERN SURETY COMPANY, a                    )
    foreign corporation; CAPITOL                 )
    INDEMENITY CORPORATION, a                    )
    foreign corporation,                         )
    )
    )
    Defendants.              )
    FEARING, J. — Owner Gary Gregg appeals the superior court’s summary dismissal
    of his claims against contractor JRCC for defective workmanship. Because Gregg failed
    to comply with a pre-suit notice requirement, we affirm the dismissal.
    FACTS
    Gary Gregg owned Cougar Liquor in Soap Lake. Before the store’s initial
    opening, an old ice machine malfunctioned and leaked water. The resulting flood
    damaged the main floor’s tiling. Gary Gregg contracted with Just Right Cleaning &
    No. 37855-1-III
    Gregg v. JRCC, Inc., et al.
    Construction Inc. (JRCC) to install new floor tiles. The written contract included a
    “terms and conditions” section that read:
    7. If any dispute arises between the parties, the parties will make a
    good faith effort to first resolve the dispute without resort to litigation. In
    the event a dispute arises and either party seeks and receives legal counsel
    for which a fee is charged, the prevailing party shall in all cases be awarded
    his or her reasonable attorneys’ fees regardless of whether the dispute is
    resolved through settlement or arbitration. [As] [a] condition precedent in
    any lawsuit, the Customer must first present any claim in writing to the
    contractor and provide the contractor a reasonable opportunity to correct or
    complete any work which the Customer claims to be defective and require
    correction or completion. After complying with the preceding condition
    precedent, either party may file suit in an appropriate court of jurisdiction.
    ....
    8. Prior to making final payment to the contractor the customer may
    inspect the work to determine that the work has been completed according
    to the contract. The Customer may prepare a written list of work that the
    customer believes should be completed or corrected according to the
    contract. This written list is called a punch list. There shall be only one
    punch list of work identifying work to be completed or corrected, and the
    list shall be signed by the Customer. The contractor shall expeditiously
    complete all work stated on the punch list for which the contractor is
    responsible under the terms of the contract. Upon the contractor’s
    completion or correction of the work identified on the single written punch
    list any retainage or amount withheld from final payment shall be paid
    within the next five days to the contractor.
    9. The Customer cannot contract with any alternative contractor for
    the performance or completion of work, nor claim a credit or back charge
    for the cost of completing any item stated on the written punch list, nor
    occupy or use the contractor’s work until and unless the contractor shall
    have first been given reasonable notice and opportunity to correct the work
    stated on the punch list. If the Customer does contract with an alternative
    contractor to complete the project without first affording the opportunity to
    the contractor to do so, or if the Customer commences to use or occupy the
    space or work in which the contractor performed work, the customer then
    agrees to accept all work “as is” and thereby waves [sic] any claim against
    the contractor.
    2
    No. 37855-1-III
    Gregg v. JRCC, Inc., et al.
    Clerk’s Papers (CP) at 64 (emphasis added).
    JRCC’s tile work did not satisfy Gary Gregg. Gregg disliked the layout of
    different tile colors and grouting. Some tiles sat higher than others. Gregg informed
    JRCC workers verbally and visually of his complaints. JRCC removed the tiles showing
    the color that Gregg disliked. JRCC also attempted to fix some of the unevenness.
    Gregg remained unsatisfied with JRCC’s fixes and concluded that the contractor was
    incompetent.
    A substitute contractor, Kurt Moore, advised Gary Gregg to redo the tiling. Moore
    concluded that the grout was fracturing, JRCC unevenly laid the tile, and JRCC failed to
    properly affix the tile to the floor. Gregg contracted with Moore to replace the tiles
    applied by JRCC.
    Gary Gregg’s attorney mailed a demand letter to JRCC to pay $40,380.66, the cost
    of tile replacement by Kurt Moore. The letter threatened legal action on failure to pay the
    demanded sum. By the time counsel sent the letter, Moore had begun work on removing
    the tiling.
    PROCEDURE
    Gary Gregg filed a breach of contract suit against Just Right Cleaning &
    Construction Inc. and JRCC Inc. for $40,380.66 based on the repair costs paid to Kurt
    Moore. We do not know the relationship between the defendant companies and treat
    3
    No. 37855-1-III
    Gregg v. JRCC, Inc., et al.
    them as if they are one identity, as do the parties. JRCC filed a counterclaim seeking
    $16,062.92 in outstanding payment for work performed. Gregg in turn filed a
    counterclaim to JRCC’s counterclaim. Gregg’s reverse counterclaim alleged negligence,
    negligent misrepresentation, breach of an implied covenant of good faith, and negligent
    damage to real estate. Under these asserted theories, Gregg sought dismissal of JRCC’s
    counterclaim and damages.
    The superior court granted JRCC’s motion for summary judgment to dismiss Gary
    Gregg’s complaint. The court concluded that the pre-suit contractual language
    constituted a condition precedent to suit. The superior court also dismissed Gregg’s
    counterclaim to the counterclaim under the statute of limitations, economic loss rule, and
    contractual theories. The court awarded attorney fees to JRCC. JRCC transferred its
    counterclaim to arbitration, where the counterclaim was dismissed.
    LAW AND ANALYSIS
    On appeal, Gary Gregg challenges the superior court’s grant of summary judgment
    in favor of JRCC. The trial court’s ruling and parties’ briefing address whether the
    contractual provision created a “condition precedent” to bringing suit. A condition
    precedent is a fact or event, occurring subsequent to the making of a contract, which
    event must occur before a right to immediate performance. Ross v. Harding, 
    64 Wn.2d 231
    , 236, 
    391 P.2d 526
     (1964). The clauses in the JRCC contract do not identify facts or
    events required to occur before JRCC’s substantive performance of its obligations under
    4
    No. 37855-1-III
    Gregg v. JRCC, Inc., et al.
    the contract. Rather, the clauses imposed procedural dispute requirements on the parties
    subsequent to performance and before suit. Different rules apply to dispute provisions.
    We characterize the contractual language as a “notice provision,” not a condition
    precedent.
    This court must enforce contractual notice provisions unless a party waives those
    procedures. Mike M. Johnson, Inc. v. County of Spokane, 
    150 Wn.2d 375
    , 386, 
    78 P.3d 161
     (2003). Washington courts strictly uphold notice provisions as bars to relief. NOVA
    Contracting, Inc. v. City of Olympia, 
    191 Wn.2d 854
    , 857, 
    426 P.3d 685
     (2018);
    American Safety Casualty Insurance Co. v. City of Olympia, 
    162 Wn.2d 762
    , 770, 
    174 P.3d 54
     (2007).
    We construe a contract as a whole and interpret a contract to effectuate all of its
    provisions. Colorado Structures, Inc. v. Insurance Co. of the West, 
    161 Wn.2d 577
    , 588,
    
    167 P.3d 1125
     (2007) (plurality opinion). Clause 7 of JRCC’s contract required Gary
    Gregg to provide a written claim to JRCC and provide a reasonable opportunity for the
    company to correct defective work if Gregg wished to preserve his right to bring suit.
    Similarly, clause 9 required Gregg to provide JRCC a written list of complaints before
    resorting to an alternative contractor. These clauses demanded that Gregg, before hiring
    an alternate contractor, afford JRCC written notice of complaints and a reasonable
    opportunity to cure. Absent this notice, the contract barred judicial relief.
    5
    No. 37855-1-III
    Gregg v. JRCC, Inc., et al.
    Gary Gregg argues that application of the notice provision in this case constitutes
    a disfavored forfeiture of a fundamental right. Conditions precedent will be excused if
    enforcement would involve extreme forfeiture or penalty and the condition does not form
    an essential part of the bargain. Ashburn v. Safeco Insurance Co. of America, 
    42 Wn. App. 692
    , 698, 
    713 P.2d 742
     (1986). But a contractual limitation on a cause of action is
    not a condition precedent subject to forfeiture analysis. Ashburn v. Safeco Insurance Co.
    of America, 
    42 Wn. App. at 698
    . Washington public policy strongly favors alternate
    dispute resolution. Absher Construction Co. v. Kent School District No. 415, 
    77 Wn. App. 137
    , 146, 
    890 P.2d 1071
     (1995). Our Supreme Court has “repeatedly upheld”
    notice provisions similar to the clauses in the JRCC contract. NOVA Contracting, Inc. v.
    City of Olympia, 
    191 Wn.2d 854
    , 865 (2018).
    Gary Gregg next contends that, even if this court upholds the notice requirement, a
    material issue of fact remains as to whether Gregg provided JRCC with adequate notice
    of the defects and an opportunity to cure. Nevertheless, actual notice of a protest or claim
    will not excuse noncompliance with a notice provision unless the benefiting party’s
    conduct evidences an intent to waive the notice provision. Mike M. Johnson, Inc. v.
    County of Spokane, 
    150 Wn.2d 375
    , 387-88, 391 (2003). Only unequivocal conduct
    evidences an intent to waive. American Safety Casualty Insurance Co. v. City of
    Olympia, 
    162 Wn.2d 762
    , 771 (2007).
    6
    No. 37855-1-III
    Gregg v. JRCC, Inc., et al.
    Gary Gregg must demonstrate that JRCC unequivocally waived the notice
    provision. After Gregg verbally informed JRCC of his dissatisfaction, JRCC workers
    removed the tile color that Gregg disfavored and attempted to level some of the tiles.
    Gregg did not thereafter contact JRCC before Kurt Moore removed the tile installed by
    JRCC. JRCC never announced that it deemed its duties satisfied under the contract.
    These facts do not raise a question as to whether JRCC unequivocally waived the written
    notice provision.
    Gary Gregg also contends that the trial court erred in dismissing his counterclaim
    to JRCC’s counterclaim. He argues that, even if the notice provisions prevented him
    from filing suit against JRCC, they cannot be construed to preclude a counterclaim. But,
    as Gregg concedes, the economic loss rule barred any tort theories of recovery. The
    economic loss rule holds parties to their contract remedies when a loss implicates both
    tort and contract relief. Alejandre v. Bull, 
    159 Wn.2d 674
    , 681, 
    153 P.3d 864
     (2007).
    Gary Gregg’s reverse counterclaim also advances contract theories of negligent
    misrepresentation and breach of the implied covenant of good faith. To the extent these
    theories asserted affirmative grounds for relief against JRCC, the parties’ contractual
    notice provision barred them.
    The trial court did not delineate whether any of the grounds Gary Gregg asserted
    in his counter-counterclaim survived as defenses to JRCC’s counterclaim. Nevertheless,
    7
    No. 37855-1-III
    Gregg v. JRCC, Inc., et al.
    Gregg successfully defended against JRCC’s counterclaim in arbitration. JRCC does not
    cross appeal the arbitration decision.
    Gary Gregg assigns error to the trial court’s award of attorney fees to JRCC but
    submits no argument specific to this assignment. The law enforces contractual attorney
    fee provisions benefiting prevailing parties. RCW 4.84.330. Therefore, the trial court
    did not err.
    JRCC requests attorney fees incurred on appeal. We grant this request based on
    the contractual attorney fee provision.
    CONCLUSION
    We affirm the trial court’s grant of summary judgment on the original claim,
    dismissal of Gary Gregg’s counterclaim to JRCC’s counterclaim, and award of attorney
    fees to JRCC. We award JRCC attorney fees on appeal.
    A majority of the panel has determined this opinion will not be printed in the
    Washington Appellate Reports, but it will be filed for public record pursuant to RCW
    2.06.040.
    _________________________________
    Fearing, J.
    WE CONCUR:
    ______________________________                ________________________________
    Siddoway, C.J.                                Staab, J.
    8